13 Cost Control
13 Cost Control
1500
1000
500
Report Day 0
1 2 3 4 5
$1000
Example
D
E
0 1 2 3 4 5 6 7 8 9 10
Field report at end of day 7 Activity ACWP BCWP BCWS CPI CV SPI SV
Activity Actual % Completion Incurred Cost A 600 600 600 1 0 1 0
A 100 600 B 1400 1200 1200 0.85714286 -200 1 0
B 100 1400 C 500 400 800 0.8 -100 0.5 -400
C 33 500 D 200 200 400 1 0 0.5 -200
D 50 200 E 0 0 0 - 0 0 0
E 0 0 Total 2700 2400 3000 0.88888889 -300 0.8 -600
Earned Value Method
Cost Variance, CV = BCWP - ACWP Cost Performance Index
CSI = (BCWP/ACWP)
CV = 0, Contractor estimate = Field cost =1
CV > 0, Contractor cost < estimate >1
CV < 0, Contractor cost overrun (losing money) <1