Masonry Cost Estimation
Masonry Cost Estimation
MASONRY
2-1 CONCRETE HOLLOW BLOCKS
Concrete Hollow Block Is popularly known as CHB. It is
classified as load bearing and non-bearing blocks. Load bearing
blocks are those whose thickness ranges from 15 to 20 centi ¬
meters and are used to carry load aside from its own weight .
Non-bearing blocks on the other hand, are blocks intended
for walls, partitions, fences, dividers and the like carrying its
own weight whose thickness ranges from 7 to 10 centimeters
<
m
The standard hollow blocks has three void cells and two half
cells at both ends having a total of four. These hollow cells vary
In sizes as there are different manufacturers using different
types of mold. Hence, It is recommended that concrete hollow
blocks with bigger cells be considered in estimating for a more
realistic result.
In this study, what we want to know is the quantity of the ma ¬
41
,,r
« rD ( 0
|F
NSTB
of m« following
SlMP
'wl n*r lly
s
hollow block
bloc** 'lc*lla * "
1
}
5
6
7
concrol* b° * d <° r
SStfgjrss
*", buare
Cement »»l'd >elbare and
Reinforcing *
Tie wire * "„
d »cuss8d !n this
'
iier for th
®
Item 1 to 5 will be
steel bars and Tie
wire
Reinforcement
,
Es,lma l
. for
hirn either of
masonry wor using hollow
the
oriaK
following *
methods
a By Fundamental methods
b. By the Area methods
ILLUSTRATION 2-1
A concrete hollow block wall has a general dimension of
3.00 meters high by 4.00 meters long . Determine the number of
CHB , cement and sand required to construct the wall.
4 oo m.
,
3 00 m.
50 Floor line
Footing line
ELEVATION
CONCRETE HOLLOW BLOCKS WALL
42
MASONRY
Fundamental Method )
SOLUTION - 1 ( By
3.00 = 15 layers
.20
15 x 10 = 150 pieces
WZm
1.00 m.
43
SIMP
ILLUSTRATION 2-2
find the number of 4" x 8" x
20.00 m.
4.00 m
1 ,OOin. 2 60 m .
4.00 m . Gate *
4.00 m .
PLAN ELEVATION
-
FIGURE 2 4 CHB FENCE
4 Multiply 2 and 3:
150 x 13 = 1,950 pieces.
SOLUTION - 2 ( By the Area
Method )
44
1 . Find the area of
A =
the
2.00 xM
wail.
°° m .
« «,»„meters.
MASONRY
Comments
1. Comparing the results obtained by the two methods, the
answers are practically the same, but for convenience,
the solution by the area method is much favored for be¬
ing simple and direct to the answer.
20.00 m. . 20 X . 20 post
2.60
12.00 4.00
X
I
. 40
PUN
60
Section X-X
-
FIGURE 2 6 CHB FENCE
ILLUSTRATION 2-3
-
From Figure 2 5, using class B mixture find the number of:
a) 10 x 20 x 40 cm. concrete hollow blocks
45
ESTIMATE
SIMFtimD CONSTRUCTION
b) Cement and sandposts and footings
for the
c) Concrete
)
SOLUTION - ! ( Finding the CHB
1 Find the perimeter of the wall
P « 20 20 12 8
p « 60 00 meters
by the posts
2 Find the space length occupied
3. Subtract 60 00 m . - 4 00 m.
= 56 00 m. net length for CHB.
5. Multiply by the height of fence to get the Net Area
V » 1$ x 60 \ 60
y 054 CM nv
eom
30
i
o
* to 60
ELEVATION PLAN
V = ( 20 x 20 x 2 60 x 16 ) = 1.67 cu. m.
-
Cement : Z53 x 7.5 = 19.0 bags
Sand 2 53 x .50 = 1.26 cu. m.
Gravel 2.53 x 1.0 = 2.53 cu. m.
•Note:
Concrete was thoroughly discussed in Chapter 1
-
47
SIMPLIFIED CONSTRUCTION ESTIMATE
ILLUSTRATION 2-4
the number of ic
From the following Figure, determinebuilding
x 40 cm. CHB required to construct the firewall. * 0 *
3.00
4.50
B 6.90
5.00
3.00 15 X 20 X 40 CHB Firewall
7.00 1.50
740
ELEVATION
-
FIGURE 2 7 15 CHB FIREWALL
48
MASONRY
1 ,90 = 9.50
.20
Comment:
Take note that in the preceding example solution, fundamen
¬
Reminder
Before estimating the quantity of concrete hollow blocks, be
49
ON ESTATE
SnCPUmDCOS
sure to verify the plan in the proce > - fouSwrvgql * Mue< N
whtch is very
should be grven
important
due
operation
consideration for these might affe,
result of the estimate
as indicated in the plan speCjfu
1 Does the elevation to the second floor |jne Q
floor
height from
from floor
the
to
first
ceiling ? In either J
case , the depth 0 'Sit
in the estimate , either an
beam has to be considered
or subtracted
2. Have you considered the
CHB to be installed from
line? This parr
underground foundation to the floor ar
portion of the wall is often overlook in the ofU'
process
no detailed nig r
fimating especially when there is
cross section detail . Don't ever commit the same mis° *
50
MASGtfRY
ILLUSTRATION 2-5
- -
Continuing the problem of Illustration 2 1 Figure 2 2 , deter¬
mine how many bags of cement and sand needed to install the
150 pieces 10 x 20 x 40 cm . CHB using class B" mortar.
There are three solutions offered in finding the cement mortar
for concrete hollow blocks installation .
1. By volume method .
2. By the Area Method .
3. Per Hundred Block method .
V = 15 layers x. .0048
V = .072 cu. m
This is the total .volume of the mortar in between the 15
layers of concrete hollow blocks.
craw
MfcLOf 4 I » II CHB •
4
* *
WJ
W |
**
M*
- »
**
w 00 * for th* 1 to CHB
1 0
* .
,» x OM * «« »
," ,
• •
,
•
WfWute 0 , #p 2 n< #P 4
5, 1«g l» «W * *
' 0T8
T * VNum « « 522 cu. m
Bags Cement
Mixture
Size of CHB Number Sand
in cm. persq. m A B c D cu. m
53
1
ESTIMATE
CON
SIMPLIFIED STRUCTION SAND PER
Of CEMENT AND
TABLE 2 -3
QUANTITY
HUNDRED BLOCKS
40kg
Ctmffrmt vm iBag *
u r a _
M I xjjll n « m
Sir# of CHB
3 152 2 824 0 34ft
4 176
6 33®
10 x 20 x 4 0 6 072 5 064 0 675
8 104
15 x 20 x 40 12 150
7 504
18 072 12 000 9 000 1 ooo
20 x 20 x 4 0
Comment:
Comparing the answers of
the three methods in finding th
, the results are practically nj
materials for cement mortar choice which method to f
same The estimator now has the know first the kind of Us#
but before using Table 2-2 and 2- m
3,
because this is where mn«
ture and the size of CHB to be used
errors are being committed .
ILLUSTRATION 2-6
Going back to the problem of Illustration 2-2, Figure 2-4 , find
the quantity of hollow blocks, cement and sand , for mortar using
the area method of estimating.
SOLUTION:
1. Find the area of the wall.
Area = Perimeter x Height
A * 60.00 m. x 2.60 m.
A = 156 square meters
:
156 x 12.5 = 1,950 pieces
54
MASONRY
-
3. Find the cement and sand. Refer again to Table 2 2, us¬
ing class B mortar; Multiply:
Take note that the above materials found does not include
the cement, sand and gravel for the footing . For this item , refer
to Chapter 1 where it was thoroughly discussed .
ILLUSTRATION 2-7
Continuing the problem of Illustration 2-1, find the cement
sand necessary to plaster two sides of the 3.00 x 4.00 me¬
ters wall.
55
I
* * Method
1 )
yol#
(
SOLUTION
' i Sid
Find tw two
s ®5 area
of the wall
x 2 sides 4 00
3.C
2« «
24 •"
. plaster is 16 mm ( 016 m.) aver
.
tf *
*
the , **
2
*24 *m
d # me v0 ume of the plaster
v/ninmp
* * ** *
sq . x .016
V*,
. m.
V = 364 cu
j Cement in Bags
Thickness of Plaster
Mixture
Class 8 mm 12 mm 16 mm 20 mm 25 mm
A . 144 .216 288
B
. . 360 450
096 144 . 192 240 . 300
072 108 144 180
n
Sana
1
|
. 060
006
090
012
120 . 150
. 225
. 188
SOLUTION- 2 ( By Area
Method using Table 2-0
1. Find the
area of the wall ( two sides )
Area = 3.00 x
A « 24 sq. 4.00 x 2 sides
m.
56
i
MAHONHV
2
10 mm thick plaster claw *B" mixture , multiply
- *
Solve for the cement and aand Refer to I «Me 2 4 t )r U*i
ILLUSTRATION 2-8
From the following Figure 2-9 , li t down the cement and
*
sand necessary to plaster the two faces of the fence at an av
erage thickness of 20 mm , class "C" mixture
2.70 m. 2.70
*1
15 x 20 x 40 CHB
57
Siw
.
. 1 X < 2„
.
cowl
"' "' 40.00
81
15.00 )
* "
A
A « fl. 08
sq 1-
l ** *.** * *
9.00 - 300
* 00 sq m.
, 297
-
T0 a 88
' and sand. Refer to Table 2-4 . under
4
TJXSSZ* *- * '*"'
; : ss ss «
w 1 An a 55 baas
bags
i 6.1 cu. m.
ILLUSTRATION 2-9
Th» owner of a commercial lot wants to fence the frontage of
h, Jot wTl 5 x 20 x 40 cm. concrete hollow blocks. The fence
is 3.50 rntfera high and 40 meters long provided with a 25 x 25
cm. reinforced concrete posts spaced at 4.00 meters distance
Using class B mixture list down the materials required.
350 m IP
40.00 m.
ELEVATION
.15 .25
I. 1
FIGURE 2-10
SOLUTION
58
MASONRY
Comment:
1. Take note that in finding the wall area, the height should
be measured from the top of the fence down to the
foundation line not just to the floor line only.
2. In the preceding example , two sides of the wall were
considered for plastering. The area occupied by the
posts was subtracted from the gross wall area. For
practical purposes it should not be subt
racted because
by computing back to determine
Its area and the plaster
required is considerably a waste of
time.
59
» r0N ct10N Mm M ,
J1»rurff " *
1
' •firs
CONCRETE HOIXOWBLXKKPOOT| (I
~FiHSrBS
rJS. .
§*' «o »
CHB
QXUSTRATION -
2 10
CorUn -
nQ the problem of Utustration 2 9 , Rgure 2 10 , if the
footing ts 15 centimeters th*dc and 50 centimeters wide,
-
aeterrrune the quantity of cement sand and gravel necessary
jsgyg Class A concrete .
* *
- CMB
15
mm
50
Facing * 37 25 meters lorg
40 00 m
40.00
-- (2.75
25 x 11 posts )
= 37.25 m net length
Volume = 15 x .50 x 37.25 m = 2.79 cu . m.
-
2. Refer to Table 1 2. Using class *A concrete; multiply ;
Cement
Sand
2.79 x 9 0 =
25 bags
2.79 x .50 * 1.4 cu. m.
Gravel 2.79 x 1.0 =
2.8 cu . m.
61
aw""
SIMPLIFIED CONSTRUCTION ESTIMATE
(
.£
Ces rl£d
6
' S7 28 x 038
37 25 x .076
a
M CST
2.83 cu. m .
ILLUSTRATION 2-11
figure, prepare the bill of materials
From the following u<a
class 8' mixture for concrete and mortar. Sma
25.00 M,
. 20
A.
' 0 cm CHB
3.00
.00
. Une
t
SJ00 5.00 5.00 5.00 5.00
. 15
. 40
FIGURE 2-13
SOLUTION
A. Solving for CHB
U£SL«*»>
P a
P a
62
MASONRY
63
SIMPLIFIED CONSTRUCTION ESTIM
wall Is 91.00 meters. Refer to Table 2-5. ys:n
footing class " B" mixture; multiply : 9 a iQ
Mo
Cement : 91.00 x . 300 = 27.3 say ?a K
Sand : 91.00 x .020 = 1.8 say 2 n 9Qs
Gravel : 91.00 x . 040 = 3.64 say 4
Problem Exercise
1. From the following figures, find the following materials re
quired for Its construction.
a) 15 x 20 x 40 cm . concrete.hollow blocks.
b) Cement, and sand for mortar and plastering .
64
i
MASONRY
2.00
3.00
4.00 5.00
4 50
15 x 20 x 40 CHB
Plastered on two sides
3.00
20.00
2.00
3.00
2.00 5.00
ill ..
7.00
:: 8
WM Is
3.00
! : 15 x 2 ) X 40 CHB fl. Ln.
1.00
8.00 m. 5.00 m.
ELEVATION
FIGURE 2-15
65
,, ,', K
SWU«» "
t UCT
* CONCRETE 1
beam block -
rS 'Sr -
determined by direct counting
.
hollow
m estimating the quantity of concrete The blocks , what is
considered is the side portion of the block
used in computing the cement mortar
. thickness is only
for block laying .
li
•9
£05 y
m
*
*" I< ££
14
,# OT
*
19 cm
19 cm
Beam Block
Han Block
14
+
t
19 cm
19 cm
Beam Block
Single End Block
-
FIGURE 1 1« SPECIAL TYPES OF CHB
87
CONSTRUCTIANDON ESTINiAlt
CeNBNT MND . ORAVELp
A**
,4 OUANTITV
40 kg C .
m L!!3
Clai* Mlxtur*
C Sand G
Siz* in
Centim*£3 0067
0720 OOlR
Bl*
Stretcher 20 cm * 0920 0488 0030 0041
0623
VX * *< *
0060
0687
- Bit**
L Corntr cm
2- core 20 .
.
. 0867
. 0590
,
. 0467
.
. 0041 •
0095
0070
2- core 15 cm
Single End Block . 0885 . 0698 . 0063 0090
2- core 20 cm . 0612 0482 . 0044 0075
2- core 15 cm .
.
. 0315 . 0035 0055
. 0420
2- core 10 cm.
Hell Block 0320 0030 0050
20 x 20 cm. . 0400 . ,
SOLUTION
1 rterrwzed the blocks according to its category and indicate
the number of pieces.
2-core 15 cm. Stretcher block 1, 500 pieces
Single end block 100
Hart block 120
-
L Comer Block 200
Beam Block 80
- -
2. Refer to Table 2 6. Under column class "B mixture , multi¬
ply the number of blocks to each corresponding value in
the table to get the cement , sand and gravel required .
-Cement :
e.) 80 Beam Block
80 x .0488 = 3.90 bags
Sand : 80 x .0040 = 0.32 cu m.
Gravel 80 x .0070 = 0.56 cu m.
69
lS
„
1 500
-"
511»»'
-
stretoh
120 W W cK
80 M«n
6 33 cu m *
BLOCKS
and
r
**°
* ,
» the Ma ef1
" .»
,n
** lock
als
100 tingle end block
200 L-corner block
119 bag* cement
9 88 cu m gravel
70
MASONRY
3MEX13
J
C3
SS4
*=
I
SQS> < =3 * 0
3 Q
:®as
ITALIAN S5&
=srt 3 - CD
-Yi
55 x 215 x 125 mm
©©©
BOLIVIAN
©( ©
100 x 180 x 180 mm
0 mm
MM
LUZ 100 x 140 x 240 mm
Q> * p Sog g
UMC=
3D:
rfoa 5
°
Q<7<p I|cy7£l
w goo
CJC>£1
tfotl
go 0 ?aa
100 x 250 x 250 mm
CORINTHIAN
AROMAN
ISSt
WSM100 x 230 x 250 mm
71
Tt.
r. $ r:>7* >
mmi «
f 4# /
H
*** ' w "m
Sii
3 irJMJM , 2® * 25«
QSO
\c7csa gttolyflp y&
OSO !
a«iS S> £ CL 5
JO
'06 » 256 / 230
*
<0
[MJ
salQgi ::
- R*J BC
<M/3 1
&Z
1
<30 I 250 i 2K -r
§
m
&3
Or MMB
BBS
700 * 250 i 25Cmr»
**** ** DECORA
BLOCKS
75
r
MASONRY
45
15
ILLUSTRATION 2-13
SOLUTION
K 8oMn9 for Adobe
Stone Wall
1
74
MASONRY
P
~
45 15 x 15 x 45
Ty
Adobestene x is ¥ Pli45
*1
i5 15
/ 30
1515 Buttresr
W» TUT
Buttress - 150
Ground line
*£)
15 r Pooflrw l
"
45
SECTION
L * 14.10 meters
75
®> w
s
"
-
sMrur
> saassar
4 x 4 footings =
of 2 and 3.
pieces
4. Add the
results
pieces
96 + 16 112
«
Wall Footing
C. solving for
the space occupied by
the fence minus
1. Length offooting
buttress .
m.
15.00 m. ( .45 x 3 ) = 13.65
-
plus the two 1/2 at the sides
3 is the 2 center posts
1
SZXSTZg * * ** *
Cement : 28.20 x .281
Sand : 28.20 x .024
- 8.0 bags
.68 cu. m.
2'
MS:?!?!!! 30 x 45=buttress
multiply
112
ng
pieces stone. Refer
class "B mixture
Soe a *» 4C
0 - I c a* m
Ore ?a» 2 S
* tac '5C 2C
>
~»c aces «C iec 3CC
cvres-t sf 2C -r-
D. SoMng for Cement Piaster
77
SIMPLIFIED CONSTRUCTION ESTIMAT*
pryh| p|Exercise
45
3 50 m
I 15 » 2014S done l
90
SECTION
6 00 8 00
4 00
400 1 «
PUN
rnr-t
;s
MASONRY
For taller walls , two or more rows of weep noles may be pro ¬
pose intend
.60 m.
R»
-
2:40 m. plumb
1:4 Bat!
*
Wfcrt*
1:2 B»W
5C
H »* • CfoundSn,
\
m 1:4 Batter
aH + 0.6 m I IH Minimum )
WALL
FIGURE 2-22 CROSS SECTIION OF RUBBLE RETAINING
80
T MASONRY 4
{Excavation and Placing
The bed for rip-rap is excavated doWn to f . ® re< u re<l depth
,
1
,*
, trimmed and <
and property compacted p rap
laid
foundation isstone below the depth 0 f the
of the same class as Specjf
r
°fi
[
hn9 the toe ?
trench with
Cement in Bags
Stone Grout Mixture Sand
Class A B C cu. m.
Class - A 2.574 1.716 1.287 .143
Class - B 2.448 1.620 1.214 .135
. Class - C 2.232 1.488 1.116 .124
Class - D 1.944 1.296 0.972 .108
ILLUSTRATION 2-14
A stone rip-rap retaining wail 50 meters long as shown in
Figure 2-23 specify the use of Class B stone with class C grout
81
RP
*•*•
si# 11
'
** - - ,«»#* ***4**v** »f«,
'' iS* a'* *' " **
,
/ ' 1
' £
/- » «V*
4/
r
% ***** wfl *r»0
1 *,
SOLUTION riprap
of the proposed
1 Solve for the volume
Volume
-
Width x Height x Length
Vi * 60 x 4 00 m x 50 m *
,
. 120 cu m
» 140 cu m
V2 * ( L4fix 4 00 ) x 50 m.
Total volume
-
-
2 Refer to Table 2 12 Using Class B stone and Class C
grout mixture, multiply
260 cu m
|
82
MASONRY
*,t For 2 layers weep hole , add 25 pieces 3 at 1.00 m .
4
Total: 25 pcs. 3 diameter at 1.50 m. long .
25 pcs. 3" diameter at 1.00 m . long
SOLUTION
1 • Find the volume of stem.
83
1
UKED CONSTRUCTION
LSTIM
V . ( 1S * »
3<
*
4 00 x 50 00 = go
m
30 x . 30 G<
*y pj
Bacwa
fj m 4.00
Stem »T
•
±L * 1.33
3
60 30 x .30 Grave/ FI
"
Heel . 50
150
Of RETAINING WALL
ncUR£ 24t CROSS SECTION
footing .
2. Find the volume of the
V .50 x 1.50 x 50.00 = 37.5 cu. m.
*
3. Total volume of 1 and 2.
V = 90 37.5 = 127.5 cubic meters
1 #f ££i»
; 55 * Wtj ori
'*
«0*
-
nd turraundlngt «,
4 W Mv
* **
ft
(
5#/%
& <
* %
Specifications
TFIC Gabions and Mattresses are available in many sizes
and combinations of wire diameter and mesh size . When order¬
ing TFIC Gabions and Mattresses, specify the following
1. Overall size Length (L) x Breadth (B) x Height (H)
2 m. x 1 m. x 1 m.
4 m. x 1 m. x 1 m.
3 m. x 1 m. x 1 m.
.
2 Wire diameter
Diameter in mm.
20 mm, 2.2 mm or 2.7 mm
3. Mesh size
Width x Length of mesh
10 m x 12 m.
8 m x 10 m.
or
6 m. x 6 m.
36