Inspection and Test Plan: One Sample For Every 100 Cum or Twice Weekly

This document provides an inspection and test plan for quality control of materials used in architectural finishing and public health engineering works for 6 metro stations. It lists the material or test to be conducted, specified limits, code of test procedure, frequency of testing by the contractor, third party, manufacturer and responsibility. Tests include cement compressive strength, fine and coarse aggregate grading, silt content, specific gravity, water absorption and moisture content.

Uploaded by

Abhishek Shetty
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views

Inspection and Test Plan: One Sample For Every 100 Cum or Twice Weekly

This document provides an inspection and test plan for quality control of materials used in architectural finishing and public health engineering works for 6 metro stations. It lists the material or test to be conducted, specified limits, code of test procedure, frequency of testing by the contractor, third party, manufacturer and responsibility. Tests include cement compressive strength, fine and coarse aggregate grading, silt content, specific gravity, water absorption and moisture content.

Uploaded by

Abhishek Shetty
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Quality Management System

STAR WORTH INFRASTRUCTURE & CONSTRUCTION LTD


Quality Inspection Test Format
PROJECT: Architectural Finishing Works & Public Health Engineering Works For 6 No’s stations in Reach 2 Extension (R2A & R2B) of
East-West Corridor for Bangalore Metro Rail Project, Phase-2
INSPECTION AND TEST PLAN

FIELD LABORATORY THIRD PARTY MANUFACTURER RESPONSIBILITY


Code of Test DOCUMENT
Sl. No Material/ Test to be conducted SPECIFIED LIMITS Format No REMARKS
Procedure/Spec Starworth Starwoth REFERENCE
Frequency of Test Frequency of Test Frequency of Test BMRCL
Execution QA/QC
A CEMENT (OPC) R W W
I PHYSICAL ANALYSIS
1 VISUAL INSPECTION
2 DRY SIEVE THRO 90 MICRON
IS 4031/IS 12269/ IS
3 INITIAL SETTING TIME 30 mins (Min) One sample of
1489
1000 MT of each brand /
IS 4031/IS 12269/ IS MTC/BATCH
4 FINAL SETTING TIME 600 mins ( Max) Any change in the brand of
1489
the cement
IS 4031/IS 1489 For PPC (33 grade) : 16/22/33 at 3/7/28 days
5 COMPRESSIVE STRENGTH AT 3, 7 & 28 DAYS
IS 4031/IS 12269 For 53 grade: 27/37/53 Mpa at 3/7/28 days
IS 4032/IS 12269/ IS
II CHEMICAL ANALYSIS As per IS 12269/IS 8112
1489

B FINE AGGREGATE R W W
1 INCOMING MATERIALS TEST PHYSICALLY, VISUAL AS PER LAB WP 001 DAILY EACH TRIP

Once Source (At the time


of Approval) OR Once in a
One Sample for Every 100
2 SIEVE ANALYSIS - GRADING IS 2386/ IS 383 As per IS 383 table-2 year. If any change in the
Cum or Twice weekly
source of the supply
material, to be tested.

Only Manufactured Sand


(M.Sand). No
SILT CONTENT - WET SIEVE THRO 75 MICRON OR
3 IS 2386/ IS 383 3% max River Sand or Any other
VOLUME
sand.

4 SPECIFIC GRAVITY IS 2386/ IS 383


NA
5 WATER ABSORPTION IS 2386/ IS 383 NA ONCE IN A MONTH
6 MOISTURE CONTENT IRC/36/IS 2386 NA DAILY

C COARSE AGGREGATE R W W
INCOMING MATERIALS TEST PHYSICALLY, VISUAL
1 AS PER LAB WP 001 As per IS 383 table-2 DAILY EACH TRIP
FOR SIZE AND SHAPE
Once in Source (At the time
of Approval) or Once
One Sample for Every 100 in a year. If any
2 SIEVE ANALYSIS - GRADING IS 2386/ IS 383 3% max
Cum or Twice weekly change in the source of
supply material, to be
tested.
Only Manufactured Sand
3 SILT CONTENT - WET SIEVE IS 2386/ IS 383 (M.Sand). No
NA
River Sand or Any other
ELR to be submitted during
source change/ source
4 FLAKINESS INDEX IS 2386/ IS 383 NA approval to PL

ONCE IN A MONTH
Once in Source (At the time
5 ELONGATION INDEX IS 2386/ IS 383 NA of Approval) OR
(Once in a year). If any
change in the source of
6 AGGREGATE IMPACT VALUE IS 2386/ IS 383 supply material to be
Max 30% (Wearing surface); Max 45% (for non-wearing surface) tested.
7 AGGREGATE CRUSHING VALUE IS 2386/ IS 383
Max 30% (Wearing surface); Max 45% (for non-wearing surface)
Once in Source (At the time
of Approval) OR
(Once in a year). If any
change in the source of
supply material to be
tested.

8 LOS ANGELE'S ABRASION VALUE IS 2386/ IS 383


Max 30% (Wearing surface); Max 50% (for non-wearing surface)
9 SPECIFIC GRAVITY IS 2386/ IS 383 NA
10 WATER ABSORPTION IS 2386/ IS 383 ONCE IN A MONTH
NA
11 MOISTURE CONTENT IRC/36/IS 2386 NA DAILY
Once in Source (At the time
12 PETROGRAPHIC ANALYSIS IS 2386/ IS 383
of Approval)
13 ALL IN AGGREGATE SIEVE ANALYSIS TIP NO 7/IS 383 As per IS 383 table-2 WEEKLY

D WATER R W W
1 EACH TRIP
VISUAL INSPECTION
Once in 1 year or Any
2 CHEMICAL ANALYSIS
IS 3025/IS 456 As per IS 456 Source / supply changes

E FRESH CONCRETE R W W
EVERY GRADE Once at starting of
1 FRESH CONCRETE (SLUMP) IS 1199
pour and at the time of sampling
6 cubes (set/grade/for addition
2 CUBE PREPARATION (150X150X150)mm IS 1199
every 50cum 1 set)

F HARDENED CONCRETE R W W
3 CUBES OF EACH SET FOR 7
1 COMPRESSIVE STRENGTH IS 516/ IS 456
DAYS & 28 DAYS

G STEEL REINFORCEMENTS R W W
I Fe 500 steel bars Grade as per IS 1786, Approved drawings
1 Diameter As per approved drawing
2 Unit weight plus/ minus 8%
3 Ultimate tensile stress IS 1608 Min 545 N/mm2 One Sample for 100 MT of
2
4 0.2% proof stress IS 1608 Min 500 N/mm each diameter from each
MTC / Lot
5 % elongation IS 1608 12% on gauge length of 5mm dia supplier
o
No fracture when cold bent to 45 degree 7 bent back by 22.5
6 Rebend test IS 1599
around mandrel of min.(7 dia)
7 Chemical composition IS 2062 Carbon content (max) : 0.3 % max
II On Field R W W
1 Shape and size
2 Diameter As per approved
As per approved drawing For Every Activity
3 Spacing drawing
4 Cover

H CEMENT CONCRETE SOLID BLOCK R W W


1 Water Absorption IS:2185 As per Standard Once in Source (At the time
2 Compressive Strength IS:2185 5n/mm2 of Approval)
3 Dry Density IS:2185 As per Standard

On Field R W W
1 As per Approved
Setting Out & Completed Block Work inspection Each Location
Drawing & Checklist

I AAC BLOCKS
1 Water Absorption IS:2185 As per Standard Once in Source (At the time R W W
2 Compressive Strength IS:2185 3n/mm2 of Approval)
3 Dry Density IS:2185 As per Standard

On Field R W W
1 As per Approved
Each Location
Setting Out & Completed Block Work inspection Drawing & Checklist

J PERFORATED CLAY BRICKS R W W


1 Water Absorption IS 3952-2013 15% Once in Source (At the time
2 Compressive Strength IS 3952-2013 3.5n/mm2 of Approval)
3 Dry Density IS 3952-2013 not less than 700-800 kg/m3

On Field As per Approved R W W


Each Location
1 Setting Out & Completed Block Work inspection Drawing & Checklist
K Hollow Metal Door R W W
1 Once in Source (At the time
MTC / Lot
Stalibility ,Integrity, Insulation, Fire rtaed BS-476 Part-22 & As per NFPA 80 & NFPA-252, UL 10B & UL10C of Approval)
IS:3614 Part-11
On Field As per Approved R W W
Each Location
1 Setting Out & Door Installation Drawing & Checklist

L Aluminium Door & Windows R W W


1 Once in Source (At the time
MTC / Lot
Coating Thickness, Tensile, Chemical IS:6012, IS:11035 As per Cleint Requirement & Specification of Approval)

On Field R W W
Each Location
1 installation

M Stainless Steel (Grade-304) R W W


1 Once in Source (At the time
MTC / Lot
Tensile, Chemical IS:9879 & IS:1608 As per Cleint Requirement & Specification of Approval)

On Field R W W
Each Location
1 installation

N Waterproofing R W W
1
MTC / Lot
As per manufacture Recommnedation IS:2645 As per Cleint Requirement & Specification

On Field R W W
Each Location
1 installation & Water leak test

O Ceramic & Vitrified Tiles R W W


1 Dimension , Straightness, Rectangularity, Once in Source (At the time
Warpage, Deviation in Center curvature, Edge IS:13630,Part-2, Part- MTC / Lot
As per Cleint Requirement & Specification & IS:15622 of Approval)
Curvature, Water Absorption, Modulus of 6
Rupture, Breaking Strength
On Field R W W
Each Location
1 Settingout & Installation

P Granite R W W
1 Once in Source (At the time
IS:1121, IS:1122, MTC / Lot
Dimension ,Water absorption, Breaking Strength. As per Cleint Requirement & Specification of Approval)
IS:1124

On Field R W W
Each Location
1 Settingout & Installation

Q Pavers & Kerbstone R W W


1 Once in Source (At the time
Dimension , Water Absorption, Compressive MTC / Lot
IS:15658 & IS:5758 As per Cleint Requirement & Specification of Approval)
Strength

On Field R W W
Each Location
1 Settingout & Installation

R Painting R W W
1 Volume of solids, Volatile matter, PH value,
MTC / Lot
Drying time, Accelerated Storage stability, IS:101 & IS:15489 As per Cleint Requirement & Specification
Consitency
On Field R W W
1 Surface preparation, 1st Coat, Second coat Each Location
inspection

S Pluming Works R W W
1
MTC / Lot
As per Client Requirement As per Cleint Requirement & Specification

On Field R W W
Each Location
1 Installation

NOTE:
P- PERFORM W- WITNESSED FLR- FIELD LABORATORY REPORT