This document provides an inspection and test plan (ITP) for rebar installation on the Kota Kasablanka 3 Project. The ITP outlines: 1) Preliminary inspections of shop drawings and bar bending schedules. 2) Fabrication inspections of cutting and bending rebar to specified diameters and lengths. 3) Installation inspections of cleaning areas, installing spacer concrete and rebar at specified distances and diameters, as shown on shop drawings, with tolerances of ±20mm.

Uploaded by

Daniel Sinaga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views1 page

6.ITP For Rebar

This document provides an inspection and test plan (ITP) for rebar installation on the Kota Kasablanka 3 Project. The ITP outlines: 1) Preliminary inspections of shop drawings and bar bending schedules. 2) Fabrication inspections of cutting and bending rebar to specified diameters and lengths. 3) Installation inspections of cleaning areas, installing spacer concrete and rebar at specified distances and diameters, as shown on shop drawings, with tolerances of ±20mm.

Uploaded by

Daniel Sinaga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION AND TEST PLAN

KOTA KASABLANKA 3 PROJECT


LOTTE E&C - TOTALINDO

II. ITP FOR REBAR


INSPECTION HOLD POINT / EQUIPMENT /
No. SCOPE REFERENCE ACCEPTANCE CRITERIA TOLERANCE FREQUENCY INSPECTORS RESPONSIBILITY
METHOD WITHNESS TOOLS
I. Preleminary
I.1 Preparation
Make sure the shop drawing is After respons Doc. Control and
I.1.1 Procedure Visual Stamp approved and Controlled No Witness - Engineer
approve and controlled from owner Engineer

Bar Bending schedule drawing After respons


I.1.2 Procedure Visual Stamp approved and Controlled No _ - SM and Spv BBS
available from owner

I.1.3 Decking concrete fabrication Specification teknis

II.1 Fabrication
Shop drawing and Standart Diameter and lenght of cutting not less than Sigmat and
II.1.1 Cut of Rebar Be messured ± 10mm Witness Start to work SPV, QC QC Manager, SM
detail standar detail messuring tape

Shop drawing and Standart


II.1.2 Bend of Rebar Be messured Check the diameter bending ( 5 D ) No Witness Every bending Sigmat SPV, QC QC Manager, SM
detail
III.1 Instalation rebar

III.1.1 Cleaning area Clean, no dust, no water, no Visual Client Approval - Witness Start to work - SPV, QC QC Manager
trash
Shop drawing and Standart
III.1.2 Spacer concrete install Be messured Installed in every 80 cm X Y ±50mm Witness Start to work Messuring tape SPV, QC QC Manager
detail

Shop drawing and Standart Diameter, summary, distance, tightening and QC Manager, Cons
III.1.3 Install botom reinforcement Be messured ±20mm Hold point Finish to work Measuring tape SPV, QC
detail extra bar correct with the shop drawing. Manager

Shop drawing and Standart On progress QC Manager, Cons


III.1.4 Install the chair bar Be messured In upsite spacer concrete. In every 80cm ±20mm Witness Measuring tape SPV, QC
detail work Manager

Shop drawing and Standart Diameter, summary, distance, tightening and QC Manager, Cons
III.1.4 Install top reinforcement Be messured ±20mm Hold point Finish to work Measuring tape SPV, QC
detail extra bar correct with the shop drawing. Manager