This document is a quotation from BM Power General Construction & Sales Corporation providing a cost proposal for power system analysis services for Isuzu Philippines Corporation's 4 MVA, 34.5 kV/6.6 kV substation. The services include a power system analysis, electrical system assessment and load update, and will analyze the short circuit, protection coordination, load flow, arc flash, harmonic analysis, and grounding of the system. The total price is ₱0.00 with a 30% downpayment and 70% due 30 days after completion, which is estimated to take 2 weeks for site work and 6 weeks for report preparation.

Uploaded by

Edmar Bataque
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
99 views

Electrical System Design Analysis

This document is a quotation from BM Power General Construction & Sales Corporation providing a cost proposal for power system analysis services for Isuzu Philippines Corporation's 4 MVA, 34.5 kV/6.6 kV substation. The services include a power system analysis, electrical system assessment and load update, and will analyze the short circuit, protection coordination, load flow, arc flash, harmonic analysis, and grounding of the system. The total price is ₱0.00 with a 30% downpayment and 70% due 30 days after completion, which is estimated to take 2 weeks for site work and 6 weeks for report preparation.

Uploaded by

Edmar Bataque
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

QUOTATION

Date: June 18, 2019 Reference No:BMP-Q-06172019-058

ISUZU PHILIPPINES CORPORATION


114 Technology Ave., Laguna Technopark Phase 2, Biñan, Laguna

Attention:

Thru:

Subject: Power Systems Analysis/Power System Study of the 4 MVA, 34.5 kV/6.6 kV Substation

Gentlemen,
We hereby submit the cost proposal for the below items;

Item Description QTY Unit Unit Price Total Price


I Power System Analysis 1 lot ₱0.00 ₱0.00
Scope of work:
1.0 Perform short circuit study:
1.1 Provide short circuit impedance diagram & bus KA rating.
1.2 Short circuit rating evaluation of all protection devices
included in the scope.
2.0 Perform protection coordination study:
2.1 Provide time-current curve for each circuit including
transformer and motor characteristic.
2.1.1 Phase protection
2.1.2 Ground Protection
2.2 Provide recommended summary setting for all protection
equipment.
3.0 Perform load flow analysis and voltage drop calculation:
3.1 Provide computer application base calculation for load
flow and voltage drop.
3.2 Provide summary and evaluation report of all circuit/ bus
voltage level.
4.0 Perform arc flash analysis:
4.1 Provide computer application base calculation of arc flash
in accordance to IEEE - 1584 and/or NFPA-70E.
4.2 Provide calculation summary result for the following arc
flash hazard parameters; arc fault current, incident energy,
arc flash boundary & protection equipment level.
4.3 Provide reports and recommendation ( if any).
5.0 Perform harmonic analysis:
5.1 Provide computer application base calculation for
harmonic load flow for the system.
5.2 Provide frequency scan, calculation of harmonic bus
voltage and current.
5.3 Provide THD and TDD per bus.
6.0 Perform grounding analysis:
6.1 Perform assessment of the grounding system.
6.1 Checking and evaluation of grounding cables in the system
for compliance in the code.
6.2 Perform checking of the grounding connections and
resistances.

Page 1 of 2
II Electrical System Assessment and Load Update 1 lot ₱0.00 ₱0.00
1.0 Perform load checking and data gathering for each circuit
included in the study.
2.0 Gathering of equipment data in preparation for the study
presented above.
3.0 Provide updated single line diagram with complete results
of the studies above.
4.0 To submit results and evaluation report for the above studies
ellaborated above with sign and seal of PEE.
5.0 Site mobilization/ demobilization.

NOTES:
1.The following data are necessary for the conduct of the
study:
a.) Available fault duty at point of connection from the utility
company.
b.) Line impedance of the transmission line that served the
facility.
c.) Transformer impedance, kVA rating, voltage rating and tap
changer setting.
d.) Large motor such as chiller and pumps characteristics
which include motor nameplate data, acceleration time,
locked rotor and starting characteristic.
e.) Sizes and lengths of different wires and cables of the
system (both for phases and ground).
f.) Updated load schedule and single line diagram.
g.) Rating, model, type and brand of the circuit breaker, fuse
and switches.
h.) Model, brand and type of protection relays and circuit
breaker trip unit. Also existing setting is needed.
2. The study is limited only from incoming panel upto the
load panel such as after MDBs.
3. The offer presented already include any payment (if any) to
DOLE in order to proceed the conduct of those studies.

TOTAL PRICE ( VAT INCLUSIVE) ₱0.00

Terms & Conditions:

I. Payment Terms:
Thirty percent (30%) downpayment.
Seventy percent (70%) 30 days upon completion.
II. Work duration:
Two (2) weeks visual inspection, load profile checking and equipment data gathering.
Six (6) weeks report preparation after accumulating all data needed.
III. Validity:
The prices indicated above are valid only upto 30 days after receiving of the quotation.
Prices may vary or change without prior notice after.

We hope that the above items are considerable and acceptable. For any concerns and inquiries, please don't
hesitate to contact us. Thank you.

Sincerely yours,

BM POWER General Construction & Sales Corporation