Procedure For Material Requirement Planning & Purchasing
Procedure For Material Requirement Planning & Purchasing
1. Scope: - To establish a procedure for MRP (Material Requirements Planning) and Purchasing
the material.
3. Procedure: - There are two conditions if supplier is existing or not as per our supplier approved list.
Decision is made
Product detail Product detail will be shared whether the supplier is Purchase
5
sharing with the supplier capable for Department
manufacturing or not.