Testing and Commissioning Procedure: 2017 EDITION
Testing and Commissioning Procedure: 2017 EDITION
FOR
IN
GOVERNMENT BUILDINGS
OF
2017 EDITION
This Testing and Commissioning (T&C) Procedure aims to lay down the minimum
testing and commissioning requirements to be carried out on Fire Service Installation in
Government Buildings of the Hong Kong Special Administrative Region (HKSAR). Such
requirements are applicable to both new installations upon completion and existing ones
after major alteration.
The present edition was developed from the 2012 edition by the Fire Service
Specialist Support Group that was established under the Building Services Branch
Technical Information and Research & Development Committee of the Architectural
Services Department (ArchSD). This T&C Procedure has incorporated the latest changes
in the 2017 edition of the General Specification for Fire Service Installation.
The ArchSD welcomes comments on this T&C Procedure at any time since the
updating of this T&C Procedure is a continuous process to tie in with technological
advances.
DISCLAIMER
This T&C Procedure is solely compiled for use on Fire Service Installation carried
out for or on behalf of the ArchSD in Government Buildings of the HKSAR.
1. Introduction 1
Annex
Annex Page
Annex I Testing and Commissioning Progress Chart for Fire Service 1-5
Installation
Part 2 : Declaration
(a) to vet and approve the T&C procedures proposed and submitted by the
contractor for Fire Service Installation (FS Contractor);
The FS Contractor shall carry out the T&C works as detailed in this T&C
Procedure. Supplementary T&C plans may be proposed by the FS Contractor as
appropriate and agreed by PBSE, e.g. for special equipment supplied and/or
installed by the FS Contractor.
The administrative requirements for T&C works are in general as specified in the
General Specification for Fire Service Installation 2017 Edition and all current
corrigenda/amendments thereto published before the date of first tender
invitation for the Contract issued by the ArchSD (the General Specification).
All words and expressions shall have the meaning as assigned to them under the
General Specification unless otherwise specified herein.
(b) to verify that the performance of the installed equipment/systems meet with
the specified design intent and statutory requirements, if any, through a
series of tests and adjustments; and
(c) to capture and record performance data of the whole installation as the
baseline for future operation and maintenance.
FS_TCP
Page 1 of 10 2017 Edition
3. Scope of the Testing and Commissioning Works
The purpose of these tests is to ensure that all components and systems are
in a satisfactory and safe condition before start up. Preliminary adjustment
and setting of equipment at this stage shall also be carried out at the same
time to pave way for the coming functional performance tests.
Before carrying out any test, the FS Contractor shall ensure that the
Installations comply with all relevant statutory requirements and
regulations. The T&C works shall also comply with all site safety
regulatory requirements currently in force. In particular, the FS Contractor
shall note the following:
(c) Occupational Safety and Health Ordinance (Cap. 509), and other
subsidiary legislation made under the Ordinance;
(d) Factories and Industrial Undertakings Ordinance (Cap. 59), and other
subsidiary legislation, including but not limited to Construction Sites
(Safety) Regulations; and
FS_TCP
Page 2 of 10 2017 Edition
If any test cannot be completed because of circumstances that are beyond
the control of the FS Contractor, it shall be properly documented and
reported to the PBSE, who shall then liaise with the relevant parties to
resolve the situation. The FS Contractor shall resume his testing work
immediately upon the attainment of a suitable testing environment.
The FS Contractor shall carry out tests for the Installations to meet
statutory requirements as specified in the Specification. After the proper
testing and commissioning of the Installations, the FS Contractor shall
notify the appropriate authority as specified in the Specification, through
the PBSE of the completion of the Installations and its readiness for
inspection and testing. The FS Contractor shall arrange for the necessary
inspections and tests as required by the Authority.
Statutory tests and inspections required shall include, but not limited to,
those specified in the Codes of Practice for Minimum Fire Service
Installations and Equipment and Inspection, Testing and Maintenance of
Installations and Equipment, current edition published by Fire Services
Department, the Government of the Hong Kong Special Administrative
Region (hereinafter refer to as FSDCoP).
All pipework shall be thoroughly cleaned and flushed before test. The FS
Contractor shall ascertain that there is adequate drainage nearby to
discharge by large hose in order to ensure flooding of low level areas will
not occur. Where necessary, the FS Contractor shall provide chemical
cleaning to the pipes. After flushing out the pipework, a flow test shall be
performed on the hydrant/hose reel system in accordance with the
requirements of the FSDCoP.
A water supply test with the drain and test valves fully opened shall be
made on the sprinkler system in accordance with the requirements of Loss
Prevention Council Rules for Automatic Sprinkler Installations (including
all the LPC Technical Bulletins, Notes, Commentary, and
Recommendation) incorporating BS EN 12845:2003, FSD Circular Letters
No. 3/2006 and No. 4/2010, and all the subsequent amendments by the
FSD (hereinafter referred collectively as LPC Rules for Sprinkler
Installation). An alarm test for at least 30 seconds on the water gong shall
also be carried out by opening the test valve to ensure that it shall sound
continuously after water flow in the system is detected. All controls and
air supply system for the pre-action system, recycling pre-action system
and dry pipe system shall also be tested.
For street hydrant system without pumps, the FS Contractor shall test the
incoming water supply pressure at a nearby supply point and at such time
FS_TCP
Page 4 of 10 2017 Edition
as agreed with the PBSE/PBSI before the commencement of the
installation works to establish the adequacy of the water supply pressure.
If the supply pressure is inadequate, the FS Contractor shall propose
remedial measures for the approval of the PBSE. The FS Contractor shall
find and select the most appropriate nearby supply point for the test.
- Date of test
- Apparatus or section under test
- Makers number (if any)
- Nature, duration and conditions of test
- Result of test
- Name of FS Contractor’s representative (in block letter) in charge of
test
- Name of Employer’s representative at witness the test
The FS Contractor shall arrange power failure load tests to prove proper
functioning of the fire service installation and the associated power supply
changeover control during power failure and fire mode.
The input D.C. supply to the alarm supervisory circuitry shall be checked
for correct voltage and stability such as to match the signal and alarm
triggering devices.
For fire alarm direct link to the FSD or FSD's approved centre, the FS
Contractor shall, unless approved by the PBSE, initiate the fire alarm direct
link applications to the appropriate agencies within 3 months after
commencement of the Contract so that the fire alarm direct link will be
connected and tested before the fire service inspections. The FS
Contractor shall submit a copy of the application document to the
PBSE/PBSI for record.
The FS Contractor shall co-ordinate and shall closely monitor the status of
completion of fire alarm direct link and the telephone line before the fire
service inspections by the FSD. The FS Contractor shall apply for and
provide at the FS Contractor's own cost the required telephone point for
connection of the fire alarm direct link as required. If the FS Contractor
cannot complete the fire alarm direct link by the date of fire service
inspection by the FSD, the FS Contractor shall be responsible for providing
all necessary manpower and telephone equipment, at the FS Contractor's
own expenses, solely for the purpose for a 24-hour/day full attendant
service to substitute the fire alarm direct link, to the approval of the FSD
and the PBSE, up to the date of the completion of the fire alarm direct link.
The fire alarm direct link shall be tested to the satisfaction of PBSE and
FSD after connection.
The FS Contractor shall allow carrying out on-site full discharge test after
completion of the installation when required by the FSD to confirm the
design conditions can be met and to the satisfaction of the FSD and
approval of the PBSE. The FS Contractor shall follow relevant FSD
Requirements and Circular Letters on the requirements of discharge tests.
The FS Contractor shall refill the gas cylinders with the design agents after
the tests and reset all the equipment after the discharge test.
For emergency lighting system and exit signs provided with central
monitoring, testing and logging system, the system shall be tested in
accordance with the manufacturer's specification and to meet the
requirements in the FSDCoP, EE_TC and this T&C Procedure.
Where indicated that there are emergency lighting installation and/or exit
signs in a building carried out by others and not included in the work under
the Installations, the FS Contractor shall follow the requirements of the
General Specification with particular attention to Clause B11.1.12. The FS
Contractor shall include the emergency lighting installation and exit signs
as part of the fire service installation in the submission to the FSD with the
necessary information to be provided by the relevant parties.
The FS Contractor shall carry out full visual inspection, safety check,
functional and performance test for the emergency generator installation.
The tests shall include measurement on noise confirming compliance with
the statutory requirements and/or as required by the Environmental
FS_TCP
Page 7 of 10 2017 Edition
Protection Department, the HKSAR.
After full test of the fire service installations in a building or premises has
been carried out, with all systems connected to the mains electricity supply,
the mains electricity supply shall be switched off to simulate power failure
and the emergency generator shall start automatically.
When the emergency generator has gained its capacity and is ready to
accept the fire service load, each fire service installation shall be switched
on until all installations are in operating conditions. If an automatic starting
programme or device is provided for controlling the starting sequence of
the equipment using emergency power supply, the programme or device
shall be allowed to operate and test. A 'simultaneous running' test shall
then take place and shall last for a continuous period of 1 hour. During this
period, the performance of each fire service installation shall be monitored
and recorded.
After 1 hour of testing, the emergency generator set shall be examined and
all instruments, safety devices etc. shall indicate normal running of the
generator.
Hot smoke tests shall be carried out where specified or required by the
FSD. The FS Contractor shall prepare and submit proposals including all
calculations, designs, and computer fluid dynamic simulations, etc.,
arrange, co-ordinate and carry out the hot smoke tests to meet the purpose
for simulating the prototype of a real fire under specific dynamic buoyant
flow of smoke and heat intensity in a controlled manner and for assessing
the performance of smoke management system, smoke control system and
smoke extraction system with the given building geometry. Hot smoke
tests shall follow FSD Circular Letter No. 2/2002, Australian Standard AS
4391-1999 "Smoke Management System – Hot Smoke Test" or approved
international standards and practises and to the satisfaction of the FSD and
the PBSE. The FS Contractor shall be responsible for the submissions to
the FSD and obtain comments and approval from the FSD and all relevant
parties on the detailed requirements and arrangement for the hot smoke test
FS_TCP
Page 8 of 10 2017 Edition
at early stage of the Contract.
Hot smoke tests shall be carried out to verify the effectiveness of the
smoke management systems and the like included in the work under the
installations before the compliance inspections of the FSD. Where hot
smoke tests indicate deficiency in any systems, the FS Contractor shall
rectify them to the satisfaction of the FSD and the PBSE at no additional
cost. Where the smoke management systems are not included in the work
under the installations, the FS Contractor shall report the deficiency to the
PBSE and propose improvement measures. The FS Contractor shall
submit a detailed test report at the end of each test that shall include all the
measurement results and data, recommendations and improvement
measures. A final report shall be prepared and submitted after the
compliance inspections for the approval of the FSD.
Details of the hot smoke test requirement shall refer to the General
Specification and FSDCoP.
Tests on fire service installations other than those listed in this T&C
Procedure shall be in accordance with the FSDCoP and FSD Requirements
and Circular Letters, and the approved detailed testing and commissioning
FS_TCP
Page 9 of 10 2017 Edition
procedures proposed by the FS Contractor and approved by the PBSE.
The FS Contractor shall propose and submit detailed testing and
commissioning procedures for all fire service installations for approval by
the PBSE where such details of testing and commissioning are not
available in EE_TC, FSDCoP and this T&C Procedure. The detailed
testing and commissioning procedures submitted shall be comprehensive
and sufficient to demonstrate the functioning and performance of all the
systems and equipment.
FS_TCP
Page 10 of 10 2017 Edition
Annex I
Contract Title :
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference S A S A S A S A S A S A S A S A
to T&C
Procedure
1. Hydrant and Hose Part 3.1
Reel System
Visual Inspection
G/F
1/F
2/F
3/F
4/F
Functional and
performance test
Submission of
Record of Test
Annex I FS_TCP
Page 1 of 5 2017 Edition
Annex I
Contract Title :
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
3. Manual and Part 3.3
Automatic Fire
Alarm System and
Fire Alarm Control
System
Visual Inspection
G/F
1/F
2/F
3/F
Functional and
performance test
Submission of
Record of Test
Annex I FS_TCP
Page 2 of 5 2017 Edition
Annex I
Contract Title :
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
5. Street Hydrant Part 3.5
Visual inspection
Functional and
performance test
Submission of
Record of Test
Annex I FS_TCP
Page 3 of 5 2017 Edition
Annex I
Contract Title :
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference S A S A S A S A S A S A S A S A
to T&C
Procedure
Submission of
Record of Test
Annex I FS_TCP
Page 4 of 5 2017 Edition
Annex I
Contract Title :
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference S A S A S A S A S A S A S A S A
to T&C
Procedure
14. Pressurisation of Part 3.14
Staircases System
Visual inspection
Functional test
Performance test
Submission of
Record of Test
Notes
* Delete if not applicable
(1) Insert revision no.
(2) Insert additional columns as necessary
S - schedule % completion
A - actual % completion
Annex I FS_TCP
Page 5 of 5 2017 Edition
Annex II
Part 2 : Declaration
2.2 I also certify that site tests have been performed in accordance with the
requirements set out in this T&C Procedure and that the results are
satisfactory. A record of the tests has been prepared and submitted to
the PBSE.
____________________________________ ____________________________________
____________________________________ ____________________________________
Note : 1. T&C Procedure refers to the Testing & Commissioning Procedure for Fire Service Installation.
2. The FS Contractor’s Representative signing this certificate must be a person or representative
authorised by the FS Contractor.
3. The person(s) authorised by the FS Contractor to sign part 2, 3 and 4 shall possess the relevant
qualifications required by the Particular Specification and the General Specification.
4. The FS Contractor’s Representative signing part 3 and part 4 shall be the Commissioning Engineer in
Charge of the Firm/Company who witness the test, or the same person in part 2 who witnessed the test.
Annex II FS_TCP
Page 1 of 222 2017 Edition
Annex II
3.1.2.1 Check:
a) Pipings are suitably connected to the fire pumps, fire *Yes/No/N.A. *Yes/No/N.A.
hydrants, hose reels and fire service inlets.
b) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the supply tank tally with the vertical
plumbing diagram approved by W.S.D.
Annex II FS_TCP
Page 2 of 222 2017 Edition
Annex II
d) Are the ball valves of the water tank readily accessible? *Yes/No/N.A. *Yes/No/N.A.
e) Does the size of the water pump suction water pipe from *Yes/No/N.A. *Yes/No/N.A.
the tank match the size of the pump suction inlet?
h) Are puddle flanges of the same sizes as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?
3.1.3.2 Pipework
c) Are U/G water pipes to BS EN 545:2010 Class 100 (dia. *Yes/No/N.A. *Yes/No/N.A.
80 -150), Class 64 (dia. 200 – 350) or Class 50 (dia.
400 – 600) or to BS 1387/ EN 10255 / ISO 65 heavy
grade or other approved type?
d) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?
f) Are water pipes of dia. larger than 50 mm and up to 150 *Yes/No/N.A. *Yes/No/N.A.
mm provided with mechanical pipe couplings?
Annex II FS_TCP
Page 3 of 222 2017 Edition
Annex II
g) Are water pipes of dia. larger than 150 mm provided *Yes/No/N.A. *Yes/No/N.A.
with flanged joints and flanged fittings?
h) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?
k) Are bends of water pipes larger than 50 mm dia. and *Yes/No/N.A. *Yes/No/N.A.
bends of water pipes installed outside false
ceiling/concealed void of long radius type, or as
approved?
l) Are galvanised mild steel sleeves provided for pipes *Yes/No/N.A. *Yes/No/N.A.
through wall or slab?
m) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
wall or slab filled with approved fire proof material and
sealant?
n) Are fire rated pipe sleeves provided for pipes through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab?
o) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab filled with approved fire proof
material and sealant?
q) Are sleeves projected at least 100 mm above finish floor *Yes/No/N.A. *Yes/No/N.A.
level and at least 150 mm above roof finish
t) Are pipe hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?
Annex II FS_TCP
Page 4 of 222 2017 Edition
Annex II
w) Are adequate air vents and drain cocks provided? *Yes/No/N.A. *Yes/No/N.A.
ab) Are isolating cocks/valves provided for pressure gauges? *Yes/No/N.A. *Yes/No/N.A.
ac) Are sprinkler heads provided at top of refuse chutes? *Yes/No/N.A. *Yes/No/N.A.
ae) Are equipotential earth bondings provided for all *Yes/No/N.A. *Yes/No/N.A.
sections of the pipeworks?
3.1.3.3 Hydrant
a) Do the layouts of the hydrant tally with the latest *Yes/No/N.A. *Yes/No/N.A.
approved building plans?
g) Is the outlet not obstructing any door opening, or any *Yes/No/N.A. *Yes/No/N.A.
existing exit route?
Annex II FS_TCP
Page 5 of 222 2017 Edition
Annex II
k) Are the hydrant outlet provided with bronze caps *Yes/No/N.A. *Yes/No/N.A.
complete with chains?
a) Do the layouts of the hose reels tally with the latest *Yes/No/N.A. *Yes/No/N.A.
approved building plans?
c) Is the internal bore of tubing not less than 19mm in *Yes/No/N.A. *Yes/No/N.A.
diameter?
d) Is the hose reel drum not less than 150mm in diameter? *Yes/No/N.A. *Yes/No/N.A.
e) Is nozzle fitted with simple two-way on/off valve and the *Yes/No/N.A. *Yes/No/N.A.
valve is not spring loaded?
f) Are the control valves of gate type or of simple two-way *Yes/No/N.A. *Yes/No/N.A.
ball type?
g) Are the gates valves are closed by clockwise rotation? *Yes/No/N.A. *Yes/No/N.A.
h) Are the rising mains and associated pipework not less *Yes/No/N.A. *Yes/No/N.A.
than 40mm nominal bore?
i) Are the pipes feeding individual hose reel are not less *Yes/No/N.A. *Yes/No/N.A.
than 25mm nominal bore.
j) Are the doors of the hose reel cabinets or recesses *Yes/No/N.A. *Yes/No/N.A.
provided without any locks?
k) Are manual fire alarm call points sited at a prominent *Yes/No/N.A. *Yes/No/N.A.
position near to the hose reels?
Annex II FS_TCP
Page 6 of 222 2017 Edition
Annex II
l) Are the doors clearly bear “FIRE HOSE REEL”(消防喉 *Yes/No/N.A. *Yes/No/N.A.
轆) with characters of at least 50 mm high?
o) Is the notice clearly marked with the standard wordings *Yes/No/N.A. *Yes/No/N.A.
in English and Chinese characters of at least 5mm high
in red letters on white background or vice versa?
r) Are the control valves sited adjacent to the nozzles? *Yes/No/N.A. *Yes/No/N.A.
t) Is the nozzle fitted with simple two-way on/off valve and *Yes/No/N.A. *Yes/No/N.A.
closed by clockwise rotation?
u) Are the control valves and nozzles 1350 mm or less *Yes/No/N.A. *Yes/No/N.A.
above finished floor level, and for a recessed type hose
reel not more than 500 mm from the surface of the wall?
v) Are control valves and nozzles sited in a discernible and *Yes/No/N.A. *Yes/No/N.A.
accessible position of not more than 500 mm from the
surface of the doors?
w) Are guide rings provided for fixed type hose reel? *Yes/No/N.A. *Yes/No/N.A.
z) Can the cradle be swung freely into the corridor or *Yes/No/N.A. *Yes/No/N.A.
passage when required?
aa) Are the tubing of the hose reels properly wound round *Yes/No/N.A. *Yes/No/N.A.
the drum without kinking?
ab) Are the outer faces of the hose reels flush with the wall *Yes/No/N.A. *Yes/No/N.A.
when the reels are not in use?
Annex II FS_TCP
Page 7 of 222 2017 Edition
Annex II
ac) Are the jet nozzles unbroken and housed in glass-fronted *Yes/No/N.A. *Yes/No/N.A.
cabinet secured under lock and key?
ad) Are the guide bracket unbroken and installed? *Yes/No/N.A. *Yes/No/N.A.
af) Are the manual fire alarm call points not more than *Yes/No/N.A. *Yes/No/N.A.
1200 mm above the finished floor level?
ag) Upon actuation of any manual fire alarm call point in the *Yes/No/N.A. *Yes/No/N.A.
building, shall the fixed fire pump come into operation
regardless of the zoning of the fire alarm call point?
ii) Do such doors cause no obstruction to the hose being *Yes/No/N.A. *Yes/No/N.A.
run out in either direction?
a) Are air relief valves provided for rising mains? *Yes/No/N.A. *Yes/No/N.A.
e) Are the rising main supply the correct number of hydrant *Yes/No/N.A. *Yes/No/N.A.
outlets (2 outlets per floor for industrial/godown and 1
outlet per floor for other buildings)?
Annex II FS_TCP
Page 8 of 222 2017 Edition
Annex II
i) Is/Are the Header pipe(s) provided to connect the fire *Yes/No/N.A. *Yes/No/N.A.
service inlets to the rising mains?
k) Are the number and location of fire service inlets *Yes/No/N.A. *Yes/No/N.A.
conforming to latest approved building plan?
Location
Quantity (No(s).)
Pump
Manufacturer
Motor
Pump
Model No.
Motor
Pump
Serial
Motor
Pressure (kPa)
Starting method
Annex II FS_TCP
Page 9 of 222 2017 Edition
Annex II
b) Is electricity used for driving the pump? If no, please *Yes/No/N.A. *Yes/No/N.A.
specify.
c) Is jockey pump provided for up fed system (water tank at *Yes/No/N.A. *Yes/No/N.A.
low level)?
d) Are the motor/pump set rotating parts protected by safety *Yes/No/N.A. *Yes/No/N.A.
guards?
f) Is pump motor power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power for the rated flow of the
system?
k) Are doors to pump rooms clearly labelled “FIXED FIRE *Yes/No/N.A. *Yes/No/N.A.
PUMP” ( 固 定 救 火 泵 ) *and/or “INTERMEDIATE
BOOSTER PUMP” (中途救火泵)?
m) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?
n) Are pump rooms laid clear of any exit or normal *Yes/No/N.A. *Yes/No/N.A.
communication routes through the premises?
Annex II FS_TCP
Page 10 of 222 2017 Edition
Annex II
t) Can the pump just be stopped by switching off at the *Yes/No/N.A. *Yes/No/N.A.
pump control installed near the pump, rather than by any
automatic means?
u) Are manual fire alarm call points wired for starting the *Yes/No/N.A. *Yes/No/N.A.
pump?
v) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.
w) Are the fire pump starters wired through a selector *Yes/No/N.A. *Yes/No/N.A.
switch for duty and standby pump selection?
z) Are the status of each fire pump comprising “Power *Yes/No/N.A. *Yes/No/N.A.
Supply On”, “Pump Running” and “Pump Failed”
monitored and displayed at the pump control panel in the
pump room?
aa) Are such signals repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?
ab) Are all fire pumps housed in suitable enclosures and *Yes/No/N.A. *Yes/No/N.A.
designed solely for accommodating pumps for fire
service installations?
ac) Are pump enclosures clearly marked in English and *Yes/No/N.A. *Yes/No/N.A.
Chinese characters?
ag) Are the pumps enclosures suitably locked to prevent *Yes/No/N.A. *Yes/No/N.A.
unauthorised tampering of the pumps?
ah) Are the running and static pressure at any hydrant outlet *Yes/No/N.A. *Yes/No/N.A.
not exceeding 850kPa?
Annex II FS_TCP
Page 11 of 222 2017 Edition
Annex II
a) Height between the topmost hydrant and the lowest F.S. ___________ _____________
inlet (m): _
h) Are the motors driving the pumps rated to give 20% *Yes/No/N.A. *Yes/No/N.A.
more power in addition to the hydraulic power required
for the rated flow?
k) Are the Start/stop push buttons with pump running *Yes/No/N.A. *Yes/No/N.A.
indication light and buzzer provided adjacent to the fire
service inlet?
l) Are the status of each fire pump comprising “Power *Yes/No/N.A. *Yes/No/N.A.
Supply On”, “Pump Running” and “Pump Failed”
monitored and displayed at the pump control panels in
the pump enclosures?
m) Are such signals repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?
n) Are all fire pumps housed in suitable enclosures and *Yes/No/N.A. *Yes/No/N.A.
designed solely for accommodating pumps for fire
service installations?
o) Are the pump enclosures suitably locked and laid clear *Yes/No/N.A. *Yes/No/N.A.
of any exit or normal communication routes through the
premises?
Tested / Checked by : Signature - Post :
(Name of FS Contractor’s Representative)
Tel. No. :
( ) Date :
Witnessed by: Signature - Post :
(Name(s) of *PBSE/PBSI)
Tel. No. :
( ) Date :
Annex II FS_TCP
Page 12 of 222 2017 Edition
Annex II
p) Are the pump enclosures clearly marked in English and *Yes/No/N.A. *Yes/No/N.A.
Chinese characters?
a) Are the fire service inlet couplings between 600 mm and *Yes/No/N.A. *Yes/No/N.A.
1000 mm above finished floor level?
b) Are the fire service inlets suitably enclosed and *Yes/No/N.A. *Yes/No/N.A.
protected?
c) Are the fire service inlets readily accessible by Fire *Yes/No/N.A. *Yes/No/N.A.
Services personnel?
e) Are the fire service inlet enclosures clearly and *Yes/No/N.A. *Yes/No/N.A.
permanently labelled “F.S. INLET” (消防入水掣) with
characters at least 50 mm high?
3.1.3.9 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.1)?
Annex II FS_TCP
Page 13 of 222 2017 Edition
Annex II
3.1.4.1 Pipeworks
f) Do the gate valves, stop valves and globe valves *Yes/No/N.A. *Yes/No/N.A.
function properly?
Annex II FS_TCP
Page 14 of 222 2017 Edition
Annex II
a) Do the pumps and motors run at the designed discharge *Yes/No/N.A. *Yes/No/N.A.
water pressure and operating electrical current? (Test
records on Part 4.1 Table 3)
e) Do the fixed fire pumps come into operation upon *Yes/No/N.A. *Yes/No/N.A.
actuation of any manual fire alarm call point, regardless
of the zoning of the fire alarm call point?
f) Are the status of fire pumps including “power supply *Yes/No/N.A. *Yes/No/N.A.
on”, “pump running” and pump failed” displayed at the
pump control panel and repeated at the main fire service
control panel?
g) Do the float switches in the water tanks for controlling *Yes/No/N.A. *Yes/No/N.A.
the transfer pumps function properly?
h) Do the high and low water level alarms and indications *Yes/No/N.A. *Yes/No/N.A.
for the water tanks function properly?
Annex II FS_TCP
Page 15 of 222 2017 Edition
Annex II
a) Can the hose reel tubing be drawn out freely and easily *Yes/No/N.A. *Yes/No/N.A.
in any direction without obstruction?
b) Are the hose reels capable to cover within 6 m of each *Yes/No/N.A. *Yes/No/N.A.
part of the occupied area? (Test Records on Part 4.1
Table 5)
c) Are the hose reels capable to project a water jet of 6 m *Yes/No/N.A. *Yes/No/N.A.
or greater? (Test Records on Part 4.1 Table 5)
d) Is the water tightness of the stop valves, nozzles, and *Yes/No/N.A. *Yes/No/N.A.
tubing connections satisfactory when the fire pump is
running?
3.1.4.6 Hydrant
b) Do the flow capacity and pressure test satisfy Fire *Yes/No/N.A. *Yes/No/N.A.
Services Department’s requirements as the following
Table? (Test records on Part 4.1 Tables 6 and 7)
Note : Each hydrant outlet shall have a flow of 450 L/min at a running pressure of not less than 350 kPa.
Annex II FS_TCP
Page 16 of 222 2017 Edition
Annex II
b) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the sprinkler tank tally with the vertical
plumbing diagram approved by W.S.D.?
e) Are the ball valves of the water tank readily accessible? *Yes/No/N.A. *Yes/No/N.A.
Note: (1) Positive head - water capacity between pump centre line and the lowest effective water
level of tank not exceeding one-third total capacity.
(2) Suction lift - vertical height between pump centre line and the lowest effective water
level of tank not exceeding 3.2 m.
(4) The pump centre line shall be no more than 2 m above the low water level of suction tank.
Annex II FS_TCP
Page 17 of 222 2017 Edition
Annex II
f) Are the sizes of the water pump suction water pipes *Yes/No/N.A. *Yes/No/N.A.
correct as the Table above?
j) Are puddle flanges of the same size as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?
l) Are sizes of priming water pipes correct? (LH - 25 mm, *Yes/No/N.A. *Yes/No/N.A.
OH and HH -50 mm)
Annex II FS_TCP
Page 18 of 222 2017 Edition
Annex II
2m
Max. distance from wall/partition 2.3 m 2m Clause 12.4.1
(standard)
Min. distance from the bottom edge Item 2.45 of FSD Circular
0.3 m 0.3 m 0.3 m
of air duct/obstructions Letter No. 3/2006
Annex II FS_TCP
Page 19 of 222 2017 Edition
Annex II
(xii) Are construction of open ceiling spacing and location of *Yes/No/N.A. *Yes/No/N.A.
sprinkler heads in accordance with LPC Rules as the
following Table and regarding :
Requirements of Open Ceiling (LH and OH Only) (See LPC Rules Incorporating BS EN 12845 Clause
12.4.14)
Min. dimensions of opening (shall not be smaller than vertical thickness of ceiling) 25 mm
Min. vertical separation between sprinklers and suspended ceiling for flat spray
300 mm
sprinkler
Min. vertical separation between sprinklers and suspended ceiling for sprinkler other 800 mm
than flat spray sprinkler
Annex II FS_TCP
Page 20 of 222 2017 Edition
Annex II
b) Is there any sheet metal or fire resistance sheet not less *Yes/No/N.A. *Yes/No/N.A.
than 200mm wide and 150mm high located midway
between the sprinkler or by using intervening
construction features when there is possibility for
adjacent sprinklers from wetting each other?
c) Are there any baffles with its top edge extend above the *Yes/No/N.A. *Yes/No/N.A.
sprinkler deflector by 50mm to 75mm if the baffles is
fitted on the range pipe when there is possibility for
adjacent sprinklers from wetting each other?
Annex II FS_TCP
Page 21 of 222 2017 Edition
Annex II
i) Are the Nos. of sprinklers installed on the range and *Yes/No/N.A. *Yes/No/N.A.
distribution pipes in accordance with LPC Rules as the
following Tables?
j) Are sprinklers installed in upright position for either type *Yes/No/N.A. *Yes/No/N.A.
of pre-action installation unless otherwise recommended
by the corresponding manufacturer of the installation?
l) Are sprinkler heads installed in upright position for dry *Yes/No/N.A. *Yes/No/N.A.
pipe system installations in cold room?
Light Hazard
20# 1
25 3
Annex II FS_TCP
Page 22 of 222 2017 Edition
Annex II
Max. No. of
Pipe Size Sprinklers
Range Pipes
(nominal dia. mm) allowed on Range
Pipes
(a) Ranges at remote end of each distribution
pipe spur
Annex II FS_TCP
Page 23 of 222 2017 Edition
Annex II
3.2.1.4 Pipeworks
d) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?
f) Are water pipes of dia. larger than 50 mm and up to 150 *Yes/No/N.A. *Yes/No/N.A.
mm operating on or below 1600 kPa provided with
mechanical pipe couplings?
g) Are water pipes of dia. larger than 150 mm provided *Yes/No/N.A. *Yes/No/N.A.
with flanged joints and flanged fittings?
h) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?
k) Are bends of water pipes larger than 50 mm dia. and *Yes/No/N.A. *Yes/No/N.A.
bends of water pipes installed outside false
ceiling/concealed void of long radius type, or as
approved?
l) Are galvanised mild steel sleeves provided for pipes *Yes/No/N.A. *Yes/No/N.A.
through wall or slab?
m) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
wall or slab filled with approved fire proof material and
sealant?
Annex II FS_TCP
Page 24 of 222 2017 Edition
Annex II
n) Are fire rated pipe sleeves provided for pipes through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab?
o) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab filled with approved fire proof
material and sealant?
q) Are sleeves projected at least 100 mm above finish floor *Yes/No/N.A. *Yes/No/N.A.
level and at least 150 mm above roof finish
t) Are pipe hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?
v) Are adequate air vents and drain cocks provided? *Yes/No/N.A. *Yes/No/N.A.
x) Are outlet valves on fire service water tanks, sprinkler *Yes/No/N.A. *Yes/No/N.A.
installation and elsewhere as specified locked at OPEN
position with security devices including chains,
padlocks, tamper-proof serially numbered security tags,
and durable warning labels to prevent tampering/
unauthorised operation, and with a log book to keep
track of maintenance services and operation, of the outlet
valves?
z) Can all sections of water pipes be drained with the *Yes/No/N.A. *Yes/No/N.A.
exception of drop pipes to single sprinklers in a wet
installation?
aa) Are the water pipes suitably sloped and drained to the *Yes/No/N.A. *Yes/No/N.A.
installation drain valve as far as practical?
ab) Are the drain points adequate in the installation? *Yes/No/N.A. *Yes/No/N.A.
Annex II FS_TCP
Page 25 of 222 2017 Edition
Annex II
ac) Are drain points connected to the nearest drain for *Yes/No/N.A. *Yes/No/N.A.
routine testing of all flow switches?
ad) Are installation drain pipes and valves of correct sizes? *Yes/No/N.A. *Yes/No/N.A.
(min. for LH - 40 mm, OH and HH - 50 mm)
ae) Are the water pipes laid to the following minimum *Yes/No/N.A. *Yes/No/N.A.
slope?
af) Are correct sizes of drain pipes and valves provided as *Yes/No/N.A. *Yes/No/N.A.
following for pipeworks to be drained?
50 mm 20 mm
65 & 80 mm 32 mm
100 mm 50 mm
ah) Are isolating cocks/valves provided for pressure gauges? *Yes/No/N.A. *Yes/No/N.A.
aj) Are installation control valves in accordance with BSB *Yes/No/N.A. *Yes/No/N.A.
Guide Drawings?
ak) Are main stop valves secured at OPEN position with *Yes/No/N.A. *Yes/No/N.A.
security devices including chains, padlocks, tamper-
proof serially numbered security tags, and durable
warning labels to prevent tampering/unauthorised
operation, and with a log book to keep track of
maintenance services and operation, of the valves?
al) Are main stop valves placed at proximity to an entrance *Yes/No/N.A. *Yes/No/N.A.
to the premises?
am) Are location plates for main stop valves provided with *Yes/No/N.A. *Yes/No/N.A.
correct wording and character sizes?
Annex II FS_TCP
Page 26 of 222 2017 Edition
Annex II
an) Are each set of alarm valve and alarm gong provided *Yes/No/N.A. *Yes/No/N.A.
with identification label and number?
ao) Is the total equivalent length of water pipe between *Yes/No/N.A. *Yes/No/N.A.
alarm valve and alarm gong 25 m or less?
ap) Is the centreline of alarm gong higher than 6 m above the *Yes/No/N.A. *Yes/No/N.A.
point of connection to the alarm valve?
aq) Are equipotential earth bondings provided for the *Yes/No/N.A. *Yes/No/N.A.
pipeworks?
ar) Have the electric monitoring type subsidiary stop valves *Yes/No/N.A. *Yes/No/N.A.
given visual signals back to the fire alarm control and
remote indicating panel to identify the status of
subsidiary stop valves at open/close state with security
devices?
as) Have the security devices installed with warning labels *Yes/No/N.A. *Yes/No/N.A.
and serial numbers and complied with the requirements
of FSD Circular Letter No. 4/2010 and as approved by
the Supervising Officer?
at) Has the FS Contractor adopted the sprinkler subsidiary *Yes/No/N.A. *Yes/No/N.A.
stop valves management system in accordance with the
requirements of FSD Circular Letter No. 4/2010 on
subsidiary stop valves?
Annex II FS_TCP
Page 27 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 28 of 222 2017 Edition
Annex II
Or
b) Does the pre-action system control panel comply with *Yes/No/N.A. *Yes/No/N.A.
the requirements of BS 5839-1:2002+A2:2008 where
appropriate and incorporate the necessary relays, timers,
key types switches, alarm and trouble lights essential to
the operation of the system?
c) Does the control panel employ printed circuit boards for *Yes/No/N.A. *Yes/No/N.A.
the components and is completely factory wired and
ready for connection on the Site?
e) Are the pre-action control panel relays and circuitry *Yes/No/N.A. *Yes/No/N.A.
operating the pre-action alarm valve solenoid valves or
actuator mechanisms duplicated and wired such that no
single fault or failure shall render the installation
inoperable?
f) Does the fire detection system used to activate a pre- *Yes/No/N.A. *Yes/No/N.A.
action sprinkler system comply with the appropriate
parts of BS 5839: Part 1:2002+A2:2008, BS 6266:2011
and LPC Recommendation EDP 3 (or its equivalent,
where appropriate) and the following items (ref. LPC
Rules for Sprinkler Installations: Clause TB 208.5.8 of
the LPC Rules Incorporating BS EN 12845)?
Annex II FS_TCP
Page 29 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 30 of 222 2017 Edition
Annex II
(x) Air supply system including air compressor, piping *Yes/No/N.A. *Yes/No/N.A.
and fittings
5) Is the heat probe stainless steel and the top *Yes/No/N.A. *Yes/No/N.A.
colour coded for temperature set point and
spacing?
8) Are the detectors spaced for not more than 12 *Yes/No/N.A. *Yes/No/N.A.
m apart and 6 m from walls or as approved?
Annex II FS_TCP
Page 31 of 222 2017 Edition
Annex II
3) Are the binding tapes used with the cables *Yes/No/N.A. *Yes/No/N.A.
flame retardant?
5) Does the fire resistance cable comply with the *Yes/No/N.A. *Yes/No/N.A.
Clause 26.2 of BS 5839-1:2002+A2:2008 for
fire detection and fire alarm systems or other
international standards which is acceptable to
the Director of Fire Services?
7) Does a reset button on the panel reset the timer *Yes/No/N.A. *Yes/No/N.A.
and alarm circuits after system operation?
Annex II FS_TCP
Page 32 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 33 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 34 of 222 2017 Edition
Annex II
Location
Quantity (No(s).)
Manufacturer Pump
Motor
Model Pump
Motor
Motor
Pressure (kPa)
Starting method
Annex II FS_TCP
Page 35 of 222 2017 Edition
Annex II
a) Are the motor/pump set rotating parts protected by safety *Yes/No/N.A. *Yes/No/N.A.
guard?
b) Is pump motor power rated at 10% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power?
d) Are the diesel sprinkler pump sets installed with the *Yes/No/N.A. *Yes/No/N.A.
manually operated shut down mechanism labelled as
“SPRINKLER PUMP SHUT-OFF” 終止花灑泵運行?
e) Has each switch for the dedicated power supply to an *Yes/No/N.A. *Yes/No/N.A.
electric sprinkler pump motor labelled as “ SPRINKLER
PUMP MOTOR SUPPLY - NOT TO BE SWITCHED
OFF IN THE EVENT OF FIRE ” 花灑泵電源供應 – 在
火警發生時切勿切斷電源?
k) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?
Annex II FS_TCP
Page 36 of 222 2017 Edition
Annex II
o) Can the pump just be stopped by switching off at the *Yes/No/N.A. *Yes/No/N.A.
pump control not installed near the pump, rather than by
any automatic means?
p) Are manual fire alarm call points wired for starting the *Yes/No/N.A. *Yes/No/N.A.
pump?
q) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.
r) Are the fire pump starters wired through a selector *Yes/No/N.A. *Yes/No/N.A.
switch for duty and standby pump selection?
u) Are the status of each fire pump condition comprising *Yes/No/N.A. *Yes/No/N.A.
“Power Supply On”, “Pump Running” and “Pump
Failed” monitored and displayed at the pump control
panel in the pump room and repeated at a panel in the
fire control room or at the main entrance of the building?
x) Are start/stop push buttons with pump running indication *Yes/No/N.A. *Yes/No/N.A.
light and buzzer provided adjacent to the fire service
inlet?
3.2.1.9 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.1)?
Annex II FS_TCP
Page 37 of 222 2017 Edition
Annex II
3.2.2.1 Pipeworks
b) With the installation valve primed in the ready position, *Yes/No/N.A. *Yes/No/N.A.
is it possible to fully pressurise the installation in one
hour, at any time ?
Annex II FS_TCP
Page 38 of 222 2017 Edition
Annex II
a) Heat Detector
Annex II FS_TCP
Page 39 of 222 2017 Edition
Annex II
(ii) When the temperature drops below the set point, is *Yes/No/N.A. *Yes/No/N.A.
the circuit re-established? At 420oC sustained
ambient temperature, does the tell-tale tab drop
away, indicating possible detector damage?
b) Mode of Operation
(iii) The fire alarm bell to continue to sound until the *Yes/No/N.A *Yes/No/N.A
reset button is pushed. Should the temperature
build to the trip point of any detector during any
phase of the cycle, the system will continue to flow
or immediately start the flow of water to the fire.
c) Control Panel
(i) Does system operation or low air pressure activate *Yes/No/N.A. *Yes/No/N.A.
the corresponding light and the audible trouble
alarm and other alarms required which can be
silenced by ON/OFF switches?
(iii) If the detector circuit and/or pressurised air are *Yes/No/N.A. *Yes/No/N.A.
unavailable for service, will the system turn into an
ordinary automatic dry pipe or wet pipe system?
(iv) Do all alarms except the low air pressure alarm *Yes/No/N.A. *Yes/No/N.A.
operate constantly unless shut off and cycling
features are negated?
Annex II FS_TCP
Page 40 of 222 2017 Edition
Annex II
d) Air Supply
(iii) Does the compressed air system allow the *Yes/No/N.A. *Yes/No/N.A.
recharging of the recycling installation manually
after the sprinkler system has been operated and the
actuated sprinkler heads are replaced?
a) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current? (Test records on Part 4.2 Table 2)
c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?
e) Do the float switches in the water tanks controlling the *Yes/No/N.A. *Yes/No/N.A.
water pumps function properly?
f) Are the temperatures of the water pump bearings normal *Yes/No/N.A. *Yes/No/N.A.
at running condition?
Annex II FS_TCP
Page 41 of 222 2017 Edition
Annex II
l) Do the pressure switches controlling the jockey, duty and *Yes/No/N.A. *Yes/No/N.A.
standby pumps operate properly? (Test records on Part
4.2 Table 3)
m) Are the pumps fully operational within 30 sec. after *Yes/No/N.A. *Yes/No/N.A.
starting ?
a) Do the flow switches for zone operating indication and *Yes/No/N.A. *Yes/No/N.A.
alarm function properly? (Test records on Part 4.2 Table
4)
Annex II FS_TCP
Page 42 of 222 2017 Edition
Annex II
b) Does the water alarm for each installation valve operate *Yes/No/N.A. *Yes/No/N.A.
when the test valve is opened?
c) Do the high and low water level alarms and indication *Yes/No/N.A. *Yes/No/N.A.
for the water tanks function properly?
d) Are the alarm valves and subsidiary stop valves signals *Yes/No/N.A. *Yes/No/N.A.
indicated at the main fire service control panel?
Note: ps is the static head loss due to the height of the highest sprinkler in the array concerned above the
control valve set ‘C’ gauge, in bar.
Annex II FS_TCP
Page 43 of 222 2017 Edition
Annex II
3.3 Manual and Automatic Fire Alarm System and Fire Alarm Control System
3.3.1.3 Detectors
a) Heater detector:
Annex II FS_TCP
Page 44 of 222 2017 Edition
Annex II
b) Smoke detector :
c) Multi-sensor detector :
d) Flame detector:
f) Others :
Manufacturer/model No. : ____________
FSD approved type or listed by a recognised
Product Certification Body : *Yes/No
Type : ____________
Annex II FS_TCP
Page 45 of 222 2017 Edition
Annex II
Type : Bell [ ]
Yodalarm [ ]
Horn [ ]
Siren [ ]
Electronic sounder [ ]
Others [ ]
(please specify ________________ )
Annex II FS_TCP
Page 46 of 222 2017 Edition
Annex II
3.3.2 Zoning
3.3.2.1 Detectors
Annex II FS_TCP
Page 47 of 222 2017 Edition
Annex II
(use separate sheets or computer printouts in full accordance with the above format if the space is not
sufficient for inserting all the zones)
3.3.3.1 General
3.3.3.1.1 All fire detection and equipment are conformed to FSD’s *Yes/No/N.A. *Yes/No/N.A.
requirements.
3.3.3.1.2 All individual components of a fire alarm system are *Yes/No/N.A. *Yes/No/N.A.
mutually compatible.
Annex II FS_TCP
Page 48 of 222 2017 Edition
Annex II
3.3.3.1.6 Log book is provided adjacent to the alarm annunciation *Yes/No/N.A. *Yes/No/N.A.
panel.
3.3.3.2 Detectors
3.3.3.2.3 Detection zonings are properly labelled at the alarm *Yes/No/N.A. *Yes/No/N.A.
annunciation panel.
(a) heat detector is used in kitchen and electrical and *Yes/No/N.A. *Yes/No/N.A.
mechanical plant room.
*Yes/No/N.A. *Yes/No/N.A.
(b) smoke detector is used in other areas except
toilets, bathrooms and staircases where sprinkler is
provided. *Yes/No/N.A. *Yes/No/N.A.
(c) Sounder base is provided for smoke detectors
installed in guestrooms of hotels/ guesthouse/
bedrooms of student hostels except for detectors
installed inside concealed space.
3.3.3.2.7 The aggregate floor area covered by any single detection *Yes/No/N.A. *Yes/No/N.A.
loop circuit is ≦ 10,000 m2 calculated on those portions
of the premises installed with fire detectors.
3.3.3.2.8 The aggregate floor area covered by a single detection *Yes/No/N.A. *Yes/No/N.A.
zone is ≦ 2,000 m2 calculated on those portions of the
premises installed with fire detectors.
3.3.3.2.9 Remote indicating lamps are provided to show visually *Yes/No/N.A. *Yes/No/N.A.
the position of the fire detection signal for search
distance > 30 m.
Annex II FS_TCP
Page 49 of 222 2017 Edition
Annex II
3.3.3.2.10 Remote indicating lamps outside doors (near door exit) *Yes/No/N.A. *Yes/No/N.A.
are provided for detectors installed inside rooms if doors
are likely to be locked.
3.3.3.2.11 Remote indicating lamps are provided for detectors in *Yes/No/N.A. *Yes/No/N.A.
inaccessible areas such as ceiling voids or floor voids, if
addressable text display in conjunction with layout plans
is not provided adjacent to the control and indicating
equipment.
3.3.3.2.12 All the remote indicating lamps are installed with name *Yes/No/N.A. *Yes/No/N.A.
plates engraved with “Fire 火警” and graphic symbol
showing the locations they serve. The wordings and
graphic symbols are in full compliance with Appendix I
to List 2 – General Specification of Remote Indicating
Lamp Plates of the FSD Circular Letter No. 1/2009.
3.3.3.2.13 Detectors are provided for horizontal void ≧ 800mm *Yes/No/N.A. *Yes/No/N.A.
high.
3.3.3.2.14 Detectors are provided for horizontal void < 800mm and *Yes/No/N.A. *Yes/No/N.A.
with the following conditions:
3.3.3.2.15 Clear space below each detector is ≧ 500mm except *Yes/No/N.A. *Yes/No/N.A.
inside ceiling and floor voids and areas with no
horizontal dimension greater than 1m.
3.3.3.2.16 Point smoke detector is installed within the general *Yes/No/N.A. *Yes/No/N.A.
ceiling height limit of 10.5m.
3.3.3.2.17 Heat detector is installed within the general ceiling *Yes/No/N.A. *Yes/No/N.A.
height of 9m for detector conforming to BS EN 54-5,
Class A1 and 7.5m for conforming to other classes of BS
EN 54-5.
3.3.3.2.18 Under flat ceiling, horizontal distance between any point *Yes/No/N.A. *Yes/No/N.A.
and the nearest heat detector is ≦5.3m.
Annex II FS_TCP
Page 50 of 222 2017 Edition
Annex II
3.3.3.2.19 Under flat ceiling, horizontal distance between any point *Yes/No/N.A. *Yes/No/N.A.
and the nearest smoke detector is ≦7.5m.
3.3.3.2.21 In corridors ≦2m wide, smoke detectors are sited at *Yes/No/N.A. *Yes/No/N.A.
intervals of ≦15m or ≦7.5m from end wall.
3.3.3.2.24 Detectors are mounted ≧1m from any air inlet of forced *Yes/No/N.A. *Yes/No/N.A.
ventilation system.
3.3.3.3.2 An alarm sounder is provided near the control and *Yes/No/N.A. *Yes/No/N.A.
indicating equipment.
Annex II FS_TCP
Page 51 of 222 2017 Edition
Annex II
3.3.3.3.3 One alarm sounder is provided at each hose reel point. *Yes/No/N.A. *Yes/No/N.A.
3.3.3.3.4 The system is incorporated with at least two alarm *Yes/No/N.A. *Yes/No/N.A.
sounders and each fire compartment is provided with at
least one sounder. (Note: Meaning of fire compartment is
as defined in Clause 5 of the Code of Practice for Fire
Resisting Construction published by the Buildings
Department, the HKSAR (the FRC))
3.3.3.3.5 All alarm sounder cases are painted in red colour and *Yes/No/N.A. *Yes/No/N.A.
clearly marked ‘FIRE ALARM’ ‘火警’ in white colour.
The height of all the English and Chinese wordings shall
not be less than 10 mm and 15 mm respectively.
3.3.3.3.6 A clearly labelled facility is provided at or near the alarm *Yes/No/N.A. *Yes/No/N.A.
annunciation panel to enable silencing of alarm signals.
3.3.3.4.1 Zoning of manual call points is at least one zone per *Yes/No/N.A. *Yes/No/N.A.
floor or storey.
Annex II FS_TCP
Page 52 of 222 2017 Edition
Annex II
3.3.3.4.2 One manual call point is located at each of the following *Yes/No/N.A. *Yes/No/N.A.
equipment/location.
3.3.3.4.3 The travel distance for finding a manual call point is ≦ *Yes/No/N.A. *Yes/No/N.A.
30 m.
3.3.3.4.4 For exit opening ≧12m in width, two manual call points *Yes/No/N.A. *Yes/No/N.A.
are provided within 2m from each end of the opening
before the exit (or before the entrance lobby if such
lobby leads only to the exit).
3.3.3.4.5 Manual call points are fixed at a height of about 0.9- *Yes/No/N.A. *Yes/No/N.A.
1.2m above the finished floor level.
3.3.3.4.6 Manual call points are surface mounted or semi-recessed *Yes/No/N.A. *Yes/No/N.A.
mounted as per manufacturer’s design.
3.3.3.5.1 VFA signal lamps are labelled ‘FIRE ALARM’ ‘火警’. *Yes/No/N.A. *Yes/No/N.A.
The height of English and Chinese characters is not less
than 10 mm and 15 mm, respectively.
3.3.3.5.2 Visual alarm signal is in the form of red flashing light. *Yes/No/N.A. *Yes/No/N.A.
3.3.3.5.3 VFA flashing light is visible to normal eyesight in all *Yes/No/N.A. *Yes/No/N.A.
areas required to be protected.
3.3.3.5.4 Each compartment is provided with at least one VFA *Yes/No/N.A. *Yes/No/N.A.
signal lamp.
3.3.3.5.5 One VFA point is located near every hose reel. *Yes/No/N.A. *Yes/No/N.A.
3.3.3.5.6 Distance between any two VFA points is ≦60m. *Yes/No/N.A. *Yes/No/N.A.
3.3.3.5.7 Areas to be covered by VFA system are in full complian *Yes/No/N.A. *Yes/No/N.A.
ce with the approved building plans and the Design Man
ual: Barrier Free Access 2008 of Buildings Department.
Annex II FS_TCP
Page 53 of 222 2017 Edition
Annex II
3.3.3.6.1 Time related system and/or transmission delay unit are/is *Yes/No/N.A. *Yes/No/N.A.
provided.
3.3.3.6.2 Time related system and/or transmission delay unit are/is *Yes/No/N.A. *Yes/No/N.A.
approved by FSD.
3.3.3.7.1 The alarm annunciation panel is located in an area on the *Yes/No/N.A. *Yes/No/N.A.
ground floor and in the immediate vicinity of the
building entrance easily to be accessed by the FSD or in
the building’s Fire Control Centre/Room.
3.3.3.7.3 Where the control and indicating equipment is installed *Yes/No/N.A. *Yes/No/N.A.
in a severe weather environment, a weatherproof
protective enclosure with adequate ventilation is
provided to protect it from being damaged by high
humidity and water.
Annex II FS_TCP
Page 54 of 222 2017 Edition
Annex II
3.3.3.7.4 Zone indications are provided at the control and *Yes/No/N.A. *Yes/No/N.A.
indicating equipment.
3.3.3.7.5 All the alarm and zone indications are displayed in both *Yes/No/N.A. *Yes/No/N.A.
Chinese and English so that the origin of the alarm and
zone positions in relation to this building can be easily,
quickly and unambiguously identified.
3.3.3.7.7 The operation of all manual controls and isolating *Yes/No/N.A. *Yes/No/N.A.
devices shall be limited to authorised personnel. It may
be provided by restricting access to the equipment by
means of the following : -
3.3.3.7.8 The wirings are compatible with the type of control *Yes/No/N.A. *Yes/No/N.A.
panel as recommended by the panel manufacturer.
(2-wire system/4-wire system/twist pair/……………….)
Annex II FS_TCP
Page 55 of 222 2017 Edition
Annex II
3.3.3.8.4 Circuit supplying fire alarm system is not protected by a *Yes/No/N.A. *Yes/No/N.A.
residual current device unless this is necessary to comply
with the requirements of the Code of Practice for the
Electricity (Wiring) Regulations published by the
Electrical and Mechanical Services Department, the
HKSAR (hereinafter referred to as EECoP).
3.3.3.8.7 Every isolator, switch and protective device, other than *Yes/No/N.A. *Yes/No/N.A.
the main isolator for the building that can supply for the
fire alarm system is properly labelled as appropriate :
3.3.3.8.8 Normal and standby battery supplies can each be capable *Yes/No/N.A. *Yes/No/N.A.
of supplying the maximum alarm load irrespective of the
condition of the other supply.
Annex II FS_TCP
Page 56 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 57 of 222 2017 Edition
Annex II
3.3.3.9.3 Cables other than MICS cable complying with BS EN *Yes/No/N.A. *Yes/No/N.A.
60702 or steel wire armoured cables complying with BS
7846 shall be mechanically protected if :
3.3.3.9.5 Conductors carrying fire alarm power or signals are *Yes/No/N.A. *Yes/No/N.A.
separated from conductors used for other systems by one
or more of the followings :
3.3.3.9.6 All joints, other than those within system components, in *Yes/No/N.A. *Yes/No/N.A.
a cable is enclosed within junction boxes labelled ‘FIRE
ALARM’ ‘火警警報’ engraved in white letter/character
with red colour background. The height of all the
English and Chinese wordings is not less than 10 mm
and 15 mm respectively to avoid confusion with other
services.
3.3.3.9.8 Fire alarm cables are separated from cables of other *Yes/No/N.A. *Yes/No/N.A.
services.
3.3.3.9.9 Cables carrying power in excess of extra-low voltage are *Yes/No/N.A. *Yes/No/N.A.
segregated from extra-low voltage fire alarm circuits.
Annex II FS_TCP
Page 58 of 222 2017 Edition
Annex II
3.3.3.9.10 The colour of fire alarm cables are limited to ≦2 sets (4 *Yes/No/N.A. *Yes/No/N.A.
nos.) of common colours and one of the colours is red.
3.3.4 Testing
3.3.4.1 Detectors
3.3.4.1.1 Upon actuation of any detector in the building, the *Yes/No/N.A. *Yes/No/N.A.
correct audio/ visual warning device for the fire alarm
and detection system is initiated.
3.3.4.2.1 Upon the actuation of the detector, alarm shall be given *Yes/No/N.A. *Yes/No/N.A.
by alarm sounders installed near the main building
entrance or “Fire Service Access Point” as per FSD
Circular Letter No. 1/2009 and the alarm annunciation
panel.
3.3.4.2.2 Background noise (N) likely to persist for a period *Yes/No/N.A. *Yes/No/N.A.
longer than 30 seconds.
3.3.4.2.3 For domestic building, the minimum sound level of *Yes/No/N.A. *Yes/No/N.A.
alarm sounders is measured at 3 m from the inside of the
main entrance door with all windows fully opened and
all doors shut off at all flats/units and the result is,
…………………………… dB(A) which is :
Annex II FS_TCP
Page 59 of 222 2017 Edition
Annex II
3.3.4.2.4 For buildings other than domestic building, the minimum *Yes/No/N.A. *Yes/No/N.A.
sound level of alarm sounders is measured at 3 m from
the inside of the main entrance door with all windows
fully opened and all doors shut off at all rooms/ premises
and the result is,
…………………………… dB(A) which is :
3.3.4.2.6 For premises designed for public entertainment, retail *Yes/No/N.A. *Yes/No/N.A.
and similar premises, in which the sound pressure level
of music >80dB(A), the music is muted automatically
when a fire alarm signal is given.
3.3.4.2.7 Failure of the power supply to the secondary sounders *Yes/No/N.A. *Yes/No/N.A.
shall result in silencing of the noisy machines.
3.3.4.3.2 Upon actuation of any manual call point in the building, *Yes/No/N.A. *Yes/No/N.A.
the fixed fire pump serving the corresponding block
comes into operation regardless of the zoning of the
manual call point.
3.3.4.3.3 Upon actuation of any manual call point in the building, *Yes/No/N.A. *Yes/No/N.A.
the correct audio/ visual warning device for the fire
alarm and detection system is initiated.
3.3.4.3.4 The delay between operation of a manual call point and *Yes/No/N.A. *Yes/No/N.A.
the giving of an “Evacuate” signal in the alarm zone
within which the manual call point is located shall be ≦
3 seconds and others shall be ≦ 10 seconds.
Annex II FS_TCP
Page 60 of 222 2017 Edition
Annex II
3.3.4.4.1 All VFA flashing light is visible to normal eyesight in *Yes/No/N.A. *Yes/No/N.A.
the required protected areas when the fire alarm system
is actuated.
3.3.4.4.2 VFA signal is clearly distinguishable from any other *Yes/No/N.A. *Yes/No/N.A.
non-fire service visual signals.
3.3.4.5.1 Audio, visual alarms for the fire detection and alarm *Yes/No/N.A. *Yes/No/N.A.
system, signals for system/ detector/ manual call point/
sounder fault and signals to all the ancillary equipment
are given correctly at the control and indicating
equipment.
3.3.4.5.3 The following panel functions and switches are working *Yes/No/N.A. *Yes/No/N.A.
properly :
3.3.4.5.4 Two simultaneous faults on a manual call point or fire *Yes/No/N.A. *Yes/No/N.A.
detector circuit shall not disable protection within an
aggregate area greater than 10,000 m2 calculated on
those portions of the premises installed with fire
detectors.
3.3.4.5.5 Detector solely using as actuating devices for fire service *Yes/No/N.A. *Yes/No/N.A.
systems such as fire shutter, VAC control, fixed
installations other than water, fixed installations using
water, pressurisation system, and smoke extraction
systems are linked to the Computerised Fire Alarm
Transmission System (CFATS) through DTL.
(Note; This linking is not a mandatory requirement from
FSD)
Annex II FS_TCP
Page 61 of 222 2017 Edition
Annex II
(a) short circuit or open circuit in any circuits serving *Yes/No/N.A. *Yes/No/N.A.
manual call points or fire detectors;
(b) the removal of a manual call point or a fire detector *Yes/No/N.A. *Yes/No/N.A.
that is designed to be detachable;
(c) short circuit or open circuit of any circuits serving *Yes/No/N.A. *Yes/No/N.A.
fire alarm devices;
(d) short circuit or open circuit of any wiring between *Yes/No/N.A. *Yes/No/N.A.
any power supply that is in a separate enclosure and
the equipment to which it supplies power;
(e) any earth fault that is capable of preventing the *Yes/No/N.A. *Yes/No/N.A.
system from performing;
(f) the rupture of any fuse, or the operation of any other *Yes/No/N.A. *Yes/No/N.A.
protective device, that affects the ability of the
system to perform;
(g) a short circuit or open circuit in the wiring between
separate control and/or indicating equipment that is *Yes/No/N.A. *Yes/No/N.A.
provided;
(h) a short circuit or open circuit in the wiring between *Yes/No/N.A. *Yes/No/N.A.
main and any repeat control and/or indicating
equipment (such as a mimic diagram) that is
provided;
(i) a short circuit or open circuit in the wiring between *Yes/No/N.A. *Yes/No/N.A.
control equipment and any separate enclosure of
equipment used for transmission of alarm signals to
an alarm receiving centre;
(j) removal from its circuit of a fire alarm device that is *Yes/No/N.A. *Yes/No/N.A.
designed to be detachable.
(a) failure of the main power supply to any part of the *Yes/No/N.A. *Yes/No/N.A.
system (within 30 min. of occurrence);
(b) failure of the standby power supply (within 15 min. *Yes/No/N.A. *Yes/No/N.A.
of occurrence);
(c) failure of the battery charger (within 30 min. of *Yes/No/N.A. *Yes/No/N.A.
occurrence);
Tested / Checked by : Signature - Post :
(Name of FS Contractor’s Representative)
Tel. No. :
( ) Date :
Witnessed by: Signature - Post :
(Name(s) of *PBSE/PBSI)
Tel. No. :
( ) Date :
Annex II FS_TCP
Page 62 of 222 2017 Edition
Annex II
3.3.4.6.1 For occupied premises, the standby battery is sufficient *Yes/No/N.A. *Yes/No/N.A.
to maintain the system in operation for at least 24 hours,
plus at least 30 min. for operating in the maximum
“alarm” condition and capable of actuating the fire
service installation as required.
3.3.4.6.3 In buildings with standby generator that serves the fire *Yes/No/N.A. *Yes/No/N.A.
alarm system for 6 hours standby capacity, the capacity
of the standby battery is sufficient to maintain the system
in operation for at least (24 – 6) = 18 hours, plus at least
30 min. for operating in the maximum “alarm” condition
and capable of actuating the fire service installation as
required.
3.3.4.6.5 Each of the normal supply and the standby supply is *Yes/No/N.A. *Yes/No/N.A.
capable of supplying the maximum alarm load of the
system under all conditions.
Annex II FS_TCP
Page 63 of 222 2017 Edition
Annex II
3.3.4.7.1 Insulation test of all installed cables and wiring is made *Yes/No/N.A. *Yes/No/N.A.
at 500 V DC and all insulation resistance between
conductors, between each conductor and earth, and
between each conductor and any screen are ≧ 2 MΩ.
3.3.4.7.2 Earth continuity and earth-loop impedance is tested and *Yes/No/N.A. *Yes/No/N.A.
the results are in compliance with the EECoP.
3.3.4.7.3 Any other tests specified by the manufacturer of the *Yes/No/N.A. *Yes/No/N.A.
system and their test results are in order.
(Details of tests: )
3.3.5 Documentation
Annex II FS_TCP
Page 64 of 222 2017 Edition
Annex II
3.3.5.7 Letter certifying the completion of the DTL to the *Yes/No/N.A. *Yes/No/N.A.
FSCC/authorised service provider is provided.
3.3.5.10 As-fitted fire service installation drawings including the *Yes/No/N.A. *Yes/No/N.A.
followings are provided :
Annex II FS_TCP
Page 65 of 222 2017 Edition
Annex II
3.3.6.2 Hardware and software licensing agreements and any *Yes/No/N.A. *Yes/No/N.A.
future software upgrading for the tools, kits and
devices/instruments required for the addressable system
are wholly handed over, together with other spares and
tools required for the whole fire services installation.
(Note: Detailed T&C procedure for fire alarm control system and fire alarm control panels (G.S. Section
B8) shall be submitted by the FS Contractor and approved by the Supervising Officer prior to testing and
commissioning)
Annex II FS_TCP
Page 66 of 222 2017 Edition
Annex II
Location/Room :
Type of Gas : *CO2 / FM200 / NAFS III / Novec 1230 and other approved agents
_________________
Type of System:
Modular ( ) Cylinder ( )
Pre-engineered ( ) Engineered ( )
3.4.1.1 General
Annex II FS_TCP
Page 67 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 68 of 222 2017 Edition
Annex II
e) Does the above mentioned indication means account for *Yes/No/N.A. *Yes/No/N.A.
variation of cylinder pressure with temperature?
h) Are nozzles provided with markings showing make, type *Yes/No/N.A. *Yes/No/N.A.
and orifice size?
3.4.1.3 Pipings
b) Are all sections of the piping provided with equipotential *Yes/No/N.A. *Yes/No/N.A.
earth bonding?
Annex II FS_TCP
Page 69 of 222 2017 Edition
Annex II
ASTM A106
JIS 3454
or as approved or as approved
Annex II FS_TCP
Page 70 of 222 2017 Edition
Annex II
3.4.1.5 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?
e) Are bar code labels provided to the gas cylinder? *Yes/No/N.A. *Yes/No/N.A.
3.4.2.1 General
a) Is the computer programme for the design of the system *Yes/No/N.A. *Yes/No/N.A.
approved by FSD?
(iii) At the end of test, pressure drop not more than 1 *Yes/No/N.A. *Yes/No/N.A.
bar
Annex II FS_TCP
Page 71 of 222 2017 Edition
Annex II
g) Does the manual control require a force of not more than *Yes/No/N.A. *Yes/No/N.A.
178 Newtons to secure operation?
Annex II FS_TCP
Page 72 of 222 2017 Edition
Annex II
d) Does agent fully discharge within the time limit *Yes/No/N.A. *Yes/No/N.A.
specified by FSD?
3.5.1 General
a) Is the system:
Annex II FS_TCP
Page 73 of 222 2017 Edition
Annex II
d) Is the size of underground control valve pit cover not *Yes/No/N.A. *Yes/No/N.A.
greater than 300 mm x 300 mm and with “FH” marking
engraved on the surface?
(Remarks: isolation valve pit cover shall conform to
WSD standards)
e) Is the valve pit of control valve located between 1.5 m to *Yes/No/N.A. *Yes/No/N.A.
3 m from the street hydrant?
f) Is the valve pit of control valve located outside the *Yes/No/N.A. *Yes/No/N.A.
designated emergency vehicular access?
i) Are underground water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?
Annex II FS_TCP
Page 74 of 222 2017 Edition
Annex II
q) Are adequate clearances provided around the hydrant for *Yes/No/N.A. *Yes/No/N.A.
its free use?
r) Are hydrants sited 6 metres or greater from the building? *Yes/No/N.A. *Yes/No/N.A.
t) Is hydrant number painted with size not less than 75mm *Yes/No/N.A *Yes/No/N.A
at the hydrant (yellow for red hydrant and red for yellow
hydrant)?
Pump
Duty Standby
Location
Quantity (No(s).)
Pump
Manufacturer
Motor
Pump
Model No.
Motor
Pump
Serial No.
Motor
Motor power (kW)
Pump power (kW)
Flow rate (l/min)
Pressure (kPa)
Starting method
Tested / Checked by : Signature - Post :
(Name of FS Contractor’s Representative)
Tel. No. :
( ) Date :
Witnessed by: Signature - Post :
(Name(s) of *PBSE/PBSI)
Tel. No. :
( ) Date :
Annex II FS_TCP
Page 75 of 222 2017 Edition
Annex II
b) Are duplicate pumps provided for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.
d) Are starting instructions for diesel engine driven pump *Yes/No/N.A. *Yes/No/N.A.
prominently displayed in the pump room?
f) Are pump motors rated at 20% higher than the required *Yes/No/N.A. *Yes/No/N.A.
hydraulic power?
i) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the supply tank tally with the vertical
plumbing diagram approved by W.S.D.?
j) Are the effective water capacities of all the water tanks *Yes/No/N.A. *Yes/No/N.A.
correct?
k) Are the water tank and its capacity clearly marked in *Yes/No/N.A. *Yes/No/N.A.
English and Chinese characters?
l) Has the Fire Service Completion Advice been issued by *Yes/No/N.A. *Yes/No/N.A.
WSD?
m) For system where the tank bottom is > 20 m above the *Yes/No/N.A. *Yes/No/N.A.
centre line of the outlet coupling of the lowest street
hydrant in the system, is a bypass pipe (of the same size
as the pump suction pipe) provided connecting the pump
suction and discharge pipe with isolation valves and
check valve?
n) Are the ball valves of the water tanks readily accessible? *Yes/No/N.A. *Yes/No/N.A.
Annex II FS_TCP
Page 76 of 222 2017 Edition
Annex II
o) Do the sizes of the pump suction water pipe from the *Yes/No/N.A. *Yes/No/N.A.
tank match the size of the pump suction inlet?
r) Are puddle flanges of the same sizes as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?
cc) Are pump rooms/enclosures laid clear of any exit or *Yes/No/N.A. *Yes/No/N.A.
normal communication routes through the premises?
Annex II FS_TCP
Page 77 of 222 2017 Edition
Annex II
3.5.2.3 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.1)?
b) Are all the hydrant bodies painted in red colour for fresh *Yes/No/N.A. *Yes/No/N.A.
water system and in yellow colour for sea water system
(with white colour band when fed directly from
Government trunk main)?
c) For hydrants not in service, are all the caps for 100 mm *Yes/No/N.A. *Yes/No/N.A.
outlets painted in blue colour?
e) Is the number assigned for the hydrant painted on the *Yes/No/N.A. *Yes/No/N.A.
body facing the roadway with size not less than 75 mm
(in yellow colour for red coloured hydrant and in red
colour for yellow coloured hydrant)?
3.5.3.1 Pipeworks
c) Do the gate valves, stop valves and globe valves function *Yes/No/N.A. *Yes/No/N.A.
properly?
Annex II FS_TCP
Page 78 of 222 2017 Edition
Annex II
b) Can the pump start automatically upon opening of any *Yes/No/N.A. *Yes/No/N.A.
hydrant outlet?
d) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current? (Test records on Part 4.5 Table 2)
f) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?
g) Are the status of each pump i.e. “Power Supply On”, *Yes/No/N.A. *Yes/No/N.A.
“Pump Running” and “Pump Failed” monitored and
displayed on the pump control panel located inside the
pump room?
j) Do the float switches in the water tanks for controlling *Yes/No/N.A. *Yes/No/N.A.
the water pumps function properly?
k) Do the high and low water level alarms and indications *Yes/No/N.A. *Yes/No/N.A.
for the water tanks function properly?
Annex II FS_TCP
Page 79 of 222 2017 Edition
Annex II
s) For diesel engine driven pump, is the operation of the *Yes/No/N.A. *Yes/No/N.A.
pump starting pressure switch not affected by the main
power supply failure?
b) Is equipment arrangement for flow rate and pressure test *Yes/No/N.A. *Yes/No/N.A.
in accordance with Figure * A / B of Annex II of FSD
Circular Letter No. 1/2015?(* delete where appropriate)
c) Do the flow capacity and pressure tests satisfy FSD's *Yes/No/N.A. *Yes/No/N.A.
requirements as the following Table? (Test Records on
Part 4.5 Table 3)
Annex II FS_TCP
Page 80 of 222 2017 Edition
Annex II
c) Does the water tank have capacity for operation of the *Yes/No/N.A. *Yes/No/N.A.
drencher system for 30 minutes minimum?
d) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the drencher tank tally with the vertical
plumbing diagram approved by W.S.D.?
f) Are the ball valves of the water tank readily *Yes/No/N.A. *Yes/No/N.A.
accessible?
j) Are puddle flanges of the same size as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?
Annex II FS_TCP
Page 81 of 222 2017 Edition
Annex II
b) Has the design of the deluge installation been consulted *Yes/No/N.A. *Yes/No/N.A.
with and accepted by FSD?
c) Is the deluge valve set installed close to the inlet of the *Yes/No/N.A. *Yes/No/N.A.
drencher system?
f) Does each deluge valve control have less than 72 *Yes/No/N.A. *Yes/No/N.A.
drenchers?
3.6.1.4 Pipeworks
Annex II FS_TCP
Page 82 of 222 2017 Edition
Annex II
b) Are water pipes larger than 150 mm dia. to BS EN 545 *Yes/No/N.A. *Yes/No/N.A.
Class K12 or other approved type?
d) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?
f) Are water pipes of dia. larger than 65 mm and up to 150 *Yes/No/N.A. *Yes/No/N.A.
mm provided with mechanical pipe couplings?
g) Are water pipes of dia. larger than 150 mm provided *Yes/No/N.A. *Yes/No/N.A.
with flanged joints and flanged fittings?
h) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?
k) Are bends of water pipes larger than 65 mm dia. and *Yes/No/N.A. *Yes/No/N.A.
bends of water pipes installed outside false
ceiling/concealed void of long radius type, or as
approved?
l) Are galvanised mild steel sleeves provided for pipes *Yes/No/N.A. *Yes/No/N.A.
through wall or slab?
m) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
wall or slab filled with approved fire proof material and
sealant?
n) Are fire rated pipe sleeves provided for pipes through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab?
o) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab filled with approved fire proof
material and sealant?
Annex II FS_TCP
Page 83 of 222 2017 Edition
Annex II
q) Are sleeves projected at least 100 mm above finish floor *Yes/No/N.A. *Yes/No/N.A.
level and at least 150 mm above roof finish
t) Are pipe hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?
v) Are adequate air vents and drain cocks provided? *Yes/No/N.A. *Yes/No/N.A.
aa) Are the water pipes suitably sloped and drained to the *Yes/No/N.A. *Yes/No/N.A.
installation drain valve as far as practical?
ab) Are installation drain pipes and valves of correct sizes? *Yes/No/N.A. *Yes/No/N.A.
ac) Are correct sizes of drain pipes and valves provided as *Yes/No/N.A. *Yes/No/N.A.
following for pipeworks to be drained?
ae) Are isolating cocks/valves provided for pressure gauges? *Yes/No/N.A. *Yes/No/N.A.
ag) Are main stop valves secured at OPEN position with *Yes/No/N.A. *Yes/No/N.A.
security devices including chains, padlocks, tamper-
proof serially numbered security tags, and durable
warning labels to prevent tampering/unauthorised
operation, and with a log book to keep track of
maintenance services and operation, of the valves?
Tested / Checked by : Signature - Post :
(Name of FS Contractor’s Representative)
Tel. No. :
( ) Date :
Witnessed by: Signature - Post :
(Name(s) of *PBSE/PBSI)
Tel. No. :
( ) Date :
Annex II FS_TCP
Page 84 of 222 2017 Edition
Annex II
ah) Are main stop valves placed at proximity to an entrance *Yes/No/N.A. *Yes/No/N.A.
to the premises?
ai) Are location plates for main stop valves provided with *Yes/No/N.A. *Yes/No/N.A.
correct wording and character sizes?
aj) Are each set of alarm valve and alarm gong provided *Yes/No/N.A. *Yes/No/N.A.
with identification label and number?
ak) Is the total length of water pipe between alarm valve and *Yes/No/N.A. *Yes/No/N.A.
alarm gong 25 m or less?
al) Is the water pipe between alarm valve and alarm gong of *Yes/No/N.A. *Yes/No/N.A.
correct size?
am) Is a deluge valve installed closed to the inlet for the *Yes/No/N.A. *Yes/No/N.A.
drencher system?
an) Are manually operating devices complete with operating *Yes/No/N.A. *Yes/No/N.A.
instruction displayed nearby and provided on refuge
floor?
ap) Are equipotential earth bondings provided for the *Yes/No/N.A. *Yes/No/N.A.
pipeworks?
a) Are the motor/pump set rotating parts protected by safety *Yes/No/N.A. *Yes/No/N.A.
guard?
b) Is pump motor power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power?
Annex II FS_TCP
Page 85 of 222 2017 Edition
Annex II
i) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?
k) Are the pumps installed with the manually operated shut *Yes/No/N.A. *Yes/No/N.A.
down mechanism labelled as “DRENCHER PUMP
SHUT DOWN” 終止水濂泵運行?
o) Can the pump just be started by switching off at the *Yes/No/N.A. *Yes/No/N.A
pump control not installed near the pump, rather than by
any automatic means?
p) Are manual fire alarm call points wired for starting the *Yes/No/N.A. *Yes/No/N.A.
pump?
q) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.
r) Are the fire pump starters wired through a selector *Yes/No/N.A. *Yes/No/N.A.
switch for duty and standby pump selection?
u) Are the status of each fire pump comprising “Power *Yes/No/N.A. *Yes/No/N.A.
Supply On”, “Pump Running” and “Pump Failed”
monitored and displayed at the pump control panel in the
pump room?
Annex II FS_TCP
Page 86 of 222 2017 Edition
Annex II
v) Are such signal repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?
y) Are start/stop push buttons with pump running indication *Yes/No/N.A. *Yes/No/N.A.
light and buzzer provided adjacent to the fire service
inlet?
3.6.1.6 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.1)?
g) Is the water flow rate maintained at not less than 10 litres *Yes/No/N.A. *Yes/No/N.A.
per minute per square metre of the external wall
openings?
h) Does the water mist system comply with NFPA *Yes/No/N.A. *Yes/No/N.A.
750:2006 and its design and construction acceptable to
the FSD and the Supervising Officer?
i) Does the Water Spray fixed system comply with NPFA *Yes/No/N.A. *Yes/No/N.A.
15:2007 and its design and construction acceptable to the
FSD and the Supervising Officer?
j) Do the Foam-Water Sprinkler and Foam-Water Spray *Yes/No/N.A. *Yes/No/N.A.
systems comply with NFPA 16:2007 and their design
and construction acceptable to the FSD and the
Supervising Officer?
Annex II FS_TCP
Page 87 of 222 2017 Edition
Annex II
3.6.2.1 Pipeworks
d) Do the gate valves, stop valves and globe valves function *Yes/No/N.A. *Yes/No/N.A.
properly?
a) Do the pumps and motors run at the designed discharge *Yes/No/N.A. *Yes/No/N.A.
water pressure and operating electrical current?
Annex II FS_TCP
Page 88 of 222 2017 Edition
Annex II
c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?
e) Do the float switches in the water tanks controlling the *Yes/No/N.A. *Yes/No/N.A.
water pumps function properly?
k) Do the pressure switches controlling the jockey, duty and *Yes/No/N.A. *Yes/No/N.A.
standby pumps operate properly?
l) Are the pumps fully operational within 30 sec. after *Yes/No/N.A. *Yes/No/N.A.
starting?
m) Are pumps status; “Power supply on”, Pump running” *Yes/No/N.A. *Yes/No/N.A.
and “Pump failed” monitored and displayed at the pump
control panel and repeated at the main fire service
control panel or at a status panel at the main entrance of
the building?
a) Do the installation pressure and flow rate comply with *Yes/No/N.A. *Yes/No/N.A.
the FSD requirements?
b) Is the water flow from each nozzle the same and with a *Yes/No/N.A. *Yes/No/N.A.
similarly uniform flow pattern?
Annex II FS_TCP
Page 89 of 222 2017 Edition
Annex II
c) Is the water flow rate maintained at not less than 10 *Yes/No/N.A. *Yes/No/N.A.
L/min per m2 of external wall opening and allowing for
wastage and uneven flow (15% additional capacity)?
d) Is the hydraulic pressure at either end along any water *Yes/No/N.A. *Yes/No/N.A.
pipes identical?
3.7.1.1 General
a) Does the layout of flashing light points and loudspeakers *Yes/No/N.A. *Yes/No/N.A.
tally with the latest approved building plans?
b) Are the flashing lights and loudspeakers provided for all *Yes/No/N.A. *Yes/No/N.A.
areas that required the system?
b) Are the high level flashing lights with directional signs *Yes/No/N.A. *Yes/No/N.A.
positioned with base between 2 m and 2,5 m above
finished floor level?
c) Are the low directional signs installed with lower edge *Yes/No/N.A. *Yes/No/N.A.
not higher than 200 mm from finished floor level?
Annex II FS_TCP
Page 90 of 222 2017 Edition
Annex II
h) Is the colour of the lens/lamps of the flashing lights meet *Yes/No/N.A. *Yes/No/N.A.
FSD requirements?
i) Does the visual system comply with the FSDCoP, BS *Yes/No/N.A. *Yes/No/N.A.
5499 and BS EN 60598?
k) Are the lamp elements positioned to produce the best *Yes/No/N.A. *Yes/No/N.A.
illumination effect for the sign?
l) Is a flashing light control gear integrated with each sign? *Yes/No/N.A. *Yes/No/N.A.
n) Are the lamp elements in the “ON” condition in normal *Yes/No/N.A. *Yes/No/N.A.
situation?
a) Desktop Microphone
b) Amplifier/Preamplifier
Annex II FS_TCP
Page 91 of 222 2017 Edition
Annex II
(iv) Are the amplifiers provided with at least 10% *Yes/No/N.A. *Yes/No/N.A.
spare capacity/power to drive all the speakers
within the broadcasting zone?
(vi) Does the amplifier have an audio response level *Yes/No/N.A. *Yes/No/N.A.
within +2 dB from 50 Hz to 14 kHz at full output,
and the total harmonic distortion not exceed 1%
at full load?
(ix) Does amplifier have a low hum level and low *Yes/No/N.A. *Yes/No/N.A.
over-shoot or ringing when a square wave
generator is connected to the input level within
the working range and variable tone control
providing attenuation of the high frequencies, i.e.
0 – 20 dB at 8 kHz?
(xii) Are the signal incoming leads terminate at the *Yes/No/N.A. *Yes/No/N.A.
rear of the amplifier through suitable screened
type plug mountings?
(xiv) Are input sockets and output terminals well *Yes/No/N.A. *Yes/No/N.A.
separated and in separate cut-outs in order to
prevent coupling between the amplifier input and
output?
Tested / Checked by : Signature - Post :
(Name of FS Contractor’s Representative)
Tel. No. :
( ) Date :
Witnessed by: Signature - Post :
(Name(s) of *PBSE/PBSI)
Tel. No. :
( ) Date :
Annex II FS_TCP
Page 92 of 222 2017 Edition
Annex II
(xvii) Is the power amplifier completed with mixer, for *Yes/No/N.A. *Yes/No/N.A.
single broadcasting zone?
(xix) Does each power amplifier have built in with *Yes/No/N.A. *Yes/No/N.A.
On/Off switch, headphone outlet, volume control
for each channel and matching transformers with
tapping to enable loudspeakers to be driven at
100V, 70V or 50V up to 8Ω?
(xxi) Is the power output adequate for the connected *Yes/No/N.A. *Yes/No/N.A.
loudspeakers in the broadcasting zone?
(xxv) Is the power output adequate for the number of *Yes/No/N.A. *Yes/No/N.A.
connected loudspeakers within the zone?
c) Loudspeaker
Annex II FS_TCP
Page 93 of 222 2017 Edition
Annex II
(ii) Are they constructed of sheet steel or high impact *Yes/No/N.A. *Yes/No/N.A.
ABS plastic in white colour or as specified
matching the false ceiling or wall finishes?
(v) Is the attenuator integral with the speaker unit *Yes/No/N.A. *Yes/No/N.A.
and comprise carbon type volume controls with
adjustment?
d) Cassette Deck
(i) Does cassette deck have two individual cassette *Yes/No/N.A. *Yes/No/N.A.
players with standard interlocking set of play,
stop, pause, fast forward and fast reverse buttons
and auto-reverse playback feature?
(ii) Does it have a playing tape speed of 4.75 cm/s *Yes/No/N.A. *Yes/No/N.A.
and an nominal output signal of 1 V, and a signal
to noise ratio better than 40 dB?
(iii) Has the recorded message been submitted to the *Yes/No/N.A. *Yes/No/N.A.
Supervising Officer for approval?
Annex II FS_TCP
Page 94 of 222 2017 Edition
Annex II
d) Are all cables running continuously from the originating *Yes/No/N.A. *Yes/No/N.A.
point to termination, with no joint or connector?
g) Are components include the following items and any *Yes/No/N.A. *Yes/No/N.A.
other items necessary for the proper control and
operation of the system to the satisfaction of the Fire
Services Department?
Annex II FS_TCP
Page 95 of 222 2017 Edition
Annex II
h) Does the microphone control panel contain dual pre- *Yes/No/N.A. *Yes/No/N.A.
amplifiers continuously supervised?
i) Can the microphone control panel transfer to the standby *Yes/No/N.A. *Yes/No/N.A.
pre-amplifier upon failure of the duty unit?
l) Does the speaker zone selector switchbank control the *Yes/No/N.A. *Yes/No/N.A.
audio dispersion throughout the protected premises?
m) Does each switch permit the transfer of its zone of *Yes/No/N.A. *Yes/No/N.A.
speakers into either all call, page and fire operation
modes?
q) Will the system cause any interference with all electrical *Yes/No/N.A. *Yes/No/N.A.
or electronic system, the telephone system, radio paging
system, audible paging and other communication system
and vice versa, whether they are in operation or not?
Annex II FS_TCP
Page 96 of 222 2017 Edition
Annex II
w) Are the metal enclosures secured and have sufficient *Yes/No/N.A. *Yes/No/N.A.
space for cable routing and bending?
aa) Is the battery charger provided with voltmeter and *Yes/No/N.A. *Yes/No/N.A.
charging ammeter?
3.7.1.6 Miscellaneous
b) When the fire alarm is activated, will the following *Yes/No/N.A. *Yes/No/N.A.
operations be performed automatically?
Annex II FS_TCP
Page 97 of 222 2017 Edition
Annex II
(ii) The alarm bells and flashing light units within the
alarm zone shall operate. After 10 seconds, the
alarm bells shall stop while the flashing light units
shall continue to flash. Then the pre-recorded
audio alarm messages shall announce within the
alarm zone to alert the occupants and direct them
to evacuate immediately following the directional
and exit signs. The alarm bells and the audio
alarm messages shall repeat in sequence
continuously until the fire alarm has been reset at
the fire alarm panel.
e) Is the message audible in all areas within the specified *Yes/No/N.A. *Yes/No/N.A.
zone of the building including toilets, stores, staircases,
etc.?
f) Is the signal to noise ratio not less than 40 dB when the *Yes/No/N.A. *Yes/No/N.A.
loudspeaker output level in the area concerned is not less
than 20 dB above the background noise level normally
expected in the respective area during fire conditions?
g) Is the variation in sound power level between the outlet *Yes/No/N.A. *Yes/No/N.A.
nearest to and farthest from the amplifier not exceed 3
dB ?
Annex II FS_TCP
Page 98 of 222 2017 Edition
Annex II
b) Are the power supply cables of the audio/visual advisory *Yes/No/N.A. *Yes/No/N.A.
system fire resisting cables conform to BS 6387 Cat
AWX or SWX or BS 6207 or BS EN 60702 and Clause
B9.9 of the General Specification?
d) Is the wiring so arranged that any damage to the wiring *Yes/No/N.A. *Yes/No/N.A.
for any one loudspeaker or directional sign will not
affect the proper operation of other loudspeakers or
directional signs?
b) Are all mounting fixtures provided and fixed in place? *Yes/No/N.A. *Yes/No/N.A.
Annex II FS_TCP
Page 99 of 222 2017 Edition
Annex II
g) Are all fire extinguishers and fixed sprayer unit provided *Yes/No/N.A. *Yes/No/N.A.
with certificates signed by a registered class 3 fire
service contractor? (Certificates shall be enclosed)
k) Are cabinets for housing the fire extinguishers at outdoor *Yes/No/N.A. *Yes/No/N.A.
robust and weather-proof with easily identifiable labels/
wordings fixed or engraved on them?
a) Are the remote monitoring units for fire extinguishers *Yes/No/N.A. *Yes/No/N.A.
fixed in appropriate locations in full accordance with
manufacturer’s recommendations?
b) Are the local audio alarms for theft control, condition *Yes/No/N.A. *Yes/No/N.A.
control, battery replacement alert and faulty operation of
the remote monitoring unit functioning properly?
e) Is the remote alarm panel functioning properly as per the *Yes/No/N.A. *Yes/No/N.A.
requirements of Section B10.5 of the G.S.?
Annex II FS_TCP
Page 100 of 222 2017 Edition
Annex II
Use: On electrical fires, flammable liquids, delicate equipment, important documents, or fires in
confined spaces.
Maintenance: This type of extinguisher shall be examined every 12 months and the following
maintenance carried out :-
(i) The total weight shall be checked against that recorded when the extinguisher was put into service.
If a loss of weight of more than 10 per cent is detected, the extinguisher shall be discharged and
returned to the suppliers for examination, test and recharging.
(ii) The body of the extinguisher shall be examined and, if there are signs of damage or extensive
external corrosion, the extinguisher shall be discharged and returned to suppliers for examination,
test and recharging.
(iii) The discharge horn and hose shall be checked to see that it moves freely and shall be replaced if
damaged is detected.
(iv) Hydraulic pressure test shall be carried out every five years on the cylinder in accordance with the
manufacturers' instructions. Extreme care shall be exercised when preparing and conducting the
test.
Maintenance: This type of extinguisher shall be examined every 12 months and the following
maintenance carried out :-
(GAS-CARTRIDGE TYPE)
(i) The vent holes in the cap shall be checked for cleanliness and free from obstruction.
(ii) Remove the headcap to check the liquid level. The liquid shall be topped up as necessary.
(iii) The nozzle, strainer and internal discharge tube shall be checked for cleanliness and free from
obstruction. Defective items shall be replaced.
(iv) The gas cartridge shall be weighed and the weight checked against that marked on the cartridge.
The cartridge shall be renewed if a loss of more than 10 per cent of the contents is recorded.
Annex II FS_TCP
Page 101 of 222 2017 Edition
Annex II
(v) No corrosion, damage or rust shall be visible either externally or internally. Special attention shall
be paid to the concealed parts of the container.
(vi) Before the headcap is replaced and while the gas cartridge is unscrewed therefrom, the plunger or
other operating device shall be checked to see that it operates freely. The washer shall be examined
and replaced if necessary. The cap shall then be tightly screwed to the container to form a gas-tight
joint.
(vii) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all cartridges in the
remainder shall be replaced. Extreme care shall be exercised during preparing and conducting
discharge test. Prior to discharging, the container shall be ensured in good condition such as no
corrosion, damage or rust shall be visible externally or internally on any part of the container;
otherwise hydraulic pressure test shall then be carried out to confirm the container structurally
sound. Should there be doubt about the condition of the container, hydraulic pressure test shall be
conducted instead.
(viii) Corroded parts shall be cleaned up and refinished after the hydraulic pressure test.
(ix) Hydraulic pressure test shall be carried out every five years on the container in accordance with the
manufacturers' instructions. Extreme care shall be exercised when preparing and conducting the
test.
(x) Before carrying out hydraulic pressure test, remove the headcap, disconnect the gas cartridge and
clear the contents. Never empty the contents by discharging the extinguisher.
(xi) Also, before disposal of unserviceable fire extinguisher, remove the headcap, disconnect the gas
cartridge and clear the contents. Never empty the contents by discharging the extinguisher.
(STORED-PRESSURE TYPE)
(i) The pressure indicating device shall be checked to see the correct pressure is being maintained
within the extinguisher body.
(ii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap shall be checked for
cleanliness and free from obstruction. Defective items shall be replaced.
(iii) No corrosion, damage or rust shall be visible externally on any part of the container. Special
attention shall be paid to the concealed parts of the container.
(iv) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all extinguishers shall
be overhauled and recharged.
(v) Prior to recharging, the container shall be ensured in good condition such as no corrosion, damage
or rust was noted; otherwise hydraulic pressure test shall be conducted to confirm the container
structurally sound.
(vi) Hydraulic pressure test shall be carried out every five years on the container in accordance with the
manufacturers’ instructions. Extreme care shall be exercised when preparing and conducting the
test.
Annex II FS_TCP
Page 102 of 222 2017 Edition
Annex II
Maintenance: This type of extinguisher shall be examined every 12 months and the following maintenance
carried out :-
(GAS-CARTRIDGE TYPE)
(i) The vent holes in the cap shall be checked for cleanliness and free from obstruction.
(ii) The extinguisher shall be weighed to check that it contains the correct weight of powder. The
weight when fully charged shall be recorded at the time of charging. If the weight is found to have
dropped by more than 10 per cent, the dry powder shall be replaced by a fresh charge. Care shall be
taken not to mix different types of dry powder because they could react with one another.
(iv) Remove the headcap to check the condition of powder. The chemical shall be renewed if it is not in
good condition.
(v) The nozzle and discharge control (if fitted) shall be checked for cleanliness and free from
obstruction. Defective items shall be replaced.
(vi) The gas cartridge shall be weighed and the weight checked against that marked on the cartridge.
The cartridge shall be renewed if a loss of more than 10 per cent of the contents is recorded.
(vii) No corrosion, damage or rust shall be visible either externally or internally. Special attention shall
be paid to the concealed parts of the container.
(viii) Before the headcap is replaced and while the gas cartridge is unscrewed therefrom, the plunger or
other operating device shall be checked to see that it operates freely. The washer shall be examined
and replaced if necessary. The cap shall then be tightly screwed to the container to form a gas-tight
joint.
(ix) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all cartridges in the
remainder shall be replaced. Extreme care shall be exercised during preparing and conducting
discharge test. Prior to discharging, the container shall be ensured in good condition such as no
corrosion, damage or rust shall be visible externally or internally on any part of the container;
otherwise hydraulic pressure test shall then be carried out to confirm the container structurally
sound. Should there be doubt about the condition of the container, hydraulic pressure test shall be
conducted instead.
(x) Corroded parts shall be cleaned up and refinished after the hydraulic pressure test.
(xi) Hydraulic pressure test shall be carried out every five years on the container in accordance with the
manufacturers' instructions. Extreme care shall be exercised when preparing and conducting the
test.
(xii) Before carrying out hydraulic pressure test, remove the headcap, disconnect the gas cartridge and
the dry powder shall be collected for subsequent re-cycling/disposal. Never empty the contents by
discharging the extinguisher.
Annex II FS_TCP
Page 103 of 222 2017 Edition
Annex II
(xiii) Also, before disposal of unserviceable fire extinguisher, remove the headcap, disconnect the gas
cartridge and the dry powder shall be collected for subsequent re-cycling/disposal. Never empty
the contents by discharging the extinguisher.
(STORED-PRESSURE TYPE)
(i) The extinguisher shall be weighed to check it contains the correct weight of powder. If the weight
is found to have dropped by more than 10 per cent, the dry powder shall be replaced by a fresh
charge. Care shall be taken not to mix different types of dry powder because they could react with
one another.
(ii) The pressure indicating device shall be checked to see the correct pressure is being maintained
within the extinguisher body.
(iii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap shall be checked for
cleanliness and free from obstruction. Defective items shall be replaced.
(iv) No corrosion, damage or rust shall be visible externally on any part of the container. Special
attention shall be paid to the concealed parts of the container.
(v) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. The dry powder shall be discharged to an enclosure for
collection and subsequent re-cycling/disposal. Should any extinguisher fail in the test, all
extinguishers shall be overhauled and recharged.
(vi) Prior to recharging, the container shall be ensured in good condition such as no corrosion, damage
or rust was noted; otherwise hydraulic pressure test shall be conducted to confirm the container
structurally sound.
(vii) Hydraulic pressure test shall be carried out every five years on the container in accordance with the
manufacturers' instructions. Extreme care shall be exercised when preparing and conducting the
test.
(viii) Unserviceable extinguisher shall be discharged prior to disposal. The dry powder shall be
discharged to an enclosure for collection and subsequent re-cycling/disposal.
Notes:
(a) Dry powder extinguishers must be thoroughly dry internally before they are recharged.
(b) Advice shall be obtained from the Fire Services Department as to the possible reaction between the
powder or expellent and the material to protected.
Annex II FS_TCP
Page 104 of 222 2017 Edition
Annex II
Maintenance: This type of extinguisher shall be examined every 12 months and the following
maintenance carried out :-
(PORTABLE TYPE)
(i) The pressure indicating device shall be checked to see the correct pressure is being maintained
within the extinguisher body.
(ii) The extinguisher shall be weighed to check against the total weight record when it is put into
service. If a loss of weight of more than 10 per cent is detected, the extinguisher shall be
discharged to a closed recycling system and returned to the supplier for examination, test and
recharging.
(iii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap shall be checked for
cleanliness and free from obstruction. Defective items shall be replaced.
(iv) No corrosion, damage or rust shall be visible externally on any part of the container. Special
attention shall be paid to the concealed parts of the container.
(v) If there are signs of damage or external corrosion, the extinguisher shall be discharged to a closed
recycling system and returned to the suppliers for examination, test and recharging.
(vi) Hydraulic pressure test shall be carried out every five years on the container in accordance with the
manufacturers' instructions. Extreme care shall be exercised when preparing and conducting the
test.
(vii) Unserviceable extinguisher shall be discharged to a closed recycling system prior to disposal.
(ii) The extinguisher shall be weighed to check against the total weight record when it is put into
service. If a loss of weight of more than 10 per cent is detected, the extinguisher shall be
discharged to a closed recycling system and returned to the supplier for examination, test and
recharging.
(iii) The deflector and the sensing element shall be checked and cleaned.
(iv) No corrosion, damage or rust shall be visible externally on any part of the container. Special
attention shall be paid to the concealed parts of the container.
(v) If there are signs of damage or external corrosion, the extinguisher shall be discharged to a closed
recycling system and returned to the suppliers for examination, test and recharging.
(vi) Hydraulic pressure test shall be carried out every five years on the container in accordance with the
manufacturers' instructions. Extreme care shall be exercised when preparing and conducting the
test.
(vii) Unserviceable extinguisher shall be discharged to a closed recycling system prior to disposal.
Annex II FS_TCP
Page 105 of 222 2017 Edition
Annex II
Maintenance: This type of extinguisher shall be examined every 12 months and the following
maintenance carried out :-
(i) The nozzle and the vent holes in the cap shall be checked for cleanliness and free from obstruction.
(ii) Remove the headcap to check the liquid levels in the body and in the inner container. Any slight
loss may be made up with water; otherwise a new charge shall be used.
(iii) No corrosion, damage or rust shall be visible either externally or internally. Special attention shall
be paid to the concealed parts of the container.
(iv) Before the headcap is replaced, the plunger, the headcap lever for the sealing device or other
operating device shall be checked to see that it operates freely. The washer shall be replaced if
necessary and the cap shall then be tightly screwed to the container to form a gas-tight joint.
(v) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all shall be tested by
discharge. Extreme care shall be exercised during preparing and conducting discharge test. Prior to
discharging, the container shall be ensured in good condition such as no corrosion, damage or rust
shall be visible externally or internally on any part of the container; otherwise hydraulic pressure
test shall then be carried out to confirm the container structurally sound. Should there be doubt in
the condition of the container, hydraulic pressure test shall be conducted instead.
(vi) Corroded parts shall be cleaned up and refinished after the hydraulic pressure test.
(vii) Hydraulic pressure test shall be carried out every five years on the outer container in accordance
with the manufacturers' instructions; the inner container shall be examined to ensure it is in good
condition and not leaking. Extreme care shall be exercised when preparing and conducting the test.
(viii) Before carrying out hydraulic pressure test, remove the headcap and clear the contents. Never
empty the contents by discharging the extinguisher.
(ix) Also, before disposal of unserviceable extinguisher, remove the headcap and clear the contents.
Never empty the contents by discharging the extinguisher.
Note:
Inverted type chemical foam extinguishers have ceased production and not permitted for sale. However,
products already sold may continued to be used.
Maintenance: This type of extinguisher shall be examined every 12 months and the following
maintenance carried out :-
Annex II FS_TCP
Page 106 of 222 2017 Edition
Annex II
(GAS-CARTRIDGE TYPE)
(i) The vent holes in the cap shall be checked for cleanliness and free from obstruction.
(ii) Remove the headcap to check the liquid level. If the liquid level was found to have dropped by
more than 10 per cent, the foam concentrate or foam solution as appropriate shall be replaced by a
fresh charge.
(iii) The branchpipe, strainer and internal discharge tube shall be checked for cleanliness and free from
obstruction. Defective items shall be replaced.
(iv) The gas cartridge shall be weighed and the weight checked against that marked on the cartridge.
The cartridge shall be renewed if a loss of more than 10 per cent of the contents is recorded.
(v) No corrosion, damage or rust shall be visible either externally or internally. Special attention shall
be paid to the concealed parts of the container.
(vi) Before the headcap is replaced and while the gas cartridge is unscrewed therefrom, the plunger or
other operating device shall be checked to see that it operates freely. The washer shall be examined
and replaced if necessary. The cap shall then be tightly screwed to the container to form a gas-tight
joint.
(vii) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all cartridges in the
remainder shall be replaced. Extreme care shall be exercised during preparing and conducting
discharge test. Prior to discharging, the container shall be ensured in good condition such as no
corrosion, damage or rust shall be visible externally or internally on any part of the container;
otherwise hydraulic pressure test shall then be carried out to confirm the container structurally
sound. Should there be doubt about the condition of the container, hydraulic pressure test shall be
conducted instead.
(viii) Corroded parts shall be cleaned up and refinished after the hydraulic pressure test.
(ix) Hydraulic pressure test shall be carried out every five years on the container in accordance with the
manufacturers' instructions. Extreme care shall be exercised when preparing and conducting the
test.
(x) Before carrying out hydraulic pressure test, remove the headcap, disconnect the gas cartridge and
clear the contents. Never empty the contents by discharging the extinguisher.
(xi) Also, before disposal of unserviceable fire extinguisher, remove the headcap, disconnect the gas
cartridge and clear the contents. Never empty the contents by discharging the extinguisher
(STORED-PRESSURE TYPE)
(i) The pressure indicating device shall be checked to see the correct pressure is being maintained
within the extinguisher body.
(ii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap shall be checked for
cleanliness and free from obstruction. Defective items shall be replaced.
(iii) No corrosion, damage or rust shall be visible externally on any part of the container. Special
attention shall be paid to the concealed parts of the container.
Tested / Checked by : Signature - Post :
(Name of FS Contractor’s Representative)
Tel. No. :
( ) Date :
Witnessed by: Signature - Post :
(Name(s) of *PBSE/PBSI)
Tel. No. :
( ) Date :
Annex II FS_TCP
Page 107 of 222 2017 Edition
Annex II
(iv) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher failed in the test, all extinguishers
shall be overhauled and recharged.
(v) Prior to recharging, the container shall be ensured in good condition such as no corrosion, damage
or rust was noted; otherwise hydraulic pressure test shall be conducted to confirm the container
structurally sound.
(vi) Hydraulic pressure test shall be carried out every five years on the container in accordance with the
manufacturers' instructions. Extreme care shall be exercised when preparing and conducting the
test.
Use: On fires involving flammable liquids, such as small fires in the kitchen and laboratory.
Method For Drape the blanket over the flames to seal off air. Switch off heat and leave in position
Use: until cool.
Maintenance: This blanket shall be examined every 12 months or after use in fire. The following
maintenance shall be carried out :-
(iii) If manufacturer’s instructions are not available, fire blanket can be washed (soak overnight in
detergent, gently hand rinse in warm water). Do not machine wash or dry clean.
Remarks:
(i) Fire blankets are classified into two categories, namely:-
"Heavy Duty" fire blankets (BS 7944:1999); and
"Light Duty" fire blankets (BS EN 1869:1997)
(ii) Only "Heavy Duty" and "reusable" fire blankets will be approved as a Fire Services Standard
Requirement.
(iii) "Light Duty" fire blankets may be accepted for use on a private basis and shall be disposed of after
use.
Annex II FS_TCP
Page 108 of 222 2017 Edition
Annex II
3.9.2 Installation
b) Where smoke detectors are provided for the actuation of *Yes/No/N.A. *Yes/No/N.A.
the shutter, are they fitted to both sides of the wall
opening?
e) Are manual controls provided to both sides of the wall *Yes/No/N.A. *Yes/No/N.A.
opening?
Annex II FS_TCP
Page 109 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 110 of 222 2017 Edition
Annex II
3.10.2.1 Has fuel tank room been inspected and approved by FSD *Yes/No/N.A. *Yes/No/N.A.
Regional Office?
(N.B. : Supporting document to be attached)
3.10.2.2 Has surveyor report for fuel tank been obtained as *Yes/No/N.A. *Yes/No/N.A.
required by FSD Dangerous Goods Division?
3.10.2.3 Has DG licence for fuel tank room holding more than *Yes/No/N.A. *Yes/No/N.A.
2,500 litres diesel (or as approved) been obtained?
(N.B. : Supporting document to be attached)
a) Is adequate space (not less than 600 mm) provided all *Yes/No/N.A. *Yes/No/N.A.
round emergency generator for maintenance/cleaning?
b) Are air supply and discharge ductworks (if any) provided *Yes/No/N.A. *Yes/No/N.A.
free from obstruction?
e) Is generator built-in fuel tank not greater than 500 litres? *Yes/No/N.A. *Yes/No/N.A.
i) Is a shut off valve provided on the supply pipe from fuel *Yes/No/N.A. *Yes/No/N.A.
tank to the service tank of generator?
Annex II FS_TCP
Page 111 of 222 2017 Edition
Annex II
k) Are the batteries kept in fully charged condition and is *Yes/No/N.A. *Yes/No/N.A.
the trickle charge operating?
d) Are audible and visual alarms given locally, and at fire *Yes/No/N.A. *Yes/No/N.A.
control main panel when the generator starting sequence
is locked out due to starting failure?
e) After one hour of running test, do all instruments, safety *Yes/No/N.A. *Yes/No/N.A.
devices, etc. indicate “normal” condition?
f) Will the generator set continue to run after a pre- *Yes/No/N.A. *Yes/No/N.A.
determined time recommended by manufacturer unless it
is stopped manually if the normal power supply has
resumed?
Annex II FS_TCP
Page 112 of 222 2017 Edition
Annex II
g) Are all testing carried out with generator room doors *Yes/No/N.A. *Yes/No/N.A.
kept closed?
h) Is warning signal given locally and at fire control main *Yes/No/N.A. *Yes/No/N.A.
panel when manual/auto selector switch turn to manual
position?
(N.B. such provision is strongly recommended)
i) Is remote control valve on supply pipe to the service tank *Yes/No/N.A. *Yes/No/N.A.
in good working order?
j) Are all moving parts effectively and rigidly guarded for *Yes/No/N.A. *Yes/No/N.A.
safety?
l) Is any exhaust leak detected inside generator room while *Yes/No/N.A. *Yes/No/N.A.
the generator is running?
o) Does emergency generator pass the running test at full *Yes/No/N.A. *Yes/No/N.A.
load?
Annex II FS_TCP
Page 113 of 222 2017 Edition
Annex II
a) Does the fireman’s lift serve the floors of the building *Yes/No/N.A. *Yes/No/N.A.
without having to traverse more than two floors by the
fire service personnel?
c) Is separate lift shaft provided for the fireman's lift? *Yes/No/N.A. *Yes/No/N.A.
d) Is the lift car minimum internal dimension of 1.1m, a net *Yes/No/N.A. *Yes/No/N.A.
internal floor area 1.35 m² or greater?
e) Is the rated load of the lift car 680 kg or greater? *Yes/No/N.A. *Yes/No/N.A.
g) Is the opening of the lift car/landing door 800 mm wide *Yes/No/N.A. *Yes/No/N.A.
and 2000 mm high or greater?
h) Are the car and landing door fitted with power operated *Yes/No/N.A. *Yes/No/N.A.
automatic self-closing device?
Annex II FS_TCP
Page 114 of 222 2017 Edition
Annex II
p) Are notices provided outside and inside the building in *Yes/No/N.A. *Yes/No/N.A.
conformity with the Code of Practice for Fire Safety in
Buildings?
a) Does the opening of the safety hatch door inside the lift *Yes/No/N.A. *Yes/No/N.A.
car automatically cut off the electric fan?
b) Does the fireman's switch when operated over-ride all *Yes/No/N.A. *Yes/No/N.A.
registered instructions and return to the designated floor
of entry?
c) Is the fireman's lift capable to travel from the designated *Yes/No/N.A. *Yes/No/N.A.
floor of entry to the topmost floor within 1 minute
calculating from the lift door completely closed to the lift
door started to open? (Actual sec.)
Annex II FS_TCP
Page 115 of 222 2017 Edition
Annex II
c) Are there not less than two emergency luminaires in each *Yes/No/N.A. *Yes/No/N.A.
space?
g) Are self-contained exit signs and centrally supplied exit *Yes/No/N.A. *Yes/No/N.A.
signs provided in accordance with approved drawings?
Annex II FS_TCP
Page 116 of 222 2017 Edition
Annex II
m) Are bar code labels provided to the battery lighting and *Yes/No/N.A. *Yes/No/N.A.
central battery system?
q) Does the exit sign comply with FSD requirements (letter *Yes/No/N.A. *Yes/No/N.A.
sizes and colour)?
r) Is single type of exit sign installed within the same *Yes/No/N.A. *Yes/No/N.A.
development or project?
s) Are exit signs and directional signs installed with LED *Yes/No/N.A. *Yes/No/N.A.
lamps as per the requirements of Section B11.2 of the
G.S.?
t) Are the emergency lighting and exit sign connected to *Yes/No/N.A. *Yes/No/N.A.
emergency generator power supply?
Annex II FS_TCP
Page 117 of 222 2017 Edition
Annex II
y) Is there any dark out LED cell(s) in LED exit and *Yes/No/N.A. *Yes/No/N.A.
directional signs?
a) Acceptance Testing
b) Discharge Test
Annex II FS_TCP
Page 118 of 222 2017 Edition
Annex II
c) Functional Test
d) Performance Test
(iv) Does the central monitoring, testing and logging *Yes/No/N.A *Yes/No/N.A
system perform as specified (G.S. Clause
B11.1.7)?
(Remark: Detailed testing and commissioning
procedures to be submitted by the FS Contractor
for approval.)
Tested / Checked by : Signature - Post :
(Name of FS Contractor’s Representative)
Tel. No. :
( ) Date :
Witnessed by: Signature - Post :
(Name(s) of *PBSE/PBSI)
Tel. No. :
( ) Date :
Annex II FS_TCP
Page 119 of 222 2017 Edition
Annex II
a) Acceptance Testing
Does the installation comply with BS 5499 and BS 5266: *Yes/No/N.A. *Yes/No/N.A.
Part 1 and FSDCoP?
b) Discharge Test
(1) Connections between the battery and the source *Yes/No/N.A *Yes/No/N.A
of charging current to be such that in no
circumstances shall the battery discharge other
than to the secondary lighting circuits.
c) Functional Test
d) Performance Test
(i) Is the illumination level adequate when all signs *Yes/No/N.A *Yes/No/N.A
are on using battery supply?
Annex II FS_TCP
Page 120 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 121 of 222 2017 Edition
Annex II
3.13.1.1 Method of overriding control (Refer to para. 5.27 in C.O.P for Minimum F.S.I. & Equipment
and FSD Circular Letter No. 2/2005):
3.13.1.2 Shut down of the MVAC systems utilising: * Conventional AFA/ Addressable AFA/ BMS/
CCMS
3.13.1.3 On/Off status monitoring of MVAC systems at: FS Control Room/B.M. Office/MVAC
Control Console
b) Do the sizes of the MVAC systems and associated air *Yes/No/N.A. *Yes/No/N.A.
ducts tally with the FSD endorsed MVAC layouts?
c) Are all the MVAC systems required to be included in the *Yes/No/N.A. *Yes/No/N.A.
VAC control system highlighted on the air-side
schematic diagram?
e) Are the supply/ return/ intake/ exhaust points installed at *Yes/No/N.A. *Yes/No/N.A.
the correct level?
Annex II FS_TCP
Page 122 of 222 2017 Edition
Annex II
b) Are the probes length (>2/3 duct width in most products) *Yes/No/N.A. *Yes/No/N.A.
and model appropriate?
d) Are the filters at the end of the smoke collecting/ *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?
e) Is the smoke collecting probe installed in such a way that *Yes/No/N.A. *Yes/No/N.A.
the smoke collecting holes are facing the air stream
being detected?
a) Can all the MVAC systems involved in the VAC control *Yes/No/N.A. *Yes/No/N.A.
system be shut off when this switch is activated?
b) Does any breakage in circuit wiring of this switch cause *Yes/No/N.A. *Yes/No/N.A.
the above MVAC systems to shut down?
Annex II FS_TCP
Page 123 of 222 2017 Edition
Annex II
a) Does the MVAC system shut down or fault signal *Yes/No/N.A. *Yes/No/N.A.
indicated on the panel when the detector head is removed
from its mounting base?
b) Does the MVAC system shut down or fault signal *Yes/No/N.A. *Yes/No/N.A.
indicated on the panel when the power supply to the
detector is lost?
a) Each MVAC system shall operate steadily to its rated *Yes/No/N.A. *Yes/No/N.A.
speed and capacity first. Smoke is generated and
conveyed to the lower pressure side of the MVAC
system or air duct where it can be collected and detected.
After a reasonably short period of time, the MVAC
system must be able to shut down and a signal will be
relayed to the F.S. Panel in the F.S. Control Room. All
other MVAC systems installed within and serving the
same compartment must also be shut down through
interlocking arrangement. No MVAC system can
resume normal function unless the fire signal registered
has been cleared. (Test records on Part 4, 4.13 Table 1)
b) Is the VAC control system design for the MVAC system *Yes/No/N.A. *Yes/No/N.A.
fail-safe?
a) The central fresh air supply and/ or exhaust system shall *Yes/No/N.A. *Yes/No/N.A.
be shut down.
b) The central fresh air supply and/or exhaust system shall *Yes/No/N.A. *Yes/No/N.A.
not require to be shut down but the fresh air and/or
exhaust to the affected compartment/unit shall be closed
off from the central system by actuation of a local
motorised smoke damper.
Annex II FS_TCP
Page 124 of 222 2017 Edition
Annex II
(Note: As-fitted drawings, and the formal documents showing the system design calculation
and the system operating principles & sequences must be ready and available on the Site at the
time of T&C)
b) Pressurised space :
- Escape staircase; or *Yes/No/N.A. *Yes/No/N.A.
- Fire fighting staircase. *Yes/No/N.A. *Yes/No/N.A.
c) Equipment to be provided :
- Single fan with motor: or *Yes/No/N.A. *Yes/No/N.A.
- Duplicated fans complete with motors: or *Yes/No/N.A. *Yes/No/N.A.
- Single fan with duplicated motors: or *Yes/No/N.A. *Yes/No/N.A.
- Others : *Yes/No/N.A. *Yes/No/N.A.
Annex II FS_TCP
Page 125 of 222 2017 Edition
Annex II
3.14.2.1 General
Annex II FS_TCP
Page 126 of 222 2017 Edition
Annex II
j) Are the fan motors duplicated with belt connected for *Yes/No/N.A. *Yes/No/N.A.
duty and standby used for buildings with more than one
pressurised staircase?
k) Are sleeping risk premises and where designated by the *Yes/No/N.A. *Yes/No/N.A.
Director of Fire Services, provided with a single
pressurised staircase, duplicate fans and motors?
Fan / Motor Set Data : Single Supply Fan Multiple Supply Fan
Duty Duplicated No. 1 No. 1 No. 2 No. 2
Motor Motor Duty Fan Standby Fan Duty Fan Standby Fan
Location
Fan
Manufacturer
Motor
Fan
Model
Motor
Fan
Serial No.
Motor
Starting method
Annex II FS_TCP
Page 127 of 222 2017 Edition
Annex II
a) Is pressurisation fan & motor supplied from one single *Yes/No/N.A. *Yes/No/N.A.
proprietary manufacturer specialised in the manufacture
of the pressurisation of staircases system?
c) Is nominal fan motor power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power?
f) Are pressurisation fan motors protected with HRC fuses? *Yes/No/N.A. *Yes/No/N.A.
i) Are the fans installed in a separate fire resistant plant *Yes/No/N.A. *Yes/No/N.A.
room or enclosed by fire resistant enclosure with a FRP
not less than that of the staircase served?
k) Are doors to fan room provided with key locking *Yes/No/N.A. *Yes/No/N.A.
devices?
l) Are door(s) to fan room provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closer(s)?
n) Shall the plant room housing the staircase pressurisation *Yes/No/N.A. *Yes/No/N.A.
fans contain no other services?
Annex II FS_TCP
Page 128 of 222 2017 Edition
Annex II
b) Is position of air intake located away from any potential *Yes/No/N.A. *Yes/No/N.A.
fire hazards (such as basement smoke vent)?
c) Is air duct provided from the intake to the fan when air *Yes/No/N.A. *Yes/No/N.A.
intake is distant from the fan?
d) Is smoke detector of a type suitable for use in air duct / *Yes/No/N.A. *Yes/No/N.A.
plenum installed?
e) Can the pressurisation system be shut down when the *Yes/No/N.A. *Yes/No/N.A.
duct type smoke detector is activated?
a) Are two air intakes, which spaced apart and facing *Yes/No/N.A. *Yes/No/N.A.
different directions, provided?
g) Is air duct provided from the intake to the fan when air *Yes/No/N.A. *Yes/No/N.A.
intake is distant from the fan?
h) Is smoke control damper properly actuated when the duct *Yes/No/N.A. *Yes/No/N.A.
type smoke detector is activated?
Annex II FS_TCP
Page 129 of 222 2017 Edition
Annex II
i) Are gaps / spaces between ductwork and wall openings *Yes/No/N.A. *Yes/No/N.A.
filled with approved sealant?
l) Are duct hangers and supports rigidly fixed and in good *Yes/No/N.A. *Yes/No/N.A.
conditions?
o) Is the system NOT equipped with fire / smoke dampers *Yes/No/N.A. *Yes/No/N.A.
or any other restrictions along the passage of supply &
exhaust air in accordance with the approved drawings?
Annex II FS_TCP
Page 130 of 222 2017 Edition
Annex II
q) Do sizes of air duct, discharge outlet and pressure relief *Yes/No/N.A. *Yes/No/N.A.
damper sizes tally with drawings?
i) between the door into pressurised space and the start *Yes/No/N.A. *Yes/No/N.A.
of the partitioning? or,
ii) on each office & unit, the size of each air relief vent *Yes/No/N.A. *Yes/No/N.A.
is capable of discharging the total air flow from the
pressurised space?
g) When the shaft is designed for dual purpose, is automatic *Yes/No/N.A. *Yes/No/N.A.
control fire & smoke damper (note: fusible link type fire
& smoke damper is NOT acceptable) provided at each
branch duct?
Annex II FS_TCP
Page 131 of 222 2017 Edition
Annex II
h) Are special vents for external vent provided on at least *Yes/No/N.A. *Yes/No/N.A.
two sides of the sealed building?
k) Is extraction flow rate greater than the total pressurised *Yes/No/N.A. *Yes/No/N.A.
air flow rate of all served staircase pressurisation
systems?
iii) for pressurisation system for fire fighting, is the local *Yes/No/N.A. *Yes/No/N.A.
motorised smoke damper in fire floor opened and
dampers for other compartments / units closed? or,
iv) for pressurisation system for escape, are the local *Yes/No/N.A. *Yes/No/N.A.
motorised smoke dampers in fire floor and two
above floors opened and dampers for other
compartments / units closed?
Annex II FS_TCP
Page 132 of 222 2017 Edition
Annex II
b) Door lock, latch, bolt, push bar & etc. are not provided at *Yes/No/N.A. *Yes/No/N.A.
the external exit doors?
b) Are the pressure sensors and its associated equipment of *Yes/No/N.A. *Yes/No/N.A.
industrial process grade conforming to BS EN 60654-4
or equivalent?
Annex II FS_TCP
Page 133 of 222 2017 Edition
Annex II
h) Is the pressure sensing unit(s) connected with fire rated *Yes/No/N.A. *Yes/No/N.A.
cables of high temperature grade to BS 6724 suitable for
operating at 250 oC?
i) Is the high temperature grade fire rated type cable *Yes/No/N.A. *Yes/No/N.A.
enclosed in galvanised steel conduit and run within the
pressurised space in the fire resistance duct?
b) Are the binding tapes used for the cables of flame *Yes/No/N.A. *Yes/No/N.A.
retardant?
c) Are the cables installed in cable trays or other approved *Yes/No/N.A. *Yes/No/N.A.
supports, and fastened by approved fasteners or clamps
specially designed and constructed for the purpose?
d) Are the cables installed outside the pressurised staircase *Yes/No/N.A. *Yes/No/N.A.
enclosed by fire resistant enclosure with FRP not less
than that of the compartment served or 2 hrs FRP,
whichever is the higher?
Annex II FS_TCP
Page 134 of 222 2017 Edition
Annex II
f) Are electrical supplies for all equipment (such as fans, *Yes/No/N.A. *Yes/No/N.A.
air relief damper, over-pressure device, controller,
supervisory panel & etc) fed from the same essential
source?
h) Are power supplies for the differential pressure sensors, *Yes/No/N.A. *Yes/No/N.A.
control, overpressure devices, air release devices
distributed from the sub-circuit of staircase
pressurisation system?
ii) Are all controls, starters, relays, etc suitable for *Yes/No/N.A. *Yes/No/N.A.
continuous operation at 250°C for not less than 1
hour?
e) Does the control panel incorporate the necessary relays, *Yes/No/N.A. *Yes/No/N.A.
timers, key type switches, alarm and trouble lights
essential to the operation of the system?
Annex II FS_TCP
Page 135 of 222 2017 Edition
Annex II
f) Is the indicator light actuated by devices that sense the *Yes/No/N.A. *Yes/No/N.A.
effective operation of the relevant components (i.e.
airflow switch / air pressure switch) of the pressurisation
system?
i) Are all switches and indicators clearly labelled (red *Yes/No/N.A. *Yes/No/N.A.
letters on white background, not less than 3 mm high) to
indicate the operating positions and systems served?
j) A further label shall be provided with letters not less than *Yes/No/N.A. *Yes/No/N.A.
6 mm high stating that the controls shall be operated by
authorised personnel.
3.14.2.10 Miscellaneous
a) Are all ductworks and metal works properly painted for *Yes/No/N.A. *Yes/No/N.A.
identification?
Annex II FS_TCP
Page 136 of 222 2017 Edition
Annex II
c) Are door sets (i.e. doors, frames and ironmongery *Yes/No/N.A. *Yes/No/N.A.
hardware) complying with Building Authority’s
requirement and suitable for use continuously at 35 oC
and 100% RH, and with certificates enclosed as
required?
g) If, however, except for sleeping risk premises, is the total *Yes/No/N.A. *Yes/No/N.A.
air requirement for each pressurised staircase made up
from two or more separate supplies acting together (e.g.
top and bottom plants)? (If yes, then no further
duplication of equipment is necessary)
h) Are all doors sets (i.e. doors, frames and hardware) *Yes/No/N.A. *Yes/No/N.A.
providing access to or from any pressurised staircase to
the satisfaction of the Building Authority?
j) Are self closers provided for all the doors to ensure *Yes/No/N.A. *Yes/No/N.A.
integrity of the enclosure? The closers shall have been
part of a “door, door frame and ironmongery” test
assembly which has successfully passed the test in
accordance with British Standard 476: Part 22? Are the
closers of such a design that they cannot be defeated i.e.
no removable pins or bolts, etc.?
l) When plant room served more than one pressurisation *Yes/No/N.A. *Yes/No/N.A.
system, is separate fire rated enclosure provided to each
pressurisation system in order to maintain fire
compartmentation between different pressurised spaces?
m) When fan room is used as an air plenum, are all the *Yes/No/N.A. *Yes/No/N.A.
control panels located outside the fan room, or protected
by fire resistant enclosure(s)?
Annex II FS_TCP
Page 137 of 222 2017 Edition
Annex II
o) Are all joints between frames & building structure *Yes/No/N.A. *Yes/No/N.A.
provided with sealants in compliance with BS 476: Part
23?
p) Is finished sill under the closed doors wear resistant? *Yes/No/N.A. *Yes/No/N.A.
b) Does the system actuate directly from the local automatic *Yes/No/N.A. *Yes/No/N.A.
fire alarm control panel and remain in operation? (Refer
to Para. 5.21 in FSDCoP)
c) Are manual reset and monitoring provision with audio / *Yes/No/N.A. *Yes/No/N.A.
visual indications provided? (Refer to Para. 5.21 in
FSDCoP)
f) Can the fan just be stopped by switching off at the fan *Yes/No/N.A. *Yes/No/N.A.
control rather than by any automatic means?
Annex II FS_TCP
Page 138 of 222 2017 Edition
Annex II
k) Is variable flow control for fan(s) adopting for “normal” *Yes/No/N.A. *Yes/No/N.A.
operating mode?
n) Is performance test carried out and is the test result *Yes/No/N.A. *Yes/No/N.A.
satisfactory?
r) Is the air intake fire/ smoke damper closed when the duct *Yes/No/N.A. *Yes/No/N.A.
type smoke detector is activated? or
s Is the staircase pressurisation system shut down when the *Yes/No/N.A. *Yes/No/N.A.
duct smoke detector at air intake is activated (for the air
intake only facing in one direction)?
Annex II FS_TCP
Page 139 of 222 2017 Edition
Annex II
3.14.3.2 Others
Annex II FS_TCP
Page 140 of 222 2017 Edition
Annex II
Operating Air Flow Pattern : *Scouring Pattern / Cross Flow Effect with low level supply
and high level extraction
Annex II FS_TCP
Page 141 of 222 2017 Edition
Annex II
3.15.2.1 General
e) Does system layout tally with that in approved building *Yes/No/N.A. *Yes/No/N.A.
plans and F.S.I. drawings?
f) Is smoke zone boundary and auto smoke curtain location *Yes/No/N.A. *Yes/No/N.A.
in accordance to approved smoke control layout?
j) Are FSD approved procedures and set up details for *Yes/No/N.A. *Yes/No/N.A.
testing & commissioning available?
l) Are all systems completed and tested to ensure that they *Yes/No/N.A. *Yes/No/N.A.
are functioning correctly before the final full test and
demonstration take place with FSD Officers in
attendance?
m) Has a full set of test and functional operation check *Yes/No/N.A. *Yes/No/N.A.
records submitted accompanying Register Professional
Engineer’s signature confirming or otherwise that he is
satisfied that the installation(s) are operating in
accordance with his design and the requirements of
F.S.D?
Annex II FS_TCP
Page 142 of 222 2017 Edition
Annex II
o) Are all systems with “fail safe” design to ensure a free *Yes/No/N.A. *Yes/No/N.A.
passage of smoke?
p) Are the fire shutters tested to the relevant requirements *Yes/No/N.A. *Yes/No/N.A.
of the T&C Procedure for Fire Service Installation?
q) Has exemption been granted for one extraction / supply *Yes/No/N.A. *Yes/No/N.A.
system used to serve several compartments?
r) Where the motorised fire and smoke dampers are *Yes/No/N.A. *Yes/No/N.A.
required, has the entire assembly of the fire and smoke
damper been tested to maintain efficient operation at
250oC for not less than one hour?
s) Has the Director of Fire Services approved the adoption *Yes/No/N.A. *Yes/No/N.A.
of performance based fire engineering approach?
t) Where the smoke extraction rate is designed with fire *Yes/No/N.A. *Yes/No/N.A.
engineering approach, is the maximum area of the smoke
reservoir restricted to 2000 m2?
y) Shafts used for smoke extraction purposes shall contain *Yes/No/N.A. *Yes/No/N.A.
no other services.
Annex II FS_TCP
Page 143 of 222 2017 Edition
Annex II
Fan
Manufacturer
Motor
Fan
Model
Motor
Fan
Serial No.
Motor
Starting Method
Annex II FS_TCP
Page 144 of 222 2017 Edition
Annex II
c) If the fans are installed within the service compartment, *Yes/No/N.A. *Yes/No/N.A.
is the fan system (including fans, motors, drives,
electrical works, ductworks, boundary of compartment)
protected by a fire resisting material of rating not less
than one hour?
d) Is the supply / makeup air rate at least 80% of the overall *Yes/No/N.A. *Yes/No/N.A.
extraction rate?
g) Is fan motor(s) power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required nominal fan power?
i) Is the fan itself coated with finishing material capable of *Yes/No/N.A. *Yes/No/N.A.
withstanding exposure to an ambient temperature of 250
o
C for a period of not less than one hour without
producing smoke or any toxic fumes, and certified by
the fan manufacturer?
l) Are smoke extraction fans connected with power supply *Yes/No/N.A. *Yes/No/N.A.
from essential source?
Annex II FS_TCP
Page 145 of 222 2017 Edition
Annex II
o) Are doors to smoke extraction plant room provided with *Yes/No/N.A. *Yes/No/N.A.
locking devices?
p) Are doors to smoke extraction plant room provided with *Yes/No/N.A. *Yes/No/N.A.
automatic door closer(s)?
3.15.2.3 Ductworks
a) Is air intake distant from any potential fire hazards and is *Yes/No/N.A. *Yes/No/N.A.
prevented from contamination by the same source of
smoke?
d) Does the size of the outside air intake duct tally with *Yes/No/N.A. *Yes/No/N.A.
vertical air flow diagram approved by FSD?
Annex II FS_TCP
Page 146 of 222 2017 Edition
Annex II
i) Are gaps / spaces between ductwork and wall opening *Yes/No/N.A. *Yes/No/N.A.
filled with approved sealant?
l) Are duct hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?
o) Does system clear from any fire / smoke dampers or any *Yes/No/N.A. *Yes/No/N.A.
other restrictions of air passage as approved?
r) Do sizes of air duct, discharge outlet and pressure relief *Yes/No/N.A. *Yes/No/N.A.
damper sizes tally with drawings?
t) Are motorised fire / smoke dampers provided only for *Yes/No/N.A. *Yes/No/N.A.
system where one extraction or supply system is used to
serve several compartments as approved?
Annex II FS_TCP
Page 147 of 222 2017 Edition
Annex II
x) Are fire and smoke dampers provided at the main *Yes/No/N.A. *Yes/No/N.A.
exhaust outlet louvre and / or main supply intake louvre
and are they approved by FSD?
y) Do fire and smoke dampers comply with UL 555s class I *Yes/No/N.A. *Yes/No/N.A.
or other international standards?
Annex II FS_TCP
Page 148 of 222 2017 Edition
Annex II
d) Are the filters at the end of the smoke collecting / *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?
g) Is the smoke detector connected with fire resisting cable *Yes/No/N.A. *Yes/No/N.A.
to the control panel?
b) Is the whole smoke extraction system wired with fire *Yes/No/N.A. *Yes/No/N.A.
resisting cables?
d) Are the binding tapes used for the cables of flame *Yes/No/N.A. *Yes/No/N.A.
retardant?
e) Are the cables installed in cable trays or other approved *Yes/No/N.A. *Yes/No/N.A.
supports, and are fastened by approved fasteners or
clamps specially designed and constructed for the
purpose?
f) Are the cable routes provided with proper protective *Yes/No/N.A. *Yes/No/N.A.
enclosure to reduce the likelihood of failure due to
external effects – mechanical, electrical or physical?
Annex II FS_TCP
Page 149 of 222 2017 Edition
Annex II
c) Is the control panel for each smoke extraction system *Yes/No/N.A. *Yes/No/N.A.
normally manned or installed in public area?
g) Does the control panel incorporate the necessary relays, *Yes/No/N.A. *Yes/No/N.A.
timers, key type switches, alarms and trouble lights
essential to the operation of the system?
h) Are the controls, starters, relays, etc., suitable for *Yes/No/N.A. *Yes/No/N.A.
continuous operation at 250 oC for not less than one
hour?
i) Is the indicator light actuated by devices that sense the *Yes/No/N.A. *Yes/No/N.A.
effective operation of the relevant components (i.e.
airflow switch / air pressure switch) of the smoke
extraction system?
l) Are all switches and indicators clearly labelled (red *Yes/No/N.A. *Yes/No/N.A.
letters on white background, not less than 3 mm high) to
indicate the operating positions and systems served?
Annex II FS_TCP
Page 150 of 222 2017 Edition
Annex II
n) Are switches for all smoke extraction systems grouped in *Yes/No/N.A. *Yes/No/N.A.
one area of the panel together with those for staircase
pressurisation systems or the like? Where the smoke
extraction system is served by both supply and extract
fans, are on/off switches for each fan provided?
o) Is label provided with letters not less than 6 mm high *Yes/No/N.A. *Yes/No/N.A.
stating that the controls shall be operated by authorised
personnel?
e) Does the fault silence switch silence the audible alarm *Yes/No/N.A. *Yes/No/N.A.
while leaving visual light ON?
f) Does the alarm silence switch silence the audible alarm *Yes/No/N.A. *Yes/No/N.A.
while leaving the red alarm indicating light ON until the
system is reset?
h) Does test switch for simulating alarm condition and *Yes/No/N.A. *Yes/No/N.A.
operate properly?
Annex II FS_TCP
Page 151 of 222 2017 Edition
Annex II
3.15.2.8 Miscellaneous
c) Are all ductworks and metal works properly painted? *Yes/No/N.A. *Yes/No/N.A.
Annex II FS_TCP
Page 152 of 222 2017 Edition
Annex II
b) Has full and complete records been taken of all tests and
the results submitted with not less than the following in
the report :
c) Has mechanical check for motorised smoke / fire damper *Yes/No/N.A. *Yes/No/N.A.
been conducted and accepted by Registered Professional
Engineer under CAP 409?
d) Are smoke curtains dropped down smoothly and the *Yes/No/N.A. *Yes/No/N.A.
bottom bars stop at the correct position?
Annex II FS_TCP
Page 153 of 222 2017 Edition
Annex II
e) Are switches for all smoke extraction / removal systems *Yes/No/N.A. *Yes/No/N.A.
grouped in one area of the panel together with those for
staircase pressurisation systems or the like?
f) Are all switches have the same method / direction of *Yes/No/N.A. *Yes/No/N.A.
operation?
h) Are all switches and indicators clearly labelled (red *Yes/No/N.A. *Yes/No/N.A.
letters on white background, not less than 3 mm high) to
show operating positions and systems served and stating
that the controls shall be operated only by authorised
personnel?
a) Are the electrically driven fans equipped with audio and *Yes/No/N.A. *Yes/No/N.A.
visual warnings to indicate the fault signals?
Annex II FS_TCP
Page 154 of 222 2017 Edition
Annex II
iii) The correct balancing and direction of air flow? *Yes/No/N.A. *Yes/No/N.A.
d) Are egress / escape routes kept free from smoke (i.e. *Yes/No/N.A. *Yes/No/N.A.
smoke flow shall be away from the escape route)?
e) Are air / smoke flow paths under “scouring” or “cross- *Yes/No/N.A. *Yes/No/N.A.
flow” effect in all areas within the fire compartment as
approved?
j) Does makeup air supply follow an air path as direct and *Yes/No/N.A. *Yes/No/N.A.
short as possible, and enter at low level in order to avoid
premature mixing with the hot gases?
Annex II FS_TCP
Page 155 of 222 2017 Edition
Annex II
b) Does the system actuate directly from the local automatic *Yes/No/N.A. *Yes/No/N.A.
fire alarm control panel and remain in operation? (Refer
to Para. 5.22 in FSDCoP)
c) Are manually reset and monitor by audio & visual *Yes/No/N.A. *Yes/No/N.A.
indication function provided? (Refer to Para. 5.22 in
FSDCoP)
g) Can the fan just be stopped by switching off at the fan *Yes/No/N.A. *Yes/No/N.A.
control rather than by any automatic means?
Annex II FS_TCP
Page 156 of 222 2017 Edition
Annex II
Operating air flow pattern : *Scouring pattern / Cross flow effect with low level supply
and high level extraction
Annex II FS_TCP
Page 157 of 222 2017 Edition
Annex II
1) *Smoke Generator(s)
2) *Tracer Smoke
3) *Fire Chamber
4) *Combustion Fuel
5) *Thermal Couples
6) *Temperature Sensor(s)
7) *Anemometer
8) *Clamp-on Ammeter
9) *Voltmeter
10) *Tachometer
13) *U gauges
Annex II FS_TCP
Page 158 of 222 2017 Edition
Annex II
3.16.3.1 General
e) Does system layout tally with that in approved building *Yes/No/N.A. *Yes/No/N.A.
plans and F.S.I. drawings?
f) Are all wet fire service installations completed with full *Yes/No/N.A. *Yes/No/N.A.
testing & commissioning?
g) Are all automatic fire alarm installations completed with *Yes/No/N.A. *Yes/No/N.A.
full testing & commissioning?
h) Are all static & dynamic smoke extracting installations *Yes/No/N.A. *Yes/No/N.A.
completed with full testing & commissioning?
i) Is smoke zone boundary and auto smoke curtain location *Yes/No/N.A. *Yes/No/N.A.
in accordance to approved smoke control layout?
n) Are all finishes of building envelop completed with full *Yes/No/N.A. *Yes/No/N.A.
inspection?
o) Are FSD approved procedures and set up details for *Yes/No/N.A. *Yes/No/N.A.
Testing & Commissioning available?
p) Does the smoke re-enter into the building through *Yes/No/N.A. *Yes/No/N.A.
building openings or fresh air intake louvres?
q) Is mock-up test with set up details for Testing & *Yes/No/N.A. *Yes/No/N.A.
Commissioning available and approved by the
Supervising Officer?
Annex II FS_TCP
Page 159 of 222 2017 Edition
Annex II
w) Are all systems completed and tested to ensure that they *Yes/No/N.A. *Yes/No/N.A.
are functioning correctly before the final full test and
demonstration take place with FSD Officers in
attendance?
x) Has a full set of test and functional operation check *Yes/No/N.A. *Yes/No/N.A.
records submitted accompanying Register Professional
Engineer’s signature confirming or otherwise that he is
satisfied that the installation(s) are operating in
accordance with his design and the requirements of
F.S.D?
z) Are all fire fighting squads available throughout the *Yes/No/N.A. *Yes/No/N.A.
testing process?
aa) Is the safety arrangement and precautions for the test *Yes/No/N.A. *Yes/No/N.A.
approved by the Supervising Officer and accepted by the
FSD?
Annex II FS_TCP
Page 160 of 222 2017 Edition
Annex II
d) Are the filters at the end of the smoke collecting / *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?
f) Is the smoke management supply fan tripped off upon *Yes/No/N.A. *Yes/No/N.A.
the sensing of smoke at the air intake passage by the
designated smoke detector?
g) Is the smoke detector connected with fire resisting cable *Yes/No/N.A. *Yes/No/N.A.
to the control panel?
3.16.3.3 Miscellaneous
d) Is static photo recording carried out to record the smoke *Yes/No/N.A. *Yes/No/N.A.
movement upon the hot smoke test?
Annex II FS_TCP
Page 161 of 222 2017 Edition
Annex II
a) Are the ductwork and all relevant parts of the systems for *Yes/No/N.A. *Yes/No/N.A.
the hot smoke test tested satisfactorily in accordance
with the T&C Procedure for Air-conditioning,
Refrigeration, Ventilation and Central Monitoring
Control System Installation?
b) Are preliminary and visual test on the sealing of all *Yes/No/N.A. *Yes/No/N.A.
openings in the ductwork using chemical “white” smoke
generators be carried out?
c) Has mechanical check for motorised smoke / fire damper *Yes/No/N.A. *Yes/No/N.A.
been conducted and accepted by Registered Professional
Engineer under CAP 409?
d) Are smoke curtains dropped down smoothly and the *Yes/No/N.A. *Yes/No/N.A.
bottom bars stop at the correct position?
Annex II FS_TCP
Page 162 of 222 2017 Edition
Annex II
a) Is the fire size identified with total heat output estimated *Yes/No/N.A. *Yes/No/N.A.
to ensure the test to be carried out without damage to the
building?
d) Are the plume temperature reading data logged with *Yes/No/N.A. *Yes/No/N.A.
computer programme and linked to trigger the alarm
signal for executing fire suppression, if required?
Annex II FS_TCP
Page 163 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 164 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 165 of 222 2017 Edition
Annex II
4.1.2 Records
(This form can also be used for hydraulic test carried out during the construction period)
Annex II FS_TCP
Page 166 of 222 2017 Edition
Annex II
Pressure (bars)
Pressure Reducing Riser/Stair No. Floor Level
Set No. Upstream Downstream
Standby
Pump Standby
Standby
Duty Pump
Standby Pump
Annex II FS_TCP
Page 167 of 222 2017 Edition
Annex II
Table 6 Test Records on Flow Capacity and Pressure of Hydrant (Fixed fire pump)
Location of Hydrant Floor Level Riser/Stair No. Pressure (bars) Flow rate (L/min)
Topmost outlet
Bottom outlet
Intermediate outlet
Table 7 Test Records on Static Pressure without Pump at the Topmost Hydrant Outlet
Annex II FS_TCP
Page 168 of 222 2017 Edition
Annex II
Table 8 Test Records on Flow Capacity and Pressure of Hydrant (with intermediate booster pump)
Location of Hydrant Floor Level Riser/Stair No. Pressure (bars) Flow rate (L/min)
Topmost outlet
Bottom outlet
Intermediate outlet
Remark:
Annex II FS_TCP
Page 169 of 222 2017 Edition
Annex II
Type of town mains: *single end feed/ double end feed/ direct feed/ unrestricted
Annex II FS_TCP
Page 170 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 171 of 222 2017 Edition
Annex II
4.2.2 Records
Annex II FS_TCP
Page 172 of 222 2017 Edition
Annex II
Jockey Pump
Sprinkler Duty
Pump
Standby
Transfer Duty
Pump
Standby
Jockey Pump
Duty Pump
Standby Pump
Note: Duty pump cut-in pressure shall be not less than 80% of the design/maintained pressure in
the trunk main.
Annex II FS_TCP
Page 173 of 222 2017 Edition
Annex II
Annex II FS_TCP
Page 174 of 226 2017 Edition
Annex II
Table 5 Test Record of Proving of Water Supplies with Measuring Orifice Fitted
#- Actual minimum running pressure = Installation pressure - Static pressure of highest sprinkler
Table 6 Test Record of Proving of Water Supplies with Standard Test Orifice Fitted
Remark:
Annex II FS_TCP
Page 175 of 222 2017 Edition
Annex II
4.3 Record of Tests on Manual and Automatic Fire Alarm System and Fire Alarm Control System
Alarm Bell
Heat
Fire Smoke
Detector
Probe Unit
Sprinkler Flow
Switch
Annex II FS_TCP
Page 176 of 222 2017 Edition
Annex II
4.3.1.1.2 Detectors
a) Heat detector:
Manufacturer/model No. : ____________________________________
Type : ____________________________________
Location : ____________________________________
Annex II FS_TCP
Page 177 of 222 2017 Edition
Annex II
4.3.2 Records
Table 1 Test Record of Manual Call Points, Alarm Bells Visual Fire Alarms and Control Panel
Control Panel
Location/ LED Indicator Floor on which Fault Signal
Identification Local/Remote Alarm Bell Sounds Zone No. and Buzzer
of Detector (ON/0FF) and Visual Fire Indication
(Heat/Smoke) Alarm Flashes (No./ON/OFF) (ON/OFF)
Remark:
Annex II FS_TCP
Page 178 of 222 2017 Edition
Annex II
4.4 Record of Tests on Gaseous Extinguishing Installation
Location/Room :
Type of Gas : *CO2 / FM200 / ________________
Type of System :
Modular ( ) Cylinder ( )
Pre-engineered ( ) Engineered ( )
Annex II FS_TCP
Page 179 of 222 2017 Edition
Annex II
4.4.2 Records
Annex II FS_TCP
Page 180 of 222 2017 Edition
Annex II
Remark:
Annex II FS_TCP
Page 181 of 222 2017 Edition
Annex II
4.5 Record of Tests on Street Hydrant
4.5.2 Records
Start End
Date Location/Section Duration
(min)
Time Pressure (kPa) Time Pressure (kPa)
Annex II FS_TCP
Page 182 of 222 2017 Edition
Annex II
Table 2 Test Record of Pump/Motor Set
Jockey Pump
Others
Remark:
Annex II FS_TCP
Page 183 of 222 2017 Edition
Annex II
4.6 Record of Tests on Drencher System
Type of town mains : *single end feed/ double end feed/ direct feed/ unrestricted
Water tank capacity : m³ at Location :
Total Nos. of drencher head/water spray nozzle : Nos.
Total Nos. of deluge valve set : Nos.
Nos. of drencher head/water spray nozzle connected to each deluge valve set :
9
Use separate sheet for large installation.
Annex II FS_TCP
Page 184 of 222 2017 Edition
Annex II
4.6.2 Records
Motor Current
Pump/Motor Set Pump Discharge Pressure
(A)
Duty
Standby
Duty
Standby
Annex II FS_TCP
Page 185 of 222 2017 Edition
Annex II
Table 4 Test Record of Proving of Water Supplies with Measuring Orifice Fitted
Note: # - Actual minimum running pressure = Installation pressure - Static pressure of highest nozzle
Table 5 Test Record of Proving of Water Supplies with Standard Test Orifice Fitted
Remark:
Annex II FS_TCP
Page 186 of 222 2017 Edition
Annex II
4.7 Record of Tests on Audio/Visual Advisory System
Control Panel
Floor on which
Location of Loudspeakers Loudspeakers Zone No. and
Loudspeaker
Operated Indication
(ON/OFF)
(No./NO/OFF)
Annex II FS_TCP
Page 187 of 222 2017 Edition
Annex II
Table 2 Test Record of Flashing Light/Flashing Directional Sign
Control Panel
Location/
Flashing Lights Zone No. and Flashing
Identification
(ON/OFF) Indication Light
of Flashing Lights
(No./ON/OFF) (ON/OFF)
Note: Flashing lights in the same area shall operate in synchronous mode.
Remark:
Annex II FS_TCP
Page 188 of 222 2017 Edition
Annex II
4.8 Record of Tests on Portable Hand-Operated Approved Appliance
Note: *Capacity and type of fire extinguishers and their locations shall be stated.
Remark:
Annex II FS_TCP
Page 189 of 222 2017 Edition
Annex II
4.9 Record of Tests on Fire Shutters
Operation
Annex II FS_TCP
Page 190 of 222 2017 Edition
Annex II
Table 2 Test Record of Detector and Control Panel
Control Panel
Location/ LED Indicator Floor on which
Identification Local/Remote Alarm Bell Sound Zone No. and Buzzer
of Detector (ON/OFF) Indication
(Heat/Smoke) (No./ON/OFF) (ON/OFF)
Remark:
Annex II FS_TCP
Page 191 of 222 2017 Edition
Annex II
4.10 Record of Tests on Emergency Generator Installation
4.10.1.3 Alternator
a) Make :
b) Model :
c) Serial No. :
d) Rated kVA :
e) Voltage (V) / Full load current (A) :
f) Phase / Rated p.f. :
g) Insulation class :
Annex II FS_TCP
Page 192 of 222 2017 Edition
Annex II
4.10.1.4 Starting Battery
a) Manufacturer :
b) Make/Model No. :
c) No(s). of battery / Voltage (V) :
d) Ampere hour :
e) Starting time (sec) :
Annex II FS_TCP
Page 193 of 222 2017 Edition
Annex II
4.10.4 Installations and Equipment Connected
Annex II FS_TCP
Page 194 of 222 2017 Edition
Annex II
4.10.5 Control Function Test
Simulate Test 1 ^
Mains Failure Test 2 **
Delay Start Timer
Delay Repeat Start
b. Stopping Manual
Resumption of Mains ***
Delay Stop Timer ****
c. Engine
Overload Trip (MCCB)
Protection
Engine HL
Overspeed LL
Low Lub-oil HL
Pressure (kPa) LL
High Water HL
Temp. (oC) LL
Under Voltage Trip
Overvoltage Trip
Response Time from Mains
d. Others
Failure to Changeover (sec)
Battery 4 Attempt Start
Quick closing Mechanism
Governor Function
Voltage Regulator (346V -
380V)
Auto-starting of Vent. Fan
Manual Override Facilities
Phase Sequence of Alternator
Output
Frequency Setting
Note: ^ Refer to function test on capability to start and transfer load to generator automatically.
** Refer to function test on capability to start but without load transfer if mains resumes during
engine starting.
*** Refer to function test on capability to automatic transfer load back to mains automatically
after a preset time delay and immediately back to generator if mains fails within the above
time delay period.
**** Refer to function test on capability to cool engine for a preset period after load is transferred
to mains.
Annex II FS_TCP
Page 195 of 222 2017 Edition
Annex II
4.10.6 On Load Test
Annex II FS_TCP
Page 196 of 222 2017 Edition
Annex II
4.10.7 Dummy Load Test
Annex II FS_TCP
Page 197 of 222 2017 Edition
Annex II
4.10.8 Earthing Protection Test
Remark:
Annex II FS_TCP
Page 198 of 222 2017 Edition
Annex II
4.11 Record of Tests on Fireman's Lift
Lift No.
Manufacturer
Speed (m/s)
Floor served to to to
Annex II FS_TCP
Page 199 of 222 2017 Edition
Annex II
4.11.2 Records
Items tested/
checked by
FS Contractor
When Fireman's Switch ON
e) Alarm? *Yes/No/N.A.
f) Intercom? *Yes/No/N.A.
4.11.2.5 When lift NOT at main floor and stopping at other floor with
door OPEN :
Annex II FS_TCP
Page 200 of 222 2017 Edition
Annex II
Items tested/
checked by
FS Contractor
c) Lift returns to main floor ? *Yes/No/N.A.
4.11.2.6 When lift NOT at main floor and stopping at other floor with
door CLOSE :
e) Door is totally closed with car call button or door close button *Yes/No/N.A.
pressed continuously otherwise door opened ?
g) Lift stops at nearest car call and all other car calls cancelled ? *Yes/No/N.A.
c) Door remains fully opened and car call can be registered again ? *Yes/No/N.A.
Remark:
Annex II FS_TCP
Page 201 of 222 2017 Edition
Annex II
4.12 Record of Tests on Emergency Lighting & Exit Signs
Exit Sign
Directional Sign
Annex II FS_TCP
Page 202 of 222 2017 Edition
Annex II
4.12.2 Record of Test
Floor 2
Floor 3
Floor 4
Floor 5
Floor 6
Floor 7
Floor 8
Floor 9
Floor 10
Annex II FS_TCP
Page 203 of 222 2017 Edition
Annex II
4.12.2.2 Exit Signs
Type (self-
Test
contained/battery Operating
facilities
Location kit/central battery Number hours Voltage Current cd/m2
checked
system, battery (if tested)
(Yes/No)
type, etc.)
Floor 1
Floor 2
Floor 3
Floor 4
Floor 5
Floor 6
Floor 7
Floor 8
Floor 9
Floor 10
Remark:
Annex II FS_TCP
Page 204 of 222 2017 Edition
Annex II
4.13 Record of Tests on Ventilation and Air-conditioning (VAC) Control System
Operate
MVAC Manual
Ref. No. Shut down system override Other
Method of Fire signal
and type of by smoke unable to switch to shut MVAC
Tripping registered in
MVAC detector restart while off the MVAC system
off FS Panel
system and type fire signal system and interlocked
exists test on ‘FAIL
SAFE’
Remark:
Annex II FS_TCP
Page 205 of 222 2017 Edition
Annex II
4.14 Record of Tests on Pressurisation of Staircases System
*Contract/Sub-contract/Quotation No. :
Date of Test :
Date of calibration :
Annex II FS_TCP
Page 206 of 222 2017 Edition
Annex II
4.14.2 Records
Remarks :
(i) Take at least 10 measurements, uniformly distributed over the doorway for accurate air velocity
measurement.
Annex II FS_TCP
Page 207 of 222 2017 Edition
Annex II
Table 2 Record of Door Opening Force and Pressure Differential Measurement
Notes :
(i) For Class A System
(a) Measure the differential pressure across a closed door between the pressurised stair and the
lobby/corridor, the pressure difference shall be ≧50 Pa ± 10%.
(ii) For Class B System
(a) Measure the differential pressure across lift well and accommodation area with all doors
closed, the pressure difference shall be ≧50 Pa ± 10%.
(b) Measure the differential pressure across stairway and accommodation area with all doors
closed, the pressure difference shall be ≧50 Pa ± 10%.
(c) Measure the differential pressure across closed doors between each lobby and accommodation
area with all doors closed, the pressure difference shall be ≧45 Pa ± 10%.
(iii) All measurements shall be made when all doors to the lift, stair and lobby and the final exit doors
are closed and the air release path from the accommodation area is open.
Annex II FS_TCP
Page 208 of 222 2017 Edition
Annex II
4.15 Record of Tests on Smoke Extraction System
*Contract/Sub-contract/Quotation No. :
Date of Test :
Date of calibration :
Annex II FS_TCP
Page 209 of 222 2017 Edition
Annex II
4.15.2 On-Site Inspection Data
Yes No Remark
Annex II FS_TCP
Page 210 of 222 2017 Edition
Annex II
4.15.3 Records
Remarks :
Annex II FS_TCP
Page 211 of 222 2017 Edition
Annex II
Table 2 Record of Dynamic Smoke Extraction System(s)
Remarks :
Annex II FS_TCP
Page 212 of 222 2017 Edition
Annex II
4.16 Record of Hot Smoke Test
*Contract/Sub-contract/Quotation No. :
Date of Test :
Thermometer :
Others :
Compartment volume : m3
Headroom height : m
Annex II FS_TCP
Page 213 of 222 2017 Edition
Annex II
4.16.2 System Design Assumption
Yes No Remark
Annex II FS_TCP
Page 214 of 222 2017 Edition
Annex II
4.16.4 Records
T1 T2 T3 T4 T5 T6 T7 T8 T9 T10
Annex II FS_TCP
Page 215 of 222 2017 Edition
Annex II
4.17 Record of Inspection and Witness of Tests on Works installed by Others
The following fire service installations by others, related fire service installations and related fire service
provisions are inspected and the final tests are witnessed (G.S. Clause A3.4, B12.7 and D4.10) :
Note: The inspection and witness of final tests on works by others shall only be made on items and
aspects related to and required in FSDCoP and for fire service inspection by Fire Services
Department.
Remark:
Annex II FS_TCP
Page 216 of 222 2017 Edition
Annex II
4.18 Record of Factory/Off-Site Test Certificates
This is to certify that the following fire service installation *has/have been tested in factory/off-site with
the following test certificates and factory test certificates (G.S. Clause D1.8, B4.13, B5.8, etc.) :
Remark:
Annex II FS_TCP
Page 217 of 222 2017 Edition
Annex II
4.19 Test Equipment
Remark:
Annex II FS_TCP
Page 218 of 222 2017 Edition
Annex II
Item tested/
checked by
FS Contractor
Does the calibration requirements for test instruments used for *Yes/No/N.A.
testing/measuring comply with FSD Circular Letter No. 1/2016 and all
subsequent amendments and subsequent issued FSD Circular related to this
subject? .
Annex II FS_TCP
Page 219 of 222 2017 Edition
Annex II
4.20 Documents required in Specification
Item tested/
checked by
FS Contractor
4.20.1 Recommended spare parts and special tools lists with prices. *Yes/No/N.A.
(3 sets) (G.S. Clause A4.4.4 and B13.2)
4.20.7 Key data summary sheet (3 sets). (G.S. Clause A4.4.4) *Yes/No/N.A.
4.20.8 *Form 501 /Fire certificate or FSD acceptance memo /Form *Yes/No/N.A.
WR1-a or equivalent by electrical workers /Certificates on
heavy load support and pressurised equipment /Certificates on
gas cylinder /Submissions for Form 314, Form 251, D.G.
store, PPE licence, restaurant licence, etc. /Batch approval
certificate for fire extinguishers /Performance based fire
engineering reports and certificates of designer and
independent checker /Certification by Ventilation Contractor
/Other certificates and licences to be included as record.
(G.S. Clause A4.4.4)
Annex II FS_TCP
Page 220 of 222 2017 Edition
Annex II
4.21 Equipment Schedule of Approved and Installed Equipment
(*The equipment schedule shall include all equipment items of the installation. Catalogues and approval
certificate/factory certificate shall be provided and attached)
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Remark:
Annex II FS_TCP
Page 221 of 222 2017 Edition
Annex II
4.22 Record of Certification on Design by FS Contractor
*Contractor/Sub-contractor : _____________________________________________________
I certify that the following Fire Service Installations as specified in the Contract/Sub-
*contract/Quotation have been designed in accordance with relevant standards, guidelines,
codes of practice, statutory regulations, and good trade practice to meet with the functional,
performance, operation and maintenance requirements and in accordance with the
Specifications and the contract requirements. I certify that the Fire Service Installations have
been checked and tested satisfactorily to comply with the design:
1. _________________________________________________
2. _________________________________________________
3. _________________________________________________
4. _________________________________________________
5. _________________________________________________
Note: 1. This certificate must be signed by the person responsible for the design and authorised by the
Firm/Company.
2. The person authorised by the Firm/Company shall possess the relevant qualifications required
by the Particular Specification and the General Specification
Annex II FS_TCP
Page 222 of 222 2017 Edition