SOPs-Craning and Rigging Standard
SOPs-Craning and Rigging Standard
Summary of Changes
Section
Rev No. Revision Made
Changed
1 Changed Business Units. Transferred to New Template.
Scope This standard applies to all mobile cranes, truck mounted cranes and boom trucks with a
capacity 2000 kg or more, which work for Suncor, or any of Suncor’s contractors or
subcontractors. This standard applies to lifting devices, including cranes and hoists, with a
rated load capacity of 2000 kg or more. (Overhead cranes and hoist shall be covered
under separate standards).
Purpose To ensure that craning and rigging activities involve a systematic identification of
associated loss exposures and remedial actions are established to control the risk to
people, equipment, materials, process and the environment.
To define the guidelines for proper and safe performance of craning and rigging activities
consistent with legislation, codes, best practices, procedures and work practices best
suiting Suncor Energy Inc., Oil Sands directed lease operations.
Roles and The following individuals and groups have the following roles and responsibilities:
Responsibilities
Document Approver • Ensures this standard is necessary and that it aligns with
management and company direction.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 1 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
References • CAN/CSA-Z150.98
• ASME B 30.20-2006 “Below the Hook Lifting Devices”
• LMP0018A – Refusal To Work On Grounds Of Imminent Danger
• MSS0003A – Use of Portable Frequency Communication Devices
• RGM10001 – Oil Sands and In Situ Contractor Safety Regional General Manual
• LMS0042A – Safety Requirements for Suncor Rentals Standard
The Director, 1.2 Ensures the Crane Supply Company will meet the specifications and conditions set
Materials out in Safety Requirements for Suncor Rentals or Contractor Supplied Equipment, -
Management, LMS0042A. (Reference: Occupational Health and Safety Act / Code).
Planning and
Note: Only crane companies that have been pre-qualified by Suncor Energy Inc.,
Control
Oil Sands are permitted to perform work on the Suncor site. This includes all work
directly contracted or indirectly through contractor/sub-contractor agreements.
Senior 1.3 Ensures the crane end user is aware of the relationship between the load, the rigging
Management of and crane risks as it relates to the specific job site and the individual craning and
the Business rigging responsibilities.
Units
Senior 1.4 Ensures stability of ground area is communicated to the crane end user. (Reference:
Management of Occupational Health and Safety Act / Code).
the Business
Units
Senior 1.5 Ensures the crane end user is aware of their responsibility for using only certified
Management of crane equipment and qualified personnel capable of completing the job in a safe and
the Business efficient manner, in accordance with all Suncor standards, procedures, work
Units practices, rules and applicable legislation. (See Appendix I-A to I-G).
Senior 1.6 Ensures the crane operator, site supervisor/lift coordinator, lift engineer/rigging
Management of specialist, rigger and signal person will meet their role criteria, as defined in the
the Business Construction Owners Association of Alberta (COAA) Best Practice.
Units
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 2 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Continued
Senior 1.8 Ensures all spreader bars and other lifting devices are built and certified according
Management of to the ASME Standard B30.20-2006, “Below the Hook Lifting Devices.
the Business
Units
2. Lift Classification
Note: A competent professional with involvement or input by Business Area owner must
establish the classification of a lift. Although the classification is often expressed as a
percentage of the capacity of the crane, it can also apply to lifts made in a hazardous
location, where crane configuration is non-standard, or when Plant Assets or load is
deemed critical, expensive or irreplaceable.
2.2 Ensures a critical lift team, under the direction the Lift Coordinator will be established
to evaluate critical lift hoisting operations, with continuing assistance from a crane
expert, and a Province of Alberta Certified Professional Engineer, who has been
properly trained in lift studies. (Reference: Specifications and Certifications OH&S
Code - Part 3, Section 12, Cranes, Hoists and Lifting OH&S Code – Part 6 and
Rigging OH&S Code – Part 21).
Note: The Lift Coordinator will report to Site or Area Maintenance Supervisor.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 3 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Continued
2.4 Electrical:
• Refer to Appendix V - Operating Near Electrical Power Lines and Appendix VI –
Electrical Distribution Department Standards, when any load is to be lifted within
the approach limits electrical power line while taking deflection and induction
potential of any lift into consideration.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 4 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Continued
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 5 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Item Description
3.1 The following will be considered, depending on the Lift Plan classification:
• Copies of Lift Plans and all relevant authorizations will be posted with the Safe
Work Permit.
• Lift and Hazard Assessment Processes.
• Lift Planning Processes – knowing the load, verifying the load weight,
confirming the supporting surface stability, the machine deck level, any crane
travel, daily environmental conditions, types of rigging required, dealing with
unnecessary personnel, conducting a dry run.
• Consideration of induction potential of near-by overhead power lines and
procedure for proper grounding.
• Classifications of Lifts – terminology, standards, controls (Standard, Serious,
and Critical.
• Criteria for Engineered Lifts versus Non-Engineered Lifts.
• Crane lift capability, percentage of capacity and selection matched to load.
• Operator skills and competencies selection matched to lift requirements.
• Supervision of lifts (responsibilities for ensuring compliance to lift requirements
and plans).
• Permits.
• Meetings of all types – planning meetings, pre-lift meetings, hazard assessment
meetings, etc.
• Communications – pre-lift check list, during the lift, post-lift, signaling, etc.
• Emergency planning and procedures – no lift criteria, lift veto, abort pre-planning,
lift abort, crane failure quarantine area, procedures, crane shutdown conditions
(securing the machine in high winds).
• Incident response.
• Lift Procedures – standardized checklist review process, depth dependant on lift
criteria and classification.
• Post Lift reviews will be completed.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 6 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Continued
4. Incident Reporting
Note: In general, ALL crane incidents are to be reported and investigated to determine the
root cause of the incident. The following lists, which are not all inclusive of incidents
that must be reported, are:
Item Description
4.1 Personal injuries.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 7 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Continued
4.5 Any repairs or modifications made to a crane that have not been approved by a
professional engineer or in some instances the manufacturer.
4.11 Critical lifts performed without completion of the” Critical Lift Calculation and
Approval Form” (Appendix III).
4.12 Serious lifts performed without completion of the” Serious Lift Calculation and
Approval Form” (Appendix IV).
4.13 Personnel hoisting performed without completion of the “Personnel Lifting Check
Sheet” (Appendix II A).
4.17 Operation without outriggers - except when using the on rubber chart.
4.20 Radio infringements – any interrupted radio communication during the lift.
End of Standard
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 8 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix I – A
FACILITY/SITE OWNER
Definition:
1. Person in legal possession of the work site or the person with an ownership interest in the work-site, who
requests that the work be done. Reference OH&S Act 1(i.01).
2. The facility/site owner is specifically responsible for, but not limited to:
a. Clearly define requirements, expectations, and specifications in contract documents.
b. Confirm crane owner and end users have been qualified to work on the site.
c. Require and confirm that third parties providing cranes and/or operators are in compliance with
applicable laws and regulations, including facility owner’s standards.
d. The assignment of a designated lift coordinator for all critical lifts and serious lifts.
e. Require and confirm that key personnel (lift engineer, crane operator, rigger, lift coordinator and site
supervisor) know and understand their roles and responsibilities including facility owner’s standards
and carry them out. Verification of experience and qualifications of personnel participating shall be
performed on critical lifts.
f. Ensure that a documented risk assessment is performed and identified hazards are mitigated or
controlled prior to the lift.
g. Consult with crane owner/end user to determine if any site preparation is required.
h. Determine the level of supervision to be supplied by the crane owner/end user.
i. Confirm all lifts have been planned and appropriately assessed, including emergency action plans.
j. Confirm all permits and authorizations for crane activities are issued as required
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 9 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix I – B
CRANE OWNER /SUPPLIER
Definition:
2. The crane owner/supplier is specifically responsible for, but not limited to:
a. Providing equipment capable of completing the job in a safe and efficient manner, in accordance with all
applicable legislation.
b. Ensuring that all personnel involved in maintaining, repairing, transporting, assembling and operating
the equipment are suitably trained, experienced and competent to handle their specific jobs in a safe
and efficient manner and in compliance with Alberta Occupational Health and Safety Regulations and
Code.
c. Ensuring that a thorough crane maintenance and inspection program is established and maintained
according to manufacturer’s recommendations and specifications.
d. Maintaining for examination the most recent inspection and/or certification record for each crane.
Certification to include both mechanical and hoisting components of carrier and crane as per
CAN/CSA-Z150.98
e. Certification to include both mechanical and hoisting components of carrier and crane as per
CAN/CSA-Z150.98 Safety Code on Mobile Cranes and in compliance with Alberta Occupational
Health and Safety standards and applicable ANSI /ASME Standards.
f. Providing representation to participate in the appropriate hazard assessment prior to conducting the
lift.
g. Ensure that all spreader bars and other lifting devices are built and certified in accordance with the
standards laid out in ASME B 30.20-2006, “Below the Hook Lifting Devices”.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 10 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix I – C
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 11 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
n. Ensure that a secure means of communication is established. If radio communications is used, there
must be dedicated channels with no possibility of interference. See LMS0066A – Use of Portable
Frequency Communication Devices.
o. Ensuring that the crane and associated equipment are in a safe, operable condition supported by
applicable certification in accordance with the manufacturer’s requirements, legislation and applicable
ANSI / ASME Standards. This includes that a thorough crane and rigging maintenance and inspection
program is established and maintained with log books kept up to date.
p. Ensure crane owner/supplier has met the equipment certifications as detailed above as well as those
outlined in LMS0042A.
q. Ensure that associated lift equipment (Spreaders bars, Containers, Slings etc.) are designed and
certified for particular purpose and bears marking to indicate its maximum load rating as per OH&S
Code and in compliance with ASME B 30.20-2006, “Below the Hook Lifting Devices”.
r. Ensure that a periodic inspection and testing of rigging components are completed and recorded as
per appropriate Standards, Codes, Specifications and Procedures.
Ensure storage and use of rigging components are as per manufacturer’s specifications.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 12 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix I – D
CRANE OPERATOR
Definition:
1. The crane operator is responsible for the safety of the crane operation. If there is reasonable
cause to believe the lift might be dangerous or unsafe, the operator must refuse to lift until the
concern(s) have been reported to the supervisor, any hazards rectified and safety conditions
assured.
2. The crane operator is specifically responsible for, but not limited to:
a. Knowing the machine functional capability, limitations and its particular operating characteristics.
b. Creation of lift plans for Serious and Personnel Lifts in concert with the Lift Coordinator.
c. Participate in the appropriate hazard assessment prior to conducting the lift.
d. Being totally familiar with the information contained in the crane’s operating manual and to understand
the crane’s limitations, including any attachments.
e. Proper set up of the crane as per the manufacturer's specifications, "Best Practice" and site rules.
f. Being totally familiar with the crane’s load chart. The operator must understand the correct meaning of
all notes and warnings and be able to calculate or determine the cranes actual net capacity for every
configuration of the machine.
g. Inspecting and maintaining the crane regularly as prescribed by the owner and manufacturer. Confirm
operating aids and safety devices are operational, i.e. load movement indicator, etc.
h. In the event that a crane must be left unattended within an operating process area where mechanical
failure of any type might permit any component of the crane to come into contact with area process
equipment, the crane end user must obtain written authorization from the area’s Operations Manager
or their designate. As per Appendix VIII
i. Informing the owner of any problem needed maintenance or necessary repairs to the machine. This
should be done in writing, preferably in the machine’s log book or inspection report.
j. Recording in the log or report the details of all inspections, maintenance and work done on the crane
while in the field. In the case of the mechanic servicing or repairing, it is his/her responsibility to make
entries in the Crane Logbook.
k. Being aware of any site conditions that could affect the crane operation such as, underground pipe-
ways, culverts and particularly around power lines and weather. The operator must refuse to operate
if the crane, hoist rope or load will come closer to a power line than the absolute limit of approach
specified by Alberta OH&S code.
l. Checking the site is adequately prepared for the crane (e.g. hazards identified, base level and
compaction tests). Confirming the ground beneath the crane can support the loads imposed by the
crane and any attachments. Ground assessment should include an evaluation, which takes into
account the load point that could occur over any outrigger or track that can accommodate the bearing
ability of the maximum weight expectation as well as induction potential from high voltage lines in
proximity.
m. Access roads are adequately prepared.
n. Reviewing the planned operation and requirements with the site supervision/ lift coordinator
o. Finding out the load and rigging weight and determining where the load is to be placed. Although the
operator is not responsible for determining the weight of the load, if the operator lifts it without
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 13 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
checking the weight with site supervision, then the operator becomes totally responsible for the lift
and any consequences that come from it.
p. Determining the number of parts of hoist line required.
q. Checking the load chart to ensure the crane has sufficient load capacity for every lift.
r. When not provided with a critical or serious lift plan, selecting (from the crane capacity charts and
manufacturer’s notes and warnings) the best boom, jib and crane configuration to meet lift
requirements (suit the load, site and lift conditions) and determine the net lifting capacity of this
configuration.
s. Assembling, setting up and rigging the crane (including attachments) properly in accordance with
manufacturer’s specifications.
t. Following the manufacturer’s operating instructions in accordance with the load chart.
u. Considering all factors that might reduce crane capacity and adjusting the load weight to suit.
v. Knowing load rigging procedures and ensuring that they are applied - when the load is visible to the
operator.
w. Maintaining a secure communication process with signal persons.
x. Assess weather conditions at time of lift to confirm lift can safely proceed.
y. Complete a “Serious Lift Calculation and Approval Form” for each serious lift (refer to Appendix IV for
a sample form).
z. Moving the crane around the work-site either with or without a suspended load.
aa. Vehicle entry authorizations for restricted work areas are to be obtained from the respective permit
centre prior to work commencing.
bb. Shutting down and securing the machine properly when it is unattended – this will include the heater
in a restricted hot work area where there is potential ignition hazard.
cc. Ensuring loads are not lifted over workers unless the workers have been warned of the dangers in
accordance with OH&S Code.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 14 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix I – E
SITE SUPERVISOR/LIFT COORDINATOR
Definition:
1. Person in charge of the lift is the person representing the crane end user at the lift site that has the
ultimate responsibility for the safe and effective execution of the lift.
2. Site supervisor/lift coordinator is acting on behalf of the crane end user and has overall responsibility for the
lift and therefore must plan all phases of the operation. This includes complete cooperation with the operator
who has the final say regarding the lift occurring.
3. The site supervisor/lift coordinator:
a. Is part of the Lift Assessment Team that determines the classification of lift.
b. Ensures appropriate lift plan for the classification of lift.
c. Participates in the development of lift plans for all Serious and Critical Lifts.
d. Participate in the appropriate hazard assessment prior to conducting the lift.
e. Ensures appropriate personnel review lift plans.
4. Site supervisor/lift coordinator is specifically responsible for site preparation - “Providing a well prepared
working area for the crane before it arrives, so the job can be done safely”. Site preparation may include, but
is not limited to the following:
a. Cranes are currently certified with all known deficiencies corrected.
b. Confirming the ground beneath the crane can support the loads imposed by the crane and any
attachments. Ground assessment should include an evaluation, which takes into account the load
point that could occur over any outrigger or track that can accommodate the bearing ability of the
maximum weight expectation.
c. Access roads are adequately prepared.
d. Adequate space is provided to safely assemble, erect, and/or extend the boom and operate the crane,
as well as materials such as timber mats, cribbing and blocks.
e. Blocking will be used to support the boom while it is being assembled and dismantled.
f. Operating locations are graded, level and compacted.
g. Suitable pads are used under outriggers, as required.
h. Operating locations are chosen so that the minimum clearances from power lines are maintained. If not,
the power lines must be shut down, relocated or specifically insulated by the utility. (contact Suncor
Electrical Distribution Department)
i. Appropriate grounding or bonding is provided to mitigate the induction potential from high voltage power
lines in the proximity of the lift.
j. Operating locations are far enough away from shoring, excavations, trenches, buried utilities,
foundations, etc., to eliminate risk of collapse.
k. Appropriate banner guard or barricades are positioned to prevent entry into restricted areas around the
crane including the swing area, thus limiting access to authorized personnel.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 15 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 16 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix I – F
LIFT ENGINEER/RIGGING SPECIALIST
Definition:
1. A person who is a Professional Engineer (as defined by the Occupational Health and Safety Code) and/or
deemed by the employer to be appropriately trained in the preparation and development of lifting studies.
2. The requirement for using the expertise of a lift engineer/rigging specialist will be determined by the site
owner and crane end users based on the specifics of the lift to be done.
3. The lift engineer/rigging specialist is specifically responsible for, but not limited to:
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 17 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
i. Verify all “Below the Hook Lifting Devices” are built and certified according to the
standards laid out in ASME B 30.20-2006.
3.2.3 Communicate the Lift
a. Issue drawings, plans and specifications to the people who will make the lift.
b. Review, discuss and revise as required with the people who will make the lift.
3.2.4 Planning
a. Review drawings and/or site information to verify access and clearances; identify
obstructions; and eliminate interference with respect to the lift.
b. Verify lift lug information, both head and tail if required.
c. Verify crane charts, boom length, and accessories required.
3.2.5 Design
a. Plan how the crane(s) will physically make the lift.
b. Specify the rigging, sling diameter, length and quantity.
c. Select shackle size, clearance and quantity.
d. Select and detail any new items required.
e. Prepare sketches/drawings.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 18 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix I – G
RIGGER
Definition:
1. A competent worker designated as the rigger. Note: The degree of competency and responsibilities for
the rigger must meet and be consistent with the complexity of the lift to be performed.
2. The rigger is specifically responsible for, but not limited to:
a. Rig loads and equipment to the manufacturer’s recommendations.
b. Interpret the sling and hardware charts and lift plans.
c. Identify appropriate rigging components for the load to be lifted.
d. Visually inspect rigging components on a regular basis and prior to each lift to ensure compliance with
appropriate ANSI /ASME Standards, Codes, Specifications and Procedures.
e. Know and understand the general operating parameters of cranes.
f. Participate in the appropriate hazard assessment prior to conducting the lift.
g. Be capable of identifying different rigging components and to be knowledgeable in their proper application.
o Capable of performing inspections of applicable rigging components to ensure they are in an adequate
condition to perform the lifting tasks.
o Able to produce documentation showing hours of training accomplished in understanding and applying
principles and components.
o Knowledgeable of the different sling configurations available and know which to use on different load
applications.
o Knowledgeable of the weight of the load to be lifted.
o Knowledgeable and capable of using the hand signal chart for hoisting and moving loads.
o Giving all signals in a slow, smooth and decisive manner.
o Aware of overhead hazards and obstructions. Be aware that the swing path must be kept clear of
vehicular and pedestrian traffic.
o Aware that the load should never be brought over the top of people.
o Communicate with the crane operator throughout all stages of the rigging process
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 19 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 20 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
respect to the platform floor. The intermediate rail shall be positioned at an equal distance
between the toe board and the top rail. The toe board shall be around the periphery of the
platform and shall be a minimum of 90 mm (3.5 in) in height. The lower barrier shall span the
distance between the toe board and intermediate rail and be of solid construction or expanded
metal;
q. have continuous hand or grab rail inside the perimeter of the suspended platform;
r. have flooring with a slip-resistant surface, with provision to allow free drainage of liquids;
s. have means of securing loose items with the platform; and
t. If built with an access gate, be equipped with an acting device to restrain the gate from
accidental opening. When provided, access gates shall swing into the platform.
u. Shall be recertified by a professional engineer annually and records maintained and available by
equipment owner.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 21 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
• Suspended by the primary support, lift the personnel platform 1 m off the ground to verify the
integrity of the primary support; and
• Suspended by the primary support, lift the personnel platform to all work locations to verify the lift
routes and that these work locations can be reached by the crane using a maximum of 50% of
the crane’s capacity. If the lift area is congested, the personnel platform may be lifted an equal or
greater radius in the same quadrant of crane capacity to verify ground support and stability of the
crane.
Note: Trial and load test need not be repeated for continuous use, providing crane positioning has
not changed and personal platform has not been disconnected. Personal platforms for use in
emergency evacuation situations must be pre planned and separately assessed.
• General
The platform that the worker is on shall:
• Be capable of supporting, without failure, its own weight and at least five times the rated
load of the platform; with a minimum carrying capacity of 136 kg (300 lb.);
• Be designed and approved by a professional engineer;
• Have a design safety factor of not more than 50% of yield strength for ductile materials, or
20% of ultimate strength for brittle materials that do not have clearly defined yield strength
for static loading. Where the platform is subjected to dynamic loading, this loading shall be
included;
• Have design drawings that set out the size and specifications of all components of the
platform, including the type and grade of materials used for it, the rated load of the platform,
and instructions for the proper maintenance of the platform;
• Be designed to prevent overturning;
• Be constructed and maintained in accordance with the design drawings;
• Have all weldments conforming to CSA Standard W59 or ANSI/AWS D14.3. Similar
standards or procedures are acceptable, providing the welding process meets or exceeds
the criteria of CSA Standard W59 or ANSI/AWS D14.3;
• Have its weight and rated load conspicuously posted on a plate or by other means of
permanent marking;
• Be modified or repaired in accordance with the manufacturer’s specifications or as directed
by a professional engineer;
• Be equipped with means of self-leveling the platform and guarded against overturning;
have the basket be not less than 990 mm (39 in) nor more than 1140 mm (45 in) in height
with respect to the platform floor;
• Have a barrier that spans the full distance between the floor to rail and is of solid
construction or expanded metal; and
• Be equipped with slip-resistant flooring, with provisions to allow free drainage of liquids.
• Shall be recertified by a professional engineer annually and records maintained and
available by equipment owner.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 22 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
1.6.6 Inspection
Cranes used for personnel lifting shall follow Suncor Standards and CSA-Z150-98-CAN/CSA
Safety code on mobile cranes requirements.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 23 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
1.6.8 Responsibilities
The supervisor/employer in charge of the operation shall:
• Ensure that an adequate means of communication between the worker on the platform and
the crane operator is established, maintained, and used;
• Ensure that sufficient lighting for the job is provided;
• Conduct a pre-lift meeting to ensure that every worker involved with the hoisting operation
receives adequate instructions about the requirements, restrictions, and hazards associated with
the hoisting operation; and
• Develop adequate means of evacuation or rescue procedures and communicate these in writing
to all workers involved with the hoisting operation. Completion of Personnel Lifting Check sheet
(see Appendix II-A).
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 24 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix II – A – Personnel Lifting Check Sheet – Form OS-0106 Rev 2/04 must be ordered from the Print
Room by phoning 743-6420 or Daily Tools/Forms on Intranet.
O IL S AN D S
COMMENTS:
_____________________________________________________________________________________
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 25 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 26 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix II B – (Continued)
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 27 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix III – CRITICAL LIFT AUTHORIZATION FORM – Page 1 of 2 OSG-0012.1 Rev 7/04. Forms must be
ordered from the Print Room by phoning 6420 or see Daily Tools/Forms on Intranet
O IL S AN D S
Comments:
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 28 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
LMS0039A - APPENDIX III - CRITICAL LIFT AUTHORIZATION FORM – Page 2 of 2 OSG-0012.1 Rev 7/04. Forms
must be ordered from the Print Room by phoning 743-6420 or see Daily Tools/Forms on Intranet
O IL S AN D S
Environmental Controls:
Will the weather conditions, (e.g. wind speed and direction, temperature, rain, lightning and air pollution etc.), be a
factor as per original equipment manufacturer's (OEM) specifications, applicable legislation, industrial codes and
practices, and Suncor standards, procedures, safe work practices or rules?
____________________________________________________________________
Has the crane capacity been reduced as per risk for cold weather? No Yes
Has the potential for induced voltage from surrounding high voltage power lines been taken into consideration?
No Yes
What are the most critical aspects of this lift?
___________________________________________________________________________________
___________________________________________________________________________________
Nothing in this submission and/or acceptance of this authorization is to be considered as relieving the
contractor of any responsibility for a safe operation.
Approvals Print Name Signature Date
Area Manager, Ops.
Area Manager, Mtce.
Contractor or Supervisor
Lift Coordinator
Lift Plan Engineer
Review Engineer
Date of Lift: _______________________________ Time Lift Started:__________________________
Total Time: ______________________________
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 29 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
LMS0039A - APPENDIX IV – SERIOUS LIFT CALCULATION AND APPROVAL FORM – Page 1 of 1 OSG-
0084 Rev 2/04 - Forms must be ordered from the Print Room by phoning 743-6420 or see Daily Tools/Forms on
Intranet.
O IL S AN D S
NOTE: Completion of these Serious Lift Calculation and Approval Forms is mandatory and appropriate approval signatures must be in place
before serious lifts are performed. Completion must conform to the conditions of the Suncor Crane Standard and Crane charts.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 30 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Note: When a crane is operated near a source such as a radio transmitter or energized high-voltage electrical
equipment that may induce an electric charge, there may be a hazard to workers. As a precaution, the crane
should be effectively grounded. Any induced electric charge on the load should be dissipated by applying
grounding cables or other effective means before workers contact the load, and all flammable materials should be
removed from the immediate work area.
The safe limit of approach distances listed above do not apply to a load, equipment or building that is
transported under energized overhead power lines if the total height, including equipment transporting, is less
than 4.15 metres.
1. Except where the electrical distribution and transmission lines have been de-energized and visibly
grounded at the point of work, or where insulating barriers not a part of, or an attachment to, the crane
have been erected to prevent physical contact with the lines, cranes shall operate so that no part of the
crane or load enters into the minimum safe distance shown in Table 3.
2. When operating, no part of any crane or its load shall be permitted to approach closer to any power line
than the distance specified in schedule 4, unless the electrical authority has been notified and the line
de-energized or insulated.
3. In the event of induced voltage from surrounding high voltage power lines,
• The crane or hoist must be effectively grounded or bonded to a solidly grounded structure;
• Any induced electric charge on the load must be dissipated by applying grounding cables or by other
effective means before workers contact the load.
4. It shall be the responsibility of the user controlling the crane to
• provide an competent signal person;
1 Conductors must be insulated or covered throughout their entire length to comply with the group.
2 Conductors must be manufactured to rated and tested insulation levels.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 31 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
• provide adequate advance notification to the electrical authority to allow for insulation or isolation and
grounding of the line or lines;
• ensure that the electrical authorities are fully informed as to when the operations are to begin, when
they are due to be completed, and when any location changes are planned;
• Ensure that whenever cranes must be repeatedly travel beneath power lines a route is plainly marked, and
“rider poles” are erected on each side of the crossing approach to ensure that the crane structure is
lowered to a safe position. The routes shall be located as close to the power line support tower or pole as
possible in order to take advantage of the greater ground clearance;
• measure for induced voltage and sufficiently ground the crane;
• ensure that if a crane will be working in a relatively fixed location near electrical hazards, it is electrically
grounded with a ground rod, permanent grounding bus, or ground mat;
Note: Grounding instruments should be placed as close to the machine as possible. The ground lead
should first be connected to the grounding instrument and then to the machine. All personnel must be
instructed to stay clear of both the lead and rod at all times. When removing the ground, the lead
should first be disconnected from the machine. If a ground mat is used, the equipment must be placed
on the mat and bonded to it. The ground mat area should be enclosed with a fence to prevent
personnel from stepping on and off the mat during operation of the machine. For grounding instruments
requiring ground penetration refer to LMS0059A Ground Disturbance.
• Report every incident involving contact with a live line to the electrical authority and safety inspector, so
that inspections and repairs can be made to prevent damaged live lines from falling at a later date; and not
use the crane until it has been completely inspected by a competent person for possible damage caused
by electrical contact.
5. In the event that the crane or load makes contact with an energized circuit, the operator shall, if feasible:
• Remain inside the cab;
• Instruct all other personnel to keep away from the machine, rope, and load;
• Try, unaided, and without anyone approaching the machine, to back off the crane until it is well clear of the
power line; and
• If the machine cannot be self-propelled away or disentangled from the line, remain inside the machine until
the electrical authorities de-energize the circuit and confirm that conditions are safe.
Notes:
• If the operator decides to leave the machine, he or she shall not, under any circumstances,
step down, allowing part of his or her body to be in contact with the ground while any other
part is touching the machine.
• Because there may be a hazardous voltage differential on the ground, the operator should
jump with feet together, maintain balance, and shuffle slowly across the affected area.
6. Caution shall be exercised when working near overhead lines having long spans, since they tend to swing
laterally in response to the wind and present a contact hazard.
7. Cage-type boom guards, insulating links, and proximity-warning devices have limitations, and their
use does not alter the requirements of Clauses 1 to 6.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 32 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
UOS0049A - Addition or Removal of Conductors (All Sizes / All Voltages) on the EDD System
Alberta Occupational Health and Safety Code, Part 17 – Overhead Power lines
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 33 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
The following are recommendations on cold weather operating procedures representing industry best practices.
Refer to Crane Manufacturers guidelines per specific equipment on cold weather lifting restrictions.
• At temperatures colder than -15°C all possible precautions shall be taken to avoid impact or shock loading on
cranes and rigging.
• Operations involving hydraulic cranes should be conducted with due regard to potential failure of hydraulic
components.
o o
• In cold weather operation between –15 C and –30 C, cranes should be de-rated as per manufacturer
specifications or by 25% if not specified.
o
• All rigging hardware and crane hooks for use at -25 C and below must be free of all nicks, gouges or notches.
o o
• Between –30 C and –40 C, cranes should be de-rated by 40% for all lifts and consideration given to stopping all
lifting activities.
o
• Lifting at temperatures below –40 C is not recommended except in the case of an emergency, unless the cranes
and rigging are specially engineered for cold weather operation. Efficiency and safety of personnel is a prime
consideration in extreme cold and wind chill conditions.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 34 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 35 of 36
Subject: Craning and Rigging Standard Number: MSS0012A Rev: 1
Appendix IX – Rigging
Pull Tests:
• An employer must ensure that slings at a worksite are not subjected to pull tests beyond 100 percent of their
rated load capacity other than the proof testing done at time of manufacture.
• Pull tests in excess of 1 to 1 may only be performed by the sling manufacturer or his designate in order to
maintain responsibility and accountability.
• Pull tests for site safety requirements must not exceed 1 to 1.
• Slings do not require re-certification unless damaged and repaired.
• If repaired, the sling may then be pulled to 2 to 1 by the manufacturer or his designate for purposes of re-
certification.
• All slings shall be appropriately tagged with the type of construction, safe working load, serial number and
material of construction
• All Rigging, previously used in offshore applications, shall not be used on Suncor sites.
Winch Line End Connections:
• Any winch, tugger or running line shall not be operated unless a proper, engineered end connection device
such as a socket and wedge, cable clamps, swaged, plug, spelter or resin socket is used. Under no
circumstances may a winch, tugger or running line be operated with a knot tied in the end of the line for the
purpose of attachment to the hook.
ASME Hoisting Safety Factors:
• Hooks, slings, spreader bars, shackles and all other hardware below the hoist ropes, boom point or bridge of
the crane - 5 to 1
• Hoist ropes (running lines on cranes) 3.5 to 1
• Hoist ropes (running lines on cranes) 3.5 to 1
• Hoist ropes (non-rotating) 5 to 1
• Personnel Hoisting 0 to 1
• Tugger lines and blocks (hoisting) 5 to 1
• Tugger lines and blocks (pulling) 3 to 1
• Pendant lines and guy lines 3 to 1
Hook Standards:
The following standard must be followed to ensure loads on hooks will not exceed 20% of ultimate breaking
strength.
• Hooks must be taken out of service if any indication of spreading or twisting of the hook is evident.
• No more than two slings shall be placed on a hook. More than two slings must be attached to a shackle and
the shackle shall be placed on the hook.
• Slings must be placed at angles of 60° or greater unless the hook is marked with 45° angles.
• Hooks must receive a periodic visual inspection for cracks, nicks or gouges as per the requirements of ASME
B30.10.
• Remove from service any hook with a crack, nick or gouge. Deformations may be dressed out with a file or
grinder provided manufacturer specifications are followed.
• Hooks used on multi sling bridles should be equipped with locking, load rated safety latches of the type
sometimes referred to as “Shur-Lok”.
• Hooks used with pulsating or frequent load cycles such as on a Vibro-hammer, shall be subject to periodic
non-destructive inspection such as magnetic particle or dye penetrant.
• Hooks must not be repaired, altered or re-shaped by heating, welding or bending.
• Hooks must be equipped with a properly functioning safety device that will prevent slings from being dislodged.
• Hook manufacturer “Best Practice” requires not less than 80% of shackle pins to bear the loads imposed by lift lugs.
• Hooks must never be side loaded, back loaded or tip loaded.
• Safety latches must not be distorted or bent and must not be placed under any load whatsoever.
D/d Ratio
Employers must ensure that all rigging used employs the D/d Ratio required by the manufacturer to ensure safe
usage and proper application. If workers do not employ special shackles and hooks with and increased D/d Ratio
(of a type sometimes known as “Sling Saver”) are used, the rigger must either oversize shackles and hooks or de-
rate slings 15%.
WARNING - Uncontrolled when printed. The current revision of this document is available in LiveLink.
Approved By: Christina Ellerbeck, Director, Maintenance Support Services
Page 36 of 36
The following individuals have approved and signed this document.