FRL Weekly Progress Report Lagos State Multi-Agency Complex Building

This weekly progress report provides an update on the construction of the Lagos State Multi-Agency Complex building in Alausa, Lagos State, Nigeria. Based on the report, construction is currently 32 weeks into the project duration and 83% of the work is still in progress. Several key systems like HVAC, plumbing, and fire fighting still require resolution in order to continue further construction work.

Uploaded by

sellitt ng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
125 views

FRL Weekly Progress Report Lagos State Multi-Agency Complex Building

This weekly progress report provides an update on the construction of the Lagos State Multi-Agency Complex building in Alausa, Lagos State, Nigeria. Based on the report, construction is currently 32 weeks into the project duration and 83% of the work is still in progress. Several key systems like HVAC, plumbing, and fire fighting still require resolution in order to continue further construction work.

Uploaded by

sellitt ng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

FRL Lagos State Multi-Agency Complex Building

Weekly Progress Report

FRL
Date: 13/08/2021 Job No:
Week 32 Report No: 2
WEEKLY PROGRESS REPORT Location: ALAUSA, IKEJA LAGOS STATE
Project Title: LAGOS STATE MULTI AGENCY OFFICE COMPLEX ALAUSA
Contractor: METROL FITTINGS & ACCESSORIES LTD
Sub-Contractor:
Project Duration: Commencement Date: Completion Date:
Overall Project Status to Date:
Work Weeks Completed to Date: Work Weeks Left to completion:
On Track Off Track Delayed
LEGEND:

DISTRIBUTION LIST
Contacts Name Phone No Email
The Special Adviser
Perm. Secretary
Dir. Architectural Services
Dir. Mechanical Services
Dir. Electrical Services
MD Metrol Fittings & Acc.
MD MC&T
MD Palmyra

SUMMARY OF WEEKLY WORK PROGRESS WEEK __32


Items Project Activities Average Total % Progress
1 Mobilization 90% 90%
100%
2 Demolition & Alteration 75% 75%
80%
3 MEP Works 0% 60%

4 Wet Works 15% 40%


15%
5 Dry Works 0% 20%
0% 0% 0% 0%
0%
6 External Works 0%
Mobilization Demolition & Alteration
MEP Works Wet Works
7 Commissioning & Handover 0% Dry Works External Works

Issues/Delays/Disruptions

Status Tallies Priority Tallies


0%
17%
1 nos
Not Started High 1 nos17%

1 nos16%
In Progress Medium
4 nos
67%

5 nos
83%
Closed Low

Items Description Status Priority Assignee Comments


1 Resolution of HVAC system In Progress High Ministry
2 Approval of Architectural Drawings In Progress High Metrol/Ministry
Submission of construction methodology, HSE management
3 In Progress High Metrol/Mct
plan and Quality management plan
4 Resolution of plumbing system In Progress High Metrol/Ministry
5 Resolution of Fire Fighting System In Progress Medium Metrol/Ministry
6 Sewage Treatment - (Bio-digester option) Not Started Low