1. Gantt Chart
2. Kaizen
4. Lean Manufacturing
5. Pipeline stock
6. Make to Order
7 SQC
OR
[B] What are the routing, dispatching, prioritization and expediting? Explain 07
Q.3 [A] You are given the following data regarding the processing times of some jobs on three machines 07
I, II and III. The order of processing is I-II-III. Determine the sequence that minimizes the total
elapsed time (T) required for completing the jobs. Also evaluate T and idle time of II and III.
Processing Time ( Hours)
JOB M I M II M III
A 3 4 6
B 8 3 7
C 7 2 5
D 4 5 11
E 9 1 5
F 8 4 6
G 7 3 12
[B] What is Aggregate Production Planning? Discuss the strategies in aggregate planning to manage 07
demand & supply.
Page 1 of 3
OR
Q.3 [A] Describe Product layout and Process layout. Give the example of the same where each would be 07
more applicable than the other.
[B] The Polycab company produces slip ring bearings. Employees have taken 10 samples (during a 07
10 days period) of five slip ring bearings and measured the diameter of the bearings. If σ = 0.08,
develop a mean chart with 3-sigma limits to monitor the process in the future.
Q.4 [A] Explain concept of six-sigma. Describe the steps of six sigma breakthrough strategy for quality 07
improvement.
[B] The following table shows, for each activity of a project, the normal and crash times as also the 07
normal and crash costs. The contract includes a penalty clause of Rs 200 /day in excess of 19
days. The overhead cost Rs 400/day.
Draw the project n/w and determine critical path. Crash the project activities and determine the
optimal duration of the project and the cost involved for same.
OR
[B] The owner of a chain of fast food restaurants is considering a new computer system for accounting 07
and inventory control. A computer company sent the following information about the system
installation:
Page 2 of 3
Activity Immediate Optimistic Time Most Likely Time Pessimistic
Predecessors Time
A - 4 6 8
B A 5 7 15
C A 4 8 12
D B 15 20 25
E B 10 18 26
F C 8 9 16
G E 4 8 12
H D,F 1 2 3
I G,H 6 7 8
Construct an arrow diagram for this problem and determine the critical path, expected project
completion time and variance of the project length.
Q.5 For a special component outsourced to a vendor and used in textile machinery manufactured by 14
Amar Machine tool works, we have the following situation:
The ordering cost, independent of purchase quantity, is Rs 1500 each purchase. The price of the
component is Rs 75/unit. Annual holding cost is 20% of the value of the component (inventory
interest rate 20%). Assuming 230 working days per year. Calculate
(II) Total inventory costs per year and total inventory costs per working day with purchase
quantity 1,00,000 units
OR
(II) Total inventory costs per year and total inventory costs per working day with EOQ and with
a safety stock decreased to 5000 units.
*************