Method Statement For General Pre-Casting Works at Pre-Casting YardPart-1
Method Statement For General Pre-Casting Works at Pre-Casting YardPart-1
Where it is identified that there is a need to change the method of work due to unforeseen
circumstances, then revision, authorisation and issue will follow the same procedure as the
original.
1.2 PROJECT DESCRIPTION
Ho Chi Minh City Urban Railway Construction Project – Ben Thanh – Suoi Tien section
(Line 1), contract Package 2 consists of approximately 12 km long of elevated viaduct
structures, erected by span-by-span Method.
All activities related to the construction of reinforced concrete precast segments will be
carried out in the precast yard, located in Road 11, Long Binh Ward, District 9 (HCMC),
covering approximately 40,000 square metres of area, including:
Rebar storage & rebar jigs area (rebar cage fabrication area)
Segment casting area (moulds)
Stores & workshop area
Segment storage area
Site offices & basic facilities for staffs
1.3 SCOPE OF WORK
This procedure is developed for application in the scope of works and applies to the casting
Operations of the Precast segments composing the viaduct superstructure works of the
HCMC Metro Project.
1.4 REFERENCES
This procedure is All reference documents are intended to refer to the last issued revision.
1.5 DEFINITIONS
Method Statement
Identify all hazard & risk per activity, and reduce the probably of each risk by using different
kind of solutions, such as: training for workers to prevent and inform them, inspection,
check-list etc…
The purpose of this procedure is to clearly identify all inspection, check-list and test which
have to be done in order to respect with Quality & Safety requirements.
U-Section
Precast concrete section typically, U-shaped, consisting of a bottom slab, two side webs and
lateral top flanges. It concerns all segment used for this project.
Typical segment
The segments used in the central parts of the spans and between the pier segments. They are
characterized by an almost constant shape.
Pier segment
It defines the first and the last segment of the span, and which are positioned on a pier by
means of bearings.
The segment being cast in the formwork (also called mould). One face is formed using a
fixed bulkhead; the other face is formed using either a Stop-End or the match-cast (M/C)
segment face.
Match-casting means the segment is cast in the formwork between either a Stop-End or a
fixed bulkhead formwork at one end, and a previously fresh cast segment (F/C) at the other
end. Match-casting is accomplished by either the Short Line or Long Line casting method.
Casting segments one at a time in the mould between a fixed bulkhead at one end and a
previously fresh cast segment at the other. The first segment is cast between a fixed bulkhead
and a movable bulkhead, called Stop-End.
Mould which is used to cast typical segment of curved and straight spans, by using the Short
line casting method. For this project, 3 Short Line Typical moulds (SLT#1, SLT#2 & SLT#3)
are provided.
Mould which is used to cast pier segment of straight and curved spans, by using the Short line
casting method. For this project, 4 Short Line Pier moulds (SLP#1, SLP#2, SLP#3 & SLP#4)
are provided.
Mould which is used to cast typical segments of straight spans, by using the Long line casting
method. For this project, 3 Long Line Typical moulds (LLT#1, LLT#2 & LLT#3) are
provided.