2018 Contracts With Negative Slippage
2018 Contracts With Negative Slippage
HISTORY:
1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
PCMA 8/31/2021 5:02:32 PM Page 7 Of 93
11 18L00044 A. 433,789,598.11 A. 4/29/2018 A. 99.99 P00200389MN- On-going negotiations with affected Project suspended effective
CONC./WIDENING (2 INTO 4 B. 434,892,336.68 B. 3/14/2019 B. 86.29 CW3 (Permit to owners December 16, 2020. Once project is
LANES)/RECONST. OF C. 2/26/2021 C. -13.70 enter issues) resumed and equivalent Time
BUHANGIN-TIGATTO-MANDUG- Extension is approved, revised
CALLAWA-FATIMA RD planned schedule will be 93.556%
BYPASS,PACKAGE and incurred slippage 0.096%.
ULTICON BUILDERS, INC. Revision in the PCMA is on process.
(17267) / COASTLAND
CONSTRUCTION & HISTORY:
DEVELOPMENT CORP. (11487) 1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
P00200390MN- On-going negotiations with affected Project suspended effective
CW1 (Permit to owners December 16, 2020. Once project is
enter issues) resumed and equivalent Time
Extension is approved, revised
planned schedule will be 93.556%
and incurred slippage 0.096%.
Revision in the PCMA is on process.
HISTORY:
1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
PCMA 8/31/2021 5:02:32 PM Page 8 Of 93
11 18L00044 A. 433,789,598.11 A. 4/29/2018 A. 99.99 P00200390MN- On-going negotiations with affected Project suspended effective
CONC./WIDENING (2 INTO 4 B. 434,892,336.68 B. 3/14/2019 B. 86.29 CW2 (Permit to owners December 16, 2020. Once project is
LANES)/RECONST. OF C. 2/26/2021 C. -13.70 enter issues) resumed and equivalent Time
BUHANGIN-TIGATTO-MANDUG- Extension is approved, revised
CALLAWA-FATIMA RD planned schedule will be 93.556%
BYPASS,PACKAGE and incurred slippage 0.096%.
ULTICON BUILDERS, INC. Revision in the PCMA is on process.
(17267) / COASTLAND
CONSTRUCTION & HISTORY:
DEVELOPMENT CORP. (11487) 1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
P00200389MN- -The respective Local Government 12/4/2020 Project suspended effective
CW1 (Epidemic Unit issued Executive Order No.20 December 16, 2020. Once project is
(s)) and strictly implemented resumed and equivalent Time
community quarantine to prevent Extension is approved, revised
the spread of COVID-19 virus planned schedule will be 93.556%
inspection. and incurred slippage 0.096%.
Revision in the PCMA is on process.
HISTORY:
1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
PCMA 8/31/2021 5:02:32 PM Page 9 Of 93
11 18L00044 A. 433,789,598.11 A. 4/29/2018 A. 99.99 P00200389MN- On-going negotiation between the 12/4/2020 Project suspended effective
CONC./WIDENING (2 INTO 4 B. 434,892,336.68 B. 3/14/2019 B. 86.29 CW1 (Permit to land owners and rrow personnel. December 16, 2020. Once project is
LANES)/RECONST. OF C. 2/26/2021 C. -13.70 enter issues) resumed and equivalent Time
BUHANGIN-TIGATTO-MANDUG- Extension is approved, revised
CALLAWA-FATIMA RD planned schedule will be 93.556%
BYPASS,PACKAGE and incurred slippage 0.096%.
ULTICON BUILDERS, INC. Revision in the PCMA is on process.
(17267) / COASTLAND
CONSTRUCTION & HISTORY:
DEVELOPMENT CORP. (11487) 1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
P00200389MN- On-going negotiation between the 12/4/2020 Project suspended effective
CW2 (Permit to land owners and rrow personnel. December 16, 2020. Once project is
enter issues) resumed and equivalent Time
Extension is approved, revised
planned schedule will be 93.556%
and incurred slippage 0.096%.
Revision in the PCMA is on process.
HISTORY:
1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
PCMA 8/31/2021 5:02:32 PM Page 10 Of 93
11 18L00044 A. 433,789,598.11 A. 4/29/2018 A. 99.99 P00200389MN- On-going negotiation between the 12/4/2020 Project suspended effective
CONC./WIDENING (2 INTO 4 B. 434,892,336.68 B. 3/14/2019 B. 86.29 CW3 (Permit to land owners and rrow personnel. December 16, 2020. Once project is
LANES)/RECONST. OF C. 2/26/2021 C. -13.70 enter issues) resumed and equivalent Time
BUHANGIN-TIGATTO-MANDUG- Extension is approved, revised
CALLAWA-FATIMA RD planned schedule will be 93.556%
BYPASS,PACKAGE and incurred slippage 0.096%.
ULTICON BUILDERS, INC. Revision in the PCMA is on process.
(17267) / COASTLAND
CONSTRUCTION & HISTORY:
DEVELOPMENT CORP. (11487) 1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
P00200390MN- On-going negotiation between the 12/4/2020 Project suspended effective
CW1 (Permit to land owners and rrow personnel. December 16, 2020. Once project is
enter issues) resumed and equivalent Time
Extension is approved, revised
planned schedule will be 93.556%
and incurred slippage 0.096%.
Revision in the PCMA is on process.
HISTORY:
1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
PCMA 8/31/2021 5:02:32 PM Page 11 Of 93
11 18L00044 A. 433,789,598.11 A. 4/29/2018 A. 99.99 P00200390MN- On-going negotiation between the 12/4/2020 Project suspended effective
CONC./WIDENING (2 INTO 4 B. 434,892,336.68 B. 3/14/2019 B. 86.29 CW2 (Permit to land owners and rrow personnel. December 16, 2020. Once project is
LANES)/RECONST. OF C. 2/26/2021 C. -13.70 enter issues) resumed and equivalent Time
BUHANGIN-TIGATTO-MANDUG- Extension is approved, revised
CALLAWA-FATIMA RD planned schedule will be 93.556%
BYPASS,PACKAGE and incurred slippage 0.096%.
ULTICON BUILDERS, INC. Revision in the PCMA is on process.
(17267) / COASTLAND
CONSTRUCTION & HISTORY:
DEVELOPMENT CORP. (11487) 1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
P00200389MN- On-going negotiation between the 12/4/2020 Project suspended effective
CW1 (Demolition land owners and rrow personnel. December 16, 2020. Once project is
or other clearing resumed and equivalent Time
related issues Extension is approved, revised
(except utilities)) planned schedule will be 93.556%
and incurred slippage 0.096%.
Revision in the PCMA is on process.
HISTORY:
1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
PCMA 8/31/2021 5:02:32 PM Page 12 Of 93
11 18L00044 A. 433,789,598.11 A. 4/29/2018 A. 99.99 P00200389MN- On-going negotiation between the 12/4/2020 Project suspended effective
CONC./WIDENING (2 INTO 4 B. 434,892,336.68 B. 3/14/2019 B. 86.29 CW2 (Demolition land owners and rrow personnel. December 16, 2020. Once project is
LANES)/RECONST. OF C. 2/26/2021 C. -13.70 or other clearing resumed and equivalent Time
BUHANGIN-TIGATTO-MANDUG- related issues Extension is approved, revised
CALLAWA-FATIMA RD (except utilities)) planned schedule will be 93.556%
BYPASS,PACKAGE and incurred slippage 0.096%.
ULTICON BUILDERS, INC. Revision in the PCMA is on process.
(17267) / COASTLAND
CONSTRUCTION & HISTORY:
DEVELOPMENT CORP. (11487) 1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
P00200389MN- On-going negotiation between the 12/4/2020 Project suspended effective
CW3 (Demolition land owners and rrow personnel. December 16, 2020. Once project is
or other clearing resumed and equivalent Time
related issues Extension is approved, revised
(except utilities)) planned schedule will be 93.556%
and incurred slippage 0.096%.
Revision in the PCMA is on process.
HISTORY:
1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
PCMA 8/31/2021 5:02:32 PM Page 13 Of 93
11 18L00044 A. 433,789,598.11 A. 4/29/2018 A. 99.99 P00200390MN- On-going negotiation between the 12/4/2020 Project suspended effective
CONC./WIDENING (2 INTO 4 B. 434,892,336.68 B. 3/14/2019 B. 86.29 CW1 (Demolition land owners and rrow personnel. December 16, 2020. Once project is
LANES)/RECONST. OF C. 2/26/2021 C. -13.70 or other clearing resumed and equivalent Time
BUHANGIN-TIGATTO-MANDUG- related issues Extension is approved, revised
CALLAWA-FATIMA RD (except utilities)) planned schedule will be 93.556%
BYPASS,PACKAGE and incurred slippage 0.096%.
ULTICON BUILDERS, INC. Revision in the PCMA is on process.
(17267) / COASTLAND
CONSTRUCTION & HISTORY:
DEVELOPMENT CORP. (11487) 1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
P00200390MN- On-going negotiation between the 12/4/2020 Project suspended effective
CW2 (Demolition land owners and rrow personnel. December 16, 2020. Once project is
or other clearing resumed and equivalent Time
related issues Extension is approved, revised
(except utilities)) planned schedule will be 93.556%
and incurred slippage 0.096%.
Revision in the PCMA is on process.
HISTORY:
1.) Project was resumed effective
December 04, 2020
2.) Project was suspended effective
February 01, 2019 due to road right-
of-way problem
(structures/improvements, & land).
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 92.497% and incurred
negative slippage -6.203%.
Negotiations with the affected
owners were put on hold until the
situation is back to normal condition.
PCMA 8/31/2021 5:02:32 PM Page 14 Of 93
12 18L00047 A. 283,069,266.20 A. 6/13/2018 A. 100.00 P00200408MN- Tagging, inventory, and .Project was completed as
IMPV'T./RECONST./CONC. OF B. 283,124,967.38 B. 4/8/2019 B. 97.47 CW1 (Permit to identification of affected persons scheduled. Documents are
MAHAYAG-GATUNGAN- C. 7/12/2020 C. -2.53 enter issues) were done to come up with a processed for approval. Once
CALLAWA DIVERSION ROAD detailed estimates that were used approved, request for revision will be
INCL. ROW, DAVAO CITY to be the basis of giving cash submitted to PMD-BOC for approval.
GEMMA CONSTRUCTION assistance to the affected
SUPPLY, INC. residents. Project was suspended
(FORMERLY:GEMMA CON (5044) effective 07 March 2019 due to
Road Right-of-Way at the project
site.
P00200408MN- Tagging, inventory, and .Project was completed as
CW2 (Permit to identification of affected persons scheduled. Documents are
enter issues) were done to come up with a processed for approval. Once
detailed estimates that were used approved, request for revision will be
to be the basis of giving cash submitted to PMD-BOC for approval.
assistance to the affected
residents. Project was suspended
effective 07 March 2019 due to
Road Right-of-Way at the project
site.
P00200408MN- Tagging, inventory, and .Project was completed as
CW3 (Permit to identification of affected persons scheduled. Documents are
enter issues) were done to come up with a processed for approval. Once
detailed estimates that were used approved, request for revision will be
to be the basis of giving cash submitted to PMD-BOC for approval.
assistance to the affected
residents. Project was suspended
effective 07 March 2019 due to
Road Right-of-Way at the project
site.
P00200408MN- The said designs and plans were .Project was completed as
CW1 (Changes in processed for approval. Once scheduled. Documents are
approved approved, request for revision will processed for approval. Once
plans/designs) be submitted to PMD-BOC for approved, request for revision will be
approval submitted to PMD-BOC for approval.
P00200408MN- Letters to the corresponding 6/10/2020 .Project was completed as
CW1 telecommunication and utility scheduled. Documents are
(Removal/Relocat companies were sent to request processed for approval. Once
ion of utilities) them for removal/transfer of approved, request for revision will be
electrical post/utilities. submitted to PMD-BOC for approval.
HISTORY:
1.Project suspended effective
February 01, 2021, waiting for the
release of permit/clearance from
PNP for blasting of hard rock
materialst o await the issuance of
permit/clearance from the Philippine
National Police of IGACOS for
blasting of hard rock materials. Once
project is resumed and equivalent
Time Extension is approved, revised
planned schedule will be 99.530%
and incurred slippage 0.230%.
Revision in the PCMA is on process.
2.Project resumed effective July 16,
2020. Revision in the PCMA on
process, waiting for approved time
extension in view of the approved
suspension and resumption order.
PCMA 8/31/2021 5:02:32 PM Page 56 Of 93
43 18L00154 A. 270,160,985.15 A. 8/14/2018 A. 100.00 P00257898MN- The contractor issued letter to the 7/16/2021 Project resumed effective July 16,
SAMAL BRIDGE LEADING TO B. 280,949,960.57 B. 6/9/2019 B. 93.11 CW1 (Issuance of PNP requesting for the issuance of 2021. Revision in the PCMA on
SAN REMIGIO, SAMAL ISLAND, C. 12/28/2020 C. -6.89 necessary permit/clearance for blasting of process,
DAVAO DEL NORTE certification by hard rock materials.
VICENTE T. LAO PNP) HISTORY:
CONSTRUCTION (7040) 1.Project suspended effective
February 01, 2021, waiting for the
release of permit/clearance from
PNP for blasting of hard rock
materialst o await the issuance of
permit/clearance from the Philippine
National Police of IGACOS for
blasting of hard rock materials. Once
project is resumed and equivalent
Time Extension is approved, revised
planned schedule will be 99.530%
and incurred slippage 0.230%.
Revision in the PCMA is on process.
2.Project resumed effective July 16,
2020. Revision in the PCMA on
process, waiting for approved time
extension in view of the approved
suspension and resumption order.
44 18L00155 A. 404,496,669.33 A. 7/9/2018 A. 100.00 P00200423MN- Corresponding documents of Final Project completed as of November
CONC. OF NABUNTURAN-NEW B. 404,496,669.33 B. 5/24/2019 B. 92.47 CW1 (Changes in Variation Order was complied to 15, 2020. Time extension on process
BATAAN DIV. ROAD,PACKAGES C. 7/23/2019 C. -7.53 approved suit actual site condition. Once once approved revisions will be
A & B, COMPOSTLEA VALLEY, A) plans/designs) approved, Request for Revision in forwarded to BOC-PMD
CONC. OF NABUNTURAN-NE the PCMA will then be sent to the
ULTICON BUILDERS, INC. BOC-PMD for approval.
(17267) P00200424MN- Corresponding documents of Final Project completed as of November
CW1 (Changes in Variation Order was complied to 15, 2020. Time extension on process
approved suit actual site condition. Once once approved revisions will be
plans/designs) approved, Request for Revision in forwarded to BOC-PMD
the PCMA will then be sent to the
BOC-PMD for approval.
P00200423MN- on process revised plan 10/14/2020 Project completed as of November
CW1 (Changes in 15, 2020. Time extension on process
approved once approved revisions will be
plans/designs) forwarded to BOC-PMD
P00201475MNA- Ongoing negotiations with PAPs 3/17/2021 Once the final variation order is
CW3 (Permit to who refused to sign Permit to enter approved, final quantities will be
enter issues) reflected in the PCMA.