Forensic Delay Analysis - Session 5 Disruption, Acceleration and Case Study 2
Forensic Delay Analysis - Session 5 Disruption, Acceleration and Case Study 2
ANALYSIS TRAINING
1
AGENDA
▪ Case Study – Concurrent Delay
▪ Case Study (2) Exercise*
▪ Schedule/Delay risk management
▪ Mitigation
▪ Acceleration
▪ Constructive acceleration
▪ Schedule for acceleration claims
▪ Disruption
2
Concurrent Delay
Case Study
3
Case Study: Concurrent Delay
▪ Main Contractor Claim
• 26 weeks EOT
• £6m / $8m delay costs
5
Case Study: Concurrent Delay
6
SCL Protocol
7
Concurrent Delays
▪ With the critical path determined by the
Adjudicator, I worked through the critical path
and progress records and identified concurrent
causes of delay on the critical path.
8
Car Lift Stonework (blue)
9
Car Lift Stonework
10
11
Concurrent causes
of delay to scaffold
Car Lift Stonework removal on critical
path
Dismantle scaffold
next critical activity
12
Non-critical delays
(subcontractors)
▪ Briefly, I simply looked at the critical path and delays
through to completion of a number of packages:
• Passenger lifts
• Structural roof works
• Brickwork
• M&E
13
Case Study 2: Exercise
▪ 62 Thorpe Road
14
62 Thorpe Road
▪ Background
• FIDIC 99 RB
• Completion: W26
▪ The defence
• No entitlement to EOT
• Delays caused by poor progress and defects
• Claim rejected
62 Thorpe Road
▪ You are instructed as independent delay expert to:
Substructure
Superstructure 62 Thorpe Road
20
Avoidance vs. mitigation
We try to either:
• Minimise:
• Mitigation
• Acceleration
Can we really avoid delays?
• Allot of focus on delay avoidance
• This involves:
1. Resequencing activities
2. Increasing resources
3. Increasing working time
4. Temporary works
Mitigation
5d
4d
6d
5 d (0 delay)
6 d (+2 delay)
4 d (-2 acceleration)
(1) Resequencing activities
• Temporary waterproofing
• Temporary windows/doors
• Temporary lighting
• Access/egress arrangements
Mitigation costs
• Mitigation costs money:
1) Re-sequencing /
Concurrent working X X X X
2) Increasing Resources X X X X
3) Increased Working
Time: Additional Shifts
and/or Overtime
X X X X X X
4) Temporary Works X X X
Constructive Acceleration
• “Constructive” Acceleration” is acceleration implemented as a result
of pressure to complete on time in the face of a valid EOT claims,
without an agreement Employer agreement for acceleration costs
2) The Contractor must have must have notified in a timely manner and
actually requested time-extension;
3) The Employer / Engineer must have been delayed or refused the EOT;
1 E.g. Fraser Construction Co v United States (2004) 384 F3d 1354, 1361
Issues with Constructive
Acceleration Outside US
1. Lack of consensual agreement to accelerate
3. Engineer has no authority to instruct acceleration for Excusable delay (e.g. RB 99 SC 8.6)
4. Engineer is not the agent of the Employer (and cannot therefore bind the Employer)
5. Lack of serious threat (depending on when LADs will be deducted, if Bond will be pulled)
39
CPM/Scheduling in Acceleration
Claims
• Therefore, important to have a series on reliable
contemporaneously updated schedules, i.e. monthly
40
CPM/Scheduling in Acceleration
Claims
• But crucial to differentiate:
41
CPM/Scheduling in Acceleration
Claims
• The contemporaneous delay analysis
methodologies discussed in session 1 to 4 have the
same applications here
44
Schedule disruption
▪Methods for assessing disruption
▪ Measured mile is straightforward with the correct records – no complicated analysis involved,
just some simple calculations
▪ But these records rarely kept in practice, hence measured mile analysis rarely used effectively
47
Earned Value analysis
▪ Comparison of budgeted hours for work incurred to actual hours for that work
▪ Fully resourced schedule / BOQ man-hours abstract required for budgeted hours
▪ Again, Earned Value analysis is straightforward with the correct records, but these
records rarely provided in practice
48
Summary
▪ Delay risk management requires avoidance and minimisation
(mitigation)
50