Cem 801 - CONTRACT-QB
Cem 801 - CONTRACT-QB
UNIT 1: BUILDINGS
1. What are the steps involved in analysis of rates for material, labour
and contractor profit.
2. What are the steps involved in analysis of rates different items of
works like (use annexure 2)
a. Earthwork excavation up to 10 m depth and lead up to 50m
b. Cement concrete in foundation and roof slab with 1:2:4
proportion
c. Brickwork for superstructure 1:5 with cement mortar.
d. RCC slabs with 1:2:4
e. Cement plaster 12mm thick and 1:6 cement mortar
f. White washing and painting
g. Wood work in Door and Window frames
3. Calculate the quantities of materials of given items of work
a. Plain cement concrete with 1:5:10 and 1:4:8 proportions
b. Brick work with 1:6 and 1:5 proportions with cement and lime
mortar
c. Plastering and pointing work with cement mortar or proportions
1:3 and 1:2
7.5 m
1m
10 m