Rigging and Lifting SOP
Rigging and Lifting SOP
This material, including documentation and any related computer programs, is protected by
copyright controlled by Nokia. All rights are reserved. Copying, including reproducing, storing,
adapting or translating, any or all of this material requires the prior written consent of Nokia.
This material also contains confidential information, which may not be disclosed to others
without the prior written consent of Nokia.
Version, status
Date 2018-12-13
Creator Eadie, Andrew
Owner Davies, Gareth
Function Health, Safety & Environment (HSE)
Approver Eadie, Andrew
Doc ID 44ISPA3ISPS4-1013285096-40296
Doc Location H&S SharePoint
Change History
Table of Contents
1 Introduction ........................................................................................................................... 4
1 Introduction
The SOP is split into sections; each section gives detail on the steps that must be followed for
the weight limits that are specified in the two relevant standards; the Global Rigging & Lifting
Standard and the Working at Height Standard.
Use the sections that are appropriate for the weight of the equipment being lifted onto the
structure in the country, to develop a localized procedure.
The tools to calculate the loads and the steps required to complete the lift are available as
Appendices to the SOP; these tools help ensure that the lift is done in a safe and controlled
manner.
CE0120
Table 1
Fall arrest system will vary for each country; the equipment that is used must be in line with the
specific country’s legislation and the type of structures present on the sites.
Basic Rigging System (3:1 Mechanical Advantage System) (1 – 100Kg Maximum Load)
No. Tool Picture Equipment to be Application
Accessories per certified by relevant
person standards or equivalent
1 Connectors EN362:1992 Personal Used to connect
(Locking protective equipment various rigging/work
karabiners) against falls from at height
height - connectors. components to each
other or to anchor
points.
Table 2
Basic rigging system will vary for each country; the equipment that is used must be in line with the
specific country’s legislation and the type of structures present on site.
13 Universal cross Fit for purpose and safe for Allows the gin pole
over plate use as per engineer’s to be connected to
design and installation the standoff bracket
requirement.
Table 3
Advanced rigging system will vary for each country; the equipment that is used must be in line
with the specific country’s legislation and the type of structures present on the sites.
Please note that NOT ALL components in the above list are required for all lifting methods, they
need to be identified and fit for purpose by way of the lifting plan requirements.
4 Loads up to 6kg
Work at height MUST always be completed with a minimum of a 2-person Team
The individual climbing the structure must always be FASTENED, either by a fixed fall arrest
system or the use of a double lanyard.
A load of up to 6kg can be carried up using any one of the following: -
1. Attached to the person’s harness for lifting and climbing (Fig. 4.0)
2. Carried in a back pack (Fig. 4.1)
3. Attached to a Rope & Lifted up (Fig. 4.2)
It is important that the load is attached in a way that does not catch on the structure being
climbed.
Sequence of work
Lifting Pre-Check:
• Check all documentation and complete the toolbox talk / safety brief.
• Check all equipment are in good condition and properly rated (harness, positioning rope
double lanyard with shock absorber, sling shackle)
• Check each other’s equipment (buddy Check) before anyone climbs
4.0 Attached to the person’s harness for 4.1 Carried in a back pack
lifting and climbing.
DO NOT ALLOW THE ROPE TO BE LEFT SO THAT IT CAN BE DAMAGED OR WALKED ON.
DO NOT CUT THE ROPE FOR LENGTH TO A SPECIFIC JOB.
5.0 Load between 6-20kg must be lifted 5.1 A Lift being done by a 2-person Team where
via 2 men on the ground, one person lifting the flying rope is not required, by using shackle
the load with the 2nd person directing the sling and pulley between the 2 ends of the rope
load from the tower via a flying rope. The the load is keep close to the pulling rope acting as
3rd person is FASTENED on the tower a flying rope as well.
waiting for the load to be lifted to the
designated location.
5.2 An example of the equipment set up at the top of the tower for lifting the weight. The
diagram above reflects the ‘’Backup rope’’ secured via a sling and shackle and the pulling rope
running through a ‘’non-return device’’ combined with a pulley attached to the tower structure
via a sling and shackle.
DO NOT ALLOW THE ROPE TO BE LEFT SO THAT IT CAN BE DAMAGED OR WALKED ON.
DO NOT CUT THE ROPE FOR LENGTH TO A SPECIFIC JOB.
Positioning of Load:
• Ensure that the Setup of the load in the lift point area is in line with pulley system.
• Make sure the load is orientated correctly so it is not lifted upside-down.
• Check all equipment is secured, certified and in the correct position and all ropes are
taut.
6.1 Lifts between 20-50kg – 3 men on 6.2 Note this may be able to be completed with a
the ground are required, 2 men lifting 3-person team if the environment permits this.
the load and the 3rd directing the load
away from the tower via the flying rope.
The 4th person is on the tower waiting
for the load to be lifted to the
designated location for fitting it.
6.3 & 6.4: The drawings show a 2nd pulley with a “Non-return ‘’ device attached to the
bottom tower leg via a sling and shackle, directing the pulling force in line with the tower leg
- reducing the load weight for an easier lift.
Sequence of work
Lifting Pre-Check:
• Check all documentation and complete the toolbox talk / safety brief.
• Check all equipment (harness, positioning rope double lanyard with shock absorber,
sling shackle are in good condition and properly rated.
• Check all equipment has been installed / set up correctly and is secure.
• Check each other’s equipment (buddy Check) before anyone climbs
• Ensure a drop zone is in place.
DO NOT ALLOW THE ROPE TO BE LEFT SO THAT IT CAN BE DAMAGED OR WALKED ON.
DO NOT CUT THE ROPE FOR LENGTH TO A SPECIFIC JOB.
Positioning of Load:
• Ensure that the Setup of the load in the lift point area is in line with pulley system.
• Make sure the load is orientated correctly so it is not lifted upside-down.
• Check all equipment is secured, certified and in the correct position and all ropes are
taut
7.0 The diagrams show a team lifting a load between 7.1 The Load is attached via a sling shackle and
50-100 kg having 2 men on the ground, 1 lifting the pulley to provide a secured and easier lift.
load using a capstan winch with the 2nd person
directing the load from the tower with a flying rope.
The 3rd person is on the tower waiting for the load
to be lifted to the location and for fitting it. Note:
Image doesn’t reflect the number of persons
required for the lift this can range from a 3-person
team or more. This will be dictated by the lift.
Figure 7.2 & 7.3 Gin Pole or Derrick (Lifting Beam) must be set up on the top of the tower to
accommodate the heavier loads to be lifted. The Gin pole must be installed and secured across the
two tower legs and be fitted at the end of it with an eyelet, shackle and pulley for the puling rope.
7.4 & 7.5. The Capstan winch with ‘’non-return device’’ is fitted on the bottom of the tower leg for
directing the pulling force in line with the tower leg. The lift is controlled by the person via a foot
pedal, attached to the Capstan Winch
Sequence of work
Lifting Pre-Check:
• Check all documentation and complete the toolbox talk / safety brief.
• Check all equipment (harness, positioning rope double lanyard with shock absorber,
sling shackle are in good condition and properly rated.
• Check everything has been installed / set up correctly and is secure.
• Check each other’s equipment (buddy Check) before anyone climbs
• Ensure a drop zone is in place.
DO NOT ALLOW THE ROPE TO BE LEFT SO THAT IT CAN BE DAMAGED OR WALKED ON.
DO NOT CUT THE ROPE FOR LENGTH TO A SPECIFIC JOB.
Positioning of Load:
• Ensure that the Setup of the load in the lift point area in line with pulley system.
• Make sure the load is orientated correctly so it is not lifted upside-down.
• Check all equipment is secured, certified and in the correct position and all ropes are
taut.
8.0 The diagrams show the process to be 8.1 With multiple pulleys at the load end, using a
used for lifting a load over 100 kg. 2 men are spreader beam will allow for the pulleys and
on the ground 1 lifting the load via a capstan shackles to avoid clashing with each other and
winch, the 2nd person directing the load from keep the lines clear and not twisted.
the tower via a flying rope. A 3rd person is on
the tower waiting for the load to lifted to the
designated location for fixing it. Note: The
diagram here shows a 3-person team
performing the lifting activities, the number
in the team will be dictated by the lift.
Figure 8.2 & 8.3 The Gin Pole or Derrick (Lifting Beam) is to be set up on the top of the
tower to accommodate heavier loads to be lifted. The Gin pole must be installed and
secured across the two tower legs and be fitted at the end of it with an eyelet, shackle and
pulley for the puling rope.
8.4 and 8.5 A Capstan winch with ‘’non-return device’’ fitted on the bottom of the tower leg
for directing the pulling force in line with the tower leg. The lift is controlled by the person
via a foot pedal.
10 Document Reference
Rigging & Lifting Standard
Lifting Calculator
Equipment List
Equipment Checklist
Completion Checklist