PV Commissioning Form
PV Commissioning Form
David Damiani
Renewable Energy Program Technical manager
6/8/2011
Required Form
• As of January 2011
– A new form was added to Final As Built
Package
• Form is called
– “PV Commissioning Form”
(Or equivalent form)
Purpose
• At Installation Location:
PVwatts
• Total System Estimated kWh Production
• Enter correct DC rating (system size)
• Make necessary changes to default page
– Shading percentage
– Inverter efficiency percentage
– Module power tolerance percentage
• Click “calculate”
• AC Energy (kWh) column is the estimated
production per year
Section 2
Shading
• Total System Shading %
– Conduct shading analysis (4 corners of array)
• Use program approved shading tool to establish
percentage amount of shading on site
• Solmetric
• Pathfinder
• Need to make a decision on Pathfinder software conclusions.
Section 3
String Commissioning
• Inverters
– Basic information off
nameplate
• Manufacturer
• Model #
• Serial #
• kWAC
Section 5
• Inverters (cont.)
– AC watts (on site verification)
• With inverter operational, read the output
screen showing instantaneous watts and
document
Section 5
• Inverters (cont.)
– AC volts (on site verification)
– Take a reading to verify the amount of
voltage is feeding the inverter
Section 6
• Meter
– Manufacturer
– Model
– Serial Number
– Meter Register Read kWh
– Verify that meter is ANSI c.12 compliant