Plan For Co-Firing Test: Complete Activity of 100 Hrs. Incorporating Both GE and EPQL Timelines

The document outlines a plan for a 100-hour co-firing test incorporating GE and EPQL timelines. The plan can be divided into three sections: a 37-hour first borescope inspection, 14 hours of co-firing test points runs, and a 49-hour second borescope inspection. Three scenarios are proposed for executing the activity: opportunity-based testing within a plant standby period of 5 days with zero fuel oil, an optimized plan with test points before a scheduled outage, or testing within a scheduled outage with 14 hours for the test energy and zero fuel oil.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views

Plan For Co-Firing Test: Complete Activity of 100 Hrs. Incorporating Both GE and EPQL Timelines

The document outlines a plan for a 100-hour co-firing test incorporating GE and EPQL timelines. The plan can be divided into three sections: a 37-hour first borescope inspection, 14 hours of co-firing test points runs, and a 49-hour second borescope inspection. Three scenarios are proposed for executing the activity: opportunity-based testing within a plant standby period of 5 days with zero fuel oil, an optimized plan with test points before a scheduled outage, or testing within a scheduled outage with 14 hours for the test energy and zero fuel oil.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Plan for Co-Firing Test

Complete activity of 100 hrs. incorporating both GE and EPQL Timelines.


Co-Firing Plan can be clubbed into three sections:
1st Borescope – 37 hrs.
Co-Firing Test Points run – 14 hrs.
2nd Borescope – 49 hrs.

Following scenarios can be followed for executing this activity:

August September
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

If Plant Standby for any 5 days - (Zero FO)


1 - Opportunity Based:

Test Points run before SO start – (37 hrs. FO)


2- Optimized Plan:

Zero FO – (14 hrs. Test Energy)


3- Within Scheduled Outage:

www.engro.com 1
Timeline
Time
GE Parallel Activities
(hrs.)
Fuel change-over
Test Run at part load at Unit Shutdown 1
Test
GT Shutdown 2 Back up as running code & as running
constant.
Cooling time / Turning Gear for handover for BI 16 Compare modified code & as running
1st BI 14 Pressure transmitters calibration /
1st BI
8 verification.
GT Zero Speed / Software download / upload
(in parallel) Downloading updated m6b file.
Turning Gear 4
GT Start-up 1
Ramp machine to 70% load 4 Deploy trends and forcing as per test plan.
Conduct Co-Firing & Mix fuel operation as
Test Points Run
Cofiring test points operation 10 per test plan.
Collect & upload test trends for review.
Shutdown 2
Cooling time / Turning Gear for handover for BI 16
Revert to pre test software, download
2nd BI 14
2nd BI backed up code to the Mark VI panel
TG / Offline water wash 12
Turning Gear 4
GT Start-up 1
www.engro.com 2