Deterministic and Probabilistic Engineering Cost
Deterministic and Probabilistic Engineering Cost
Abstract: Accurate and reliable project cost estimates are fundamental to achieve successful municipal capital improvement (CIP)
programs. Engineering cost estimates typically represent critical information for key decision makers to authorize and efficiently allocate
the necessary funds for construction, budgeting, to generate a request for proposals, contract negotiations, scheduling, etc. for these
reasons, cost estimators are using different estimating methods and approaches that allow for required levels of accuracy. As the project’s
scope becomes more detailed and the potential risks are identified and/or the project design stage progresses these cost estimates are
revised and updated. In this paper, the most common project cost estimation methods and approaches were collected and categorized into
two main groups of (1) probabilistic and (2) deterministic methods. Under these groups overall ten different methods were identified and
discussed addressing their requirements, advantages, and shortcomings, including the potential risk that can positively or negatively affect
the project’s cost outcome. This paper will be a good resource for professionals who are in budget development and/or are seeking to a
better understanding of different methods in determining an appropriate base cost margin and produce a meaningful and reliable project
cost estimate.
Keywords: Risk Management; Deterministic; Probabilistic; Engineering Cost Estimating; Uncertainty; Cost Estimating Methods; Urban
Drainage Infrastructure; Capital Improvement (CIP) Programs
The sources of risks and uncertainties in a project are several. 2. Accuracy of Cost Estimates
At the early stage of the project, the uncertainty in a cost
estimate increases due to the available information quantity The overall purpose of an accurate cost estimate is its use in
and quality. As the design progress, more and better establishing the budget for a project and as a tool used for
information becomes available; the uncertainty in the cost scheduling and monitoring and controlling of the project cost.
estimate is gradually reduced [38, 42-43, 49].In the The level of accuracy of engineering cost estimates increases
deterministic approach, information about uncertainties and as the project phase progresses and the potential risks are
their characteristics such as higher or lower values, ranges of identified. The earlier the estimate in the life of the project the
quantities, and potential costs cannot easily be taken into lower its accuracy consequently, assessments of conceptual
consideration even though this information is generally estimate accuracy are quite low [2, 10, 19, 45]. Figure1
Volume 8 Issue 10, October 2020
www.ijser.in
Licensed Under Creative Commons Attribution CC BY
Paper ID: 18092001 1 of 13
International Journal of Scientific Engineering and Research (IJSER)
ISSN (Online): 2347-3878
Impact Factor (2018): 5.426
below shows the Characteristic curve of accuracy vs. time to
make estimates.
Tc = � PCR P ni (2)
i
TC = � qi (Mi + Wi + Li ) + � Ij �UCj � (3)
Where: 𝐏𝐏𝐈𝐈 = parameter of independent variable of interest; i j
𝐧𝐧𝐢𝐢 = exponent used to transform𝐏𝐏𝐈𝐈
n= is the number of units (Suppose that a construction Where: 𝐓𝐓𝐂𝐂 = Total Cost; 𝐪𝐪𝐢𝐢 = quantity of work; 𝐌𝐌𝐢𝐢 = Unit
project is divided into “n” elements material cost; 𝐖𝐖𝐢𝐢 = Unit Wage rate; 𝐋𝐋𝐢𝐢 = Unit Labor Rate;𝐈𝐈𝐣𝐣
for cost estimation). = measure of work in indirect cost elements; 𝐔𝐔𝐔𝐔𝐣𝐣 = Unit cost
of in indirect elements.
The exponents ni (E.q-2) used to transform and normalize the
temporal effects of cost including an inflation, rapid increases Certainly, the detailed cost estimating is the most accurate
of material cost, and for an independent variable and other and provides insight into the major cost contributors, all cost
metrics. In general, Parametric cost estimating can also be components and make sure nothing can be overlooked [33,
incorporated with probabilistic estimating to form range 20]. However, it can also be time-consuming, and requires a
estimating that predict uncertainties and potential risks [34, lot of effort to establish especially in large and complex
39, 46, 52, 66]. Table-1 below shows the advantages and projects with numerous work breakdown structure
disadvantages of Parametric Cost Estimating Method. components [16, 22, 57]. Table-2 below shows the
advantages and disadvantages of Detailed Cost-Estimating
Table 1: Parametric Cost Estimating Method Method.
Advantage Disadvantage Requirement
Relatively quick Documentation of Cost Sufficient Table 2: Detailed Cost-Estimating Method
and accurate way Estimating Relationships historical data for Advantage Disadvantage Requirement
to estimate costs (CERs) can be difficult statistical analyses A greater level of More time needed Collaboration of
Reduced Database with confidence Very high to develop the the engineers that
likelihood of Traceability of CERs can historical data that accuracy possible estimate conduct the work
serious cost be difficult can be updated more costly to
overruns regularly All cost components develop than Work Breakdown
Reduced cost of are taken into account relationship Structure
Historical data must be
preparing project Database estimating
available
proposals Additional ‘sanity’
Multiple decision Improper use of CERs Nothing can be Historical data must
check or
options for can lead to serious overlooked be available
benchmark
project managers estimating errors Project’s scope
Model can be Parts of the estimates must be determined
used as basis for Maintenance of database can be reused and understood
uncertainty with historical data considerably
andrisk analyses Actual cost data of
Easy to combine Periodically updated to Confidence level
ongoing project can
with other capture the most current difficult to
be used as predictor
estimating cost, technical, and determine
for future
methods programmatic data.
In probability theory, variance gives a measure of how much Table 4: Confidence Level Using the Standardized Normal
the values of a function of a random variable x vary as we Distribution
sample x from a probability distribution. When the variance is Confidence Level Value of Z
low, values of f(x) cluster around its expected value. The 90% 1.28
square root of the variance is known as the standard deviation 95% 1.65
and usually indicated with the symbol σ [38, 43]. 98% 2.05
99.9% 3.09
III. Covariance
3.1.3. Probability Distributions
Covariance measures how two values are linearly related, as
well as scale of variables. Calculating correlation is an Different cost parameters coupled with several simple
important to analyze the correlation between two or more cost probability distributions are useful in many engineering cost
components that can have a large impact on the degree of risk estimation modeling and risk analysis. Normal, Lognormal,
associated with using the variance. If two random variables Beta, Triangular and Weibull are typical probability
have no correlation with covariance equal to zero they are distributions that are commonly used in the construction
called independent [11]. The covariance can be high absolute, industry [4, 11, 17, 43, 56, 60, 65-66]. Below are summary of
positive, zero or negative. High absolute values of covariance discussion together with the probability density function
means values change very much and are both far from their (PDF), the cumulative density function (CDF), the expected
mean. Positive value means both variables take relatively value (E(X)) and the variance (Var(X)) of each distributions.
high values far from mean. Negative value means one Table-5 below shows the advantages and disadvantages of
variable takes on high values & another takes low values [59, Probabilistic Cost Estimating Method.
63].
Volume 8 Issue 10, October 2020
www.ijser.in
Licensed Under Creative Commons Attribution CC BY
Paper ID: 18092001 5 of 13
International Journal of Scientific Engineering and Research (IJSER)
ISSN (Online): 2347-3878
Impact Factor (2018): 5.426
I. Uniform Distribution ⎧ 2(𝑥𝑥 − 𝑎𝑎)
⎪(𝑏𝑏 − 𝑎𝑎)(𝑚𝑚 − 𝑎𝑎) 𝑖𝑖𝑖𝑖 𝑎𝑎 ≤ 𝑥𝑥 ≤ 𝑚𝑚
The uniform distribution is a continuous probability 𝑓𝑓𝑥𝑥 (𝑥𝑥) = (21)
distribution the assumption: the random event is equally ⎨ 2(𝑏𝑏 − 𝑥𝑥)
⎪(𝑏𝑏 − 𝑎𝑎)(𝑚𝑚 − 𝑎𝑎) 𝑖𝑖𝑖𝑖 𝑚𝑚 ≤ 𝑥𝑥 ≤ 𝑏𝑏
likely in an interval. It is defined by two parameters, the ⎩
minimum possible value (a) and the maximum possible value
(b).A variable X is said to be uniformly distributed if the
density function is: The cumulative probability distribution of the triangular
distribution is given by
1
𝑓𝑓(𝑥𝑥) = �𝑏𝑏 − 𝑎𝑎 𝑓𝑓𝑓𝑓𝑓𝑓 𝑜𝑜𝑜𝑜 − ∞ < 𝑎𝑎 ≤ 𝑥𝑥 ≤ 𝑏𝑏 < ∞ (17) 𝑓𝑓𝑥𝑥 (𝑥𝑥)
0 0
⎧
⎪ (𝑥𝑥 − 𝑎𝑎)2
Figure-3, below shows the sample of the uniform distribution ⎪ 𝑖𝑖𝑖𝑖 𝑎𝑎 ≤ 𝑥𝑥 < 𝑚𝑚
(𝑏𝑏 − 𝑎𝑎)(𝑚𝑚 − 𝑎𝑎)
curve graph =
⎨ (𝑏𝑏 − 𝑥𝑥)2
⎪ 1− 𝑖𝑖𝑖𝑖 𝑚𝑚 ≤ 𝑥𝑥 < 𝑏𝑏
⎪ (𝑏𝑏 − 𝑎𝑎)(𝑏𝑏 − 𝑚𝑚)
⎩1
(22)
The expected value is given by:
𝑎𝑎 + 𝑚𝑚 + 𝑏𝑏
𝐸𝐸(𝑋𝑋) = (23)
3
𝑓𝑓 (𝑥𝑥)
In this method, it is assumed that a Triangular or Beta 1 𝛤𝛤(𝛼𝛼 − 𝛽𝛽) 𝑥𝑥 − 𝐿𝐿 𝛼𝛼−1 𝐻𝐻 − 𝑥𝑥 𝛽𝛽−1
distribution can be used to describe each item T (a, m, b). This = � � � �
𝐻𝐻 − 𝐿𝐿 𝛤𝛤(𝛼𝛼)𝛤𝛤(𝛽𝛽) 𝐻𝐻 − 𝐿𝐿
� �
𝐻𝐻 − 𝐿𝐿
� 𝐿𝐿 < 𝑥𝑥 < 𝐻𝐻
means that the user gives an optimistic estimate a, a most = 0 𝑜𝑜𝑜𝑜ℎ𝑒𝑒𝑒𝑒
likely estimate m and finally a pessimistic estimate b [5, 32,
(26)
56]. Figure-4, below shows sample of triangular distribution
The shape parameters: 𝜶𝜶 > 𝟎𝟎, 𝜷𝜷 > 𝟎𝟎Figure-5, below shows
graph.
sample of beta distribution graph.
Or, from the expected value (μ) and the distribution P (L, M, H) the parameters α and β can be derived by
Where: 𝜶𝜶 > 𝟎𝟎, 𝜷𝜷 > 𝟎𝟎; (L), lowest; (H) Highest and (M) Most likely values.
IV. Normal Distribution N (µ, σ). Here µ is its mean,𝜹𝜹𝟐𝟐 its variance, and σ is its
standard deviation [10, 12, 25]. The normal distribution is a
The normal distribution is a continuous probability continuous distribution with probability density function of:
distribution and it has two parameters, µ and σ and is denoted
1 1 𝑥𝑥−𝜋𝜋 2
𝑓𝑓𝑥𝑥 (𝑥𝑥) = 𝑒𝑒 −2� 𝜎𝜎
�
(30)
𝛿𝛿√2𝜋𝜋
𝑥𝑥
1 1 𝑥𝑥−𝜋𝜋 2
−� � � � 𝑑𝑑𝑑𝑑
𝑓𝑓𝑥𝑥 (𝑥𝑥) = 𝑃𝑃(𝑋𝑋 ≤ 𝑥𝑥) = � 𝑒𝑒 2 𝜎𝜎 (31)
−∞ 𝛿𝛿√2𝜋𝜋
1 1 𝑙𝑙𝑙𝑙 𝑥𝑥 − 𝛼𝛼 2
𝑓𝑓(𝑥𝑥) = 𝑒𝑒 �− � � � (34)
𝑥𝑥𝑥𝑥√2𝜋𝜋 2 𝛽𝛽
1
𝜇𝜇 = 𝑒𝑒 �𝛼𝛼 + 𝛽𝛽 2 � (35)
2
Figure 6: Sample of Standard Normal Distribution Graph 𝛿𝛿 = �𝑒𝑒[2𝛼𝛼 + 𝛽𝛽 2 ](𝑒𝑒[𝛽𝛽 2 ] − 1) (36)
1 𝛼𝛼 2
𝛼𝛼 = 𝑙𝑙𝑙𝑙 𝜇𝜇 − 𝑖𝑖𝑖𝑖 �� � + 1� (37)
2 𝜋𝜋
A continuous function X is said to have a Weibull From the director of the public work's point of view, the
distribution with parameters δ> 0 and β> 0 if the PDF of X expected cost of a portfolio of projects is of more interest than
is: the costs of projects cost separately. Individual projects are
considered at the mean of simulated cost distribution,
𝛽𝛽 𝑥𝑥 𝛽𝛽−1 𝑥𝑥 𝛽𝛽 typically the P50 estimate. The P50 cost value is an estimate
𝑓𝑓(𝑥𝑥) = � � 𝑒𝑒 �− � � � ,
𝛿𝛿 𝛿𝛿 𝛿𝛿 of the project cost based on a 50% probability that the cost
(43)
𝑓𝑓𝑓𝑓𝑓𝑓 𝑥𝑥 > 0, 𝑎𝑎𝑎𝑎𝑎𝑎 𝑓𝑓(𝑥𝑥) = 0, 𝑓𝑓𝑓𝑓𝑓𝑓 𝑥𝑥 will not be exceeded. The P90 value is an estimate of the
≤0 project cost based on a 90% probability that the cost will not
be exceeded. Project proponents (and their management)
Volume 8 Issue 10, October 2020
www.ijser.in
Licensed Under Creative Commons Attribution CC BY
Paper ID: 18092001 8 of 13
International Journal of Scientific Engineering and Research (IJSER)
ISSN (Online): 2347-3878
Impact Factor (2018): 5.426
often prefer to have less commercial (and political) exposure aggregating inputs. However, aggregating inputs that reflect
in respect of capital budgets and often look for a P90 figure the type of risk exposure or other logical model structures
(or equivalent if done deterministically), meaning the such as aggregation based on geographically discrete work
contingency allowance on top of the base estimate is packages may be more suitable. Costs representing the most
sufficient to ensure that there is a 90% chance that the amount likely, the best case and worst case in this example are
will not be exceeded [69]. hypothetical only.
4. Validation through Case Studies The selected typical capital improvement project
demonstrates the validity, usefulness, and benefit of the
An example of deterministic approach, range based approach different deterministic and risk-based probabilistic cost
and Risk Based – Probabilistic Approach have been prepared estimation approach. It compares the actual costs with
as an accompaniment to this journal with all formulae intact. traditional deterministic methods of cost estimation (such as
Practitioners are welcome to utilize this model for training or single-point base-case estimates inclusive of contingency)
as a template, modified as appropriate for their own and provide valuable insights that can aid management in
circumstances. evaluating alternatives and make informed decisions when
estimating and allocating budgets to a portfolio of Urban
The example uses typical capital improvement project Cost drainage system and associated drainage infrastructure
Breakdown (PCB) template structure as the basis for rehabilitation projects.
Table 6: Drainage Rehabilitation Capital Improvement Project (Base Cost Only) case study-1
A. Deterministic Approach The Square Root approach delivers one single figure which
is the sum of all base costs plus the square root of the sum of
The deterministic approach delivers a single figure that is the squares of the risk contingencies as shown below
the sum of the products of the most likely quantity
multiplied by the most likely price as shown below:
𝐂𝐂𝐂𝐂𝐂𝐂𝐂𝐂 = �� 𝐂𝐂𝐂𝐂𝐂𝐂𝐂𝐂 𝐈𝐈𝐈𝐈𝐈𝐈𝐈𝐈 (𝐦𝐦𝐦𝐦𝐦𝐦 − 𝐌𝐌𝐌𝐌𝐌𝐌)𝟐𝟐
= � 𝐌𝐌𝐌𝐌𝐌𝐌𝐌𝐌 𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥 𝐪𝐪𝐪𝐪𝐪𝐪𝐪𝐪𝐪𝐪𝐪𝐪𝐪𝐪𝐪𝐪 𝐱𝐱 𝐦𝐦𝐦𝐦𝐦𝐦𝐦𝐦 𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥 𝐩𝐩𝐩𝐩𝐩𝐩𝐩𝐩𝐩𝐩] + � 𝐌𝐌𝐌𝐌𝐌𝐌 = 𝟓𝟓𝟓𝟓, 𝟑𝟑𝟑𝟑𝟑𝟑. 𝟗𝟗𝟗𝟗 𝐔𝐔𝐔𝐔𝐔𝐔
= $ 𝟓𝟓𝟓𝟓, 𝟗𝟗𝟗𝟗𝟗𝟗. 𝟑𝟑𝟑𝟑 𝐔𝐔𝐔𝐔𝐔𝐔
B. Risk Based – Probabilistic Approach
B. Range approach with Minimum, Most Likely, and
Maximum Cost. Risk Based - Probabilistic Approach include base cost
uncertainty, the monetary impact of discrete risks as defined
Range approach with Minimum, Most Likely, and in the risk register plus escalation, as well as the monetary
Maximum Cost Approach delivers three results as the sums impact of schedule delays through extended overhead and
of the following elements: additional escalation caused by schedule delays. The
non-escalated base-cost estimate for this contract has been
= ∑ 𝐌𝐌𝐌𝐌𝐌𝐌. 𝐐𝐐 ∗ 𝐌𝐌𝐌𝐌𝐌𝐌. 𝐔𝐔𝐔𝐔 = $𝟓𝟓𝟓𝟓, 𝟕𝟕𝟕𝟕𝟕𝟕. 𝟗𝟗𝟗𝟗 𝐔𝐔𝐔𝐔𝐔𝐔 determined through the estimating process to be $57,992.36
= ∑ 𝐌𝐌𝐌𝐌𝐌𝐌𝐌𝐌 𝐋𝐋𝐋𝐋𝐋𝐋𝐋𝐋𝐋𝐋𝐋𝐋 (𝐦𝐦𝐦𝐦)𝐐𝐐 ∗ 𝐦𝐦𝐦𝐦𝐦𝐦𝐦𝐦 𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥𝐥. 𝐔𝐔𝐔𝐔 = USD. Assuming no risk or uncertainty on this value and
$𝟓𝟓𝟓𝟓, 𝟗𝟗𝟗𝟗𝟗𝟗. 𝟑𝟑𝟑𝟑 𝐔𝐔𝐔𝐔𝐔𝐔 incorporating projected escalation provides an escalated
=∑ 𝐌𝐌𝐌𝐌𝐌𝐌. 𝐐𝐐 ∗ 𝐌𝐌𝐌𝐌𝐌𝐌. 𝐔𝐔𝐔𝐔 = $𝟔𝟔𝟔𝟔, 𝟎𝟎𝟎𝟎𝟎𝟎. 𝟏𝟏𝟏𝟏 𝐔𝐔𝐔𝐔𝐔𝐔 base-cost estimate of $1,077 USD. Further incorporating
risk associated with: (i) the base cost estimate, (ii) specific
A. Square root Approach event risks and (iii) potential schedule delay provides a
risk-based estimate of total Project costs. As shown in
Volume 8 Issue 10, October 2020
www.ijser.in
Licensed Under Creative Commons Attribution CC BY
Paper ID: 18092001 9 of 13
International Journal of Scientific Engineering and Research (IJSER)
ISSN (Online): 2347-3878
Impact Factor (2018): 5.426
Figure 9, there is an 80% probability that this cost will lie (90th percentile). At the 70th percentile, the risk-based cost
between $1,075 million (10th percentile) and $1,235 million estimate is $1,188 million.
0.9
$58,000.0
0.8 $63,220.00
Probablity of Not Exceeding
0.7
0.6
0.5 $62,060.00
0.4
0.3 $58,580.00
0.2
0.1
Cost (US $)
To compare this to a traditional cost estimating approach (in allowance/contingency over the escalated base cost estimate
which allowance and/or contingency are set at fixed of $1,077 million (to ensure a level of confidence of 70
proportions of the base cost estimate), this outcome suggests percent).Figure -9 provides a graphical representation of
the Project should budget a 10.3 percent cost-risk results.
Table 7: Drainage Rehabilitation Capital Improvement Project (Base Cost Only) case study-2
Table 8: Pros and Cons of Deterministic and Probabilistic Cost Estimations Methods
Deterministic Probabilistic
Pros Cons Pros Cons
Varity of techniques may be Does not determined residual risk.
more complex, still
used including engineering Unknown risk, can be inconsistent known risk, handles areal
wide-spread
judgement, factor of safety, between sites. For areal sources, selection sources in a consistent way
misunderstanding
etc . of deterministic event is uncertain
simple to use , Doesn’t rely Needs probabilistic thinking
away from measured or interpreted data, Uses impartial statistical rules,
on statistics, Maintains & understanding Needs
Not statistical, Exhaustive cases can be run,
dependencies software support
No probability information of single All potential risks are included,
One single figure Well-known
value No Value at Risk information More best estimation assumptions,
& accepted Quick Can be Time consuming
often than not on the unsafe side (high, and follow well established
performed “manually”
unknown probability of cost overruns) methodology.
Good accuracy for similar Accuracy is limited, Cost impacting Multiple and common cause of
systems if comparative and factors have to be determined, and failures can be easily assessed Comparison factors
recent data is available Normalization required and addressed at the early stage
It should be emphasized that a forecast is only good as the [9] Ballard, G., &Pennanen, A. (2013). Conceptual
probabilistic model and the quality of data that is fed to the estimating and target costing. In Proc. 21st Ann. Conf.
model. A probabilistic analysis does not necessarily imply of the Int’l. Group for Lean Construction (pp. 31-2).
precluding the use of a deterministic analysis. In fact, [10] Bates, J., Burton, C. D. J., Creese, R. C., Hollmann, J.
deterministic analysis is often required to provide input to K., Humphreys, K. K., McDonald Jr, D. F., & Miller, C.
probabilistic analysis. The key point is that deterministic A. (2005). Cost estimate classification system–as
analyses alone can have significant disadvantages and in applied in engineering, procurement, and construction
such cases, should be complemented by probabilistic for the process industries.
analyses as is seen through the fiscal results of the case [11] Beck, J. V., & Arnold, K. J. (1977). Parameter
studies. estimation in engineering and science. James Beck.
[12] Bier, V. M. (1997). An overview of probabilistic risk
References analysis for complex engineered systems. Fundamentals
of risk analysis and risk management, 67.
[1] AACE International 2003, “Cost Estimate Classification [13] Black, J. (1984). Application of parametric estimating
System” to cost engineering. AACE transactions, B-10.
http://www.aacei.org/technical/rps/18r-97.pdf [14] Blank, L., & Tarquin, A. (2005). Engineering economy.
[2] Abou Rizk, S., & Mohamed, Y. (2002, December). McGraw-Hill.
CEPM 1: optimal construction project planning. [15] Burak Evrenosoglu, F. (2010). Modeling Historical Cost
In Proceedings of the 34th conference on Winter Data for Probabilistic Range Estimating. Cost
simulation: exploring new frontiers (pp. 1704-1708). Engineering, 52(5), 11.
Winter Simulation Conference. [16] Burns, T. J., Page, E. C., Gregory, R. A., & Pryor, G.
[3] Akintoye, A. (2000). Analysis of Factors Influencing M. (1993). U.S. Patent No. 5,189,606. Washington, DC:
Project Cost Estimating Practice. Construction U.S. Patent and Trademark Office.
Management and Economics, 18(7) 77-89 [17] Chou, J. S. (2009). Generalized linear model-based
[4] Anderson, S. D., Molenaar, K. R., & Schexnayder, C. J. expert system for estimating the cost of transportation
(2007). Guidance for cost estimation and management projects. Expert Systems with Applications, 36(3),
for highway projects during planning, programming, 4253-4267.
and preconstruction (Vol. 574). Transportation Research [18] Chou, J.-S. 2011. ‘Cost Simulation in an Item-Based
Board. Project Involving Construction Engineering and
[5] Ayyub, B. M., & McCuen, R. H. (2016). Probability, Management.’ International Journal of Project
statistics, and reliability for engineers and scientists. Management 29 (6): 709–17.
CRC press. [19] Christensen, P., & Dysert, L. R. (2003). AACE
[6] Bajaj, A., Gransberg, D. D., & Grenz, M. D. (2002). international recommended practice no. 17R-97 cost
Parametric estimating for design costs. AACE estimate classification system. AACE International,
International Transactions, ES81. USA.
[7] Bakhshi, P., & Touran, A. (2012). A Method for [20] Clark, F., & Lorenzoni, A. B. (1996). Applied cost
Calculating Cost Correlation among Construction engineering. CRC Press.
Projects in a Portfolio. International Journal of [21] Council, P. S. R. (2009). Benefit-Cost Analysis:
Architecture, Engineering and Construction, 1 (3), General Methods and Approach. The Council.
134-141. [22] Dell’Isola, M. D. (2003). Detailed cost
[8] Bakhshi, P., & Touran, A. (2014). An overview of estimating. Excerpt from Archit. Handb. Prof. Pract,
budget contingency calculation methods in construction 1-13.
industry. Procedia Engineering, 85, 52-60.