Testing and Commissioning Procedure For Moving Walks
Testing and Commissioning Procedure For Moving Walks
19
02.04.19
02.04.19
02.04.19
02.04.19
INSPECTION & TEST PLAN Testing & Commissioning of Moving Walks
Doha Metro - Green Line Elevated & At Grade Doc.: M009-SPH-TCH-PRO-00008 Rev. 1 Date: 01-04-2019 ITP_00008
Intervention Points (# - Engineer/Engineer's Assistant to be notified by Contractor of readiness of Hold Point and Witness Intervention Points)
Legend: H= Hold Point - WIR to be issues and work shall not proceed without approval/waiver from responsible party ; W= Witness Point - WIR to be issued and work may proceed if responsible party does not attend ; R="Record Review"- (The
documents to be submitted for review)
Engineer's
Contractor
Control Documents
Engineer/
# Works
Assistant
3rd Party
Checking Activity to be Responsible Required
Subcon.
Acceptance Criteria Documents
Performed Job function Frequency
Vol. Clause
Intervention Points (# - Engineer/Engineer's Assistant to be notified by Contractor of readiness of Hold Point and Witness Intervention Points)
Legend: H= Hold Point - WIR to be issues and work shall not proceed without approval/waiver from responsible party ; W= Witness Point - WIR to be issued and work may proceed if responsible party does not attend ; R="Record Review"- (The
documents to be submitted for review)
Engineer's
Contractor
Control Documents
Engineer/
# Works
Assistant
3rd Party
Checking Activity to be Responsible Required
Subcon.
Acceptance Criteria Documents
Performed Job function Frequency
Vol. Clause
Approved T&C
Check the voltage on the For each moving
Procedure
Voltage Check, Equipment controller. Equipments Criteria as per approved T&C / Site walk, after pre-
3.3 M009-SPH-MEP-PRO- H W W N/A TKEQ/TCP02/F-03-01
Levelling, Handrail & Brakes levelling, handrail tension & check sheets Engineer commissioning
00011 rev. 3
braking distance. checks.
(Sec. 4.3, page 12)
Approved T&C
For each moving
Procedure
Check the slow speed & full Criteria as per approved T&C / Site walk, after pre-
3.4 Functional Check M009-SPH-MEP-PRO- H W W N/A TKEQ/TCP02/F-03-01
speed current at NO LOAD. check sheets Engineer commissioning
00011 rev. 3
checks.
(Sec. 4.4, page 12-19)
Intervention Points (# - Engineer/Engineer's Assistant to be notified by Contractor of readiness of Hold Point and Witness Intervention Points)
Legend: H= Hold Point - WIR to be issues and work shall not proceed without approval/waiver from responsible party ; W= Witness Point - WIR to be issued and work may proceed if responsible party does not attend ; R="Record Review"- (The
documents to be submitted for review)
Engineer's
Contractor
Control Documents
Engineer/
# Works
Assistant
3rd Party
Checking Activity to be Responsible Required
Subcon.
Acceptance Criteria Documents
Performed Job function Frequency
Vol. Clause
Approved T&C
For each moving
Check all the safety Procedure
Safety Features Check, Lights & Criteria as per approved T&C / Site walk, after pre-
3.5 features, lights and the M009-SPH-MEP-PRO- H W W N/A TKEQ/TCP02/F-03-01
Cleaning check sheets Engineer commissioning
cleanliness of the unit. 00011 rev. 3
checks.
(Sec. 4.3, page 12-19)
ITP_00006
Rev. 1
Appendix A
Testing & Commissioning of Moving Walk
PROJECT: DOHA METRO PROJECT TKEQ/TCP02/F‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
UNIT No.: Page 1 of 1
Drawing Ref.:
A. FIELD WIRINGS AND VOLTAGE CHECKLIST
SI No. CHECK POINT (CONTROLLER) CHECK ITEM CRITERIA FIELD VALUE
B. INSULATION TEST OF THE MOTOR CABLES
CRITERIA (1000 Vdc
SI No. CHECK POINT (CONTROLLER) CHECK ITEM FIELD VALUE
Test Voltage)
1 U Motor Cable > 0.5 MΩ MΩ
2 V Motor Cable > 0.5 MΩ MΩ
3 W Motor Cable > 0.5 MΩ MΩ
Test Instrument Details:
Calibration Calibration Date / Due
SI No. Instrument Name & Model Serial No.
Certificate No. Date
RESULTS:
To be rectified and resubmitted before commissioning
To be rectified / comments will be checked at the beginning of commissioning
Confirmed / OK for commissioning
Remarks:
NAME
POSITION
DATE
SIGNATURE
Testing & Commissioning of Moving Walk
PROJECT: DOHA METRO PROJECT TKEQ/TCP02/F‐02‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
UNIT No.: Page 1 of 3
Drawing Ref.:
PRE‐COMMISSIONING CHECKLIST FOR MOVING WALK
ACCEPT
REJECT
REFERENCE
SI No. DESCRIPTION CRITERIA REMARKS/ READING
STANDARD
A LOTO
Lock Out Tag Out (LOTO) must be enforced
1
before the equipment energization
B BRIEF SPECIFICATION
1 Travel Distance of Moving walk
2 Angle of Inclination
3 Speed
4 Handling Capacity
C DRIVE MOTOR NAMEPLATE
1 Serial No.
2 Rated Power (kW)
3 Rated Current (A)
4 Rated Voltage (V)
5 RPM
D PALLETS
1 Width
EN115 Clause 5.3.2.1.2
2 Depth step/pallet depth should
not be less than 0.38m.
3 Should be free from sharp/knife edges
E FLOOR PLATES, COMBS & OTHERS
1 Condition of floor plates
2 Condition of comb teeth
3 Condition of skirt panels
4 Condition of inner decking
F REDUCERS
1 Check oil level in the reducers
G MAINTENANCE FACILITIES AND NOTICES
Availability of single phase 3‐pin socket
1 EN115 Clause 5.8.3.2
inside both the machinery space/pits.
Emergency Stop Switch at drive and tension
2 EN115 Clause 5.8.4
station should be available.
3 Warning stickers should be clearly legible.
Emergency stop switches are clearly
4
labelled.
Testing & Commissioning of Moving Walk
PROJECT: DOHA METRO PROJECT TKEQ/TCP02/F‐02‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
UNIT No.: Page 2 of 3
Drawing Ref.:
PRE‐COMMISSIONING CHECKLIST FOR MOVING WALK
ACCEPT
REJECT
REFERENCE
SI No. DESCRIPTION CRITERIA REMARKS/ READING
STANDARD
H EARTHING
1 Is the control enclosure bonded to earth?
Is the body of moving walk connected to
2
earth?
I HANDRAIL
1 Handrail surface shall be smooth
2 Width 70mm ~ 100mm EN115 Clause 5.6.2.2
J BALUSTRADE
Gap between balustrade exterior and the
1 ≥ 100mm EN115 Clause 5.5.2.2
wall or obstacle
K SAFETY DISTANCES AND AREAS
1 Clear Height above the Pallet Min.2300 mm EN115 Clause A.2.1
Distance between outer edge of handrail
2 ≥ 80mm EN115 Clause A.2.2
and wall or obstacle
Distance between the handrails for adjacent Must not be less
3 EN115 Clause A.2.3
moving walks than 160mm
L SAFETY CONTINUITY CHECK (DRIVE STATION)
1 User stop push button
2 Right comb plate
3 Left comb plate
4 Maintenance space opening control
5 Right handrail inlet
6 Left handrail inlet
7 Maintenance space emergency stop
8 Pallet supervision switch
9 Middle user stop push button
M SAFETY CONTINUITY CHECK (TENSION STATION)
1 User stop push button
2 Right comb plate
3 Left comb plate
4 Right chain tension
5 Left chain tension
6 Right handrail inlet
7 Left handrail inlet
8 Maintenance space emergency stop
Testing & Commissioning of Moving Walk
PROJECT: DOHA METRO PROJECT TKEQ/TCP02/F‐02‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
UNIT No.: Page 3 of 3
Drawing Ref.:
PRE‐COMMISSIONING CHECKLIST FOR MOVING WALK
ACCEPT
REJECT
REFERENCE
SI No. DESCRIPTION CRITERIA REMARKS/ READING
STANDARD
9 Pallet supervision switch
10 Maintenance space opening control
Test Instrument Details:
Instrument Name & Calibration Certificate
SI No. Serial No. Calibration Date / Due Date
Model No.
Remarks:
POSITION
DATE
SIGNATURE
Testing & Commissioning of Moving Walk
PROJECT: DOHA METRO PROJECT TKEQ/TCP02/F‐03‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
UNIT No.: Page 1 of 3
Drawing Ref.:
FUNCTIONAL PERFORMANCE TEST CHECKLIST FOR MOVING WALK
ACCEPT
REJECT
REFERENCE
SI No. DESCRIPTION CRITERIA REMARKS/ READING
STANDARD
A SAFETY BARRICADES AND SIGNAGES
Ensure safety barricades are placed at both
1
ends.
2 Ensure appropriate signages are displayed.
B CONTROLLER SUPPLY VOLTAGE
Three Phase Supply
L1 ~ L2 380~415V AC
1
L2 ~ L3 380~415V AC
L1 ~ L3 380~415V AC
2 Single Phase Supply 220~240V AC
3 24V Supply 24V DC
C EQUIPMENT LEVELING
1 Check the leveling of the floor plates
2 Check the leveling of the pallets
D HANDRAIL
Speed of handrail compared to speed of Not more to be EN115 Clause
1
pallets more than 2% 5.6.1
Check the operation of safety guard at EN115 Clause
2
handrail entry and exit. 5.6.4.3
3 Check tension and pull of handrail
E BRAKES
For 0.5 m/s,
0.2m to 0.3m
1 Braking distance
For 0.65 m/s,
0.3m to 0.4m
2 Condition of the brake shoe
F FUNCTIONAL CHECKS
1 Current at no load (Forward)
2 Current at no load (Backward)
3 Slow Speed 0.2 m/s
4 Full Speed at no load (Forward)
5 Full Speed at no load (Backward)
G SPACINGS, CLEARANCE & MEASUREMENTS
≤7mm, <4mm at EN115 Clause
1 Spacing between skirt and pallet
one side 5.5.5.1
Spacing between floor plate and comb
3 ~ 5mm
plate.
Testing & Commissioning of Moving Walk
PROJECT: DOHA METRO PROJECT TKEQ/TCP02/F‐03‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
UNIT No.: Page 2 of 3
Drawing Ref.:
FUNCTIONAL PERFORMANCE TEST CHECKLIST FOR MOVING WALK
ACCEPT
REJECT
REFERENCE
SI No. DESCRIPTION CRITERIA REMARKS/ READING
STANDARD
H KEY OPERATING SWITCHES
1 Start key switch
2 Directional control with key switch
I MEASUREMENTS
Spring tension measurement at the tension
1
station
J SAFETY FEATURES
Emergency stop switch (drive station EN115 Clause
1
landing) 5.12.3.2.3.1
Emergency stop switch (tension station EN115 Clause
2
landing) 5.12.3.2.3.1
EN115 Clause
3 Intermediate stop switch
5.12.3.2.3.1
4 Drive station maintenance area stop switch EN115 Clause 5.8.4
Tension station maintenance area stop
5 EN115 Clause 5.8.4
switch
EN115 Clause
6 Handrail inlet switch
5.6.4.3
7 Main drive shaft break safety
EN115 Clause
8 Pallet missing device
5.2.3.2.4.1
EN115 Clause
9 Comb plate switch
5.7.3.2.6
10 Handrai speed monitoring device EN115 Clause 5.6.1
11 Phase sequence relay EN115 5.12.1
12 Broken pallet device
EN115 Clause
13 Chain tension switch
5.4.3.3
14 Passenger entry sensor
K LIGHTS
1 Pallet demarcation light
Testing & Commissioning of Moving Walk
PROJECT: DOHA METRO PROJECT TKEQ/TCP02/F‐03‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
UNIT No.: Page 3 of 3
Drawing Ref.:
FUNCTIONAL PERFORMANCE TEST CHECKLIST FOR MOVING WALK
ACCEPT
REJECT
REFERENCE
SI No. DESCRIPTION CRITERIA REMARKS/ READING
STANDARD
L CLEANING
1 Cleaning of the handrail
2 Cleaning of the balustrade glasses
3 Cleaning of the pallets
4 Cleaning of the pits
5 Clean the guide rail tracks
M INTEGRATION WITH FIRE EMERGENCY SYSTEM
Check the operation of the unit in case of
1
Fire with simulated signal
N TRIAL RUN TEST
Run the moving walk for 30 minutes in
1 FORWARD Direction and another 30
minutes in BACKWARD direction.
Test Instrument Details:
Instrument Name & Calibration Certificate
SI No. Serial No. Calibration Date / Due Date
Model No.
Remarks:
POSITION
DATE
SIGNATURE
Testing & Commissioning of Moving Walk
PROJECT: DOHA METRO PROJECT TKEQ/EMHP/01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
SECTION: AL RIFFA (GWST080) Date:
UNIT No.: Page 1 of 1
Drawing Ref.:
INSPECTION SIGN‐OFF SHEET MW (HOLD POINT 1 )
ACCEPT
REJECT
SI.No. NATURE OF INSPECTION REMARKS
Pre‐Commissioning
1 Lock Out Tag Out (LOTO)
5 Continuity Check
Commissioining
7 Safety Barricades & Signages
9 Functional Check
REMARKS:
SIGNATURE
Property: TC Dept. Status: Final
M009-SPH-TCH-PRO-00008 Rev. 1 1 of 1 SPH JV - Internal Use Only