Roject Anagement Rofessional: Dr. Ahmed Hassan, PGMP, PMP, RMP, Pba
Roject Anagement Rofessional: Dr. Ahmed Hassan, PGMP, PMP, RMP, Pba
PMP
Project Cost Management
Determine Budget
Project budget
Control Costs
Presented by:
2 24 10 12 1
187
TAILORING CONSIDERATIONS
Project Cost Management processes are applied. Considerations for
tailoring include :
• Knowledge management.
• Estimating and budgeting.
• Earned value management.
• Use of agile approach.
• Governance.
MONITORING
& CONTROLLING
PLANNING
$
188
01 PROJECT CHARTER
02
PROJECT MANAGEMENT PLAN
01 Expert judgment
02
Data Analysis
03 Meetings
191
01
Cost management plan
Describes how the project costs will be planned, structured, and
controlled.
• Units of measure.
• Level of precision. rounded up or down.
• Level of accuracy. The acceptable range (e.g., ±10%).
• Organizational procedures links. Each control account is
assigned a unique code or account number(s) that links
directly to the performing organization’s accounting system.
• Control thresholds. the percentage deviations from the
baseline plan.
• Rules of performance measurement. EVM rules
• Reporting formats. The formats and frequency for cost
reports.
192
02
PROJECT DOCUMENTS
03
ENTERPRISE ENVIRONMENTAL FACTORS
04
ORGANIZATIONAL PROCESS ASSETS
194
01 Expert Judgment
02 Analogous Estimating
03 Parametric Estimating
04
Bottom-up Estimating
05
Three-point Estimating
$
06 PMIS
07 Decision Making
08 Data Analysis
Alternatives Analysis - Reserve Analysis - Cost Of Quality.
195
02 BASIS OF ESTIMATES
should provide a clear and complete understanding of how the cost estimate
was derived.
01 EXPERT JUDGMENT
02 COST AGGREGATION
The work package cost estimates are then aggregated for the
higher component levels of the WBS (such as control accounts)
and, ultimately, for the entire project.
03
04
DATA ANALYSIS
PROJECT BUDGET.
6. Management Reserves
Project Budget.
5. Control Accounts
4. Contingency Reserve
01
COST BASELINE
It is the approved version of the project budget, excluding any
management reserves, Can only be changed through formal change
control procedures.
02 PROJECT FUNDING REQUIREMENTS
Total funding requirements and periodic funding requirements (e.g.,
quarterly, annually) are derived from the cost baseline.
Total funds required are those included in the cost baseline plus
management reserves
03 PROJECT DOCUMENTS UPDATES
Cost estimates - Project schedule - Risk register
202
Project budget.
203
Project budget.
$
204
01
Project management plan
• Cost management plan
• Cost baseline
• Performance measurement baseline
02 Project documents
• Lessons learned register
01 EXPERT JUDGMENT
02
DATA ANALYSIS
Earned value analysis (EVA). compares the performance measurement baseline to
the actual schedule and cost performance.
Planned value (PV) :The Budgeted Cost of Work Scheduled so far at a specific
date.
Earned value (EV) :Budgeted Cost of Work Performed.
Actual cost (AC) :The total expenditure for the work so far at a specific date.
Schedule variance (SV) : SV = EV – PV
Positive = Ahead of Schedule / 0 = On schedule / Negative = Behind Schedule
Cost variance (CV) : CV = EV – AC
Positive = Under Budget / 0 = On Budget / Negative = Over Budget
207
The cost variance at the end of the project will be the difference between the budget
at completion (BAC) and the actual amount spent.
VAC = BAC – EAC
$
208
$
Example : Required: PV, EV, AC, SV, CV, SPI, CVI
Cost/Unit Quantity
Budget 1,000 120
Actual 1,200 130
Forecasting. the project team may develop a forecast (EAC) that may differ from
the budget at completion (BAC) based on the project performance
1. If the CPI is expected to be the same for the remainder of the project,
EAC = BAC/CPI
4.If both the CPI and SPI influence the remaining work,
EAC = AC + [(BAC – EV)/(CPI x SPI)]
$
210
03
TO-COMPLETE PERFORMANCE INDEX
A measure of the cost performance that must be achieved with the remaining resources
in order to meet a specified management goal,
• The efficiency that must be maintained in order to complete on plan.
TCPI = (BAC – EV)/(BAC – AC)
• The efficiency that must be maintained in order to complete the current EAC.
TCPI = (BAC – EV)/(EAC – AC)
TCPI > 1.0 Harder to complete
TCPI = 1.0 Same to complete
TCPI <1 .0 Easier to complete
04 PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)
$
Exercise
Earned Value Management
Assume 4 equal sides, budget 200$ per side, schedule 1 side per day. Finish
4 days & cost 800$.
• Day1: side 1 complete, budget of 200$ spent.
• Day2: side 2 started but not complete, Incurred cost will be 220$
• Day3: side 2 completed, and half of side 3 completed but team left
early and only spent 140$
Where we are now? Ahead or Behind
$
EVM Example:
Exercise
Earned Value Management
• Project of Highway Paving 100 Km; for each 10 Km we need a month with cost
100 k$, total project budget is 1 million and duration 10 Month.
• MONTH1: 10 km complete, budget of 90k spent.
• MONTH2: 15 km complete, budget of 150k spent.
• MONTH3: 15 km complete, budget of 110k spent.
• MONTH4: 10 km complete, budget of 100k spent.
215
Answer
02 Cost forecasts
03 Change requests
04
Project management plan updates
• Cost management plan
• Cost baseline
• Performance measurement baseline
05
Project documents updates
• Assumption log
• Basis of estimates
• Cost estimates
• Lessons learned register
• Risk register
Project Management Professional
(Thanks)
Presented by: