0% found this document useful (0 votes)
85 views

4.1 Division of Works

This document outlines the division of works for a project and includes the following sections: 1. General provisions such as bonding, insurance, taxes, coordination, payments, and quality assurance. 2. General supplies needed for the project such as lubricants, chemicals, gases, water, fuel, electricity, and compressed air. 3. Engineering requirements including design, drawings, specifications, schedules, reports, and as-built documents. 4. Provisions for erection and commissioning including installation, testing, pre-commissioning, and performance testing. 5. Transportation of equipment and materials to the site, customs clearance, and site handling and storage. 6. Site storage and

Uploaded by

ruhul01
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
85 views

4.1 Division of Works

This document outlines the division of works for a project and includes the following sections: 1. General provisions such as bonding, insurance, taxes, coordination, payments, and quality assurance. 2. General supplies needed for the project such as lubricants, chemicals, gases, water, fuel, electricity, and compressed air. 3. Engineering requirements including design, drawings, specifications, schedules, reports, and as-built documents. 4. Provisions for erection and commissioning including installation, testing, pre-commissioning, and performance testing. 5. Transportation of equipment and materials to the site, customs clearance, and site handling and storage. 6. Site storage and

Uploaded by

ruhul01
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 32

SECTION - 4

DIVISION OF WORKS

PART I - GENERAL PROVISIONS

No. DESCRIPTION

1 GENERAL

1-1 Bond
(1) Advance payment
(2) Performance Bond
(3) Retention Bond

1-2 Insurance
(1) Erection All Risk Insurance
(2) Marine Insurance for Project Cargo
(3) Marine Insurance for None-Project Cargo
(4) Third Party Liability Insurance
(5) Worker's Compensation Insurance
(6) Automobile Liability Insurance
(7) Insurance for Construction Equipment
(8) Insurance of temporary facilities, tools, non-commercial cargo, construction and testing
(9) Documentations for insurance claim
(10) Any Other Insurance - Required by Law and / or which the Sub-contractor
Desirable for Carrying out the Work

1-3 Stamp Duty


(1) Local Law & Regulations

1-4 Taxes
(1) Corporate Tax
(2) Sales Tax
(3) Expatriate Personal Income Tax
(4) Local Employee's Personal Incomes Tax and Social insurance, if any.
(5) Import Tax and Duty
(6) Others (if any)

1-5 Coordination
(1) General / Commercial Coordination
(2) Technical / Engineering Coordination
(3) Coordination with Local Authorities & other concerned parties

1-6 Progress Payment Schedule

1-7 Quality Assurance & Quality Control

1-8 Governing Law


(1) Solicitor

2 GENERAL SUPPLIES

2.1 Lubricants (Oil, Grease etc)


a Initial filling and up to Taking over by Owner
- For permanent equipments
- For construction equipments

2.2 Chemicals for Permanent Systems / Equipments


a Initial filling and up to Taking over by Owner
b For Chemical cleaning for permanent systems

2.3 Gas (H2, C02, N2 etc.,)


a Initial filling and up to Taking over by Owner
b For Construction

2.4 Water
a For Flydro test
b For Chemical Cleaning
c For Steam Blow out
d For Flushing
e For Commissioning
f For Site office
g For Construction
h For Accommodation

2.5 Fuel
a Initial filling and up to Taking over by Owner
b For construction
c For commissioning

2.6 Temporary Materials and Consumables


a For Blow out
-Motor Valves
-Piping, supports
-Blanking plates, plugs
-Target Plates
-Any other
-Silencer
b For Chemical cleaning
-Equipments, pumps and tanks
-Piping, support
-Chemical
-Any other
c For Oil Flushing
-Piping, supports, valves
-Pumps and Filters
-Mesh
-Flushing Oil
-Any other
d For Flydro test
-Pumps, Gauges
-Piping, supports
-Blanking plates, Plugs
-Chemicals (02 Scavenger, etc)
-Any other
e For Water Flushing
-Piping, supports
-Mesh, hose
-Blanking plates, Plugs
-Instruments
-Any other
f For Pig Cleaning
Air compressor and other equipments
Piping, supports, Launchers etc
-Pig
Any Others

2.7 Welding Rods and Filler Wires


a For Temporary Works
b For Carbon Steel
c Special materials (like Stainless Steel, Aluminum etc)
d Special materials (alloy steel)

2.8 Electricity
a For Construction
b For Site office
c For Storage
d For Accommodation
e DG set for Construction and Accommodation

2.9 Compressed Air for Construction

3 ENGINEERING

3.1 Overall Plant Design Philosophy

3.2 Conceptual Plant Engineering

3.3 Plot Plan and General Layout

3.4 Obtain Owner approval

3.5 Construction Drawings and Information


a Equipment Installation Drawings
b Template for Anchor Bolts
c All basic Layout
d All Detailed drawings required for construction / erection
e Erection Procedure for equipments
f Material, equipment specification
g Erection Test procedure
h Instrumentation Calibration Procedure
i Welding Procedure Specification (WPS)
j Procedure Qualification report (PQR)
k Welding Qualification Test (WQT)
1 Non Destructive Test (NDT) Procedure
m Hydro Test Procedure
n Air Leakage test Procedure
o Water Flushing / Air Blow / Oil Flushing Procedure
p HV Test procedure for SWGR, Bus ducts, Cables
q Blow Out Procedure
r Mark up drawing for as built (At site correction )

3.6 Detailed Supply list of Plant Equipment and Materials

3.7 As Built Drawings

3.8 Operation and Maintenance Manual

3.9 Delivery Schedule of Plant Equipment & Material

3.10 Construction and Commissioning Schedule


a Overall Project Schedule
b Detail Schedule

3.11 Monthly Progress Report

3.12 Technical Meeting Co-ordination

3.13 Technical Correspondence Co-ordination

3.14 Document Control


3.15 Quality Procedure and Control

3.16 Terminal Point List

4 PROVISION DURING ERECTION AND COMMISSIONING

4.1 Erection
a Co-ordination for Equipment Delivery and Erection
b Control of Work force including supervision
c Work force
d Work schedule preparation
e Monitor and report on work schedule
f Quality Control
g Technical advisors (vendor representative)
h Erection report
i Co-ordination between Sub-contractor and others

4.2 All Construction and Erection Equipment and Tools


a Special Tools (if any)
b Construction and Erection equipment and tools
c All Lifting Tackles and Handling devices
d General Tools
e Transformer Insulation Oil Treatment and Filling System and Equipments
f Instruments and other required materilas and consumables

4.3 Temporary Foundation for Heavy Lift Equipment (if required)

4.4 Chemical Cleaning

4.5 Piping Cleaning / Flushing


a Water Flushing of Pipe Line System
b Oil Flushing of Equipment Lube Oil/Control Oil System
c Air blow for Air Pipe Line System
d Pig Cleaning for Fuel Gas Line and Steam Line

4.6 Pre-Commissioning
a Management of Commissioning team
b Technical Direction to work force
c Schedule preparation
d Monitor and report
e Test Report
- Erection / Installation
-Pre-commissioning
f Tests during Pre-commissioning
-Test Equipment
-Test Engineers
-Work force
-Instrument calibration

4.7 Site Test for Erection / Installation and Workmanship


a Flydro tests
b Leakage Test by Air / Water
c NDT for Site Welding
d Insulation resistance test
e Die eclectic test
f Load Tests for all Cranes, Hoists, etc.

4.8 Commissioning
a Test Equipment
b Test Engineers
c Work force

4.9 Performance Test


a Test Equipment
b Test Engineers
c Work force for Preparation and Restoration

4.10 Reliability Test


a Test Engineers
b Work force

5 TRANSPORTATION
5.1 Transportation
a Delivery of Project Cargo and Components from Port of Export to
Port of Unloading
b Delivery of Project Cargo and Components from Port of Import to
to Project Site / Storage area
c For Other materials / equipments

5.2 Custom Clearance


a For Project Cargo and Components
b For Other materials / equipments

5.3 Demurrage
a Due to fault of Transporter for Project Cargo / Components
b Due to fault of Receiver (Sub-contractor)

5.4 Unloading work at Site


a At the storage area
b At the project site

5.5 Transported Container management Work


a Unloading and staffing work at site
b Handling work of container
c Off loading the Container to the trailer due to return back to port.
d Trailer Arrangement and coordination

5.6 Transportation / Handling of Equipments / Materials from Storage area to erection point

5.7 Preparation of Access Roads


a Main Access road
- In Project area
- In Storage Area
- In Office Area
b Sub Access Roads (All areas)

5.8 Removal of any obstruction / widening & strengthening of Access roads (if required)
during transportation within the Project area, Storage area, Storage area to
erection point (for all cargoes)

6 SITE STORAGE / INVENTORY


6.1 Land for Storage
a On site
b Off site (if necessary)
c Land Leveling and compaction

6.2 Checking unloaded Equipments and Materials at site

6.3 Devanning from Container and on loading the container to trailer

6.4 Mateial receiving inspection and prepare the report


6.5 Inventory control / Planning

6.6 Storing, supervising, maintaining, watching, securing at site for all Equipments and materials

6.7 Preparation of Necessary indoor storage of equipment and materials


(including temperature controlled)

6.8 Preparation of Material Receipt and or Damage report

6.9 Storage of test equipments

7 SITE OFFICE FACILITIES


7.1 Site Office
a For Contractor
b For Sub-Contractor

7.2 Store House

7.3 Workshop

7.4 Earthwork like leveling, compaction, grading

7.5 Parking area

7.6 Communication System


(1) Internal wiring of Telephone at the Site Area
a. For Contractor
b. For Sub-contractor
(2) External wiring of Telephone
a. For Contractor
b. For Sub-contractor

7.7 Provision of Local Labor facilities such as Toilets, shelters, canteen, smoking rooms and other
required facilities

7.8 Electric Power supply Distribution

7.9 Provision of Field Communication system as required

7.10 Potable water supply distribution

7.11 Provision of First aid facilities, medical services

7.12 Provision of Fire temporary Fighting equipments for Office, Storage and Construction Area

7.13 Ambulance service (if required)

7.14 Maintenance and repair of all facilities above (7.1 to 7.14)

8 SITE WORKS AND SERVICES


8.1 Site Organization
a Site Manager
b Vendor representative at site
c Technical advisors for equipment and Commissioning Engineer
d Supervision and control of Workforce
e Any other manpower including craft labor, foreman, technicians etc required
for erection work

8.2 Administrative Staff (clerk, secretary, office boy etc)


8.3 Provision of Accommodation facilities for staff

8.4 Provision of Accommodation facilities for expatriate personnel

8.5 Provision of Accommodation facilities for others

8.6 Operational vehicles such as cars, buses etc (supply, maintenance


and operation of vehicles) including insurance

8.7 Overall Project area Boundary Fencing, Main Gate and Security

8.8 Guard blouse, Guard for Office, Construction and Storage area

8.9 Temporary area lighting for all areas

8.10 Maintaining and guarding facilities for equipments and materials up to taking over by Owner

8.11 Temporary work permit, staying permit and any other local permits as required by Local Law

8.12 Necessary work permit, visa and other permits as per local law to bring in overseas staff / personnel

8.13 Training of Owner's Personnel at Project Site

8.14 Site Security (till taking over to Owner)


a Storage area
b Office area
c Construction area
d Main Gate for Site Boundary and total Site Boundary Area

8.15 Rubbish disposal


a Storage area
b Office area (including Contractor's)
c Construction area

8.16 Applied Code and Standard


a Obligatation of the ASME Stamp (Contractor to be taken necessary action)
b Obrigation the Bangladesh Boiler Act (Contractor to be taken necessary action)

9 SITE HEALTH, SAFETY AND ENVIRONMET CONTROL

9.1 Health, Safety, and Environment Control Procedure

9.2 Safety Patrol and Control

9.3 Safety appliances like helmets, shoes, welding mask, goggles etc

9.4 Any other safety protection required for safe working

9.5 Site Traffic safety, discipline, control


Provided by
REMARKS
CLIENT CONTACTOR

X
X

X
*lx *1 : For CLIENTs Equipment only
X X For each own
X X For each own
X X For each own
X X For each own
*2x *2 : Contractor's provided only
X X For each own
X X For each own
X

*lx *1 For the Contractor's


*lx
X *lx
*lx
*lx
*lx

X *2x *2 Cooperate and assist to the CLIENT


X *2x
*3x X *3 Assist to the Contractor

X *4x *4 Designated format will be given by the CLIENT

*2 x X *2 Assist to the Contractor

X X For each own

X *lx *1 Installation by Contractor


X

X *lx *1 Installation by Contractor


X

X *lx *1 Installation by Contractor


X

X
X

X
X
X

X X For Each Own


X
X X For Each Own

*lx *2x *1 Assist to Contractor. *2 Installation by Contractor


X
*lx *2x *1 Assist to Contractor. *2 Installation by Contractor

X
X
X
X

X
X

X
X
X

X
X

X
X

X
X
X

X if required
X

X
X
X
X

X
X
X

X
X
X

X
X X For Each own
X
X X For Each own
X

X
X
X
*lx X For Owner approval, if required, for assist to Contractor
*lx X *1 for Assist to Contractor
X
*lx X *1 for Assist to Contractor
*lx X *1 for Assist to Contractor
*lx X *1 for Assist to Contractor
*lx X *1 for Assist to Contractor
*lx X *1 for Assist to Contractor
*lx X *1 for Assist to Contractor
*lx X *1 for Assist to Contractor
*lx X *1 for Assist to Contractor
*lx X *1 for Assist to Contractor
X
*lx X *1 for Assist to Contractor
X

X X as per item 3.5

X *2x *2 For Assist to CLIENT


X

X *2x *2 For Assist to CLIENT

X *2x *2 For Assist to CLIENT

X X For Each Own


*lx X *1 For Assist to CLIENT

X *2x *2 For Assist to CLIENT


X
X
*lx X *1 For Assist to CLIENT
*lx X *1 For Assist to CLIENT
*lx X *1 For Assist to CLIENT
X

X
*lx X *1 For Assist to CLIENT

*3x *3 If approved by Owner


X including calibration certificate
X
X

X
X

for instrument piping


X
X

X
X

X *2 x *2 For Assist to CLIENT


X *2 x *2 For Assist to CLIENT
X *2 x *2 For Assist to CLIENT

X
X *2 x *2 For Assist to CLIENT

X
X

X
X *2 x *2 Contractor need to supply the Work Force

X
X
X

X
X
X

X
X
X as assistance

X
X as assistance

X as assistance

X For CLIENT Supply only

X For CLIENT Supply only

X X For Each Own

X For CLIENT Supply only


X X For Each Own

X For CLIENT Supply only


X

X
X

X
X Xl) 1) Contractor to be handle the container according to Employer
X trailer to be arranged by Employer
X x 2) 2) Contractor need to support to Employer.

X
X
X
X

X
X

X material receiving inspection will be carried out with Owner


*lx X *1 For Assist to Contractor

X Contractor need to support for the Owner Inspection also.

X X For each own

X X For each own

Shall be maintained by Contractor during the duration of the

X
X

X
X

X X For Each Own


X

X
X
X

X X For Each Own


X X For Each Own

X X For Each Own

X X For Each Own

X X For Each Own

Main gate is controlled by Owner.

X X For Each Own

X
X X For Each Own
X

X
X
X

X
DIVISION OF WORKS
PART II - Detailed PROVISIONS for temporary works

No. DESCRIPTION

1 TEMPORARY SITE FACILITIES


1.1 Land Space with Access Road in the Site Area
(1) Land Space
a. Site office and Guard House of the TPSC own
b. Site office and Storage area of the Ccontractor own
c. Storage Area of permanent materials & equipment
d. Accommodation for the Contractor
(2) Materials for Maintenance of yard and access road
a. Gravel
b. Sand
c. Concrete
d. Steel Plates
e. Any Other

1.2 Site Office


(1) Site Office
a. For TPSC
b. For Contractor
(2) Furniture and Fixtures for Site office
a. For TPSC
b. For Contractor
(3) Electric Power Distribution
a. Equipment with Spare Parts
1) Transformers
2) D/B, Switch Device
3) Measuring Device
4) D/G
5) Foundation
6)Fence
7) Any Other
b. Cabling and Wiring Materials
1) Cable and Wire
2) Connection Materials
3) Supporting Materials
4) Cable and Wire Conduit Materials
5) Earth Connection
6) Any Other
c. Charge of Electric Power
(4) Toilet
(5) Sewage Treatment Facilities
(6) Drainage
(7) Potable Water
a. Equipment with Spare Parts
1) Tank
2) Pump
3) Strainer
4) Measuring Device
5) Foundation
6) Any Other
b. Piping and Fitting
1) Pipe
2) Valve
3) Fitting
4) Supporting Materials
5) Any Other
(8) Telephone
a. For Contractor
b. For Sub-contractor

1.3 Accomodation
(1) Furnitures
(2) Telephone
(3) Electric Power Distribution
a. Equipment with Spare Parts
1) Transformers
2) D/B, Switch Device
3) Measuring Device
4) D/G
5) Foundation
6)Fence
7) Any Other
b. Cabling and Wiring Materials
1) Cable and Wire
2) Connection Materials
3) Supporting Materials
4) Cable and Wire Conduit Materials
5) Earth Connection
6) Any Other
c. Charge of Electric Power
(4) Toilet
(5) Sewage Treatment Facilities
(6) Drainage
(7) Potable Water
a. Equipment with Spare Parts
1) Tank
2) Pump
3) Strainer
4) Measuring Device
5) Foundation
6) Any Other
b. Piping and Fitting
1) Pipe
2) Valve
3) Fitting
4) Supporting Materials
5) Any Other

1.4 Warehouse with fixtures and Storage Yard


1.5 Workshop for Erection

1.6 Car Park (Including for Contractor)

1.7 Guard House

1.8 Dark Room and Instrument Caliberation Room

1.9 First Aid


(1) First Aid Office and Facilities
(2) Nurse
(3) Ambulance and Driver
(4) Medicine

1.10 Electrical Power Distribution for Construction, Storage Yard, Guard House and Ware house

a. Equipment with Spare Parts


1) Transformers
2) D/B, Switch Device
3) Measuring Device
4) D/G
5) Foundation
6)Fence
7) Any Other
b. Cabling and Wiring Materials
1) Cable and Wire
2) Connection Materials
3) Supporting Materials
4) Cable and Wire Conduit Materials
5) Earth Connection
6) Any Other
c. Charge of Electric Power

1.11 Communication System


(1) Internal wiring of Telephone at the Site Area
a. For TPSC
b. For Contractor
(2) External wiring of Telephone
a. For TPSC
b. For Contractor
(3) Charge for Telephone
a. For TPSC
b. For Contractor

1.12 Water for Construction


a. Equipment with Spare Parts
1) Tank
2) Pump
3) Strainer
4) Measuring Device
5) Foundation
6) Any Other
b. Piping and Fitting (including all distribution network)
1) Pipe
2) Valve
3) Fitting
4) Supporting Materials
5) Any Other
c. Charges for Water Consumption

1.13 Compressed Air for Construction and Workshop


(1) Equipment
a. Compressor with Filter and Lubrication
- Portable Type
- Fixed Type
b. Fleader
c. Local Header
d. Any Other
(2) Materials
a. Pipe and Hose
b. Valve and Fitting
c. Hose & Connectors
d. Supporting Materials
e. Any Other

1.14 Vehicle for Transportation between to and from site


(1) For the TPSC's Personel
a. Vehicle with Spare Parts
b. Running Cost Including Fuel, Oil Maintenance
c. Driver
d. Management
(2) For the Contractor's Personel
a. Vehicle with Spare Parts
b. Running Cost Including Fuel, Oil Maintenance
c. Driver
d. Management

1.15 Vehicle for Unloading, Hauling, Rearranging etc.


(1) Unloading Equipment & Material Transportation from Storage yard to
Construction area
a. Vehicle with Spare Parts
b. Running Cost Including Fuel, Oil Maintenance
c. Driver
d. Management
(2) Transportation of Equipment & Materials from Port of Import to Storage yard
a. Vehicle with Spare Parts
b. Running Cost Including Fuel, Oil Maintenance
c. Driver
d. Management

1.16 Fire Fighting Equipments for All Required Areas

1.17 Temporary Lighting at Construction / Storage and other all required areas

2 ENGINEERING / PLANNING / REPORTS


2.1 Storage Planning
(1) Location Plan
(2) Control Procedure
(3) Storage Procedure

2.2 Bringing in Procedure


(1) Major Equipments
(2) Others

2.3 Safety Procedure

2.4 Reports
(1) Site Organization Chart
(2) Erection Schedule (Planning and Actual)
a. Master Schedule
b. Daily Schedule
c. Weekly Schedule
d. Monthly Schedule
e. Three Month ahead Schedule
(3) Manpower Schedule
a. Estimated Monthly Schedule and three month Schedule
b. Actual (Daily and Weekly)
c. Actual (Monthly)
(4) Inspection and Test Reports
(5) Photographs for Monthly Progress reports with explanation
(6) Sub-contractor's employee list
(7) Tools and Heavy Equipment
a. Schedule and providing of Heavy Equipment
b. Maintenance, Condition Report of Tools and Equipments
c. Tools and Heavy Equipment List
(8) Returnable Cargo List
(9) Plant Equipment, Tolols, Material Status Report
(10) Safety Report
(11) Damage / Accident Report
(12) Erection Report
(13) Testing Report
(14) Other Records and Reports reasonably requested by Contractor

3 ERECTION MATERIAL AND CONSUMABLES


3.1 Steel Materials and Others for Bringing in, storaging, Hauling, Rolling and installation
(such as steel materials, steel plates, timber, covers, weather protection, scaffoldings and others)

3.2 Temporary Materials for Inspection, Testing and Pre-commissioning


(1) For Oil Flushing and Water Flushing (Such as pipings, fittings, valves,
mesh, hoses and others)
(2) For Hydrotest (such as pipings, pumps, valves, blankplates,
fittings, valves, tubing and others)
(3) For Chemical Cleaning
a. Pumps, Chemical tanks, pipings, valves, fittings
b. required Chemicals
c. requirement instruments for judgement
d. Other than above
(4) For Steam Blow Out
a. Piping, fitttings, Valves, target plate, supports, etc.
b. Other than above
c. Silencer
{6) Pig Cleaning
a. Piping, fitttings, Pigs, Valves, supports, etc.
b.Air Compressors
c. Other than above
(6) Preservation system
a. Pumps, Chemical tanks, pipings, valves, fittings
b. Gases, Chemicals
c. Other than above
(7) For Others (such as temporary supports for piping, cabling, etc)
(8) For Insulation Oil Treatment and filling equipments

3.3 Welding Rods / Fillers


(1) For Temporary Works
(2) For Carbon Steel
(3) Special materials (like Stainless Steel, Aluminium etc)
(4) Special materials (alloy steel)

3.4 Oxygen, Argon, Propane, Acetylene, Nitrogen and other gases

3.5 Oil, Compound and Grease


(1) Flushing Oil
(2) Others

3.6 Grouting Materials


(1) Flowable Grout (including Non-Shrink)
(2) Others

3.7 Test Pieces for WQT for all materials

3.8 Prequalification and Final qualification of Test Piece for WQT for all materials

3.9 Temporary scaffoldings

3.10 Temporay Bridge / spool pieces for welding

3.11 Solvent, waste, Brush, sims, packer plates, wedges etc

3.12 Timber, Tarpaulin and others

3.13 Temporary Materials for Electricity, water facilities and Lighting

3.14 Flydrazine (if required)

3.15 Consumables for erection works


(1) Terminal Lug
(2) PVC Tape
(3) Permanent Cable Tag
(4) Temporary Cable Tags / Marker
(5) Cable Glands
(6) Wire Mark
(7) Cable Binding Materials
(8) Termination materials for shielding wire
(9) Hole-in Anchors (Epansion Anchor) (Less than 4)20mm)

3.16 Supporting Materials such as Steel Channels, Angles, Beams, Plates for fixing

3.17 Weather Proof cover Materials

3.18 Sealing Materials for Floor / Wall Penetrations


(1) Steel Plates
(2) Compound

4 CONSTRUCTION EQUIPMENT AND TOOLS


4.1 Construction Equipment
1) Cars
2) Buses
3) Trucks
4) Cranes
5) Crane (Tower)
6) Fork Lifts
7) Other Lifting Equipments
8) Other Vehicles

4.2 Tools with Calibration Reports


1) Construction Tools and Machinery
2) Hand Tools
3) Electrical and Pneumatic Tools
4) Cutting Tools
5) Measuring Tools
6) Tools for Thermal Insulation and Painting
(7) Mobiles
(8) Special Tools
(9) Others

4.3 Charges for Returnable Cargo


(1) For TPSC
(2) For Contractor

5 PROVISION OF WORKS (COMMON / GENERAL)


5.1 Embedded Steel Material
a. For Cable Tray Supports
b. For Pipe Supports
c. Base Plate of equipment (if any)
d. Anchor Bolt of equipments for mechanical and electrical
e. Pipe Sleeves, penetration sleeves in floor, wall, roofs, slabs, foundations
f. Any other reasonably required for completion of works

5.2 Earthing
a. Buried earthing mesh (including risers to terminal point)
b. Earhing Rods
c. Earthing Connection to all equipments / materials
d. Earthwork (including excavation, backfilling, compaction)
e. Any other reasonably required for completion of works
f. Lightning Arrestor works (including connection to the buried earth mesh)

5.3 Cable, Cable Raceway and electrical conduits


a. Supports (including fabrication)
b. Embedded Conduits (including fabrication)
c. Fitting of exposed conduits / flexible conduits (including fabrication)
d. Cable trays / covers / raceways / accessories (including fabrication, if necessary)
e. MV, LV power cabling
f. Control Cabling
g. Instrumentation cabling
h. Pre-fabricated cabling
i. Grounding wire for above ground
j. Cable Continuity Check
k. Cable Hi Pot Test
1. Fiber Optic Cabling work including splicing
j. Any other reasonably required for completion of works

5.4 Piping (General)


a. Hanger and supports for piping (including fabrication)
b. Temporary piping for Hydrotest and / or Blowing out (including supports)
c. Pre treatment and Post Treatment for Welding
d. NDT
e. Surface preparation of pipes for painting
f. Prefabrication of pipes
g. Painting of piping and supports
h. Thermal Insulation for piping
i. Temporary piping for flushing.
j. Pig Cleaning of Piping
k. Sandblasting of piping
1. Any other reasonably required for completion of works

5.5 Instrument Installation including impuls tubing, piping and stantion installation
a. Hanger and supports for tubing and piping (including fabrication)
b. Temporary piping for Hydrotest (including supports)
c. Pre treatment and Post Treatment for Welding
d. NDT
e. Surface preparation of pipes, tubings for painting
f. Prefabrication and installation of pipes and tubes, including Pressure test
g. Painting of piping, tubing and supports
h. Thermal Insulation for piping and tubing
i. Instrument Installation
j. Stantion Installation
k. Calibration works for permanent instruments
1. Any other reasonably required for completion of works

5.6 Painting and Thermal Insulation


a. Surface Preparation (including sandblasting if required)
b. Primary / Secondary / Final / Touch up Painting
c. Thermal Insulation
d. Refractory (if required)
e. Any other reasonably required for completion of works

5.7 Cranes & Hoist


a. Cranes & Hoists

5.8 Sump Pumps (including supports, related electrical works)

5.9 Lighting
a. Lamp facilities (indoor / outdoor)
b. Fixture of Lamps (indoor / outdoor)
c. Conducing, cabling, wiring, supporting etc
d. DB's, Panels, switcboxes, switches, control devices etc
e. Street Lighting (together with local control boxes)
f. Yard Lighting (together with local control boxes)
g. Aviation Warning Lighting (together with local control boxes)
h. Any other reasonably required for completion of works

5.10 Master Clock system (including cabling)

5.11 Telecommunication System (including cabling)

5.12 Small Power System (including cabling)


a. All indoor / outdoor Sockets (Power Outlets) together with local control boxes
b. Power Source for small equipments together with local control boxes
(like rolling shutters, sump pumps etc)

5.13 Minor civil Works


a. Chipping of Foundations
b. Enlargement of Foundation Openings
c. Enlargement of Floor / Wall/ Roof / Slab penetrations
d. Grouting of equipments base
e. Grouting of Anchor Bolts for Mechanical & electrical Equipments / Materials
f. Grouting of Panel bases, Local control Panels / Boards bases
g. Grouting of Instrument rack bases and other supports
h. Any other reasonably required for completion of works

5.14 Transformer Insulaiton Oil Treatment and Filling Work


a. Equipments/Materials supply
b. Leveling and Compaction work (If required)
c. Setting and operation
d. testing of insulation oil
Provided by
REMARKS
TECHLINK CONTRACTOR

X If necessary
X

X X For Each Own


X X For Each Own
X Including for TPSC
X Including for TPSC

X
X

X X For Each Own


X X For Each Own

X X For Each Own


X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own

X X For Each Own


X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own
X

X X For Each Own


X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own

X X For Each Own


X X For Each Own
X X For Each Own
X X For Each Own
X X For Each Own

X including air conditioned ware houses


X

X X

X
X

X
X

*lx X *1 For Assist to Contractor

X X

X
*lx X *1 For Assist to Contractor
X

X
X

X
X

X
X

X
X

X
X

X *lx *1 Lost and Damaged Special tools during construction period


X

X
X

X if required.
X If required.
X If required.
X

X
X *) Only for Electrical Work

X *) Only for Electrical Work

If applicable
X

You might also like