UK Reliability Assurance Activity UK-DefStan00-43-1
UK Reliability Assurance Activity UK-DefStan00-43-1
Defence Standard
Revision Note
Historical Record
1
DEF STAN 00-43 (PART 1)/1
CONTENTS PAGE
Preface 1
2
DEF STAN 00-43 (PART 1)/1
3
DEF STAN 00-43 (PART 1)/1
4
DEF STAN 00-43 (PART 1)/1
3.1 (Contd)
Def Stan 00-40 (Contd)
Part 2 (ARMP-2): General Application Guidance on the Use of
Part 1 (ARMP-1)
Part 6 (ARMP-6): In-Service R&M
Def Stan 00-41 Reliability and Maintainability
MOD Practices and Procedures
Def Stan 00-44 Reliability and Maintainability
Data Collection and Classification
Part 1: Maintenance Data and Defect Reporting in The
Royal Navy, The Army and The Royal Air Force
Part 2: Data Classification and Incident Sentencing -
General
3.2 The Services and MOD(PE) have additional related Standards or guidance
documents, at a more detailed level, for the preparation of specifications,
plans and directives, as follows:
(a) Naval Engineering Standard (NES) 1016 - Requirement for the In-Service
Collection and Analysis of ARM Trial Data for Naval Systems.
(b) Army HQ DGEME Standard Operating Procedures (SOP) Number 3210 - Formal
Assessment of Equipment Reliability in Service.
(c) MGO Instruction 3.21 - The Achievement of Reliability and
Maintainability.
3.3 Reference in this Part of the Standard to any related document means
in any invitation to tender or contract the edition and all amendments
current at the date of such tender or contract unless a specific edition is
indicated.
DOCUMENT SOURCE
5
DEF STAN 00-43 (PART 1)/1
3.3 (Contd)
DOCUMENT SOURCE
4 Definitions
4.1 For the purpose of this Defence Standard the definitions given in the
text and in Def Stan 00-40 (Part 1) (ARMP-1) apply, together with the
following:
4.1.1 In-Service Reliability Demonstration (ISRD). An ISRD is the
demonstration of the reliability achievement using production standard
equipment under agreed in-Service environmental, operational, usage and
support conditions.
NOTE: Production standard equipment is taken to include equipment of
uniform build standard or having differences in build standard which are
agreed not to affect the R&M characteristics of the equipment or system
being demonstrated.
4.1.2 Fault, failure, defect. It is acknowledged that each of the
Services uses the terms "fault", "failure" and "defect" in different ways.
For the purposes of this document "fault", meaning the condition, is used
to encompass the other terms. It is essential that an actual ISRD uses the
terms defined in the contract specification.
6
DEF STAN 00-43 (PART 1)/1
7
DEF STAN 00-43 (PART 1)/1
6.4 (Contd)
equipment until achievement of the contractual reliability requirements
have been verified under Service conditions. Nevertheless, passing the
ISRD shall not be regarded as diminishing the legal rights of the MOD if
the quipment subsequently proves to be unreliable.
6.5 An ISRD needs to be tailored to meet the requirements and limitations
of each equipment. It will also depend on the ability of the user to
provide the in-Service resources and environment for the demonstration.
For example, an artillery gun would need a special demonstration using
ammunition fired from a sample number of guns over an agreed number of
battlefield days whereas the RAF may be able to demonstrate the achievement
of R&M requirements for an aircraft by recording and monitoring faults over
a large number of routine training sorties. Ships and their weapon systems
may require a combination of the two. This Part of the Defence Standard
identifies the common principles.
6.6 An ISRD is a measurement of achievement and therefore shall not be
considered an extension of reliability growth tests (RGTs) or other such
development activities. The embodiment of modifications during the ISRD,
whilst being beneficial in particular circumstances (see clause 19) poses
difficulties in management and analysis. The aim should be to maintain a
uniform standard of equipment under the demonstration and modifications
should not, in principle, be incorporated during the demonstration period.
6.7 The actions to be taken following demonstration failure and, where
appropriate, the consequences of requirements being surpassed, shall be
clearly stated in the contract. An ISRD will not be effective without such
linkage. Appropriate linking would typically be a continued commitment for
further engineering action by the contractor at his expense to achieve the
required reliability or the withholding of specifically linked interim
payments. Such engineering action might be the investigation of faults,
the design and proving of modifications and their fleet embodiment.
Similarly an additional incentive payment might be made for exceeding
specific levels of reliability if this had been offered and areed as part
of the contract.
6.8 The decision in principle to undertake an ISRD will be made as early
as possible and certainly before issue of the invitation to tender (ITT).
It is essential that all the factors which influence cost and contractual
risk are specified in the ITT and are subsequently made binding in the
contract. Outline details of the ISRD need therefore to be specified in
the ITT. Full details of the ISRD should then be agreed for issue as part
of the contract if it is to provide the required motivation to ensure
achievement of required reliability. A list of the vital actions and
milestones for the preparation of an ISRD is included at annex A, grouped
under activity for the Reliability Panels.
6.9 The cost of mounting the demonstration will often fall to the Service
as well as the MOD(PE) and needs to be funded in a timely fashion. Where
large amounts of consumables such as ordnance, missiles and fuels are
involved, these costs can be considerable.
6.10 Selection of environmental, operational and usage conditions is of
prime importance to the relevance of the ISRD result. They should reflect
those in the specification and should not be exceeded. However, it may not
8
DEF STAN 00-43 (PART 1)/1
6.10 (Contd)
always be possible for the purposes of the ISRD, to generate in-Service
conditions which reflect precisely those stated in the contract. In such
cases it may be necessary to define a series of trials which, collectively,
represent appropriate conditions to the satisfaction of all parties. The
key element is that the ISRD uses production standard equipments operated
by Service personnel after delivery to the Service and under defined
conditions which, within the agreed limitations, most accurately reflect
its specified use.
6.11 The procedures for an ISRD contained in this Defence Standard apply
equally to any demonstration in which it is required to provide evidence of
reliability achievement and to demonstrate reliability on production
equipment outside the controlled environment of the factory or laboratory.
7 Benefits
7.1 Provided that the contract conditions and remedies are clearly
specified, and the required support is provided, an ISRD can offer many
benefits. These include the following.
7.1.1 An ISRD fulfils the requirement of the Project Manager to provide
evidence of achievement relative to the contract requirement. It also
provides the baseline against which the continuing operational capability
can be assessed.
7.1.2 An ISRD extends the contractual influence and provides motivation
for the achievement of reliability throughout development and into
production.
7.1.3 An ISRD provides clear evidence upon which to base contractual
action.
7.1.4 An ISRD provides a clear and early indication of reliability
achievement in the operational environment.
7.1.5 An ISRD provides assurance of the reliability of production standard
equipment.
7.1.6 A successful ISRD will provide the contractor with firm evidence of
the reliability of his equipment which may be beneficial in promoting
further orders from other purchasers.
7.1.7 An ISRD collects high quality in-Service data which can be used to
update the life cycle cost (LCC) estimates and the logistic support
analysis (LSA) work.
8 Constraints
8.1 An ISRD introduces a number of potential constraints. These can be
minimized by careful and early planning to address the following aspects.
8.1.1 An ISRD requires effort in both resources and time from MOD(PE) and
the user; it may also be disruptive to planned tasks, duties and
programmes. In some cases there will be considerable impact on the user’s
resources and it is essential that the user participates at an early stage
of the planning.
9
DEF STAN 00-43 (PART 1)/1
10
DEF STAN 00-43 (PART 1)/1
11
DEF STAN 00-43 (PART 1)/1
10.2.1 (Contd)
to each panel is given at annex A. Such panels will coordinate the
management described within this section and allocated to a particular
organization.
10.2.2 Project Manager (PM). The PM is responsible for overall management
of the ISRD and is responsible for issue of the ISRD directive. The PM
will normally appoint a demonstration coordinator who will be a member of
the reliability panels. The PM will convene a regular review meeting,
perhaps as part of the reliability panel meeting, to monitor progress of
the ISRD.
10.2.3 Demonstration coordinator. The demonstration coordinator is
responsible for liaison with the user and contractor, and for coordination
of all necessary facilities prior to and during the demonstration. He will
be responsible for provision of all MOD manpower and resources to support
the ISRD. He will report to the PM on a regular basis and will refer any
unresolved disputes regarding categorizing (or sentencing) incidents to the
PM. He will coordinate a final report at the end of the demonstration and
submit it to the MOD(PE) PM. The report will be used to determine the
basis of contractual compliance.
12
DEF STAN 00-43 (PART 1)/1
10.3 (Contd)
prime contractor is responsible for providing to the assessment team all
relevant contractor data, including sub-contractor data, relating to the
operating and support of the equipment. The prime contractor will also be
responsible for prompt investigation of all fault arisings as defined by
the maintenance policy (eg fourth line) and any additional policies agreed
for the ISRD.
13
DEF STAN 00-43 (PART 1)/1
14
DEF STAN 00-43 (PART 1)/1
14 (Contd)
the R&M programme and the demonstration plan. The statistical risks shall
be evaluated as part of the demonstration plan and the confidence levels
associated with the particular demonstration established. This subject is
considered further in section six.
15 Corrective Action
15.1 Modifications. During a lengthy ISRD, for example on an aircraft,
there may be a need to incorporate modifications for operational or safety
reasons. The effect of such modifications on the rest of the system need
to be considered and methods agreed to attribute any effects, good or bad,
in the overall results. The consequential effect of such modifications
need also to be considered. Specific modifications to improve reliability
during the ISRD will not normally be allowed since this will complicate the
analysis of the actual reliability levels of the equipment in the delivered
state. The aim of the ISRD is to establish the actual achievement of
reliability, not how much better certain modifications might make such
levels.
15.2 Reliability improvements. Nevertheless for some lengthy ISRDs it
will be likely that reliability improvement modifications will be proposed
and possibly available during the period of the ISRD. Some might be simple
and quick to incorporate. Each should be evaluated and if agreement can be
reached on how the embodiment will affect the analysis and results of the
ISRD then a rapid assessment, approval and embodiment procedure should be
available to incorporate such modifications into the equipments concerned.
Liability for the subsequent embodiment of any reliability modifications
needs to be stated in the specification and contract. Any such
modifications should be subject to an agreed method and period of
validation. Such validation should be based on the maximum evidence
available within the demonstration but, where project constraints apply,
validation might be gained by an extension to the demonstration, based on a
multiple of the previously observed mean time, or cycles or rounds etc,
between faults of the failure mode affected by the modification.
Alternatively, a limited demonstration on the immediately affected system
could be considered at the end of the ISRD. It is advisable that the
effectiveness of proposed modifications should be thoroughly proven by
testing on test-rigs, trials equipment, or by prototypes prior to being
authorized for incorporation with equipment taking part in the ISRD. For
short ISRDs, lasting only weeks or a few months, reliability improvements
cannot be allowed as they would cause considerable complications.
15
DEF STAN 00-43 (PART 1)/1
16
DEF STAN 00-43 (PART 1)/1
19.2 (Contd)
whole system, inevitably to destruction, can be costly and are often
impractical; such tests may not generate sufficient data for reliability
demonstration purposes. Nevertheless, in-Service firing trials do provide
valuable additional data on system integration and overall reliability and,
consequently, data from such trials should be used to the maximum.
19.3 In some cases, where the required environment cannot otherwise be
reproduced, limited use of testing on a specified rig or specialized test
facility may be necessary. However, due consideration needs to be given to
the limitations of such tests and always recognizing that they are only
simulating the conditions and usage expected in-Service. Care should be
taken to ensure that any interface problems are addressed if the test is
being carried out on only part of a weapon system.
17
DEF STAN 00-43 (PART 1)/1
18
DEF STAN 00-43 (PART 1)/1
19
DEF STAN 00-43 (PART 1)/1
26 (Contd)
(c) A fault, which is indicated on several occasions within a single
equipment but has not been isolated or rectified, (eg an intermittent
fault, perhaps transferred between host systems by transfer of the
identified equipment) should neither be discounted nor counted as multiple
faults. The preferred option (except perhaps in the case of software) is
to count the fault as a single attributable "undefined" fault pending
further evidence; only final confirmation and isolation of the fault would
provide the necessary evidence to prove or disprove whether a fault is
attributable.
(d) Software related faults will repeat themselves, whenever identical
circumstances are met, until corrected. Each ISRD must specify whether
repeated identical symptoms, attributed to software, are counted as a
single fault or as multiple faults. The advantage of multiple counting is
that it more closely follows the operational effect; this is the preferred
option.
27 Secondary Failures
The definition of secondary failures (such as the failure of a pump due to
an actuator seal failure) needs to be carefully worded to preclude loose
interpretation. An example definition is:
A secondary failure is an event which is caused directly by a fault in
another component or system and is non-attributable except where in-built
protection or warning devices should have prevented the event.
28 Items Under Test
The exact numbers of equipments under test should be specified together
with any selection criteria or consideration of samples from different
batches. Complications may occur with differing modification or build
standards of particular batches and this may lead to disagreements on
reliability levels between differing batches. Nevertheless, it is
important to demonstrate a representative selection of several batches
accepting any penalty of a longer more drawn out ISRD. The sample size
itself needs to be carefully chosen to ensure that results obtained will be
representative for all the batches. For some equipment, such as those
fitted on board ships, the small in-Service population makes this
difficult. Additionally the point at which the equipments are selected
during the production process will also be important.
29 Timing
The timing of an ISRD affects the contractor’s risk. Where a new equipment
design is subject to an ISRD immediately upon first delivery there is a
significant risk that early production problems and user inexperience will
affect the result. Therefore, it may be appropriate to allow in–Service
operation to stabilize for an agreed period before commencing the ISRD. On
the other hand, delay in commencing the ISRD may reduce the subsequent
opportunity to embody improvements, identified as necessary during the
ISRD, into later production items. Individual projects need to determine
the extent, if any, of such settling-in but this period is to be consistent
with other statements regarding contractual timing of achievement, such as
20
DEF STAN 00-43 (PART 1)/1
29 (Contd)
"reliability shall be achieved at first entry to Service". On the other
hand, to defer final payment for too long may be unacceptable to some
contractors. The procedures to be adopted during any settling-in period
should be declared and should include identification and embodiment of
improvements and modifications. Only when any settling-in period is
concluded will the period of stable configuration (no further
modifications) apply as required at clause 15.
30 Exclusions
Any exclusions need to be defined in the contract but should be kept to an
absolute minimum and will address any artificialities imposed during the
ISRD and any constraints likely to be experienced.
31 Environment
The environment for the ISRD needs to be representative of that which was
specified originally. Consideration needs to be given to how much of the
environment, if any, needs to be simulated and the effect of the simulation
in making the demonstration unrepresentative.
32 Support Equipment
The quantities and standards of all support equipment (eg tools, test
equipment, servicing equipment, handling equipment and technical
documentation, including Government Furnished Equipment (GFE)) needs to be
defined.
33 Adjustments
Some servicing or maintenance activity can be defined as adjustment and the
principles for sentencing incidents involving adjustment, and circumstances
in which they are attributable , needs to be clearly laid down.
34 Scheduled Servicing
Routine scheduled servicing tasks will not be counted but faults found
during these activities, which in all other respects fall within the
attributable criteria, will be counted. Faults which can be attributed to
poor scheduled servicing, or induced by scheduled servicing, will not count
unless attributable to unsatisfactory documentation. The agencies
responsible for routine servicing should be specified in the directive with
any instructions for recording faults or defects found during the
servicing.
35 Special Servicing Instructions or Checks
The application of any special servicing instructions or checks will not be
counted as attributable arisings; however, any fault found during such
inspections will be counted.
21
DEF STAN 00-43 (PART 1)/1
36 Built-In-Test (BIT)
The existence of BIT and its effect on overall reliability should be
specified. The failure of BIT itself may also have a serious and
cumulative effect on reliability and the number of incidents. Furthermore,
the inherent effectiveness of BIT to identify faults is subject to an
overall confidence level and reliability in itself. Suitable provision,
therefore, needs to be made to account for, or to discount, BIT errors and
BIT induced faults.
37 Software
Errors in software can produce equipments or systems that do not work as
they should. Generally, software errors can be rectified so that under
identical conditions they will not reoccur. Nevertheless, for every
software error found there may be others which will not be found due to the
time constraints on sample size. It is policy that software errors are
always counted as faults against the system and will therefore be
attributable in the ISRD until they are corrected. Software errors are
also to be reported separately such that their effect on the reliability of
each system or equipment can be assessed.
38 Fault Tracking
Detailed arrangements need to be made for the repair of faulty items.
Adequate tracking procedures and comprehensive fault reports will be
required. Such reports will be required quickly and special handling
procedures may be needed. It is essential that investigation of faults is
undertaken quickly whether it is by in-Service repair organizations or by
the contractor or sub–contractor.
39 Component Handling
39.1 Components removed for whatever reason, and particularly those
removed as faulty, will need special identification. Equipment labels
overstamped with "Equipment X Reliability Demonstration" will assist with
tracking and identification. The assessment team will have to monitor each
component and agree from the paperwork whether the fault is attributable or
not. Depending on the number of components and the repair agencies
involved it may be practical - for the demonstration only - to have the
faults investigated at a single appropriate repair centre. Consideration
should be given in such circumstances to special handling and monitoring by
MOD(PE)QA staff. The contractor should be entitled to be represented at
any in-Service repair centre; similarly MOD(PE) should be represented at
any contractor’s facility. All evidence of component faults should be
retained until the end of the demonstration and the fulfillment of all
contractual arrangements.
39.2 For ships undergoing ISRDs at sea, investigation of faults by a
repair centre ashore may cause unacceptable delay and such constraints need
to be recognized. However, the advantages of a common standard of
investigation and the ability to have a full investigation ashore, with all
interested parties present, provides the most effective basis for
investigation.
22
DEF STAN 00-43 (PART 1)/1
23
DEF STAN 00-43 (PART 1)/1
24
DEF STAN 00-43 (PART 1)/1
47 (Contd)
For each planned mission, battlefield day or period of operation,
additional information will need to be recorded either by the user or
preferably by the assessment team. For instance, it may be highly relevant
to record data not normally recorded such as weather conditions; recording
of such data should not adversely affect the normal operation by the user.
When faults arise the assessment team will either need to track the
relevant maintenance card, to extract from it further information, or
arrange for the relevant information to be made available or recorded.
Examples of the type of information required to establish comprehensive
records are at annex C.
25
Blank Page
DEF STAN 00-43 (PART 1)/1
ANNEX A
(g) arrange for support services and facilities even though ISRD is years
away;
(h) agree with contracts staff the procedures for ISRD milestone payments
and for withholding payments for any non-achievement;
A-1
DEF STAN 00-43 (PART 1)/1
ANNEX A (Concluded)
A.4 (Contd)
(b) advice on any significant deterioration in R&M performance from the
ISRD baseline, particularly with respect to original specification;
(c) monitoring the effect of modifications on R&M performance.
A-2
DEF STAN 00-43 (PART 1)/1
ANNEX B
B-1
DEF STAN 00-43 (PART 1)/1
ANNEX B (Continued)
IN-SERVICE
EQUIPMENT XX MK 1 RELIABILITY & MAINTAINABILITY
DEMONSTRATION DIRECTIVE
References:
A. ...............................
B. ...............................
INTRODUCTION
1. Reference should be made to any general contract condition such as
part of the contract price being withheld until satisfaction of the ISRD.
References A, B etc will detail the published contract, specification and
Defence Standard 00-43 and each reference should be elaborated in this
paragraph.
2. A short summary should be provided of what reliability requirements
are to be demonstrated and how this will be done.
3. A statement of who will conduct the demonstration and where it will be
held is required together with any general caveats. The designation of the
units involved may be made specifically or generally as "the Demonstration
Unit".
4. A statement should be included to the effect that "the demonstration
shall not, except with agreement of the demonstration unit, cause any
disruption to the fulfilment of peacetime training or maintenance tasks".
The specification of definitions used should be included here by reference
to an Annex.
AIM
5. A clear and concise aim of the directive is given, eg The aim of this
directive is to define and explain the procedures which are to be used for
conducting the equipment XX Mk 1 R&M In-Service Reliability Demonstration.
GENERAL
6. The in-Service achievement will be assessed using data recorded under
normal RAF/Army/RN regulations on Forms . . . . . . (or as otherwise specified),
using approved maintenance procedures, tools and equipment and with the
maintenance undertaken by trained personnel (including civilian tradesmen
employed by the Service, or others as specified, eg suitably qualified
aircrew).
7. The level of reliability to be demonstrated will determine the overall
duration of the demonstration. A settling-in period of XXXX hrs/miles etc
in RAF/Army/RN service will be accumulated, during which time, experience
will be gained in equipment operation and maintenance, before the main
Reliability Demonstration of XXXX hours/miles etc will be commenced.
During the settling-in period training and trial-runs will be undertaken
and demonstration procedures validated.
B-2
DEF STAN 00-43 (PART 1)/1
ANNEX B (Continued)
ADMINISTRATION
8. The constitution of an assessment team will be covered together with
appointment of the Demonstration Coordinator if necessary.
Responsibilities and authority vested in the coordinator and the team
should be briefly covered. A statement of who is responsible for manning
the posts should be stated.
9. The timetable for the demonstration should be expanded together with
arrangements for selection and formation of the team.
10. Any special arrangements for financial support should be identified
together with identification of assistance from in-Service Units and
organizations. Details and arrangements for the provision of particular
administration support should be listed, eg office space, power supplies,
furniture, telephones, fax, typing support, photocopying facilities,
stationery, computer support and consumables, protective clothing,
stopwatches.
11. Further details should be given for each item where necessary. For
example, the computer support should be specified to include suitable
software for sorting the data and presenting reports, ie database,
wordprocessing, spreadsheet, graphics and desk-top publishing.
12. A statement is required to allow the assessment team free access to
all relevant equipment and records in both the Service and, subject to
contract limitations, the contractor and sub-contractor.
13. The Service personnel on the assessment team shall be administratively
controlled by ABC (eg Senior Unit Engineer) and XYZ, (eg Service Equipment
Manager) who will act as the interface between them and the Demonstration
Director or Project Manager.
14. The contractor’s staff on the assessment team shall be
administratively and functionally controlled by the Product Support Manager
of X-Y-Z Company Limited, who will act as the interface between them and
ABC, (para 13).
15. It may be necessary to state that the team shall be fully manned
during and for a particular period after the demonstration. There will be
a need for the preparation of a final report and possibly other
post–demonstration duties.
ASSESSMENT TEAM TASKING
16. The assessment team’s primary task is to plan, monitor and record the
data from the R&M demonstration. In addition, however, the team shall:
a. Provide representation on the MOD Project Panel.
b. Investigate R&M actions arising from entry to service conference.
c. Make recommendations for improvements to maintenance procedures,
publications etc.
B-3
DEF STAN 00-43 (PART 1)/1
ANNEX B (Continued)
27. Any procedures should be stated for dealing with an equipment which
for any reason has to be removed from the demonstration, including
procedures for re–admittance.
28. Procedures for dealing and counting on equipment undergoing periodic
or scheduled maintenance activity until it finishes that period of
maintenance should be specified. Defects or faults found are still to be
counted to the demonstration.
g. System identification.
B-6
DEF STAN 00-43 (PART 1)/1
ANNEX B (Continued)
SENTENCING
57. All faults and defects are to be assessed by the assessment team.
Using the definitions and exclusions given in this Directive together with
any prescribed publications such as JSP . . . . . , the team using its best
judgement will sentence each incident as being "attributable".
"non-attributable" or defer sentencing as "pending further investigation"
or "transferred to deferred log". In long demonstrations, modifications
may have to be allowed in some circumstances and will need information in
the Directive. Faults or defects which are otherwise attributable but have
a modification embodied which is agreed to prevent such faults or defects,
shall be sentenced as "modification discount (non-attributable)".
Sentencing must be a continuous activity. Faults or defects against which
an unproven modification is pending but which are otherwise attributable
will remain so until their effectiveness and integration is confirmed,
agreed and costs of embodiment apportioned. For administrative purposes
they may be grouped together as "attributable modification pending".
58. Where unanimous agreement cannot be reached between assessment team
members, the appropriate details will be considered for arbitration by the
MOD Project Manager and the contractor’s project support manager.
B-7
DEF STAN 00-43 (PART 1)/1
ANNEX B (Continued)
B-8
DEF STAN 00-43 (PART 1)/1
ANNEX B (Continued)
COMPONENT HANDLING
76. Regular Review Meetings shall be held by the MOD(PE) Project Manager
and attended by the assessment team, the host unit, the service equipment
manager, the contractor (and others as specified here). Frequency and
place should be noted together with noting the MOD(PE) Project Manager’s
responsibility to chair and provide a secretary for the meeting.
B-9
DEF STAN 00-43 (PART 1)/1
ANNEX B (Concluded)
77. The Review Meeting will review progress of the demonstration and, in
particular, shall consider any incidents with disputed or unclear
sentencing together with any modification proposals with R&M implications.
REPORTS
78. Regular reports shall be prepared and published by the assessment team
throughout the demonstration and preliminary activities. Frequency and
timing of reports should be specified together with their content. A
listing may be given here of subjects to be covered. For instance:
a. A summary of all incidents giving the sentencing classification
and rectification man–hours.
b. Current values of achieved R&M using the data so far collected and
quoted against the requirement originally specified.
c. Details and proposed solutions to any observed problems.
d. Plan of future activity.
e. Summary of any other team activity.
79. A final report shall be published within (X) months of the end of the
demonstration. The report is submitted and received by the MOD(PE) Project
Manager and the contractor and be used as a basis for agreement of
contractual compliance.
80. The MOD(PE) Project Manager will publish a Demonstration Review,
drawing as necessary on the Final Team Report, the experience of all
participants and any related activities. Strengths and weaknesses will be
covered by way of recommendations to future projects and central staffs.
The review shall have no contractual significance but a timescale for
publication should be noted.
SUMMARY
81. It may be useful to provide a short summary of the most important
points of the arrangements for the demonstration. For example, where, when
and how, and noting the final report which will form the basis for evidence
of contractual compliance. A summary of the likely remedies, in the event
of failing the demonstration, should be included (cross–reference should be
made to the appropriate clause in the contract).
B-10
DEF STAN 00-43 (PART 1)/1
ANNEX C
C-1
DEF STAN 00-43 (PART 1)/1
ANNEX C (Concluded)
C.4 (Contd)
(i) faulty item elapsed time indicator (ETI) reading or usage meter;
C-2
DEF STAN 00-43 (PART 1)/1
The following Defence Standard file reference relates to the work on this
Standard D/D Stan/350/02/12.
Contract Requirements
When Defence Standards are incorporated into contracts users are
responsible for their correct application and for complying with contract
requirements.
Revision of Defence Standards
Defence Standards are revised when necessary by the issue either of
amendments or of revised editions. It is important that users of Defence
Standards should ascertain that they are in possession of the latest
amendments or editions. Information on all Defence Standards is contained
in Def Stan 00-00 (Part 3) Section 4, Index of Standards for Defence
Procurement - Defence Standards Index published annually and supplemented
periodically by Standards in Defence News. Any person who, when-making use
of a Defence Standard encounters an inaccuracy or ambiguity is requested to
notify the Directorate of Standardization without delay in order that the
matter may be investigated and appropriate action taken.
92/60005