Inspection and Test Plan: Installation of Fire Alarm System
Inspection and Test Plan: Installation of Fire Alarm System
Contractor:
Description: INSTALLATION OF FIRE ALARM SYSTEM Page 1 of 3
Specification & Reference Parties Inspection Role
S. No. Activity Acceptance Criteria Frequency Verifying Documents
Document
Remarks:
Sub-Contractor’s Personnel: (Name, Sign & Date) Contractor’s Personnel: (Name, Sign & Date)
W - Witness point: Attendance at site is expected, H - Hold point: Attendance at site is mandatory and S- Surveillance: Random attendance & or visual R - Review: Documents to be reviewed, no signature
signature is required on check sheet or IR, but if The signature is required on the check sheet or IR at the time of inspection at site. required on the documents (R may be addition to
Engineer is not present to sign at the time, follow on the inspection in order to release for Following activity. any of the other action codes.)
work shall proceed and related documents (s) signed Work shall proceed & considered approved if employer’s
later. personnel do not show up for more than 30 minutes from
scheduled inspection time and the related document(s)
shall be signed later.
INSPECTION AND TEST PLAN
Client: Project: Document no.: Revision:
Contractor:
Description: INSTALLATION OF FIRE ALARM SYSTEM Page 2 of 3
Specification & Reference Parties Inspection Role
S. No. Activity Acceptance Criteria Frequency Verifying Documents
Document
Approved
Fire Alarm Coordination drawing.
Approved Material Submittals:
Approved
05 Ancillary Equipment Approved Method Statement: Every installation a) Inspection Request H W W
Fire Alarm Shop drawing
FFE/DPL/KFIP/E-MS-01
NFPA 72
Remarks:
Sub-Contractor’s Personnel: (Name, Sign & Date) Contractor’s Personnel: (Name, Sign & Date)
W - Witness point: Attendance at site is expected, H - Hold point: Attendance at site is mandatory and S- Surveillance: Random attendance & or visual R - Review: Documents to be reviewed, no signature
signature is required on check sheet or IR, but if The signature is required on the check sheet or IR at the time of inspection at site. required on the documents (R may be addition to
Engineer is not present to sign at the time, follow on the inspection in order to release for Following activity. any of the other action codes.)
work shall proceed and related documents (s) signed Work shall proceed & considered approved if employer’s
later. personnel do not show up for more than 30 minutes from
scheduled inspection time and the related document(s)
shall be signed later.
INSPECTION AND TEST PLAN
Client: Project: Document no.: Revision:
Contractor:
Description: INSTALLATION OF FIRE ALARM SYSTEM Page 3 of 3
Specification & Reference Parties Inspection Role
S. No. Activity Acceptance Criteria Frequency Verifying Documents
Document
Approved
Fire Alarm Coordination drawing. Approved Method Statement: a) Inspection Request
After completion of
Pre-checks and Visual
06 Approved FFE/DPL/KFIP/E-MS-01 As Fire Alarm system b) Pre-Checklist & Visual H H W
Inspection
Fire Alarm Shop drawing per approved specialist installation. Inspection form (Carried
NFPA 72 procedure(Sub Contractor) out by Subcontractor)
Remarks:
Sub-Contractor’s Personnel: (Name, Sign & Date) Contractor’s Personnel: (Name, Sign & Date)
W - Witness point: Attendance at site is expected, H - Hold point: Attendance at site is mandatory and S- Surveillance: Random attendance & or visual R - Review: Documents to be reviewed, no signature
signature is required on check sheet or IR, but if The signature is required on the check sheet or IR at the time of inspection at site. required on the documents (R may be addition to
Engineer is not present to sign at the time, follow on the inspection in order to release for Following activity. any of the other action codes.)
work shall proceed and related documents (s) signed Work shall proceed & considered approved if employer’s
later. personnel do not show up for more than 30 minutes from
scheduled inspection time and the related document(s)
shall be signed later.