Progress Report Bollard

The weekly progress report provides updates on the fabrication of bollards and barriers for a project. Material intake is 60% complete while fabrication is 10% finished. Photos document the arrival of materials and ongoing fabrication work from July 22nd to 31st.

Uploaded by

edn_mj1645
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views

Progress Report Bollard

The weekly progress report provides updates on the fabrication of bollards and barriers for a project. Material intake is 60% complete while fabrication is 10% finished. Photos document the arrival of materials and ongoing fabrication work from July 22nd to 31st.

Uploaded by

edn_mj1645
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

WEEKLY PROGRESS REPORT

period Up to 31 Juli 2021

Project : BOLLARD & BARRIER


Client : PT. TAKENAKA INDONESIA

No Description Qty Weight (kg) % Actual Progress Progress Value progress


Mat.proc Fabrication Painting Delivery Last Week Current Cumm Last Week Current Cumm
VMS KANTILEVER FRAME
A Material Incoming (60%) 60% 60% 36% 25% 15.0% 10% 6.0% 5% 3.00% 0% 35% 35% 0% 21.0% 21.0%
B Fabrication (25%)
Bulk Unloading
Safety Bollard 8" 6 175.0 1050.0 3.4% 60% 2.0% 25% 0.9% 10% 0.3% 5% 0.17% 0% 10% 10% 0% 0.3% 0.3%
Safety Bollard 4" 18 16.0 288.0 0.9% 60% 0.6% 25% 0.2% 10% 0.1% 5% 0.05% 0% 10% 10% 0% 0.1% 0.1%

Starch Warehouse
Edge Protection EP-1 20 38.8 775.0 2.5% 60% 1.5% 25% 0.6% 10% 0.3% 5% 0.13% 0% 0% 0% 0% 0.0% 0.0%
Edge Protection EP-2 1 21.0 21.0 0.1% 60% 0.0% 25% 0.0% 10% 0.0% 5% 0.00% 0% 0% 0% 0% 0.0% 0.0%
Edge Protection EP-3 3 38.1 114.4 0.4% 60% 0.2% 25% 0.1% 10% 0.0% 5% 0.02% 0% 0% 0% 0% 0.0% 0.0%
Bollard Protection BP-1 12 14.0 168.0 0.5% 60% 0.3% 25% 0.1% 10% 0.1% 5% 0.03% 0% 0% 0% 0% 0.0% 0.0%
Barrier B-1 1 136.7 136.7 0.4% 60% 0.3% 25% 0.1% 10% 0.0% 5% 0.02% 0% 0% 0% 0% 0.0% 0.0%
Barrier B-2 1 152.3 152.3 0.5% 60% 0.3% 25% 0.1% 10% 0.0% 5% 0.02% 0% 0% 0% 0% 0.0% 0.0%
Barrier Pedestrian BP-1 44 97.5 4290.0 14.0% 60% 8.4% 25% 3.5% 10% 1.4% 5% 0.70% 0% 0% 0% 0% 0.0% 0.0%
Door Barrier DB-1 1 185 185 0.6% 60% 0.4% 25% 0.2% 10% 0.1% 5% 0.03% 0% 0% 0% 0% 0.0% 0.0%
Door Barrier DB-3 1 257 257 0.8% 60% 0.5% 25% 0.2% 10% 0.1% 5% 0.04% 0% 0% 0% 0% 0.0% 0.0%
Door Barrier DB-3 1 119 119 0.4% 60% 0.2% 25% 0.1% 10% 0.0% 5% 0.02% 0% 0% 0% 0% 0.0% 0.0%
Door Barrier DB-4 1 128.5 128.5 0.4% 60% 0.3% 25% 0.1% 10% 0.0% 5% 0.02% 0% 0% 0% 0% 0.0% 0.0%

C Painting (10%) 10% 60% 6.0% 25% 2.5% 10% 1.0% 5% 0.50% 0% 0% 0% 0% 0.0% 0.0%
D Delivery (5%) 5% 60% 3.0% 25% 1.3% 10% 0.5% 5% 0.25% 0% 0% 0% 0% 0.0% 0.0%

7684.9 100.0% 21.4% 21.4%

Prepared By

PT. PBR
PHOTO WEEKLY PROGRESS
FABRICATION VMS WEEK-01

Scope of Work : Engineering, Supply Period : 22 Jul 2021 to 31 Jul 2021


Fabricator : PT. Pasrat Bumi Raya Location : Meiko Abadi V-Sidoarjo

Material Incoming
PHOTO WEEKLY PROGRESS
FABRICATION VMS WEEK-01

Scope of Work : Engineering, Supply Period : 22 Jul 2021 to 31 Jul 2021


Fabricator : PT. Pasrat Bumi Raya Location : Meiko Abadi V-Sidoarjo

Fabrication Progress 26/07/2021


PHOTO WEEKLY PROGRESS
FABRICATION VMS WEEK-01

Scope of Work : Engineering, Supply Period : 22 Jul 2021 to 31 Jul 2021


Fabricator : PT. Pasrat Bumi Raya Location : Meiko Abadi V-Sidoarjo

Fabrication Progress 27/07/2021

Fabrication Progress 28/07/2021


PHOTO WEEKLY PROGRESS
FABRICATION VMS WEEK-01

Scope of Work : Engineering, Supply Period : 22 Jul 2021 to 31 Jul 2021


Fabricator : PT. Pasrat Bumi Raya Location : Meiko Abadi V-Sidoarjo
PHOTO WEEKLY PROGRESS
FABRICATION VMS WEEK-01

Scope of Work : Engineering, Supply Period : 22 Jul 2021 to 31 Jul 2021


Fabricator : PT. Pasrat Bumi Raya Location : Meiko Abadi V-Sidoarjo

Fabrication Progress 30/07/2021


PHOTO WEEKLY PROGRESS
FABRICATION VMS WEEK-01

Scope of Work : Engineering, Supply Period : 22 Jul 2021 to 31 Jul 2021


Fabricator : PT. Pasrat Bumi Raya Location : Meiko Abadi V-Sidoarjo

Fabrication Progress 31/07/2021