0% found this document useful (0 votes)
98 views

Homework/Assignment: Full Name of Submitter: Vo Thi Thien My Student ID: IEIEIU18057

The document describes a group assignment on cellular manufacturing. The group is asked to design assembly lines to meet production demands for four products (A, B, C, D) over a year. They are given information on the operating time and monthly demand for each product. The group analyzes Product C in detail since it has the longest operating time. They calculate key metrics like takt time, number of operators and workstations needed, workstation cycle time, and total line capacity. If demand increases 20%, they determine an additional 6 operators would be needed per cell.

Uploaded by

Trân Lê
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
98 views

Homework/Assignment: Full Name of Submitter: Vo Thi Thien My Student ID: IEIEIU18057

The document describes a group assignment on cellular manufacturing. The group is asked to design assembly lines to meet production demands for four products (A, B, C, D) over a year. They are given information on the operating time and monthly demand for each product. The group analyzes Product C in detail since it has the longest operating time. They calculate key metrics like takt time, number of operators and workstations needed, workstation cycle time, and total line capacity. If demand increases 20%, they determine an additional 6 operators would be needed per cell.

Uploaded by

Trân Lê
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Homework/Assignment 6

(Cellular Manufacturing)
Full Name of submitter: Vo Thi Thien My Student ID: IEIEIU18057
Your Group number is:
 Võ Thị Thiện Mỹ - IEIEIU18057
 Nguyễn Hoàng Anh Khôi – IEIEIU18044
 Phạm Ngọc Thu Uyên – IEIEIU18114
 Nguyễn Huỳnh Ngọc Quế - IEIEIU18073
 Trần Anh Thư – IEIEIU18160
 Lê Phương Ngọc Anh – IEIEIU18004
 Trần Thị Ngọc Vy – IEIEIU18119

Title of your Group project is: Present lecture 9: How Toyota shortened production lead time

1. For the following figures


Forecast

Operati
Produc Fe Ma Ap Ma Ju J Au Se
ng time Jan Oct Nov Dec
ts b r r y n ul g p
(s)

17(*
A 90 17 17 17 17 17 17 17 17 17 17 17
)
B 60 30 30 30 30 30 30 30 30 30 30 30 30
C 120 40 40 40 40 40 40 40 40 40 40 40 40
D 210 20 20 20 20 20 20 20 20 20 20 20 20
(*): in thousands
a) Design assembly line(s) based on the following inputs.
- The line also can meet demand as demand goes up by 30%
- To avoid ergonomics issues related to repetitiveness, minimum cycle time of a workstation is not lower
than 15 seconds.
- Working time: 304 working days per year, 7 hours per shift, and 2 shifts per day.

1
Hints
- Select a representative product.
- Design assembly lines which meet demand and use minimum resources. Fill in the below table (please show
your work as well).

1 Takt rate (required pieces per hr)  

2 Takt time (sec)  

3 Total number of operators required  

4 Total number of workstations required  

5 Number of workstations per cell  

6 Number of cells  

7 Number of operators per cell  

8 Cycle time per workstation (sec)  

9 Cycle time per operator (sec)  

10 Capacity per cell per hour (pcs/hr)  

11 Total capacity (pcs/hr)

b) If forecast increases by 20%, how many extra operators required per cell?

2. Given this precedence diagram:


Takt time = 12 min

Activity Duration (min)

A 4

B (after A) 5

C (after B) 2

2
D (after A) 10

E (after D&C) 3

Design a line with the fewest number of workstations, highest efficiency

Note:
- Continue using this form to complete your works and submit on Blackboard
- Name your file
o If you submit individually: 21Lean_HW6_StudentID_FullName
o If you submit for a group (Group # are as per the number you have registered as guided in the
file “Semester Project Requirement” and be finalized by lecturer):21 Lean_HW6_G#
- Due Date is defined in detail at each “ASSIGNMENT INFORMATION” from Blackboard
- Maximum score of late submission is two third of “Point Possible”
- If you can’t submit on Blackboard: Email your work to TA, copy it to your Lecturer, attached also the
screenshot of your Blackboard showing error in that transaction
---------

Answers/Works
Question 1
a)
Operating
Products Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
time (hrs)
A 0.0250 17000 17000 17000 17000 17000 17000 17000 17000 17000 17000 17000 17000
B 0.0167 30000 30000 30000 30000 30000 30000 30000 30000 30000 30000 30000 30000
C 0.0333 40000 40000 40000 40000 40000 40000 40000 40000 40000 40000 40000 40000
D 0.0583 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000
(*): in thousands

3
total demand
Running time of
Products of each
each product
product

A 204000 5100
elasticity 0.3

B 360000 6000 minimum cycle


15 seconds
time

C 480000 16000 Total yearly


4256 hours
available time (hr)

D 240000 14000 Total demand 1284000 units

As the running time of product C is the largest, C is the representative product. The following calculation is
done as below:

Takt rate (required 1284000/4256 = 302 pieces per


1 total demand/total yearly available time
pieces per hr) hour

2 Takt time (sec) (total yearly available time/total demand) 4256/1284000 = 11.933 seconds

Total number of 0.033/11.933 = 10.06 => 11


3 operating time of C/ takt time (hr)
operators required operators

Total number of 11*(1+0.3) = 14.3 => 15


4 total number of operators x (1+elasticity)
workstations required workstations

Number of operating time of C/minimum cycle time 0.033/(15/3600) = 8


5
workstations per cell of a workstation workstations per cell

number of workstations/number of
6 Number of cells 15/8 = 2 cells
workstation per cell
Number of operators 11/2 = 5.5 => 6 operators per
7 total number of operators/number of cells
per cell cell
Cycle time per operating time/revised number of
8 0.0333*3600/8 = 15 seconds
workstation (sec) workstations per cell
Cycle time per operating time / revised number of
9 0.0333*3600/6 = 20 seconds
operator (sec) operators per cell

4
Capacity per cell per
10 3600/cycle time per operator 3600/20 = 180 pcs per hour
hour (pcs/hr)

Total capacity Capacity per cell per hour x number of


11 180*2 = 360 pieces per hour
(pcs/hr) cells

Real elasticity = Number of workstations per cell/ Number of operators per cell = 8/5 = 1.6
b)

total demand of Running time


Products
each product of each product
elasticity 0.3
A 244800 6120
minimum cycle 15 seconds
B 432000 7200
Total yearly
4256 hours
available time (hr)
C 576000 19200
D 288000 16800 Total demand 1540800 units

Based on the running time of each product, we still choose C as the representative product as C has the highest
running time. Thus, changes in calculation are presented as follow:

Takt rate (required 1540800/4256 = 362.03


1 total demand/total yearly available time
pieces per hr) pieces per hr
4256*3600/1540800 =
2 Takt time (sec) (total yearly available time/total demand)
9.94 seconds

Total number of 0.033/9.94 = 12.07 => 13


3 operating time of C/takt time (hr)
operators required operators

Total number of 13*(1+0.3) = 16.9 => 17


4 total number of operatorsx(1+elasticity)
workstations required workstations

Number of operating time of C/minimum cycle time of a 0.0333*3600/15 = 8


5
workstations per cell workstation workstations per cell
number of workstations/number of
6 Number of cells 17/8 = 2.125 => 2 cells
workstation per cell
Number of operators 13/2 = 6.5 => 7 operators
7 total number of operators/number of cells
per cell per cell
s

5
Hence, the extra operators per cell is 6 – 7 = 1 operator per cell.

Quesion 2: Given this precedence diagram:


Takt time = 12 min

Activity Duration (min)

A 4

B (after A) 5

C (after B) 2

D (after A) 10

E (after D&C) 3

Design a line with the fewest number of workstations, highest efficiency

AON diagram for this process:

5 2

B C
3
4
A, E
4
10

Takt time (desired cycle time) Cd = Ca = 12 minutes.


Flow time = 4 + 5 + 2 + 10 + 3 = 24 minutes
Theoretical minimum number of workstations is calculated by the equation:
j

∑ t i = 4+ 5+2+10+3 = 2 workstations. Thus, we need at least 2 workstations for this process.


N= i=1 12
cd

6
We group activities into 2 workstations as following to minimize the number of workstations and
maximize efficiency:

2
C
5
A4 B
,4 3
E

10
D

Workstation 1 Workstation 2
A, B, E  C, D
12 min 12 min
 Cycle time = 12 min
The efficiency of the line is calculated by the equation:
j

∑ t i = 4+ 5+2+10+3 = 100%
E= i=1 2∗12
Nca

You might also like