Performance Measurment of Ramp Door Manufacturing of M113 Armoured Personel Carrier
Performance Measurment of Ramp Door Manufacturing of M113 Armoured Personel Carrier
Performance Measurement of
Ramp Door
After this outer plate is fitted in fixture and welded. First of all hinges and spacers of
inner plate are welded with outer plate. On the outer plate one seal ledge is fitted. Then
the outer plate is welded with inner plate. After completing welding process the ramp
door is again sent to press machine for pressing. Then it is sent in CRD shop for drilling.
After that different minor assemblies are fitted and it is sent to door matching which is
also completed in this shop.
Parts of internal door also came from CRD shop and welding process starts in FAB shop.
First the inner plate of the door is fitted in fixture with minor assemblies and welding
starts. Then it is sent to pressing machine. Outer plate is fixed and welded on inner plate
after pressing. After door matching inner door is fitted in Ramp door. After pressing it is
sent for hull matching. If hull matching is successfully completed, Different assemblies
are fitted and welded. Finally it is fixed in hull after final inspection. Stage inspection is
also made by expert quality control staff.
Overall Equipment Effectiveness
Item Data
Shift Length 8 hours = 480 min.
Short Breaks 0 @ 0 min. = 0 min.
Meal Break 1 @ 30 min. = 30 min.
Down Time 15 minutes
Ideal Run Rate 0.0013793
In one day 0.6% of a Ramp Door should be completed. So ideal run
rate per minute should be 0.0013793.
Total Pieces 0.5 pieces
Reject Pieces 0.05 pieces
Operating Time
= [Planned Production Time - Down Time]
= [450 minutes – 15 minutes]
= 435 minutes
Good Pieces
= [Total Pieces - Reject Pieces]
10% pieces are rejected
= [0.5 – 0.05]
= 0.45 good pieces
Process Improvement
Firstly ramp door was completed in fabrication shop. Outer portion is first completed
then the internal door is completed. After completing they should be sent to pressing.
Then door matching is carried out. After fitment of internal door in Ramp door it is sent
to assembly shop for hull matching and finally fitted in hull.
Results
In this case study performances as well as quality are at low level as compared to
international OEE factors. Performance is at very low level. During study following
factors were identified to have major drawbacks on performance issues.
High Delay Time: High delay time exists between the requirement and supply of
one shop from other and it is not delivered according to schedule.
Low Labor Productivity: The value adding time of the operators in the assembly
was at an unacceptable level compared to total time.
There are some other minor performance losses in the factory which also be
finished.
The factors which were affecting quality are:-
Unskillful Workers: When a worker is not properly trained to do a specific job and
he is assigned to do it. He will pay his role in declined quality.
Negligence of Workers: When a worker is assigned a task or a wrong job and forced
to do it in time. He will not care for quality. Only right job should be for right person.
Conclusion
In our calculated OEE availability is at a good rate in comparison with world class OEE.
Performance and quality are less then the world class OEE. Need is to improve
performance and quality. No manufacturing organization can afford such a big lose in
quality. Performance is also affected by quality.
Quality can only be improved by strict quality control at each stage. If quality is
controlled the performance can automatically increase. Financial losses also occur due
to declined quality. Also skilled worker should be incorporated to do job. Only right
person should do right job. If a person can’t do a job better he should be assigned
another job. One of the reasons in reduction of quality is to increase availability.
Availability is not a big factor as quality is. When a worker is assigned a task and
imposed to do it in time he will not care for quality.