Oracle EAM 1
Oracle EAM 1
Truck 001
Asset Routes
A "virtual asset" that enables multiple assets to be associated to a single work
order. It eliminates the need for creating multiple work orders for the same
activity.
Asset Bills of Material
A bill of material (BOM) is used to list all items and components that make up
a particular asset, and is defined for each Asset Group.
Truck 001
Asset Hierarchy
A parent/child relationships of assets
Truck 001
(Parent)
Crane 001
(Child)
Rebuildable Items
Items that are installed, removed, and refurbished
For each operation you determine the resources you may use for it
Work Management
Overview
Work Requests
Work Orders
Work Transactions
Work orders define what resources and items are needed to conduct the work.
Easy –to-use self service web page for creating and following work
requests
Creating a Work Request
Work Orders
A plan that defines the resources and material equipment needed to
conduct work, and then associated start and end dates.
When an activity is attached to the work order, all its attributes such as
maintenance BOM, maintenance route, will be added automatically
Work Orders Life Cycle
Work Order Types
Meter Association creates the relationship between the meter definition and
the Asset Number
Entering Meter Reading
Preventive Maintenance Scheduling
A planner can then view these forecasted Work Orders, and generate them
as necessary.
Creating PM Schedule
PM Scheduling Rules Options
Date Rules: PM will be performed based on days interval
eAM Planning.
eAM Scheduling
Overview
Cost savings and work management efficiencies are achieved by
generating future planned work activities, and then using a planning
process to balance the work load for resource management.
eAM Planning
Based on Material Requirements Planning (MRP)
bills of material
scheduled receipts
lead times
order modifiers
eAM Scheduling
Using the schedule workbench to schedule work orders and operations
Expand and collapse work orders and operations, using a tree hierarchy
View and update start and end date for each resource
eAM Cost Management
Overview
These costs roll up through the Parent/Child hierarchies, and can roll up
to any level within an asset hierarchy
A Work Order's estimated and actual costs might differ because all
materials or resources, associated with a Work Order, might not actually
be used when the Work Order executes
Purchase requisitions and purchase orders of such items capture the Work Order
for which they are required
eAM Reports