p2 Risk Management Strategy Example v01
p2 Risk Management Strategy Example v01
Prince2™ Documentation
Project ID:PRDOC01
FMD Consultants Limited assumes no responsibility for the usage of any information contained in this document
and the way it is handled and disclaims all liability in respect of such information and its provision. Subject to this
disclaimer, you may copy and utilise the material contained in the document.
This information is based on OGC PRINCE2™ material. PRINCE2™ is a registered trade mark of the Office of
Government Commerce in the United Kingdom and other countries. All registered trademarks recognised &
accepted.
1 Document History
1.1 Location
This document is stored in the following location:
Filename p2_risk_management_strategy_example_v01
Location www.fmdconsultants.co.uk\web
1.3 Authorisation
This document requires the following approvals:
1.4 Distribution
This document has been distributed to:
Communications XXXXXXXXXX
Management Strategy
1 DOCUMENT HISTORY....................................................................................................2
1.1 LOCATION....................................................................................................................2
1.2 REVISION HISTORY.........................................................................................................2
1.3 AUTHORISATION............................................................................................................2
1.4 DISTRIBUTION...............................................................................................................2
1.5 RELATED DOCUMENTS....................................................................................................3
2 CONTENTS....................................................................................................................4
3 INTRODUCTION............................................................................................................5
3.1 RISK............................................................................................................................5
3.2 OBJECTIVES OF RISK MANAGEMENT..................................................................................5
3.3 SCOPE OF THIS RISK MANAGEMENT STRATEGY....................................................................6
3.4 RESPONSIBILITY OF THIS RISK MANAGEMENT STRATEGY........................................................6
4 RISK MANAGEMENT PROCEDURE.................................................................................6
4.1 IDENTIFY RISKS – RISK CATEGORIES...................................................................................7
4.2 RISK ASSESSMENT..........................................................................................................7
4.2.1 Risk Scales........................................................................................................7
4.2.2 Risk Actions......................................................................................................8
4.3 PLAN...........................................................................................................................8
4.3.1 Objective of Risk Planning................................................................................8
4.3.2 Risk Response Categories.................................................................................9
4.4 IMPLEMENT..................................................................................................................9
4.5 COMMUNICATE...........................................................................................................10
5 TOOLS AND TECHNIQUES............................................................................................10
6 RECORDS....................................................................................................................10
7 REPORTING.................................................................................................................10
8 TIMING OF RISK MANAGEMENT ACTIVITIES...............................................................11
9 ROLES AND RESPONSIBILITIES....................................................................................11
10 PROXIMITY.............................................................................................................12
10.1 CATEGORISING RISK PROXIMITY......................................................................................12
10.2 RISK PROXIMITY ACTIONS..............................................................................................12
11 EARLY WARNING INDICATORS................................................................................12
12 RISK TOLERANCE.....................................................................................................13
13 RISK BUDGET..........................................................................................................13
Appendix A – Risk Prompt List..................................................................................14
Appendix B – Risk Register........................................................................................15
Good risk management is about identifying what might go wrong, what the consequences
might be of something going wrong and finally, deciding what can be done to reduce the
possibility of something going wrong. If it does go wrong, as some things inevitably will,
making sure that the impact is kept to a minimum.
Risk management should ensure that an organisation makes cost effective use of a risk
framework that has a series of well-defined steps. The aim is to support better decision
making through a good understanding of risks and their likely impact.
Risk management should be a continuous and developing process which runs throughout the
organisation’s strategy and the implementation of that strategy, methodically addressing all
risks surrounding the council’s activities past, present and future.
This Risk Management Strategy is a subset of the corporate Risk Management Strategy and
relates specifically to procedures related to the development of software applications,
provision of methodology documentation and the presentation of that information to the
general public as a whole.
It will be reviewed on a monthly basis and changed ratified through peer-group review.
Communicate
Brainstorming – Utilise group brainstorming to identify prospective risks which may not be
recognised by an individual. Utilise disparate groups for brainstorming to provide alternative
views of risks, for example user groups, development groups, finance heads and project
related personnel.
Project Schedules – Are any areas of the project falling behind schedule i.e. is the percentage
of work package completed running to schedule. Have all approval target dates been met.
Project Finances – Is the project running to budget and within tolerance? Are there any
exceptional costs which were not forecast?
Project Performance – Is the number of issues raised higher than expected or greater than
has been experienced in earlier projects. Are there a high percentage of issues which are
unresolved. Does it take longer to resolve issues than would normally be expected. Are
problems being experienced with any of the projects product quality.
The Risk Impact and Risk Likelihood will then be multiplied to give a total risk
score, 1 being the lowest and 100 being the highest possible risk.
Project ID: PRDOC01 Doc Ref: p2_risk_management_strategy_example_v01
Page 7 of 15
Risk Management Strategy Example Date of Issue:01 January 2016
A total risk score of:
Below 30 will give a ‘green’ risk.
Between 31 and 59 give an ‘amber’ risk
Above 60 give a ‘red’ risk
4.3 Plan
Concentration should be on ‘red’ risks as these have the greatest chance of arising and are
likely to impact the project most severely. Consideration should be given to ‘amber’ risks and
‘green’ risks in order to:
Keep the risk at as low a level as is practical
Be prepared to respond to the risk should its severity level increase during the
project
Ensure that ‘green’ or ‘amber’ risks do not increase the chance of a ‘red’ risk being
encountered
4.4 Implement
The primary objective of this step is to ensure the planned risk responses are implemented,
their effectiveness monitored and corrective action taken where responses do not provide
effective solutions.
To ensure this is carried out efficiently, there will be a sole Risk Owner. This is a named
individual who is responsible for the management, monitoring and control of all aspects of a
particular risk.
There may be a Risk Actionee responsible for carrying out the required response action for a
risk or set of risks. The Risk Actionee should perform under the direction of the Risk Owner.
The Risk Owner and Risk Actionee may be the same person.
An individual may be responsible for more than one risk but consideration should be given to
their workload and abilities to ensure any individual is not allocated more risks than they can
practically manage.
4.5 Communicate
Risks will be communicated outwards as part of:
Checkpoint Reports - frequency defined in each Work Package, minimum of monthly
Highlight Reports - defined by Project Board, minimum of monthly
End Stage Reports
End Project Reports
Lessons Reports – at End Stage and End Project
Access to Risk Register forms will be restricted to those defines in the roles and
responsibilities, below and to the Risk Owner.
6 Records
Appendix B – Risk Register details the format of the Risk Register and contains descriptions
for each Risk Register field.
7 Reporting
Individual risk overviews will be entered on the Risk Summary which will be readily
available for authorised individuals and which will be circulated at Project Boards.
Access to Risk Summary will be restricted to those defined in the roles and responsibilities
(section 9) and to the Risk Owner.
It will be closed when approval for project closure has been given by the Project Executive.
Corporate Management Provide the corporate risk management policy and risk
management guide.
Senior User Ensure all risks to the users are identified, assessed and
controlled.
Senior Supplier Ensure risks relating to the supplier aspects are assessed
and controlled.
10 Proximity
10.1 Categorising Risk Proximity
Risk events will be categorised as:
Imminent – likely to be encountered immediately, typically within one week or less
Within the stage – likely to be encountered during the current stage of the project
Next stage – likely to be encountered during the next planned stage of the project
Within the project – likely to be encountered before the project is closed
Beyond the project – likely to be encountered after project closure
On completion of a stage, ‘within the stage’ risks should be assessed to determine if they were
encountered. If they were not encountered their relevance to the next planned stage should be
determined and their proximity classification modified accordingly.
On completion of a stage, ‘next stage’ risks should be assessed to determine if they are still
applicable to the next stage (i.e. the stage to be started) and, if appropriate, their proximity
should be modified to ‘within the stage’.
‘within the project’ risks should be reviewed at stage end to determine if they fall into the
‘next stage’ category (i.e. the stage after the stage to be started).
‘beyond the project’ risks should be reviewed at stage end to determine if they are still
legitimate risks. If the project is at closure stage, these risks should be highlighted in the
project closure documentation.
These should be regularly monitored by the Project Manager / Project Support to ensure each
stage is performing according to planned cost, timescales and quality.
12 Risk Tolerance
Risks are scored on a scale of 1 to 100, one hundred being the greatest risk. Risks with a score
greater than 60 should be noted to corporate management for information. Risks should be
escalated to corporate management immediately the risk score exceeds 80.
13 Risk Budget
There is no specific risk budget. Project tolerance will be employed where necessary to
minimise the impact of risks.