Agency: Department of Public Works and Highways (DPWH) Albay 3rd District Engineering Office
Agency: Department of Public Works and Highways (DPWH) Albay 3rd District Engineering Office
Review Level:
RDC
ICC-TB
NEDA board
2. Goal
Reduce flood damages and risks among structures and safeguarding lives
3. Purpose
To lessen harm to physical infrastructure and help to ensure continuation of
communities' economic and social activity
4. Project Output
Adopting the flood control design & specifications and engineering approach as
per Department Order
5. Project Activities
The project involves rehabilitation/improvement of flood mitigation structure
consisting of stone masonry, concrete slope protection, gabion and sheet piles.
6. Project Linkages
The project is under DPWH Local Programs in coordination with the concerned
Local Government Unit/s (LGUs)
IV. PROJECT FINANCING
Partial land will be occupied, and some houses will be relocated or demolished,
thus will incur social costs, mainly from disturbance cost for the relocation of
project-affected persons and for right-of-way (ROW) acquisition.
5. Economic Costs
Economic growth increase by certain percentages
VI. PROJECT IMPLEMENTATION
1. Agencies Involved
Department of Public Works and Highways (DPWH) and concerned Local
Government Units (LGUs)
2. Implementation Schedule Amount
Physical Indicator (In Million Pesos)
2021 357 Lineal Meters ₱39,987,018.03
3. Administrative Feasibility
Endorsed by the local chief executive within their territorial area of jurisdiction
4. Environmental Clearance
The conduct of environmental and social aspects study shall also be considered
as the final basis for the recommendation.
5. Social Acceptability
The conduct of public consultations to the concerned persons shall be
considered as final basis for the implementation.
Date: Date:
COMPREHENSIVE PROJECT PROFILE
Agency: Department of Public Works and Highways (DPWH) Sector: Infrastructure
Albay 3rd District Engineering Office
I. PROJECT DESCRIPTON
1. Project Title:
Rehabilitation of San Francisco River Flood Mitigation Structure at Purok 5,
Centro Oriental, Polangui, Albay
2. Project Type:
Capital Assistance √
Technical Assistance
3. Project Components:
Flood Control = 196 Lineal Meters
4. Project Location:
Provinces: Albay
Municipalities: Polangui
II. PROJECT STATUS
1. On-going
2. Pipeline
3. Proposed √
Review Level:
RDC
ICC-TB
NEDA board
2. Goal
Reduce flood damages and risks among structures and safeguarding lives
3. Purpose
To lessen harm to physical infrastructure and help to ensure continuation of
communities' economic and social activity
4. Project Output
Adopting the flood control design & specifications and engineering approach as
per Department Order
5. Project Activities
The project involves construction of ground sill dam consisting of rubble
concrete, concrete slope protection, gabion and sheet piles.
6. Project Linkages
The project is under DPWH Local Programs in coordination with the concerned
Local Government Unit/s (LGUs)
IV. PROJECT FINANCING
Partial land will be occupied, and some houses will be relocated or demolished,
thus will incur social costs, mainly from disturbance cost for the relocation of
project-affected persons and for right-of-way (ROW) acquisition.
5. Economic Costs
Economic growth increase by certain percentages
VI. PROJECT IMPLEMENTATION
1. Agencies Involved
Department of Public Works and Highways (DPWH) and concerned Local
Government Units (LGUs)
2. Implementation Schedule Amount
Physical Indicator (In Million Pesos)
2021 196 Lineal meter ₱21,386,972.66
3. Administrative Feasibility
Endorsed by the local chief executive within their territorial area of jurisdiction
4. Environmental Clearance
The conduct of environmental and social aspects study shall also be considered
as the final basis for the recommendation.
5. Social Acceptability
The conduct of public consultations to the concerned persons shall be
considered as final basis for the implementation.
Date: Date: