Chapter9 Culverts
Chapter9 Culverts
9 Culverts
TABLE OF CONTENTS
REFERENCES 9-66
9 Culverts
9.1 INTRODUCTION
9.1.1 Definition
A culvert is any structure not classified as a bridge, that provides an opening under a roadway, or
other types of access or utility.
Photo 9.1 Improved inlet during construction Photo 9.2 Same improved inlet after
on Interstate Highway 70 construction on Interstate Highway 70
9.1.2 Purpose
A culvert is used primarily to convey water through embankments, or other types of flow
obstructions. It can also be used as a passage for pedestrians, stock, wildlife, and fish, as well as
for land access and to carry utilities. This chapter focuses on drainage applications of culverts.
C h a p t e r 9 — C u l v e r t s 9-4
Flowline - a line running longitudinally with the channel, connecting the lowest points in a series
of channel cross sections.
Flow Type - the United States Geological Survey (USGS) has established seven culvert flow types,
which assist in determining the flow conditions at a particular culvert site.
Foundation - the in-place or borrow material beneath the bottom of pipe, or layer of bedding
material. The foundation material should be removed and replaced if unsuitable.
Free Outlet - a free outlet has a tailwater equal to, or lower than, critical depth. For culverts having
free outlets, lowering of the tailwater has no effect on the discharge, or the backwater profile
upstream of the tailwater.
Haunches - the haunches of a pipe are the outside areas between the springline and the bottom of
pipe.
Headwater - the depth of the upstream water surface, measured from the flowline at the culvert
entrance.
Hydraulic Grade Line - the hydraulic grade line represents the depth to which water would rise in
vertical tubes connected to the sides of the culvert barrel.
Improved Inlet - an improved inlet has an entrance geometry which decreases the flow constriction
at the inlet, and increases the capacity of culverts flowing under inlet-control conditions.
Invert - the inside bottom of the culvert.
Normal Flow - normal flow occurs in a channel reach when the discharge, velocity, and depth of
flow do not change throughout the reach. The water-surface profile and channel-bottom slope will
be parallel. This type of flow can exist in a culvert operating on a steep slope, provided the culvert
is sufficiently long.
Normal Depth - the depth of water at a steady, uniform, constant velocity and flow at a given
channel reach.
Rigid Pipe - a structure that transmits the backfill load on the pipe through the pipe walls to the
foundation beneath the pipe. An example of a rigid pipe is a reinforced concrete pipe.
Round Pipe and Corrugation Terminologies - Figure 9.1 shows the terminology commonly used
in describing round pipe. Figure 9.2 depicts a profile of a corrugated pipe (3 in by 1 in corrugation),
with terminology and sample dimensions.
Slope Types - steep slope occurs where the critical depth is greater than the normal depth. Mild
slope occurs where critical depth is less than normal depth.
Springline - the horizontal line at the midpoint of the vertical axis of the pipe.
Subcritical Slope - a slope less than the critical slope, which causes a slower flow of the subcritical
state for a given discharge.
Submerged Condition - a submerged outlet occurs where the tailwater elevation is higher than the
crown of the culvert. A submerged inlet occurs where the headwater is greater than 1.2 times the
culvert diameter, or barrel height.
Supercritical Slope - a slope greater than the critical slope, which causes a faster flow of the
supercritical state for a given discharge.
Tailwater - the depth of water downstream of the culvert, measured from the outlet flowline.
Backwater calculations from a downstream control, a normal-depth approximation, or field
observations, are used to define the tailwater elevation.
Top of Pipe - the point along the pipe vertical axis which is a wall thickness above the crown.
Trench - a cut or an excavation made in the ground for the placement of a culvert and required
bedding, embedment, backfill, and cover materials.
Trench Terminology - Figure 9.3 shows the different terminologies commonly used in trenches.
9.1.4 Symbols
To provide consistency within this Chapter and throughout this manual, the symbols given in Table
9.1 will be used. These symbols were selected because of their wide use in culvert publications.
C h a p t e r 9 — C u l v e r t s 9-7
9.1.5 Classification
9.1.6 Geometry
The geometric factors used in culvert classification are barrel shapes and inlet types.
Barrel Shapes
Numerous cross sectional shapes are available. The most commonly used shapes include circular,
rectangular, elliptical, pipe arch, and arch. Shape selection is based on the cost of construction, the
limitation on upstream water-surface elevation, roadway embankment height, and hydraulic
performance.
Inlet Types
A number of different inlet configurations are utilized on culvert barrels. These include both
prefabricated and constructed in place installations. Commonly used inlet configurations include:
projecting culvert barrels; cast in place concrete headwalls; precast or prefabricated end sections;
and, culvert ends mitered to conform to the fill slope. Drawings of these inlet configurations are
shown in Figure 9.4. Structural stability, aesthetics, erosion control, and fill retention are
considerations in the selection of various inlet configurations.
The hydraulic capacity of a culvert may be improved by appropriate inlet selection. Since the
natural channel is usually wider than the culvert barrel, the culvert inlet edge represents a flow
contraction and may be the primary flow control. The provision of a more-gradual flow transition
will lessen the energy loss, and thus create a more hydraulically-efficient inlet condition. Beveled
edges, therefore, are more efficient than square edges. Side tapered and slope tapered inlets,
commonly referred to as improved inlets, further reduce the flow-contraction losses.
Depressed inlets, such as slope tapered inlets, increase the effective head on the flow-control
section, further increasing the efficiency of the culvert. To design tapered inlets, refer to Hydraulic
Design of Highway Culverts, FHWA Hydraulic Design Series No. 5 (HDS 5).
Different materials used in constructing culverts result in different structural and performance
properties. These properties include:
• Durability;
• Structural strength;
• Hydraulic roughness;
• Embedment conditions;
• Abrasion and corrosion resistance;
• Watertightness requirements.
Durability
Durability (service life) is defined by the number of years a pipe lasts until it becomes structurally
or functionally unfit for the intended purpose. The estimated minimum-service life under normal
conditions for all types of culvert pipes listed in the CDOT Standard Specifications for Road and
Bridge Construction must be 50 years. This service life covers pipes used for highway drainage
systems, including cross culverts, siphons, and side drains.
Structural Strength
Structural design of the culvert barrel must provide adequate strength to resist the moments, thrusts,
and shears determined through structural analysis. The prism load (dead load), dynamic load (traffic
load), type of pipe material and pavements (flexible or rigid), and the properties of in situ soil,
backfill, embedment, bedding, and foundation materials should be determined before an adequate
structural analysis is performed. The designer should refer to the CDOT M & S Standards for
strength requirements of structures with standard sizes. The Bridge Engineer should be consulted
C h a p t e r 9 — C u l v e r t s 9-10
if the proposed structure is not standard, or if, for any reason, it requires special design. The
structural requirements specified by the Bridge Engineer, and those found in the CDOT M & S
Standards should apply during and after construction.
Hydraulic Roughness
Hydraulic roughness represents the hydraulic resistance to flow by culverts. Manning’s equation is
commonly used to calculate barrel-friction losses in culvert design. The hydraulic resistance
coefficients for corrugated-metal conduits are based on the size and shape of the corrugations,
spacing of the corrugations, type of joints, bolt or rivet roughness, method of manufacture, size of
conduit, flow velocity, and aging. For concrete pipe, the hydraulic resistance varies with the method
of manufacture, field installation, quality of joints, and aging. For concrete box culverts, the
hydraulic resistance is based on the method of manufacture, quality of the formwork, installation
or construction practices, and aging. Typical ranges of recommended Manning’s n values are given
HDS 5.
Embedment Conditions
For rigid pipe, the embedment distributes the load over the foundation. For flexible pipe, the
embedment resists the deflection of the pipe due to load. The flat surface makes compaction
difficult at the very bottom of large structures. Trenches should be wide enough to permit
compacting the remainder of the embedment under the haunches of the structure. Refer to CDOT
M&S Standards for limits for structure excavation backfill, and fill-height requirements (allowable
minimum and maximum cover).
Abrasion is the erosion of culvert material, primarily due to the natural movement of bedload in
the stream. Effects of abrasion on the life of culverts in Colorado are poorly documented. In the
past, only a few of the Department’s culverts required repair as a result of abrasion damage. This
C h a p t e r 9 — C u l v e r t s 9-11
changed dramatically in recent years, due to aging of existing installations. When abrasion
problems are expected, several options are available to designers:
• Debris-control structures, although requiring periodic maintenance, can be used to reduce
or eliminate flow of abrasive material into culverts.
• A liner or bottom reinforcement utilizing additional abrasion-resistant material is another
option.
• Concrete or bituminous lining of the invert of corrugated metal pipes is a commonly-
employed method to minimize effects from abrasion.
• Concrete culverts may require additional cover over the reinforcement bars, or high-
strength concrete mixes to resist abrasion.
• 2 to 6 inches of high-strength concrete, placed over the reinforcing steel, may be used to
minimize abrasion of pipes. Using Ultra High Performance Concrete (UHPC) or higher
strength concrete for culvert floors might also be a consideration.
• The use of metal or wooden planks attached to the culvert bottom, normal to the flow, will
trap and hold bedload materials, thereby providing invert protection.
• Oversized culvert barrels which are partially buried accomplish the same purpose.
Methods of predicting abrasion performance of metal pipe may be available from the manufacturer.
If preliminary evaluation indicates that deterioration of pipe by abrasion is likely, the designer may
consult with the manufacturer to determine the required pipe thickness.
All available culvert materials are subject to deterioration when placed in certain corrosive
environments. The required level of corrosion resistance (C.R.) is determined by the Region and
Staff Materials Engineers, using site soil and water tests, and by visual observations of culverts in
the area. The C.R. level must be specified in the project plans. The contractor will then be allowed
to select alternate culvert materials as specified in Section 624 - Corrosion Resistant Culverts, of
the Standard Specifications for Road and Bridge Construction.
Watertightness Requirements
Watertightness pertains to the tightness of fit of installed pipes in order to be impermeable to water.
Piping caused by seepage along a culvert removes fill material and forms a hollow similar to a pipe.
Fine soil particles are freely washed out along this hollow, and erosion inside the fill may ultimately
cause failure of the culvert or embankment. Piping may also occur through open joints in the culvert
barrel. It is important that culvert joints be as watertight as practical. The designer must ensure that
the proposed pipe system is sufficiently watertight to accommodate the hydrostatic pressure
resulting from the design headwater. Headwalls, impervious materials at the upstream end of the
culvert, and anti-seep or cutoff collars decrease the probability of piping. Anti-seep collars usually
consist of bulkhead-type plates or blocks around the entire perimeter of a culvert. They may be of
metal or of reinforced concrete and, if practical, their dimensions should be sufficient to key into
impervious material.
Culverts are classified into two basic groups, based on the flow-control type: inlet-control culverts,
and outlet-control culverts. The basis for this classification is the location of the control section.
The hydraulic capacity of a culvert depends on a different combination of factors for each type of
control. An accurate theoretical analysis of culvert flow is extremely complex and requires the
following:
C h a p t e r 9 — C u l v e r t s 9-12
Inlet control occurs when the culvert barrel is capable of conveying more flow than the inlet will
accept. The control section of a culvert operating under inlet control is located just inside the
entrance. Critical depth occurs at, or near this location, and the flow region immediately
downstream is supercritical. Figure 9.5 shows a typical inlet-control flow condition. Hydraulic
characteristics downstream of the inlet-control section do not affect the culvert capacity. The
upstream water-surface elevation and the inlet geometry represent the major flow controls. Inlet
geometry includes the barrel shape, cross sectional area, and the inlet edge. The majority of existing
culverts in Colorado highways operate under inlet control.
Three regions of flow for inlet control are shown in Figure 9.6. They are: 1) unsubmerged, 2)
transition, and 3) submerged. The equations used to develop the graphical solutions, and to define
inlet-control conditions are presented in FHWA publication HDS No. 5.
For an unsubmerged region of flow, headwater elevation is below the inlet crown, and the entrance
operates as a weir. A weir is a flow-control section where the upstream water-surface elevation can
be predicted for a given flow rate. The relationship between flow and water-surface elevation must
be determined by model tests of the weir geometry, or by measuring prototype discharges. These
tests are then used to develop equations. Appendix A of FHWA HDS No. 5 contains the equations
which were developed from model-test data.
For a submerged region of flow, headwater elevation is above the inlet, and the culvert operates as
an orifice. An orifice is an opening, submerged on the upstream side and flowing freely on the
downstream side, which functions as a control section. The relationship between flow and
headwater can be defined based on results from model tests.
C h a p t e r 9 — C u l v e r t s 9-13
The transition zone is located between the unsubmerged and submerged flow conditions, where the
flow is poorly defined. This zone is approximated by plotting the unsubmerged and submerged
flow equations, and connecting them with a line tangent to both curves.
Outlet-control flow occurs when the culvert barrel is not capable of conveying as much flow as the
inlet opening will accept. The control section for outlet-control flow in a culvert is located at the
barrel exit, or further downstream. The culvert may outfall into a pond, lake, gulch, creek, river, or
other drainageways. In an outlet-control condition, the water-surface elevations or tailwater on
these waterways are high enough to cause backwater upstream of the culvert inlet, and therefore
control the flow.
In culvert barrels operating under outlet control, either subcritical or pressure flow exists. Figure
9.7 shows typical outlet-control flow conditions. Under outlet-control flow conditions, all
geometric and hydraulic characteristics of the culvert affect its capacity. These characteristics
include all factors governing inlet control, water-surface elevation at the outlet (tailwater), slope,
length, and hydraulic roughness of the culvert barrel. Graphical representations defining flow in
culverts operating in outlet control conditions are presented in FHWA HDS No. 5.
Roadway overtopping begins when headwater rises to the elevation of the roadway. Overtopping
usually occurs at the low point of a sag vertical curve on the roadway.
C h a p t e r 9 — C u l v e r t s 9-14
Various equations
The following equation is used to define the overtopping flow across the roadway. The equation is
the same relationship used to define the flow over a broad-crested weir. Flow coefficients for flow
overtopping roadway embankments are given in Figure 9.8.
Qr = Cd L (HWr)1.5 (9.1)
Where Qr = overtopping flow rate, cfs; Cd = overtopping discharge coefficient (kt Cr);
kt = submergence coefficient; Cr = discharge coefficient; L = length of roadway crest, ft;
HWr = upstream depth, measured above the roadway crest, ft.
Crest length is difficult to determine when the crest is defined by a roadway sag vertical curve. It
is recommended to subdivide the length into a series of segments. Calculate the flow over each
segment for a given headwater. The flows for each segment are then added together to determine
the total flow. The length can be represented by a single horizontal line (one segment). The length
of the weir is the horizontal length of this segment. The depth is the average depth of the upstream
pool above the roadway.
Total flow is calculated for a given upstream water-surface elevation using the above overtopping
equation. The roadway overflow plus culvert flow must equal the total design flow. A trial-and-
error process is necessary to determine flow passing through the culvert, and the amount flowing
across the roadway. Performance curves for culvert and road overflow may be summed to yield an
overall performance (see Section 9.5).
C h a p t e r 9 — C u l v e r t s 9-15
Design criteria that must be considered for all culvert designs are listed below by categories.
Culvert Location
The Region normally submits field culvert reports, specifying culvert location with supporting
survey and topography. Survey transmitted to the Hydraulics Unit must conform with requirements
of the CDOT Survey Manual.
C h a p t e r 9 — C u l v e r t s 9-16
Cross culverts must be located as close as possible to the natural drainage waterway. Combining
flows from several channels into a common channel, in order to use only one cross culvert, is
discouraged. However, if combining is necessary, care must be taken to avoid severe erosion or
deposition of silt at the culvert outlet. The same caution applies to concentrating sheet flow from
wide or undefined waterways. Flow should not be diverted to another watershed without an
evaluation of the legal and physical consequences.
Culvert Alignment
From the standpoint of hydraulic efficiency, durability, and maintenance, abrupt changes in flow
direction are undesirable. The maximum angle of bend at any point along a culvert’s horizontal or
vertical alignment should be 22o 30’. This angle of bend must be referenced to an alignment taken
along the side of the culvert nearest to the center of curvature. Any angle of bend greater than this
value should be divided into smaller angles, and the miters spaced at a minimum interval of 1.2
times the total diameter or span of the culvert. As an alternative to mitering, and if difficulty of
construction dictates, the culvert can be curved using a minimum radius of curvature equal to 3
times the diameter or span. Similar to mitering, curving should be applied along the side of the
culvert nearest to the center of curvature.
Any abrupt change of direction at either end of a culvert will retard flow, and may trap debris and
cause scouring or silting. The ideal design is to locate a culvert in the existing streambed. Although
this is not always feasible, channel changes should be minimized. Water should be intercepted by
the cross culvert as close as possible to where the drainage channel first impinges on the highway
template. If a channel change cannot be avoided, it should be made at the culvert outlet, rather than
at the inlet. In general, when a roadway crosses an irrigation ditch, the skew angle of the crossing
cannot be changed in order to reduce the culvert length.
Culvert length and slope must be chosen to approximate existing topography. To the degree
practical, the culvert invert should be aligned with the flowline and skew angle of the stream. The
culvert entrance must match the geometry of the roadway embankment.
The length of a culvert is determined from the structure cross section. The end of a culvert is
positioned in relation to the fill slope, as shown in the CDOT M&S Standards. The culvert length
C h a p t e r 9 — C u l v e r t s 9-17
should be increased to compensate for soil sloughing from steep, high fills by projecting the culvert
end out an additional 1 foot for each 10 feet of fill height. The length should be increased as required
on skewed culverts with ends perpendicular to the flow. These guidelines may be modified when
safety, right of way, or physical obstructions dictate.
To reduce sediment deposition within a culvert, slopes should be selected steep enough to maintain
or exceed natural-channel velocities. Broken back culvert slopes are discouraged, and abrupt slope
changes may trap debris, making culvert cleaning difficult. However, in mountainous regions, a
broken-back slope may be necessary to avoid placing the outfall high on the fill. See Section 9.2.3
for a discussion on broken-back culverts.
In cases where the streambed is aggrading, the culvert flowline may be raised accordingly. This
reduces sedimentation in the barrel. However, due to the uncertainty of continued aggradation, the
culvert height should be increased, leaving the flowline as is. Conditions causing aggradation may
be natural, or man- made downstream control. The designer should not select the culvert flowline
until upstream and downstream channel-flowline elevations are known. Ground lines of a structure
cross section may not represent the channel bottom, causing the designer to erroneously set the
culvert flowline on the banks of the channel. The channel flowline may be determined from field
survey data or a contour map. The field survey data must include channel cross sections as stated
in the CDOT Survey Manual.
Ice Buildup
Debris control must be designed using Hydraulic Engineering Circular No. 9, “Debris Control
Structures,” and must be considered:
• Where experience or physical evidence indicates the watercourse will transport a heavy
volume of controllable debris;
• For culverts located in mountainous or steep regions;
• For culverts under high fills; and
• Where clean-out access is limited. However, access must be available to clean out the
debris-control device.
The designer should seek information concerning the type and the amount of debris expected during
a major flow. Since it is nearly impossible to calculate the volume by visual observation of the
basin, history from previous flows in the proximity of the site is most reliable. The designer may
attempt to retain the debris upstream of the entrance, or intentionally pass it through the culvert.
It is not feasible to retain small debris, such as silt, small stones, brush, or trash, upstream of a
culvert. Generally, it is also not feasible to retain larger debris, such as large boulders and trees.
Debris-control devices are often unsightly and expensive, and they can require considerable
maintenance after each flood occurrence. If the storage capacity of a debris trap is too small for a
C h a p t e r 9 — C u l v e r t s 9-18
major storm, water may be diverted away from the culvert entrance, causing more damage than
under natural conditions.
When debris is passed through a culvert, the size of the culvert must be adequate to prevent
excessive ponding at the entrance. If debris is to be retained upstream, a debris-control structure is
necessary.
The center web wall in a concrete box culvert can collect excessive debris. If excessive debris is
expected, a single-span culvert is favored. Cost comparisons should be made between a single span,
and larger double- or triple-cell concrete box culverts. An upstream, sloping web wall is effective
in reducing plugging by floating debris. See Chapter 10 Bridges for more information.
Generally, excessive silt is not deposited in a culvert, provided the inlet and outlet are on, or above,
the flowline of the channel. Exceptions may occur if the culvert is so wide that the velocity in the
culvert is less than in the natural channel, or if the culvert constricts a supercritical channel.
Allowable Headwater
Allowable headwater is the depth of water that can be ponded or tolerated at the upstream end of a
culvert. The allowable headwater does not permit encroachment of water into adjacent roadway, or
inundation of upstream property. Both the surrounding features and flow limitations must be
considered for each site before the allowable headwater is determined. The potential for future
development must also be considered in determining elevation of allowable headwater.
Surrounding features which may control the allowable headwater include:
• Lowest elevation of the roadway subgrade adjacent to the ponding area;
• Flowline of the roadway ditch which passes water along the roadway to another drainage
basin; and
• Upstream property, such as buildings or farm crops, which will be damaged if inundated.
Flow-limitation factors that can affect the allowable headwater values include:
When the above factors are insignificant, the ratios of headwater depth to structure depth (HW/D)
from the flowline, given in Table 9.3, should be used as maximum values in design. These values
should be reduced to a ratio of 1.0 or less when design flows are from snowmelt, or in irrigation
ditches.
The use of HW/D ratios greater than those values given in Table 9.3 must be approved by the
Region Hydraulic Engineer. For detention ponds, all hydraulic-design work should be performed
C h a p t e r 9 — C u l v e r t s 9-19
by the Region Hydraulic Engineer. Refer to Chapter 12 - Storage Facilities, and the U.S. Bureau of
Reclamation’s, “Design of Small Dams,” for additional information on design of detention ponds.
Review Headwater
Review headwater is the flood depth that does not exceed a 1-ft increase over the existing 100-year
flood elevation in the National Flood Insurance Program’s mapped floodplains, or in the vicinity
of insurable buildings. The level of inundation must be tolerable by upstream property and roadway
for the review discharge.
Minimum Velocity
Minimum velocity in the culvert barrel must result in a tractive force ( = dS) greater than critical
of the transported streambed material at low-flow rates. Use 3 ft/s when streambed material size
is not known. If clogging is probable, consider installation of a sediment trap, or a size of culvert
that facilitates cleaning.
If storage is being assumed upstream of the culvert, consideration must be given to:
• Limiting the total area of flooding;
• Limiting the average time that bankfull stage is exceeded for the design flood to 48 hours
in rural areas, or 6 hours in urban areas; and
C h a p t e r 9 — C u l v e r t s 9-20
• Ensuring that the storage area will remain available for the life of the culvert by purchase
of right-of-way or an easement.
Flood Frequency
The flood frequency used to design or review a culvert must be based on:
• Roadway classification;
• Level of risk associated with failure of the crossing, increasing backwater, or redirection
of floodwaters;
• An economic assessment or analysis that justifies flood frequencies greater or lesser than
the minimum-flood frequencies listed below; and
• Location of FEMA-mapped floodplains.
The flood frequency used to design a culvert must be based on criteria given in
Chapter 7 - Hydrology. The minimum design frequencies for various types of roads, terrain, and
flood magnitudes are listed in Table 7.2 of Chapter 7 - Hydrology. Frequencies in this table must
be used unless an economic analysis indicates otherwise. The minimum design frequency for
through-lanes of interstate highways cannot be less than a 50-year flood frequency.
Selection of culvert size and shape must be based on engineering and economic criteria related to
site conditions. The minimum diameters allowed for various types of applications are listed in Table
9.4. Land-use requirements (e.g. need for a cattle pass) can dictate a larger or different barrel
geometry than required for hydraulic considerations. Use arch or oval shapes only if required by
hydraulic limitations, site characteristics, structural criteria, or environmental criteria.
A circular culvert is the most efficient shape because of its higher ratio of cross-sectional area to
the wetted perimeter relative to other shapes with identical cross sectional areas. A narrow but high
rectangular culvert is less expensive than a wide, low culvert of the same area. However, the wider
culvert has several advantages that are very important. The wider culvert spreads the outlet flow
more, and the outlet flow is shallower and has slightly slower velocity, causing less outlet erosion
damage. A lower culvert is necessary where clearance is minimal and headwater depths are limited.
Broken-Back Culverts
A broken-back culvert, which combines two different slopes, may be necessary to accommodate a
large differential of flow-line elevation, or may result from one or more extensions to an original
straight-profile culvert.
Multiple Barrels
Multiple-barrel culverts must fit within the dominant natural channel with minor widening of the
channel to avoid conveyance loss through sediment deposition in some of the barrels. They are to
be avoided where:
• The approach flow is high velocity, particularly if supercritical. These sites require either
a single barrel, or special inlet treatment to avoid adverse hydraulic-jump effects.
• Irrigation canals or ditches are present, unless approved by the canal or ditch owner;
C h a p t e r 9 — C u l v e r t s 9-21
• Fish passage is required, unless special treatment is provided to ensure adequate low flows
(commonly one barrel is lowered);
• A high potential exists for debris problems (clogging of culvert inlet); or
• A meander bend is present immediately upstream.
Material Selection
Material selection must consider replacement cost, difficulty of construction, and traffic delay
during construction. The material selected must be based on a comparison of the total cost of
alternate materials over the design life of the structure, considering the following:
• Durability (service life);
• Structural strength;
• Hydraulic roughness;
• Bedding conditions;
• Resistance to abrasion and corrosion; and
• Water-tightness requirements.
The selection must not be made using first cost as the only criterion. Refer to Appendix C – CDOT
Pipe Material Selection Guide for an in-depth discussion on material selection.
Culvert Skew
Culvert skew is the acute horizontal angle left or right (looking in the direction of increasing
stations) between the centerlines of the roadway and culvert. The culvert skew must not be less
than 45 degrees without the approval of the Region Hydraulic Engineer.
A culvert’s inlet type must be selected from the following list, based on considerations given and
inlet coefficients. Refer to FHWA HDS No. 5 for recommended values of entrance-loss
coefficients. Consideration must also be given to safety, since some end treatments can be
C h a p t e r 9 — C u l v e r t s 9-22
hazardous to errant vehicles. All culverts 48 inches in diameter and larger should have headwalls
or slope paving on the inlet end.
Projecting Inlets or Outlets:
• Extend beyond the roadway embankment and are susceptible to damage during roadway
maintenance, and from errant vehicles;
• Have low construction cost;
• Have poor hydraulic efficiency for thin materials;
• Are used predominantly with metal pipe; and
• Must include anchoring the inlet to strengthen the weak leading edge for culverts 4 feet in
diameter and larger.
Mitered Inlets:
• Are hydraulically more efficient than thin-edge projecting;
• Must be mitered to match the fill slope; and
• Must include anchoring the inlet, to strengthen the weak leading edge for culverts 4 feet in
diameter and larger.
Tapered Inlets:
• When practicable, should only be considered for culverts that will operate in inlet control;
and
• Are not recommended when fish passage is required.
Refer to Section 9.8 for a discussion on various types of tapered inlets.
Headwalls:
• A full headwall is required for culverts with area ≥ 50 ft2, diameter ≥ 96 in;
• A concrete Type S headwall is the minimum required for metal culverts with diameters ≥
42 in, operating under inlet control;
• Headwalls should be placed perpendicular to the culvert centerline for all culverts with
span less than 7 feet;
• For wider spans, use the following steps to determine if the headwall is to be placed
perpendicular to the culvert, or parallel to the roadway:
i. Subtract the width of culvert (ft) from the culvert skew (degrees);
ii. Use headwalls perpendicular to the culvert if the result is greater than 50; or
iii. Use headwalls parallel to roadway if the result is less than 50.
Headwalls with Bevels:
• Increase the efficiency of metal pipe;
• Provide embankment stability and embankment-erosion protection;
• Provide protection from buoyancy;
• Shorten the required structure length; and
• Reduce maintenance damage.
C h a p t e r 9 — C u l v e r t s 9-23
Improved Inlets:
• Must be considered for culverts with inlet control;
• Can increase the hydraulic performance of the culvert, but may also add to the total culvert
cost. They should only be used if practicable.
• With a slope-taper, must not be considered where fish passage is required.
Commercial End Sections:
• All cross culverts and side drains must be installed with end sections, unless other types of
end treatments are shown to be more appropriate.
• Are available for both corrugated-metal and concrete pipe;
• Retard embankment erosion and incur less damage from maintenance;
• May improve projecting metal-pipe entrances by increasing hydraulic efficiency, reducing
the accident hazard, and improving their appearance; and
• Are hydraulically equal to a headwall, but can be equal to a beveled or side-tapered
entrance if a flared, enclosed transition occurs before the barrel.
Wingwalls:
• Are used to retain roadway embankment and avoid a projecting culvert barrel;
• Are used where side slopes of the channel are unstable;
• Are used where the culvert is skewed to the normal channel flow;
• Provide the best hydraulic efficiency if the flare angle is between 30oand 60o ; and
• Concrete wingwalls must be used in all box culverts and pipes with full concrete headwalls.
Wingwall geometry is initially determined by a combination of six parameters identified in Figure
9.9. These parameters include:
• The distance in feet from the flowline to the crown (H, Ba, or Rise generally fixes the value
of the height in feet of the upper end of the wingwall);
• The skew angle of the culvert, ;
• The roadway fill slope, Z;
• The height in feet of the lower end of the wingwall, k, which can be determined from the
given equation below. The site topography should dictate the actual value of k that must
be used.
• The angle between the wingwall and a line parallel to the roadway, a or b;
• The length of the wingwall, l, in feet.
A schematic drawing of the culvert layout should be shown in the plans, identifying k, , and l for
each wingwall (m should also be shown if other than standard). The following guidelines should
be used in selecting the values for the above six parameters in most situations. However, the
designer must set the wings to conform to the culvert site, even though the geometry differs from
these guidelines.
C h a p t e r 9 — C u l v e r t s 9-24
A wingwall flare angle from 20o to 40o normally provides a hydraulically-efficient inlet condition
for the culvert. Use of the recommended values for a or b given in Table 9.5, and k will generally
create a smooth flow transition from channel to culvert, and keep the spill cone out of the projected
jet of flow.
Skew Angle, a b
90 60 60
80 50 70
70 45 80
60 40 90
50 30 90
40 20 100
30 15 105
< 30 Consult the Region Hydraulic Engineer
A plan showing site contours or spot elevations is often helpful when laying out the final wingwall
geometry, especially when the wingwalls must conform to a distinct channel. Allow a spill cone
slope of 1.5:1 or flatter at the wingwall ends to assure that the main flow jet, roughly defined by
the culvert width, does not impinge on the spill cone.
Culvert headwalls must be perpendicular to the culvert centerline unless excessive cost or aesthetics
favor a skewed headwall. A wide culvert with a small skew angle usually justifies the skewed
headwall as discussed in the section on headwalls.
Aprons:
• Must be used to reduce scour from high-headwater depths, or from approach velocity in
the channel.
• Must extend at least twice the box rise / pipe diamter upstream, but should not be more
than 10 ft.
• Must not protrude above the normal streambed elevation.
• Concrete aprons must be used at the outlet of a culvert with wingwalls, and at both inlet
and outlet if the culvert also serves as a stockpass.
• Concrete aprons should be considered at the outlet for scour protection.
• If scour damage is anticipated, a concrete apron should be placed between the wingwalls.
Toe walls are required on all wingwalls, except when a concrete apron is used. Toe walls are placed
on the end of the apron as shown in the CDOT M & S Standards.
Cut-off Walls:
• Are used to prevent piping along the culvert barrel, and undermining at the culvert ends.
• Must be used on all culverts with headwalls or slope paving.
• Must be located as shown in the CDOT M&S Standards, or 20 inches below the scour hole.
Safety Considerations
Prepare a cross section of the placement site for each entrance or intersecting road pipe culvert.
Pipes should not be installed through permanent maintenance crossovers on an Interstate. Median
drainage approaching a crossover should be removed with a pipe across the mainline highway. This
will provide for safer crossover inslopes.
Weep Holes
If weep holes are used to relieve uplift pressure in wingwalls and other types of wall structures,
they must be designed in a manner similar to underdrain systems. The location of weep holes should
be selected carefully to avoid creating an icing hazard.
Performance Curves
Development of performance curves should be considered for evaluating the hydraulic capacity of
a culvert where various headwaters, outlet velocities, and scour depths are concerns. These curves
will display the consequence of high-flow rates at the site and provide a basis for evaluating flood
hazards.
Buoyancy Protection
Headwalls, endwalls, slope paving, or other means of anchoring to provide buoyancy protection,
must be considered for all flexible culverts. Buoyancy is more serious with steepness of culvert
slope (due to higher velocities and hydrodynamic forces), depth of potential headwater (debris
blockage may increase), inadequate fill height, large culvert skews, or mitered ends.
Fire Protection
A fully concrete headwall must be considered for any size of thermoplastic culvert pipes if project
site is located in areas where risk of fire is relatively high.
Outlet treatment should be designed to restore natural-flow conditions downstream. The outlet
should be carefully scrutinized for conditions which can produce scour (see Chapter 11 - Energy
C h a p t e r 9 — C u l v e r t s 9-27
Dissipators). When detrimental scour is expected, protective measures should be utilized. The two
common types of channel instability are headcutting, or knickpoint propagation, and scour holes.
Headcutting occurs over a long reach and is influenced insignificantly by the increased culvert
velocity. Generally, it is a result of concentrated flow or natural conditions downstream which are
independent of the culvert.
Scour holes are caused by high outlet velocities and concentrated flows. Aside from aesthetics,
scour holes are not necessarily detrimental, unless structural damage due to undermining occurs.
In fact, scour holes at culvert outlets provide efficient energy dissipators. As such, outlet protection
for the selected culvert design flood must only be provided where the outlet scour-hole-depth
computations indicate:
• The scour hole will undermine the culvert outlet;
• The expected scour hole may cause costly property damage;
• The scour hole causes a nuisance effect (most common in urban areas);
• The scour hole blocks fish passage; or
• The scour hole will restrict land-use requirements.
Headcutting may be controlled by a series of check dams. These will likely be located outside of
the right-of-way. Keeping the culvert-outlet elevation low will avoid or reduce the undermining
problem. However, lowering should be done only when beneficial, and then with caution so as not
to reduce the culvert’s capacity. A deep toe wall, a buried rundown, or a concrete apron will also
protect the culvert’s outlet.
Scour holes can be controlled with riprap, gabions, and plunge basins. Plunge basins are as effective
in reducing velocities as natural scour holes.
Relief Opening
Where multiple-use culverts, or culverts serving as relief openings, have their outlet set above the
normal stream flow line, special precautions are required to avoid headcuts that would undermine
the culvert outlet.
Land-Use Culverts
Consideration must be given to combining drainage culverts with other land-use requirements
necessitating passage under a highway:
• During the selected design flood, the land use is temporarily forfeited, but available during
lesser floods;
• When two or more barrels are required, with one situated to be dry during floods less than
the selected design flood. The outlet of the higher land-use barrel may need protection from
headcutting.
• A land-use culvert must be sized to ensure it can serve its intended land-frequency-use
function, up to and including a 2-year flood; and
• The height and width constraints must satisfy the hydraulic or land-use requirements,
whichever is larger.
C h a p t e r 9 — C u l v e r t s 9-28
Stock Passes
Economic justification should be determined for all proposed stock passes. Economic analyses
should be performed for both cases – with, and without, the proposed stock pass. The value of the
parcel of land on either side of the highway should be included in the economic evaluation. The
following data are required to determine if stock passes are economically justified, or necessary as
safety measures:
• The number of cattle or other livestock that would use the stock pass;
• The frequency of crossings by stock;
• The use of the stock pass for drainage; and
• The required size of drainage structure if the stock pass is not provided.
A proposed stock pass must consist of either a standard box culvert with an opening 6 feet wide
and 7 feet high, an 84-inch culvert, or a structural-plate arch culvert 5’ - 10” by 7’ - 8”. Approval
of the Region Transportation Director is required to use other sizes of stock-pass structures. Six
inches of earth fill material must be placed in the invert of a round or arch culvert after installation.
Stock passes that are not needed for drainage can be constructed away from the drainage site to
insure the most economical installation with respect to length, cover, and excavation requirement.
If unusual conditions clearly indicate the need for a larger stock pass, full details concerning the
proposed size of structures, local conditions, right of way considerations, cost comparisons, and all
other pertinent data must be submitted to the Region Transportation Director.
A 2-year minimum design-flood frequency is required for any stream crossing of a pedestrian
walkway or bikeway. A design frequency of less than 2 years may be used if appropriate, and
reasons must be stated in the drainage report. In general, selection of the appropriate design-flood
frequency for pedestrian walkways and bike paths should be justified by a cost/benefit ratio analysis
of the alternate designs.
Temporary erosion- and sediment-control measures must be included in the construction plans.
These measures include use of: silt boxes, straw silt barriers, brush silt barriers, filter cloth,
temporary silt fence, and check dams. For more information, see the CDOT Erosion Control and
Stormwater Quality Guide.
Care must be exercised in selecting the location of a culvert site in order to control erosion,
sedimentation, debris, and impact on aquatic organism passage. Select a site that will permit the
culvert to be constructed, and will limit impact on the stream, wetlands, and aquatic organism
passage. For more information, see Chapter 15 - Surface Water Environment.
Irrigation Facilities
Unless legally abandoned, an irrigation structure is required, even if the irrigation canal or ditch is
no longer used. The canal or ditch owner must approve the use of multiple-barrel culverts. In
general, the inlet and outlet ends of the irrigation structure should extend a maximum of 16.4 feet
left and right outside CDOT right of way. In some locations, extensions longer than the maximum
may be required. In both cases, construction easements must be obtained from the canal or ditch
C h a p t e r 9 — C u l v e r t s 9-29
owner. Provision must be made to accommodate any water escaping the ditch in order to avoid a
flood hazard.
Irrigation facilities must be designed to accommodate water rights and intercepted runoff using the
following criteria to give the largest culvert size:
• Constrain headwater within the existing canal or ditch banks, unless provision is made for
overflow during high flows;
• Provide freeboard to pass expected debris;
• There should be no increase in the velocity beyond what the unprotected ditch material or
protection will sustain;
• Avoid a flood hazard created by a canal or ditch failure;
• Provide a width capable of delivering the water and flood right at its existing operating
depth; and
• Provide for known winter-ice accumulation problems.
Detour Culvert Pipe Size
Temporary drainage structures, like detour culvert pipes, are normally required during construction
to accommodate both traffic and stream flows. From the standpoint of adequate hydraulic design,
the higher the design frequency used, the lower the risk of failure will be.
In general, the design flood for a temporary detour structure should be less than that of a permanent
drainage structure. The designer should select the design-flood frequency for the detour, and at the
same time minimize the cost of culvert pipes. Refer to Table 7.2 of Chapter 7 - Hydrology to
determine the design frequency used in sizing the detour culvert pipe. After the design flood is
established using reasonable and acceptable hydrology methods, the design steps outlined in sizing
permanent culvert structures may be followed to size the detour culvert pipe.
Since detour culvert pipes in general are temporary installations, they are placed without headwalls,
and sometimes without adequate cover. For this reason, installation procedures should ensure
minimal risk of failure of the detour pipe due to buoyancy forces.
Good construction practices involving detour culvert pipes include locating the detour culvert pipe
upstream of the proposed permanent-structure site, and constructing the drainage structure during
low-flow seasons.
The use of round pipe with buried inverts is sometimes necessary because of environmental
requirements or various other reasons. For example, the pipe invert must be buried under native or
borrow materials to improve passage of fish or livestock if the culvert is used as a stockpass. A
metal-pipe invert may also be buried under concrete and other lining materials to reduce or
eliminate the impact of heavy sediment loads that can cause abrasion and subsequent corrosion.
It is not always necessary to fill the invert up to the natural-channel flowline, as water will transport
sediment which will do the backfilling. To use a round pipe with a buried invert, the size of the
round pipe should be selected so that its capacity will be equivalent to that of the required unburied
pipe arch. Refer to FHWA’s publication “Design of Depressed Invert Culverts” for the procedure
C h a p t e r 9 — C u l v e r t s 9-30
to determine the required equivalent diameter of buried round pipe. The equivalent diameter is the
diameter of a circle which has an area equal to the total area above the bed of a depressed-invert
culvert. Figure 9.10 and Tables 9.6(a) and 9.6(b) provide a diagram of a buried round pipe, and a
comparison of the areas of unburied metal-arch pipes and partially-buried pipes.
On roadway, utility, and drainage projects, pipe-jacking operation is commonly used to install a
piping system with minimal, or no interruption to the vehicular traffic or any type of utility service.
Design and construction guidelines are required to accomplish pipe jacking in a cost effective
manner. Guidelines for jacking welded steel and reinforced concrete pipe (RCP) are provided in
Appendix B.
The design of a culvert system for a highway crossing of a floodplain requires information from
the following chapters in this manual: Policy, Documentation, Planning and Location, Hydrology,
Channels, Energy Dissipators, Storm Drainage Systems, Surface Water Environment, and Erosion
and Sediment Control. Each of these should be consulted as appropriate. The discussion in this
section is focused on analysis of alternatives and design methods.
Culvert alternatives must satisfy topography, and design policies and criteria. Alternatives must be
analyzed for:
• Environmental impact;
• Hydraulic equivalency; and
• Risk and cost.
C h a p t e r 9 — C u l v e r t s 9-32
Select an alternative that best integrates engineering, economic, and political considerations. The
selected culvert must conform with all selected structural and hydraulic criteria, and selection based
on:
• Construction and maintenance costs;
• Risk of failure or property damage;
• Traffic safety;
• Environmental or aesthetic considerations;
• Political or nuisance considerations; and
• Land-use requirements.
9.4.2 Design Methods
Culvert - a covered structure with both ends open. It is designed using the procedures in HDS 5.
Storm Drain - a covered structure with either end in a manhole. It is usually part of a system of
pipes. Storm drains are explained in FHWA Hydraulic Engineering Circular No. 22 (HEC 22),
Urban Drainage Design Manual, and designed using FHWA Hydraulic Toolbox software (see
Chapter 13 – Storm Drains).
Inverted Siphon - a covered structure sometimes termed a sag culvert, with both ends open, and
operates at a low head. The invert profile dips below the approach and exit channels. Inverted
siphons are designed using procedures in the U.S. Bureau of Reclamation’s Design of Small Canal
Structures.
Hydrology Methods
Constant Discharge - Constant discharge, usually the peak discharge, is assumed for most culvert
designs. This yields a conservatively-sized structure where temporary storage is available, but not
normally used.
Hydrograph and Routing - Significant storage will reduce the required culvert size. Storage
capacity behind a highway embankment attenuates a flood hydrograph and reduces the peak
discharge. It is checked by routing the design hydrographs through the culvert site to determine the
outflow hydrograph and stage (backwater) behind the culvert. Procedures are found in
Chapter 12 - Storage Facilities, and HDS 5, Section V.
Computational Methods
Computer Software:
See Section 9.11 - Software for Designing Culverts.
Graphical Solution:
• Allow a trial-and-error solution which is easy and provides reliable designs for many
applications;
C h a p t e r 9 — C u l v e r t s 9-33
• Require additional computations for tailwater, outlet velocity, and roadway overtopping;
and
• May require additional computations for hydrographs and routing.
Charts for circular and box shapes are included at the end of this Chapter. Other shapes and
improved inlets are found in HDS 5.
9.5.1 General
HDS 5 describes standard practice for hydraulic design of culverts. The following standard
practices apply:
• All culverts should be hydraulically designed;
• The overtopping flood selected should be consistent with the class of highway, and
appropriate for the risk at the site;
• Survey information should include topographic features, channel characteristics, aquatic
life, high-water information, existing structures, and other related site-specific information.
Refer to Chapter 6 - Data Collection;
• Culvert location in both plan and profile should be investigated to minimize the potential
for sediment buildup in culvert barrels;
• The cost savings of multiple uses (utilities, stock and wildlife passage, land access, and
fish passage) should be weighed against the advantages of separate facilities;
• Culverts should be designed to accommodate debris, or appropriate provisions should be
made for debris maintenance;
• Material selection should include consideration of service life that includes abrasion and
corrosion;
• Culverts should be located and designed to present a minimum hazard to traffic and people;
• The detail of documentation for each culvert site should be appropriate for the risk and
importance of the structure. Design data and calculations should be assembled in an orderly
fashion and retained for future reference as provided for in Chapter 4 – Documentation;
and
C h a p t e r 9 — C u l v e r t s 9-34
• Where practical, some means should be provided for personnel and equipment access to
facilitate maintenance.
Design Discharge - Culverts should be designed for a constant discharge, typically the peak
discharge. This will yield a conservatively-sized structure where temporary storage is available but
not used.
Control Section - The control section is the location where there is a unique relationship between
the flow rate and the upstream water-surface elevation. Inlet control is governed by the inlet
geometry. Outlet control is governed by a combination of the culvert-inlet geometry, barrel
characteristics, and tailwater or critical depth.
Minimum Performance - Minimum performance is assumed by analyzing both inlet and outlet
control, and basing the design on the highest headwater. The culvert may operate more efficiently
at times (more flow for a given headwater level), but will not operate at a lower level of
performance than calculated.
Figure 9.11 illustrates the types of inlet control flow. The USGS flow type depends on the
submergence of the inlet and outlet ends of the culvert. In all of these examples the control section
is at the upstream end of the barrel (the inlet). The flow passes through critical depth near the inlet
and becomes shallow, high-velocity (supercritical) flow in the culvert barrel. Depending on the
tailwater, a hydraulic jump may occur downstream of the inlet.
Since the control is at the upstream end, only the headwater and the inlet factors affect the culvert
performance:
Headwater Depth - is measured from the inlet invert of the inlet control section to the surface of
the upstream pool.
Inlet Area - is the cross-sectional area of the face of the culvert. Generally, the inlet face area is the
same as the barrel area. For tapered inlets (Section 9.8) the face area is enlarged, and the control
section is at the throat.
Inlet Edge - describes the entrance type. Some typical inlet edge configurations are thin-edge
projecting, mitered, square edges in a headwall, and beveled edge.
Inlet Shape - is usually the same as the shape of the culvert barrel. Typical shapes are rectangular,
circular, elliptical and arch. Check for an additional control section, if different than the barrel.
Barrel Slope - influences inlet control performance, but the effect is small. Inlet control charts
assume a slope of 2% for the slope correction term (0.5S for most inlet types). This results in
lowering the headwater required by 0.01D. In the computer program HY-8, the actual slope is used
as a variable in the calculation.
Hydraulics
Inlet control performance is defined by the three regions of flow shown in Figure 9.12:
unsubmerged, transition and submerged.
Unsubmerged
For headwater between the invert and the culvert height, as shown in Figure 9.13 A and C, the
entrance of the culvert operates as a weir. A weir is a flow control section where the upstream water
surface elevation can be predicted for a given flow rate. The relationship between flow and water-
surface elevation must be determined by model tests of the weir geometry, or by measuring
prototype discharges. These tests are then used to develop equations. Appendix A of HDS 5
contains equations developed from model test data.
Submerged
For headwaters submerging the culvert entrance the culvert operates as an orifice, as shown in
Figure 9.13 B and D. An orifice is an opening, submerged on the upstream side and flowing freely
on the downstream side, which functions as a control section.
The relationship between flow and headwater can be defined based on results from model tests.
Appendix A of HDS 5 contains flow equations developed from model test data.
Transition Zone
The transition zone is located between the unsubmerged (weir control) and the submerged (orifice
control) flow conditions, where the flow is poorly defined. This zone is approximated by plotting
the unsubmerged- and submerged-flow equations, and connecting them with a line tangent to both
curves.
C h a p t e r 9 — C u l v e r t s 9-36
Graphical Solution
The inlet-control flow versus headwater curves which are established using the above procedure
are the basis for constructing the inlet-control design charts, and for developing equations used in
software. The original equations for computer software were generally 5th order polynomial curve-
fitted equations developed to be as accurate as the graphical solution (plus or minus 10%) within
the headwater range of 0.5D to 3.0D. These equations are still being used in HY-8, but have been
supplemented with a weir equation from 0.0D to 0.5D, and an orifice equation above 3.0D. Note
that in the inlet-control solutions, HW is measured to the total upstream energy grade line, including
the approach-velocity head.
Inlet Depression
Inlet depression is created by constructing the entrance inlet below the streambed. The amount of
inlet depression is defined as the depth from the natural streambed at the face to the inlet invert.
The inlet-control equations or charts provide the depth of headwater above the inlet invert required
to convey a given discharge through the inlet. This relationship remains constant regardless of the
elevation of the inlet invert. If the entrance end of the culvert is constructed below the streambed,
more head can be exerted on the inlet for the same headwater elevation.
C h a p t e r 9 — C u l v e r t s 9-37
Outlet control has depths and velocity that are subcritical. Figure 9.13 illustrates the types of outlet-
control flow. The USGS flow type depends on the submergence of the inlet and outlet ends of the
culvert. In all cases, the control of the flow is at the downstream end of the culvert (the outlet) or
further downstream. The tailwater depth is either assumed to be critical depth near the culvert outlet
or the downstream channel depth, whichever is higher. In a given culvert, the type of flow is
dependent on all barrel factors. All inlet-control factors also influence culverts in outlet control.
Barrel Roughness - is a function of the material used to fabricate the barrel. Typical materials
include concrete and corrugated metal. Roughness is represented by a hydraulic resistance
coefficient, such as the Manning’s n value. Typical values for Manning’s n are presented in Table
9.2. Additional discussion on the sources and derivations of the Manning’s n values are contained
in HDS-5, Appendix B.
Barrel Area - is measured perpendicular to the flow.
Barrel shape - is a function of culvert type and material. Based on the location of the center of
gravity for a given area, a box is the most efficient shape, then the arch shape, followed by the
circular pipe.
Barrel Length - the total culvert length from the entrance crown to the exit crown of the culvert.
Because the design height of the barrel and the slope influence the actual length, an approximation
of barrel length is usually necessary to begin the design process.
Barrel Slope - the actual slope of the culvert barrel, often the same as the slope of the natural stream.
However, where the culvert inlet or outlet is raised or lowered, the barrel slope is different from
the stream slope. The slope is not a factor in calculating the barrel losses for USGS Flow Types 4,
6, and 7, but is a factor in calculating USGS Flow Types 2 and 3 when a water-surface profile is
calculated.
Tailwater Elevation - is based on the downstream water-surface elevation. Backwater calculations
from a downstream control, normal-depth approximation, or field observations are used to define
the tailwater elevation.
Hydraulics
Full flow in the culvert barrel is assumed for the analysis of outlet-control hydraulics. Outlet-control
flow conditions can be calculated based on energy balance from the tailwater pool to the headwater
pool. Outlet control can occur as full, partial flow, or a combination of both through the culvert.
A. Losses:
HL = HE + Hf + Hv + Hb + Hj + Hg (9.5)
Where: HL = total energy loss, ft; HE = entrance loss, ft; Hf = friction losses, ft; Hv = exit loss
(velocity head), m (equivalent to Ho; see Equation 9.8d); Hb = bend losses, ft; Hj = losses at
junctions, ft; Hg = losses at grates, ft.
These and other losses are discussed in HDS 5.
B. Velocity:
V = Q/A (9.6)
3
Where: V = average barrel velocity, ft/s; Q = flow rate, ft /s; A = cross sectional area of flow with
the barrel full, ft2.
C h a p t e r 9 — C u l v e r t s 9-38
C: Velocity Head:
Hv = V2/2g (9.7)
2
Where: g = acceleration due to gravity, 32.2 ft/s .
D. Entrance Loss:
HE = KE(V2/2g) (9.8a)
Where: KE = entrance loss coefficient.
E. Friction Loss:
Hf = [(29n2L)/R1.33] [V2/2g] (9.8b)
Where: n = Manning’s roughness coefficient; L = length of the culvert barrel, ft; R = hydraulic
radius of the full culvert barrel = A/P, ft; P = wetted perimeter of the barrel, ft.
F. Exit Loss:
Ho = 1.0 [V2/2g) – (Vd2/2g)] (9.8c)
Where: Vd = channel velocity downstream of the culvert, ft/s (usually neglected, in which case the
exit loss is equal to the full-flow velocity head in the barrel, as shown in Equation 9.8d).
Equation 9.8c may overestimate exit losses, and a multiplier of less than 1.0 can be used (see
FHWA Hydraulic Engineering Circular No. 14, HEC 14, Hydraulic Design of Energy Dissipators
for Culverts and Channels for transition loss).
Ho = Hv = V2/2g (9.8d)
C h a p t e r 9 — C u l v e r t s 9-39
G. Barrel Losses:
H = HE + Ho + Hf (9.9)
2 1.33 2
H = [1 + Ke + (29n L/R )] [V /2g]
Energy Grade Line
The energy grade line represents the total energy at any point along the culvert barrel. Equating the
total energy at Sections 1 and 2, upstream and downstream of the culvert barrel, the following
relationship results:
HWo + (Vu 2/2g) = TW + (Vd 2/2g) + HL (9.10)
Where: HWo = headwater depth above the outlet invert, ft; Vu = approach velocity, ft/s; TW =
tailwater depth above the outlet invert, ft; Vd = downstream velocity, ft/s; HL = sum of all losses
(Equation 9.1).
This equation is true only if TW is higher than critical depth at the outlet. Additionally, the total
available upstream headwater (HWo) includes the depth of the upstream water above the inlet invert
and the approach velocity head. In most instances, the approach velocity is low and the approach
velocity head is neglected. However, it can be considered to be a part of the available headwater
and used to convey the flow through the culvert. Likewise, the velocity downstream of the culvert
(Vd) is usually neglected.
The hydraulic grade line is the depth to which water would rise in vertical tubes connected to the
sides of the culvert barrel. In full flow, the energy grade line and the hydraulic grade line are parallel
lines separated by the velocity head, except at the inlet and the outlet.
HDS 5 Charts (Full Flow)
Graphical solutions have been developed assuming that the culvert barrel is flowing full and:
• TW ≥ D, Flow Type 4 (see Figure 9.13 D), or dc ≥ D, Flow Type 6 (see Figure 9.13 B);
• Vu is small and its velocity head can be considered to be a part of the available headwater
(HW) used to convey the flow through the culvert; and
• Vd is small and its velocity head can be neglected.
Equation (9.10) becomes:
HW = TW + H – SoL (9.11)
Where: HW = depth from the inlet invert to the energy grade line, ft; H = the value read from the
charts (Equation 9.5), ft; So L = drop from inlet to outlet invert, ft.
C h a p t e r 9 — C u l v e r t s 9-40
Equations (9.5) through (9.11) were developed for full-barrel flow. The equations also apply to
USGS Flow Types 6 and 7, which are effectively full-flow conditions, if TW < dc (see Figure
9.13 B).
Backwater calculations may be required for partially-full flow conditions (see Figures 9.13 A and
C). These calculations begin at the downstream water surface and proceed upstream. If the depth
intersects the top of the barrel, a full flow extends from that point upstream to the culvert entrance.
Based on numerous backwater calculations performed by FHWA, it was found that the hydraulic
grade line pierces the plane of the culvert outlet at a point approximately one half the way between
critical depth and the top of the barrel, or (dc + D)/2 above the outlet invert. This approximation
should only be used if the barrel flows full for part of its length, or the headwater is at least 0.75D.
If neither of these conditions are met, a water-surface profile should be used to establish the
hydraulic grade line. TW should be used if higher than (dc + D)/2. The following equation should
be used:
HW = ho + H - SoL (9.12)
Where: ho = the larger of TW or (dc + D)/2, ft.
Adequate results are obtained down to HW = 0.75D. For lower headwaters, backwater calculations
are required. See Figure 9.13 A if TW < dc , and Figure 9.13 C if TW > dc .
Culvert outlet velocities must be calculated to determine the need for erosion protection at the
culvert exit. Culverts usually have outlet velocities higher than the natural-stream velocities. These
outlet velocities may require flow readjustment or energy dissipation to prevent downstream
erosion. If outlet erosion protection is necessary, the flow depths and Froude number may also be
needed (see Chapter 11 - Energy Dissipators).
C h a p t e r 9 — C u l v e r t s 9-41
Inlet Control
For inlet control the velocity is calculated from Equation 9.10 after determining the outlet depth.
Either of the following methods may be used to determine the outlet depth:
• Calculate the water-surface profile through the culvert. Begin the computation at dc at the
entrance and proceed downstream to the exit. Determine the depth and flow area at the exit.
• Assume normal depth and velocity. This approximation may be used because the water
surface profile converges towards normal depth if the culvert is of adequate length. This
outlet velocity may be slightly higher than the actual velocity at the outlet. Normal depths
may be obtained by hand computation or by software (e.g. FHWA Hydraulic Toolbox).
Outlet Control
Under outlet control, the cross-sectional area of flow is defined by the geometry of the outlet and
either critical depth, tailwater depth or the height of the conduit:
• Critical depth is used where the tailwater is less than critical depth;
• Tailwater depth is used where tailwater is greater than critical depth, but below the top of
the barrel; and
• The total barrel area is used where the tailwater exceeds the top of the barrel.
9.5.6 Roadway Overtopping
Roadway overtopping will begin when the headwater rises to the elevation of the roadway. It will
usually occur at the low point of a sag vertical curve on the roadway. The flow will be similar to
flow over a broad-crested weir. Flow coefficients for flow overtopping roadway embankments are
found in Figure 9.8.
Q0 = Cd LHWr1.5 (9.13)
Where: Q0 = overtopping flow rate, ft3/s; Cd = overtopping discharge coefficient (weir coefficient)
= kt Cr in which, kt = submergence coefficient, Cr = discharge coefficient; L = length of roadway
crest, ft; HWr = the upstream depth, measured above the roadway crest, ft.
Roadway crest length is difficult to determine where the crest is defined by a roadway sag vertical
curve. Two methods may be used to overcome this:
• Subdivide the length into a series of segments. The flow over each segment is then
calculated for a given headwater. The flows for each segment are added together to
determine the total flow.
• The length can be represented by a single horizontal line (one segment). The length of the
weir is the horizontal length of this segment. The depth is the average depth (area/length)
of the upstream pool above the roadway.
Total Flow
Total flow is calculated for a given upstream water surface elevation using Equation 9.1.
• Roadway overflow plus culvert flow must equal total design flow;
• A trial-and-error process is necessary to determine the flow passing through the culvert,
and the amount flowing across the roadway; and
C h a p t e r 9 — C u l v e r t s 9-42
• Performance curves for the culvert and the road overflow may be summed to yield an
overall performance.
A performance curve is a plot of flow rate versus headwater depth, elevation, velocity, or outlet
scour. The culvert performance curve is made up of controlling portions of individual performance
curves for inlet, outlet, and roadway-control sections. Performance curves can be developed for all
culverts to evaluate hydraulic capacity of a culvert for various headwaters, outlet velocities, and
scour depths. These curves display consequences of high flow rates at the site, and provide a basis
for evaluating flood hazards.
Inlet Performance Curve - The inlet performance curve is developed using inlet-control charts (see
design charts provided at the end of this chapter).
Outlet Performance Curve - The outlet performance curve is developed using Equations 9.5 - 9.13,
outlet-control charts (see the appropriate design chart at the end of this chapter), or backwater
calculations.
Roadway Performance Curve - The roadway performance curve is developed using the equation
for roadway-overtopping flow (Equation 9.13).
Overall Performance Curve - The overall performance curve is the sum of the flow through the
culvert and the flow across the roadway, and can be determined by performing the following steps:
1. Select a range of flow rates and determine the corresponding headwater elevations for the
culvert flow alone. These flow rates should fall above and below the design discharge, and
cover the entire flow range of interest. Both inlet- and outlet-control headwaters must be
calculated.
2. Combine the inlet- and outlet-control performance curves to define a single performance
curve for the culvert.
3. When the culvert-headwater elevations exceed the roadway-crest elevation, overtopping
begins. Calculate the upstream water surface depth above the roadway for each selected
flow rate. Use these water surface depths and the equation for roadway overtopping flow
to calculate flow rates across the roadway.
4. Add the culvert flow and the roadway overtopping flow at the corresponding headwater
elevations to obtain the overall culvert-performance curve as shown in Figure 9.15.
C h a p t e r 9 — C u l v e r t s 9-43
The Culvert Design Form, shown in Figure 9.16, has been formulated to guide the user through the
design process. Summary blocks are provided at the top of the form for the project description and
the designer’s identification. Summaries of hydrologic data are also included. At the top right is a
small sketch of a culvert with blanks for inserting important dimensions and elevations.
C h a p t e r 9 — C u l v e r t s 9-44
The following design procedure provides a convenient and organized method for designing culverts
for a constant discharge, considering inlet and outlet control. The procedure does not address the
effect of storage which is discussed in Chapter 12 - Storage Facilities.
The designer should be familiar with all equations in Section 9.5 before using these procedures.
Following the design method without an understanding of culvert hydraulics can result in an
inadequate, unsafe, or costly structure.
A computation form has been provided in Appendix A to guide the user. It contains blocks for the
project description, designer’s identification, hydrologic data, culvert dimensions and elevations,
trial culvert description, inlet and outlet control HW, culvert barrel selected and comments.
control. If HWi is equal to HWoi , the culvert is both in inlet and outlet control. Use the
higher value as the controlling headwater.
Step 10 Compute Discharge Over the Roadway, Qr :
a. Compute culvert discharge Q, discharge over the roadway, Qr , and total discharge Qt ,
by
trial-and-error method, or graphically by using the performance curve. The culvert
discharge Q is the discharge corresponding to the non-overtopping elevation.
b. Determine the overtopping discharge, Qr , from the equation:
Qr = Cd L (HWr)1.5
Qr = 0 if flow does not overtop the roadway. See section on roadway overtopping for
the definition of the variables used in the equation.
c. Calculate depth above the roadway (HWr):
i. HWr = HWc − HWov
ii. HWov = height of road above inlet invert
d. If HWr 0, Qr = 0; if HWr > 0, determine Cd from Figure 9.8.
e. Determine length of roadway crest, L
f. Calculate Qr
Qr = Cd L (HWr)1.5 (9.12)
Step 11 Compute Total Discharge, Qt:
a. Determine the total discharge Qt from the equation: Qt = Q + Qr
b. Repeat the calculation process until Qt ≈ Qd. Refer to HDS 5 for procedure to construct
performance curves.
Step 12 Calculate Outlet Velocity, Vo and Depth, dn :
If inlet control is the controlling headwater:
a. Calculate flow depth at culvert exit:
i. Use normal depth, dn , or
ii. Use water surface profile
b. Calculate flow area, A.
c. Calculate exit velocity, Vo = Q/A.
If outlet control is the controlling headwater:
a. Calculate flow depth at culvert exit:
i. Use dc if dc > TW.
ii. Use TW if dc < TW < D.
iii. Use D if D < TW.
b. Calculate flow area, A.
c. Calculate exit velocity, Vo = Q/A.
Step 13 Review Results
a. Compare alternative design with constraints and assumptions. If any of the following
conditions are not met, repeat steps 5 through 12:
i. The barrel must have adequate cover;
ii. The length must be close to the approximate length;
C h a p t e r 9 — C u l v e r t s 9-48
information is to be placed with the structure note on the plan sheet, or in a tabulation. On special-
design culverts, this information is to be placed on the layout sheet. The above information is also
required for culverts to be extended, unless pipe diameter is 24 in or less. See Chapter 4 -
Documentation for additional requirements.
9.7.1 Introduction
Flood routing through a culvert is a practice that evaluates the effect of temporary upstream ponding
caused by the culvert’s backwater. By not considering flood routing, it is possible that findings
from culvert analyses will be conservative. If the selected allowable headwater is considered
acceptable without flood routing, then costly overdesign of both the culvert and outlet protection
may result, depending on the amount of temporary storage involved. Special considerations
associated with culvert flood routing are discussed in the following subsections:
Culvert Replacement Applications - Normally, a smaller culvert may be used for the same
headwater condition.
Environmental - Evaluating environmental concerns may be more realistic.
Flood Hazards - A routing culvert design may require less land for an upstream easement, and
assessments of potential flood hazards may be more realistic.
Sediment - Estimation of sediment accumulation is required.
Limitations - Temporary storage must be available.
Improved hydrologic methods or changed watershed conditions are factors that can cause an older,
existing culvert to be inadequate. A culvert analysis that relies on findings that ignore any available
temporary storage may be misleading. A flood-routing analysis may show that what was thought
to be an inadequate existing culvert is, in fact, adequate.
Often existing culverts require replacement due to corrosion or abrasion. This can be very costly,
particularly where a high fill is involved. A less-costly alternative is to place a smaller culvert inside
the existing culvert. A flood-routing analysis may demonstrate that this is acceptable where there
is sufficient storage, as no increase in flood hazard results.
Environmental
With culvert flood routing, a more realistic assessment can be made where environmental concerns
are important. The temporary time and extent of upstream ponding can be estimated. This allows
environmental specialists to assess whether such ponding is beneficial or harmful to localized
environmental features (e.g. fisheries, beaver ponds, wetlands, uplands).
Flood Hazards
Potential flood hazards increase upstream wherever a culvert increases the natural flood stage.
Some of these hazards can conservatively be assessed without flood routing. However, some
damages associated with culvert backwater are time-dependent, and thus require an estimate of
depth versus duration of inundation. Some vegetation and commercial crops can tolerate longer
C h a p t e r 9 — C u l v e r t s 9-50
periods of inundation than others, and to greater depths. Such considerations become even more
important when litigation is involved.
Sediment
Limitations
There are situations where culvert sizes and velocities obtained through flood routing will not differ
significantly from those obtained by designing to the selected peak discharge, ignoring any
temporary upstream storage. This occurs where:
• There is no significant temporary pond storage available (as in deep incised channels);
• The culvert must pass the design discharge with no increase in the natural channel’s flood
stage; and
• Runoff hydrographs last for long periods of time, such as with snowmelt runoff (or
irrigation flows).
In addition to the previous design equations (Section 9.5), the following routing equations must
be used. The basic flood routing equation is:
I - O = ∆S / ∆t, or (9.14)
2S1 / ∆t- O1 + I1 + I2 = 2S2 / ∆t + O2 (9.15)
For a finite interval of time, ∆t, equation 9.14 can be expressed by:
∆S = Qi ∆t - Q0 ∆t (9.16)
From these equations:
(I1 + I2)/2 = ∆S / ∆t + O1 /2 + O2 /2 (9.17)
Where: ∆S = S2 - S1; S1 = storage volume in the temporary pond at the beginning of the incremental
time period ∆t, ft3; S2 = storage volume in the temporary pond at the end of the incremental time
period ∆t, ft3; ∆t = incremental routing time interval selected to subdivide the hydrograph into
finite time elements, s; I = average hydrograph inflow to the temporary pond during incremental
time period ∆t, ft3/s; I1 = instantaneous inflow to the temporary pond at the beginning of the
incremental time period ∆t, ft3/s; I2 = instantaneous inflow at the end of the time period ∆t, ft3/s; O
= average outflow from the temporary pond during incremental time period ∆t, ft3/s; O1 =
instantaneous outflow at the beginning of the time period ∆t, ft3/s; O2 = instantaneous outflow at
the end of the time period ∆t, ft3/s.
9.7.3 Design Procedure
The design procedure for flood routing through a culvert is the same as for reservoir routing. The
site data and roadway geometry are obtained, (Data Collection Chapter) and the analysis of
hydrology completed, including estimating a hydrograph (Hydrology Chapter). Once this essential
information is available, the culvert can be designed.
C h a p t e r 9 — C u l v e r t s 9-51
Design Steps
• Determine the average hydrograph inflow and volume discharge corresponding to the first
selected time increment.
• Recognizing that, with an increasing headwater, the temporary pond storage will generally
reduce this inflow, select a trial outflow (from the culvert) discharge that is less than the
inflow discharge.
• With this smaller outflow discharge, estimate the headwater from the trial culvert(s)
performance curve.
• Use this headwater to estimate the storage volume corresponding to this headwater from
the upstream stage-storage curve.
• Compute the outflow volume corresponding to the selected outflow discharge and the
previously-selected time increment.
• Subtract this volume from the foregoing average inflow volume. This is the volume that
would have to go into temporary upstream pond storage.
• Compare this volume with the volume corresponding to the previously-estimated
headwater. If they are the same (or nearly so), proceed to the next step; if not, repeat this
step using a different trial outflow discharge.
Step 6a Increasing HW: The procedure for subsequent routing steps where the headwater is
increasing is similar to the initial routing step. The difference is in how storage is handled:
• Determine the average hydrograph inflow and volume discharge corresponding to the next
selected time increment.
• Recognizing that, with an increasing headwater, the temporary pond storage will generally
reduce this inflow, select a trial outflow discharge (from the culvert) that is less than the
inflow discharge.
• With this smaller outflow discharge, estimate the headwater from the trial culvert(s)
performance curve.
• Use this headwater to estimate the storage volume corresponding to this headwater from
the upstream stage-storage curve.
• Compute the outflow volume corresponding to this selected outflow discharge and the
previously-selected time increment.
• Subtract this volume from the foregoing average-inflow volume. This is the volume that
would have to go into temporary upstream storage.
• Add this volume to the volume already in storage.
• Compare this total volume with the volume corresponding to the previously-estimated
headwater. If they are the same (or nearly so), proceed to the next step. If not, repeat this
step using a different trial outflow discharge.
Step 6b Decreasing HW: This procedure is similar to the routing steps for increasing headwater.
The difference is, (1) the selected trial-culvert outflow discharge will be greater than the average
inflow hydrograph discharge, and (2) the outflow volume is greater than the inflow volume, so the
temporary pond storage volume will be decreasing:
• Determine the average hydrograph inflow and volume discharge corresponding to the next
selected time increment.
• Recognizing that, with a decreasing headwater, the temporary pond storage will be
decreasing, select a trial outflow (from the culvert) discharge that is larger than the inflow
discharge.
C h a p t e r 9 — C u l v e r t s 9-53
• With this larger outflow discharge, estimate the headwater from the trial culvert(s)
performance curve.
• Use this headwater to estimate the storage volume corresponding to this headwater from
the upstream stage-storage curve.
• Compute the outflow volume corresponding to this selected outflow discharge and the
previously-selected time increment.
• Subtract this volume from the foregoing average-inflow volume. This is the volume that
would go into temporary upstream pond storage.
• Subtract this volume from the volume already in storage.
• Compare this total volume with the volume corresponding to the previously-estimated
headwater. If they are the same (or nearly so), proceed to the next step; if not, repeat this
step using a different trial outflow discharge.
Step 7 Criteria Check: Following (or during) the previous routing steps, compare the resulting
headwater and outlet velocity, and temporary pond size and duration, with the corresponding
criteria selected for the site. If there is a violation of these criteria, return to step 1 and select a larger
trial culvert. A smaller trial culvert would be selected if there appeared to be a significant over-
design.
9.8.1 General
A tapered inlet is a flared culvert inlet with an enlarged face section and a hydraulically-efficient
throat section. A tapered inlet may have a depression, or fall, incorporated into the inlet structure
or located upstream of the inlet. The depression is used to exert more head on the throat section for
a given headwater elevation. Tapered inlets improve culvert performance by providing a more
efficient control section (the throat). Tapered inlets are not recommended for use on culverts
flowing in outlet control because the simple beveled edge is of equal benefit.
Design criteria and methods have been developed for two basic tapered inlet designs: the side
tapered inlet and the slope tapered inlet.
Tapered inlet design charts are available for rectangular-box culverts and circular-pipe culverts.
9.8.2 Side-Tapered
A side tapered inlet has an enlarged face section with the transition to the culvert barrel
accomplished by tapering the side walls (Figure 9.17). The face section is approximately the same
height as the barrel height, and the inlet floor is an extension of the barrel floor. The inlet roof may
slope upward slightly, provided that the face height does not exceed the barrel height by more than
10% (1.1D). The intersection of the tapered sidewalls and the barrel is defined as the throat section.
There are two possible control sections, the face and the throat. HWf, shown in Figure 9.17, is the
headwater depth measured from the face-section invert, and HWt is the headwater depth measured
from the throat-section invert. The throat of a side tapered inlet is a very efficient control section.
The flow contraction is nearly eliminated at the throat. In addition, the throat is always slightly
lower than the face so that more head is exerted on the throat for a given headwater elevation.
The beneficial effect of depressing the throat section below the streambed can be increased by
installing a depression upstream of the side tapered inlet. Figure 9.18 depicts a side tapered inlet
C h a p t e r 9 — C u l v e r t s 9-54
with the depression contained between wingwalls. For this type of depression, the floor of the barrel
should extend upstream from the face a minimum distance of D/2 before sloping upward more
steeply. The length of the resultant upstream crest, where the slope of the depression meets the
streambed, should be checked to assure that the crest will not control the flow at the design flow
and headwater. If the crest length is too short, the crest may act as a weir-control section. The barrel
is defined as the throat section.
The slope tapered inlet, like the side-tapered inlet, has an enlarged face section with tapered
sidewalls meeting the culvert barrel walls at the throat section (Figure 9.19). In addition, a vertical
fall is incorporated into the inlet between the face and throat sections. This fall concentrates more
head on the throat section. At the location where the steeper slope of the inlet intersects the flatter
slope of the barrel, a third section, designated the bend section, is formed.
A slope-tapered inlet has three possible control sections: the face, the bend, and the throat. Of these,
only the dimensions of the face and the throat sections are determined by the design procedures of
HDS 5. The size of the bend section is established by locating it a minimum distance upstream
from the throat, so that it will not control the flow.
S
L1
L1S
Elevation
Symmetrical
Wingwall Flare
Bf
Angles from L1 B
15° to 90°
Plan
Figure 9.17 Side-tapered inlet
The slope-tapered inlet combines an efficient throat section with additional head on the throat. The
face section does not benefit from the fall between the face and throat. The face sections of these
inlets are larger than the face sections of equivalent depressed side tapered inlets. The required face
C h a p t e r 9 — C u l v e r t s 9-55
size can be reduced by the use of bevels, or other favorable edge configurations. The vertical face
slope-tapered inlet design is shown in Figure 9.19.
The slope-tapered inlet is the most complex inlet improvement recommended in this manual.
Construction difficulties are inherent, but the benefits in increased performance can be significant.
With proper design, a slope-tapered inlet passes more flow at a given headwater elevation than any
other configuration. Slope-tapered inlets can be applied to both box culverts and circular-pipe
culverts. For the latter application, a square-to-round transition is normally used to connect the
rectangular, slope-tapered inlet to the circular pipe.
HWf
HWc
E
So HWt
D
T
S
D/2 (Min.)
Elevation
Crest
Throat Section
W
2T (Min.)
Bf B
Symmectrical
Wingwall
Angle
Face Section
Plan
Figure 9.18 Side-tapered inlet with upstream depression contained between wingwalls
Inlet Control
Tapered inlets have several possible control sections including the face, the bend (for slope-tapered
inlets), and the throat. In addition, a depressed side tapered inlet has a possible control section at
the crest, upstream of the depression. Each of these inlet-control sections has an individual
performance curve. The headwater depth for each control section is referenced to the invert of the
section. One method of determining the overall inlet control performance curve is to calculate
performance curves for each potential control section, then select the segment of each curve which
defines the minimum overall culvert performance (Figure 9.20).
C h a p t e r 9 — C u l v e r t s 9-56
Side-Tapered Inlet: The side-tapered inlet throat should be designed to be the primary control
section for the design range of flows and headwaters. Because the throat is only slightly lower than
the face, it is likely that the face section will function as a weir, or an orifice with downstream
submergence within the design range. At lower flow rates and headwaters, the face will usually
control the flow.
Slope-Tapered Inlet: The slope-tapered inlet throat can be the primary control section, with the face
section submerged or unsubmerged. If the face is submerged, the face acts as an orifice with
downstream submergence. If the face is unsubmerged, the face acts as a weir, with the flow
plunging into the pool formed between the face and the throat. As previously noted, the bend section
will not act as the control section if the dimensional criteria of HDS 5 are followed. However, the
bend will contribute to the inlet losses that are included in the inlet loss coefficient, kE.
Outlet Control
When a culvert with a tapered inlet performs in outlet control, the hydraulics are the same as
described in Section 9.5 for all culverts. The tapered inlet entrance loss coefficient kE is 0.2 for both
side-tapered and slope-tapered inlets. This loss coefficient includes contraction and expansion
losses at the face, increased friction losses between the face and the throat, and the minor expansion
and contraction losses at the throat.
C h a p t e r 9 — C u l v e r t s 9-57
Tapered-inlet design begins with the selection of the culvert barrel size, shape, and material. These
calculations are performed using the Culvert Design Form provided in the Appendix. The design
procedure is similar to designing a culvert with other control sections (face and throat). The result
will be one or more culvert designs, with and without tapered inlets, all of which meet the site’s
design criteria. The designer must select the best design for the site under consideration.
In the design of tapered inlets, the goal is to maintain control at the efficient throat section in the
design range of headwater and discharge. This is because the throat section has the same geometry
as the barrel, and the barrel is the most costly part of the culvert. The inlet face is then sized large
enough to pass the design flow without acting as a control section in the design discharge range.
Slight oversizing of the face is beneficial, because the cost of constructing the tapered inlet is
usually minor compared with the cost of the barrel.
Performance Curves
Performance curves are of utmost importance in understanding the operation of a culvert with a
tapered inlet. Each potential control section (face, throat and outlet) has a performance curve based
on the assumption that the particular section controls the flow. Calculating and plotting the various
performance curves results in a graph similar to Figure 9.21, containing the face control, throat
control and outlet control curves. The overall culvert performance curve is represented by the
hatched line. In the range of lower discharges, face-control governs. In the intermediate range,
throat-control governs. And, in the higher discharge range, outlet-control governs. The crest and
bend performance curves are not calculated because they do not govern in the design range.
C h a p t e r 9 — C u l v e r t s 9-58
9.9.1 Introduction
An alternative to installing a steeply-sloped culvert is to break the slope into a steeper portion near
the inlet followed by a horizontal-runout section. This configuration is referred to as a broken-back
culvert. Broken-back culverts can be considered an internal (integrated) energy dissipater if
designed so that a hydraulic jump occurs in the runout section to dissipate energy (see HEC 14).
9.9.2 Guidelines
The broken-back configuration is one potential mechanism for creating a hydraulic jump. Two
types are depicted in Figures 9.22 and 9.23. When used appropriately, a broken-back culvert
configuration can influence and contain a hydraulic jump. However, there must be sufficient
tailwater and there should be sufficient friction and length in Unit 3 of the culvert. In ordinary
circumstances for broken-back culverts, the designer should employ one or more devices, such as
roughness baffles, to create a tailwater that is high enough to force a hydraulic jump.
C h a p t e r 9 — C u l v e r t s 9-59
The design of a broken-back culvert is not difficult, but provisions must be made so that the primary
intent of reducing velocity at the outlet is realized. The hydraulics of circular and rectangular
culverts can be determined using the FHWA HY-8 software or the Broken-Back Culvert Analysis
Program (BCAP) software from the Nebraska Department of Roads. The design of associated
energy dissipators is described in HEC 14, Chapter 7.
This section summarizes the most commonly-available culvert protection techniques and materials,
and discusses rehabilitation, repair and replacement methods available to extend culvert service
life. This section was based largely on the National Cooperative Highway Research Program
(NCHRP) Synthesis 474, Service Life of Culverts. NCHRP 474 should be consulted for additional
information on these topics.
C h a p t e r 9 — C u l v e r t s 9-60
Predominantly used with metal culverts to increase abrasion resistance, concrete can be placed in
the invert area of the pipe to a thickness between 3 and 6 in. Thickness and width of coverage varies
with typical flow depth and anticipated abrasive potential. Although the concrete may be placed
directly on clean pipe material, steel reinforcement, wire fabric, Nelson Studs, or a combination of
these are frequently welded to the metal pipe prior to concrete placement.
Although concrete paving is utilized to rehabilitate corroded and severely deteriorated inverts in
corrugated metal pipes, it can also be used in concrete culverts if adjustments are made (Figure
9.24). This method consists of placing a concrete lining in the invert, increasing surface roughness
(Manning’s n value), and decreasing flow velocity. The invert paving sections commonly vary from
90° to 180° for the internal angle, depending on the extent of deterioration on both sides of the
slope.
Concrete invert paving is generally regarded as a temporary repair. However, a survey undertaken
by the Minnesota DOT identified a case study where paving had lasted longer than 25 years.
Additionally, the Ohio DOT assumes a 20-year add-on service life with the use of concrete paving.
The main performance factors include the use of high-strength concrete with durable aggregate,
and ensuring that the concrete is sufficiently anchored to the pipe.
C h a p t e r 9 — C u l v e r t s 9-61
In California, the use of steel armor plating 0.25 to 0.50 inches thick, placed over the bottom third
of the pipe, is used as an alternative to concrete invert paving. This technique is costly, and mainly
suitable for large-diameter (diameter greater than 48 in) corrugated metal pipe with highly abrasive
water flows.
A wide variety of epoxy-coated treatments can be applied to protect and extend the life of concrete
culverts. These coatings are typically sprayed on, and are suitable for treating minor deterioration
of exposed concrete surfaces (i.e. pop-outs, minor scaling, hairline cracks, etc.). However, use of
epoxy coatings is not appropriate for severely deteriorated concrete (i.e. where steel reinforcement
is exposed).
Epoxy coatings are hard and bond well to property cleaned and prepared concrete. These types of
coatings should be regarded as maintenance treatments, but can help retard some forms of concrete
degradations, and provide additional service life in appropriate applications.
Pipe rehabilitation and repair technologies are discussed in detail in the literature review of NCHRP
Project 14-19 Culvert Rehabilitation to Maximize Service Life While Minimizing Direct Costs and
Traffic Disruption. NCHRP 14-19 should be consulted for additional information on these topics.
Sliplining: Sliplining is a method of rehabilitation where a new pipe of smaller dimeter is inserted
into the deteriorated culvert. The annular space between the host pipe and newly installed pipe is
then grouted with cementitious material.
Correctly sliplined culverts should provide the full service life associated with the type of pipe used
in the sliplining. Sliplining is generally equivalent to full pipe replacement in terms of service life.
Spirally-Wound Liner: Spirally-would liners are fabricated in the field from a continuous
thermoplastic strip composed of one male and one female edge (Photo 5). During the helical
winding process, female and male edges interlock to form a leak-tight joint. Spirally-wound liners
typically use nonstructural grout in annular space, or no grout at all.
C h a p t e r 9 — C u l v e r t s 9-62
Caltrans uses spirally-wound liners for both flexible and rigid pipes to provide a corrosion barrier
suitable to meet a 50-year design service life for abrasion levels 1 through 3 (see NCHRP Synthesis
474).
Sprayed-On Liner (Epoxy): Sprayed-on epoxy is typically used for rehabilitation of potable water
pipes, but can also be used to line culverts. Sprayed-on epoxy can be applied to protect against
corrosion and to make the culvert watertight, and is generally applied manually. Application
thickness is normally between 0.06 in and 0.25 in per application layer, with a minimum of two
layers recommended.
Limitations associated with use of polymer-based coatings include the culvert must be completely
free of water for installation, and extensive surface preparations may be necessary for successful
application. Epoxy-lining systems are relatively new, no data on service life is currently available.
CIP liners can be conventional or composite. Composite CIP liners are high-strength fiber-
reinforced CIP liners. Fiber reinforcement provides increased stiffness and strength, resulting in
thinner walls as compared to conventional CIP liners, and can be used to rehabilitate medium to
large sewers, drains, and culverts.
Numerous trenchless technologies for pipe replacement exist, including jack and bore (see
Appendix B), tunneling, and horizontal directional drilling. These methods are not discussed in this
section, but the pipe bursting/splitting method is discussed because it reuses the same alignment of
the existing culvert.
Pipe Bursting: Pipe bursting is defined as a trenchless replacement method in which an existing
pipe is broken either by brittle fracture or by splitting, using an internal mechanically applied force
applied by a bursting tool.
HDPE pipe is most commonly used pipe in pipe bursting replacement. Since HDPE pipes are
chemically inert, they can readily flex to meet changes in loading along the culvert length while
maintaining circular shape. Additionally, fusible PVC pipe, retained jointing PVC pipe, ductile iron
pipe, and vitrified clay pipe can be installed using pipe bursting.
C h a p t e r 9 — C u l v e r t s 9-64
Pipe bursting can replace circular pipes up to 54 in in diameter. The length typically is limited to
750 ft. Applicability is not limited by culvert pipe type or condition. Replacement can be performed
in active flow conditions. Most bursting projects involve pipes that were originally installed by
trenching or open cut because the fill material surrounding them is usually conducive to pipe
bursting. The potential for upsizing through pipe bursting depends on soil conditions, overburden
cover, and other factors.
Limitations of pipe bursting replacement primarily consist of difficulties that arise when existing
pipe composed of brittle material has had point repairs with ductile material. Pipe bursting can
cause ground heave or settlement above or at a distance from the culvert. This occurs particularly
in dense sand, when the culvert pipe is shallow and ground displacement is primarily directed
upwards, cause by significant diameter increases. Additionally, pipe bursting is not applicable when
the host pipe has significant sagging or deviation from the original grade.
The service life for pipe replacement by pipe bursting is expected to be equivalent to that for the
replacement pipe material.
Computer software is available for computing the hydraulics of culverts and energy dissipators in
open channels that follow the procedures outlined in this chapter and Chapter 11 - Energy
Dissipators. The primary software used is HY-8. This software assumes a headwater pool at the
entrance (no approach velocity), and that all the velocity head is loss at the exit (standard method),
or conserved (Utah State University method). If the culvert being designed is for a constructed
channel where energy conservation is important, the HEC-RAS software should be used. If the site
conditions warrant the use of a broken-back culvert, the HY-8 software should be used.
The software versions shown in Table 9.7 are the most recent when this manual was prepared. For
current versions of software and documentation, the hydraulic engineer should consult the software
source.
Available user and reference manuals are listed in the references. However, many software
developers provide extensive help within the software in place of a user’s manual.
C h a p t e r 9 — C u l v e r t s 9-65
HY-8 The FHWA Culvert Hydraulic Analysis Program (HY-8) FHWA website
enables users to analyze culvert performance for a
highway crossing that has multiple culvert barrels that
share the same tailwater, and roadway overtopping. HY-8
uses HDS-5 procedures and includes:
• Culvert configurations with constants in HDS-5
Appendix A:
i. Table A.1 - circles, boxes, and tapered
ii. Table A.2 - pipe-arches, ellipses, metal boxes,
and arches
iii. Table A.3 SDDOT - RCB
iv. Table A.4 CON/SPAN
v. Table A.5 embedded circular
vi. Table A.6 embedded elliptical
vii. User-defined shapes use Chart 52
• Embedded or depressed invert design;
• Utah State University outlet transition loss;
• Energy dissipator analysis (HEC-14);
• Internal hydraulic jumps;
• Broken-back barrel analysis; and
• Project documentation.
REFERENCES
Pipe Jacking and/or boring is done to install pipelines under roadways, railroads, runways, canals,
etc., without interrupting surface traffic. The choice of jacking pipe either by boring out the inside
of the pipe with rotary equipment, or by mining out the material within the pipe, is the option of
the contractor performing the installation. Jetting with water is not allowed.
CDOT’s bid system does not differentiate between mining and boring. All pipes placed without
trenching are identified in the bid items as jacked.
A jacked pipe may be used as a carrier pipe, or as a casing to protect a carrier pipe. Utilities such
as electrical wiring, water, natural gas, petroleum products, and sewage are transmitted through the
carrier pipe. The carrier pipe may be within a jacked casing pipe, allowing the utility pipe to be
removed, repaired, or replaced from within the casing without disruption to traffic. Storm drainage
generally is run directly through the carrier pipe.
Jacked pipe generally is reinforced concrete pipe, precast concrete boxes, or welded steel pipe.
Thirty six inch diameter pipe is the smallest practical diameter for mining jacked concrete or steel
pipe. The controlling criteria for the diameter of jacked pipe is the ability for workmen to maneuver
within the pipe. Concrete pipe as large as 132-inch diameter can be jacked. Precast concrete boxes
may be jacked in sizes up to approximately 10 feet by 10 feet. Welded steel pipe may be bored in
diameters up to 48 inches. Small diameter pipe is generally smooth welded steel.
Pipe jacking requires sufficient surface area to provide an access pit. This pit is used to set up
jacking equipment, and to remove the earth excavated from the jacked pipe. All utilities must be
located prior to commencing the jacking operation.
A safe working pit and a safe working area near the pit are essential to jacked pipe installation. The
beginning and end of the casing pipe should extend to a point at least 1 ft away from the edge of
the roadway for every 1 ft of depth. Surface working areas must be adequate to enable the contractor
to use a crane, trucks, and backhoe. A storage area for the excavated earth from the pit and for the
casing pipe should be available at the site.
The distance that a pipe can be jacked varies with the pipe size, pipe material, soil types, and
alignment.
Bare welded steel pipe is normally used for jacked casing pipe. A wall thickness of 0.25 inch for
pipe diameters of 12 in to 20 in provides a collapse pressure of 80 psi or more, as well as providing
handling rigidity. As sizes increase in diameter, the 80-psi collapse pressure can be used as a
minimum “wall thickness / diameter guide.” Evaluation of the 80-psi minimum-collapse pressure
must be made for special load conditions. Casing pipe for railroad crossings usually requires
heavier wall thickness for steel pipe, and the wall thickness is specified by the railroad owner.
Table B.1, containing values of wall thicknesses, is based on the 80-psi collapse pressure. It can be
used as a guide for minimum wall thickness.
C h a p t e r 9 — C u l v e r t s 9-83
Casing pipe is joined by field welding. CDOT Standard Specifications for Road and Bridge
Construction require a certified welder unless waived by a Project Special Provision. When the
casing pipe is bored, grouting the outside of the casing is not required, unless voids are created or
present. When a casing pipe is jacked by mining out the material, voids are usually created, and
must be grouted to avoid settlement of the ground above. This can be done from the casing pipe
interior, through 2-inch grout plugs spaced at given intervals throughout the casing. Grouting
pressures to pump the soil cement, or sand, cement, and water-slurry mix normally need not exceed
20 psi to adequately fill all earth voids. The grouting or sand filling of the void between the outside
of the jacking pipe and the over-excavation creates an almost-perfect bedding condition and may
be superior to normal trench-bedding conditions.
Carrier pipe is installed after completion of the casing installation by threading through the casing.
The carrier pipe is supported on wooden skids banded to the carrier pipe, or with factory-installed
skid bands that have runners around the band to support the carrier. Steel casing pipe placed by
boring or mining should be bare steel. The integrity of pipe coatings inside or outside of the pipe
cannot be maintained with jacking operations, and they are impossible to replace or repair. Extra
pipe thickness should be used to protect against corrosive environments.
Reinforced concrete pipe cannot be placed by boring due to the thick walls of the pipe. The material
within the area to be occupied by the jacked pipe, including the walls, must be removed by hand
mining.
Loading Criteria - Jacked Concrete Pipe
The class of reinforced concrete jacking pipe is determined from the table for the height of fill in
CDOT Standard M 603-2.
Reinforced concrete pipe is subject to the axial forces of the jacking operations, dead load, and live
load. The jacking forces must be evenly distributed around the periphery of the ends of the pipe by
C h a p t e r 9 — C u l v e r t s 9-84
use of a heavy rope wrap or plywood. The dead load on the jacked pipe is usually less than a trench
installation (with a trench width equal to the bore), due to the cohesive force of the soil reducing
overburden load.
Reinforced concrete jacking pipe is manufactured in all joint types, with a smooth outside surface
of the pipe barrel. Although tongue and groove (TG) or rubber and concrete (RC) joints can be used
as a jacking pipe, rubber and steel (RS) joints are often used to increase the integrity of the joint
under the severe installation conditions of the jacking operation.
Jacking Installation Procedures
The leading edge of reinforced concrete pipe is usually protected with a steel cutting guide or shoe,
to protect the pipe joint. Material is excavated in front of the lead pipe, while an axial force is
applied along the pipe centerline. A lubricant such as bentonite is applied to the outside of the pipe
at the jacking pit, or is pumped through the grout nipples as the jacking operation progresses. The
jacking operation is often a continuous operation from beginning to completion. Alignment rails in
the jacking pit can be set in concrete to assist in the control of the alignment and grade. Careful
excavation at the lead pipe to prevent over-excavation, allow alignment of the guiderails in the
jacking pit, and equal distribution of axial jacking load, all contribute to a good final pipe alignment
and grade.
As the pipe is advanced, the jack ram is retracted and another section of pipe is set on the guide
rails, joined to the preceding pipe, and the jacking pressure reapplied. The size and number of jacks
required, and the size of the jacking abutment, are a function of soil types encountered, size of pipe,
and length of jacked installation.
Excavated material is usually removed through the jacking pipe installation in carts, or by a
conveyor system. Once the installation is complete, soil cement, grout, or sand is pumped through
grout nipples into the void between the excavated bore and the outside of the pipe. Nipples are
plugged after grouting.
Casing Pipe Size
The size of a jacked casing pipe is a function of the carrier-pipe size. The size of the casing pipe is
determined by the largest dimension of the carrier pipe. This is the outside diameter of the bell,
flange or other joint detail. To this must be added the dimensions of any skids used to install the
carrier pipe within the casing. The inside diameter of the casing pipe should be adequate to easily
accommodate the largest diameter of the flange or bell, allowing for 2 in by 4 in, or 4 in by 4 in
redwood skids, which are banded to the carrier pipe to facilitate sliding it through the casing pipe.
The designer must allow ample room between the carrier and the casing pipe. A minimum of 1-
inch of clearance between the casing and the skids must be allowed. A 6-inch difference between
bell outside diameter (O.D.) and carrier pipe inside diameter (I.D.) is suggested. The dimensions
of the carrier pipe joint details must be known before the casing-pipe diameter can be determined.
The designer should contact the utility or owner of the carrier pipe to determine the type of pipe,
and the dimensions of the joint details. It may be necessary to obtain manufacturers’ catalogs of
the exact pipe to obtain these details.
It is not uncommon for jacking contractors to oversize the casing pipe to compensate for
unanticipated alignment problems.
C h a p t e r 9 — C u l v e r t s 9-85
Implementation
The CDOT Pipe Material Selection Policy was initially developed by the Project Development
Branch for approval by the Chief Engineer. However, this document is no longer required to be a
separate policy document that requires the Chief Engineer’s approval. Therefore, it will now be
referred to as the CDOT Pipe Material Selection Guide and incorporated as a design procedure in
the CDOT Drainage Design Manual.
These Procedures for Pipe Material Selection (as updated April 30, 2015) supersede and replace all
previous procedures, guidelines, and policies regarding the selection of pipe materials used by
CDOT.
These procedures also replace the CDOT Chief Engineer’s memo dated February 8, 1984, Pipe to
be Used in Storm Drains.
Introduction
This guide will enable Project Managers (PMs) to select the allowable pipe material options for
each installation on a specific project. The contractor will choose the final pipe material from the
list of options provided in the Contract and as specified in applicable sections of the CDOT
Standard Specifications for Road and Bridge Construction. Any pipe that meets the corrosion and
abrasion criteria in this guide and which is installed per the plans and specifications is assumed to
have a 50-year service life.
Background
This policy/guide was originally developed to comply with the provisions of the Final Rule
published in 23 CFR 635.411(b) published in the Federal Register on November 15, 2006. On July
6, 2012, the Moving Ahead for Progress in the 21st Century Act (MAP-21) was signed into law.
With passage of MAP-21 the federal requirement for this policy/guide was nullified. However,
CDOT has determined the additional performance criteria outlined in the original policy (now
guide) is beneficial to the State. Therefore, this revised guide retains much of the original policy
and is to be incorporated into all CDOT design projects. CDOT will follow its standard practices
for the hydraulic and structural design of pipes. This guide replaces all previous policies regarding
the selection of pipe material for storm drains, cross drains, and side drains.
Selection Considerations
CDOT will evaluate the risk associated with the performance of pipe materials. Risk will be
considered to the extent that it is influenced by the pipe, other materials, or installation techniques
as they are used in construction.
This guide identifies the specific engineering and performance criteria used to evaluate the
acceptability of alternate pipe materials. CDOT allows alternate pipe materials where appropriate.
A record of the determination of abrasion and corrosion levels must be documented and maintained
in the project design files.
• Extensions of existing pipes or systems must be completed using similar material and sizes.
Exceptions to this may be made when conditions and engineering justifications merit.
• Local agencies and other organizations that will own and maintain the new pipe should be
consulted for guidance on selection of type of pipe material. Only pipe material types that
have been evaluated and approved for use by CDOT may be used. In the event a local
agency or organization will own and maintain the new pipe and the guidance provided
differs from this guide, the guidance from the local agency or organization shall govern.
Definitions
Cross Drain – pipes or culverts that convey flows from one side of a road to the other, typically
open on each end. This is also known as a cross culvert.
Side Drain – a pipe or culvert typically parallel to the roadway and under a driveway or road
approach to the mainline roadway.
Storm Drain – a network of pipes that connects inlets, manholes, and other drainage features to an
outfall.
Subsurface Drain – a network of pipes used to collect groundwater, or relieve water pressure from
a wall or structure, and transport it to a location where it will not harm the roadway features, or
where it can be conveyed by another system, often a storm sewer. A common example is a French
drain.
Type III Embankment Protector – see M-Standard 615-1.
Durability – the ability of a pipe or culvert to resist wear or decay. Although structural condition is
an important element in the performance of pipes, durability problems are a common cause for
replacement. Pipes are more likely to wear away than fail structurally. Durability is affected by two
mechanisms – corrosion and abrasion. Each is discussed in the following sections.
Corrosion – deterioration of material due to chemical or electrochemical reaction with the
environment. Corrosion of pipe materials may occur in many different types of soil and water which
may contain acids, alkalis, dissolved salts, organics, industrial wastes or chemicals, mine drainage,
sanitary effluents, and dissolved or free gases. Pipe corrosion is generally related to water and the
chemicals that have reacted to, dissolved in, or have been transported by the water.
Abrasion – the process of wearing down or grinding away surface material of pipes. It is caused by
sand, gravel, or stones within water flowing through a pipe. The abrasive force increases with rising
velocity within the pipe.
Alternate Materials – various pipe materials that will meet a project’s requirements. Alternate
materials are identified in the Contract, and the contractor may select any of them for use on the
project.
All decisions regarding pipe material type must be based on best engineering practices and
engineering judgment. The PM is responsible for all aspects of the design and schedule of the
project. The PM must schedule work associated with the pipe-material selection process to ensure
compliance with the overall project schedule. Factors which must be considered include durability,
environmental considerations, soil conditions, fill heights, the need for watertight joints, pipe
minimum and maximum slope (i.e. pipe velocity), hydraulic characteristics of inside surfaces, and
other factors relevant to the project or specific pipe application.
C h a p t e r 9 — C u l v e r t s 9-87
The PM must specify on the plans or in the special provisions when watertight joints are required.
Siphons, irrigation systems, and storm drain systems require watertight joints.
In some cases the results of the material-type selection process may include alternate material types
and different pipe diameters. In such cases the PM may specify in the plans the appropriate diameter
for each material type, or specify only the largest pipe diameter determined by the selection process
regardless of material type.
When a specific Manning’s n value is critical to a pipe’s performance, the maximum and minimum
values must be shown on the plans. If the larger diameter will not meet minimum-cover
requirements, or the material will not meet the Manning’s n-value range, that material type must
be prohibited at the relevant locations. Any material type prohibited at a specific location during
design must be clearly designated on the plans.
Where existing pipes are in place in the same drainage, the conditions of their inverts should be
documented and used as guidance. The expected stream velocity should be based upon 2-year flows
and less.
Step 3 – Determine Corrosion Level
The station of each proposed pipe must be determined by the PM. The PM must schedule soil and
water testing to ensure meeting the project schedule. Resistivity, pH, and moisture levels must be
determined in the field by Region personnel. These tests are most efficiently and effectively
conducted at the time of sampling. CDOT Materials and Geotechnical staff are available to perform
sulfate and chloride testing. The PM must schedule this work appropriately to avoid project delays.
Region personnel should develop their ability to perform these simple tests to expedite the design
process. Sample testing information is used in flowcharts (Figures 1 and 2) to select appropriate
material.
The PM must document the following properties of the soil and water using the designated test
procedure:
• Sulfate levels – CPL 2103
• Chloride levels – CPL 2104
• Resistivity – ASTM G57
• pH – ASTM G51
• Moisture levels
This information must be obtained at all pipe locations supplied by the PM and documented in the
project records. If the alluvium of the area is sufficiently homogeneous, a reduced sampling
schedule is acceptable. This determination should only be made with input from the Region
Materials Engineer (or Staff Materials) and the Region Hydraulics Engineer.
Table C.2 Minimum pipe thickness for metal pipes based on the resistivity and pH of the
adjacent soil
Soil Side Minimum Required Gauge Thickness for Metal
Resistivity, R (ohm – cm) pH Pipe Material
≥ 1,500 5.0-9.0 0.052 in (18 gauge) Aluminized Type 2
≥ 250 3.0-12.0 0.052 in (18 gauge) Polymer Coated
For storm drains, use Standard Specification 603 and write a project special provision stating the
required corrosion classification as determined by this guide (i.e. sulfate class). Use appropriate
pay items in these cases.
Step 4 – Selection of Pipe Material Type
Use the flowcharts in this document to identify acceptable pipe material types. Use Figure 1 to
determine if metal pipe is an allowable material type. Then use Table C.2 to determine whether
there are additional requirements for metal pipes.
Step 5 – Verify Fill Height
Check fill height tables in the Standard Plans. Determine if project special provisions are required
and/or if any other Standard Special Provisions are applicable. Use the latest versions of these
specifications, found at http://www.coloradodot.info/business/designsupport/construction-
specifications/2011-specs.
Step 6 – Address Exceptions to CDOT Pipe Materials Selection Guide
When sound engineering judgment justifies an exception to this guide, the PM must document this
in a justification letter. All justification letters must be approved by the Region Program Engineer
(PE III) or their designee prior to final design.
Step 7 – Documentation
All design decisions regarding pipe material type selection must be documented and a letter placed
in the project file. Prior to making final design decisions, send copies of all selection letters to the
Region Program Engineer or their designee for guidance and to verify consistency.
C h a p t e r 9 — C u l v e r t s 9-90
Abrasive Level 1
or Level 2?*
CR 0 – RCP, PE, PP, SRPE, and PVC allowed for Class 7 by Table 624-11
CR 1 – RCP, PE, PP, SRPE, and PVC allowed for Class 7 by Table 624-11
CR 2 – RCP, PE, PP, SRPE, and PVC allowed for Class 8 by Table 624-11
CR 3 – RCP, PE, PP, SRPE, and PVC allowed for Class 9 by Table 624-11
CR 4 – RCP, PE, PP, SRPE, and PVC allowed for Class 9 by Table 624-11
CR 5 – RCP, PE, PP, SRPE, and PVC allowed for Class 10 by Table 624-11
CR 6 – RCP, PE, PP, SRPE, and PVC allowed for Class 10 by Table 624-11
* Aluminum alloy pipe not allowed in environments with an Abrasion Level greater than 1.
1
When concrete pipe is selected the sulfate content dictates the CR level. Cementitious requirements for
Sulfate Protection Classes are listed in 601.04. A higher level of protection may be used. Concrete shall
have a minimum compressive strength of 4,500 psi and maximum water-to-cementitious ratio (w/cm) listed
in 601.04. Concrete may be used when the pH and chlorides exceed levels listed in Table C.1.
Figure C.1 Cross Drains and Side Drains
For Metal pipes, see “Minimum Pipe Thickness for Metal Pipes Based on the Resistivity and pH
of the Adjacent Soil” (Table C.2) in this guide.
When extending an existing pipe, the same size and type of material must be specified. If conditions
are Abrasive Level 1 or 2 and CR 0, specify material type from Section 603 pay items.
C h a p t e r 9 — C u l v e r t s 9-91
For storm drains CDOT allows the use of only reinforced concrete pipe (RCP), polypropylene (PP),
steel-reinforced polyethylene (SRPE), or polyvinyl chloride pipe (PVC) in accordance with
Standard Plans M-603-2 and M-603-5 for storm drains.
1
If Abrasion Level is 3 or 4, concrete must have a minimum compressive strength of 4,500 psi.
Cementitious requirements for Sulfate Protection Classes are listed in 601.04. A higher level of protection
may be used.
Figure 2 Storm Drains
When extending an existing pipe, the same size and type of material must be specified. If conditions
are Abrasive Level 1 or 2 and CR 0, specify material type from Section 603 pay items.
At any time, manufacturers may request in writing to have materials not approved herein evaluated
for a specific application. Requests for trial installations must follow the requirements of Procedural
Directive 1401.1. Contact information for that procedure is given below:
Product Evaluation Coordinator
Colorado Department of Transportation
Materials and Geotechnical Branch
4670 Holly Street, Unit A
Denver CO 80216
303 398-6500
• Manufacturers must provide all of the materials, equipment, and labor required for the pipe
material to be evaluated at no cost to CDOT.
• The pipe material to be evaluated must meet applicable AASHTO and ASTM design and
material standards.
• Manufacturers are responsible for all coordination with the contractor, and any additional
cost incurred by the contractor as a result of the trial installation.
• CDOT will determine a suitable location for the trial installation.
• During installation, the manufacturer must have a representative at the installation site. The
manufacturer must provide documentation to CDOT that the pipe material was designed
and installed per all current and applicable AASHTO and CDOT design and installation
standards.
C h a p t e r 9 — C u l v e r t s 9-92
• Trial installations must perform satisfactorily for at least one year before conclusions
regarding product performance are made.
• During the one-year evaluation period, at a time chosen by CDOT, the manufacturer must
provide laser video inspection services on the trial installation utilizing an inspection
contractor approved by CDOT.
• The results of the laser video inspection will be used to evaluate trial installations. The
results must demonstrate compliance with CDOT and AASHTO deflection, joint
separation, buckling, tearing, sagging, and cracking standards.
• Monitoring may include research of the trial material in use in other states.
• If further evaluation is required beyond one year, the supplier will be notified of the
justification for this evaluation extension.
• An independent evaluation performed by a local agency or other organization may be
substituted for this trial installation and evaluation process if all of the following are true:
i. The local agency or other organization owns and maintains the material being
evaluated.
ii. A representative with the local agency or organization can be contacted to verify the
information supplied.
iii. The installation specifications are available for CDOT to review.
iv. A trial installation was performed in Colorado on site applications similar to CDOT
projects.
v. A laser video inspection was performed (or can be performed) a minimum of 1 year
after installation that produced satisfactory results.
• Upon successful completion of the monitoring period, CDOT’s Drainage Advisory
Committee will review the performance and determine the acceptability of the material for
future inclusion into this guide.
• If changes to this guide, including the introduction of new materials or drainage products
are requested, they will be evaluated by the following process:
i. The Drainage Advisory Committee will evaluate documentation concerning changes
to this guide.
ii. Documentation supporting the proposed change must be submitted by the supplier to
the Product Evaluation Coordinator at the above address.
iii. The Product Evaluation Coordinator will compile all submitted documentation and
submit it to the chairperson and secretary of the Drainage Advisory Committee.
iv. The Drainage Advisory Committee will determine the future acceptability of the
material for inclusion in this guide. The Drainage Advisory Committee will forward
recommendations to the Chief Engineer for signature.