Lecture Notes: Irrigation and Hydraulic Structures
Lecture Notes: Irrigation and Hydraulic Structures
Semester:6th, B.Tech.
Department: Civil Engineering
Teacher Incharge: Prof. M A Lone
CHAPTER-4
Diversion Headworks
1.1 Definition
A structure constructed at the junction of the source (river, dam, canal) and the off taking canal.
diverts the required supply from the source channel to the off taking channel
water level in the source channel raised to the reqd. level
reduces the need of excavation in the head reach
command area is served better by flow irrigation
should be capable of regulating the supplies into the off taking channel; all supplies when
demand is keen & supplies are less
control sediment entry
weir (barrage) - minimum length for economy, uniform flow for proper functioning
under sluices - presence of deep channel to ensure adequate supply to the off-taking canal
canal alignment - capable of serving its command area without much excavation
sediment – off taking channel sited on the downstream end of the outer side of the bend
1.7.1 Weir
masonry floor with a masonry crest on top of which shutters for ponding
shutters dropped during floods to reduce afflux
stability of crest examined for water level upto the top of shutter with no flow d/s when
shutters dropped and water is on both sides of the crest
simplest but requires large qty. of stones for constn. & maintenance
afflux
pond level
min. waterway
weir crest level
generally coincides with the lowest cold weather level of the river bed at the weir site
at least 1.2 m (2 m if sediment Excluder is provided) below that of the head regulator so
that the sediment deposited u/s of the regulator does not enter the off taking canal. If
needed, the crest level of the regulator is raised.
Discharge capacity of the undersluices is maximum of the following:
Loosenes factor:
Pond level:
water level which must be maintained in the under sluice pocket (i.e. u/s of the canal head
regulator) so as to maintain FSL in the canal when full supply discharge is fed into it
Retrogression:
d/s of weir due to degradation; d/s HFL lowered; exit gradient increases during high
floods : 0.3 to 0.5 m due to large qty. of sediment; during low floods : 1.25 to 2.25m
due to relatively clear water for design flood retrogression is assumed 0.3 to 0.5 m
d/s TEL = u/s TEL - head loss ( = afflux + retrogression )
Vertical cutoffs
q calculated taking into account the concentration factor by which q is to be multiplied to take
into account the non-uniformity of flow along the waterway during the operation of weir bays
The scour depth R (for regime conditions) increased further as follows:
in the form of concrete blocks and loose stones for protection against scour
u/s: concrete blocks of size 1500x1500x900 mm laid over loose stones for a distance
equal to depth of scour below the floor level
d/s: concrete blocks on inverted filter; space between blocks filled with gravel;
length is 1.5 times the scour depth below the floor level.
for the boulder reach the size of blocks will be increased
Inverted filter in two or more layers
toe wall of masonry/concrete at the end of the filter to a depth of about 500mm
launching aprons beyond block protection on u/s & d/s ; stones larger than 300mm
undersluices gates are kept partially open while canal is taking its supplies
results in continuous flushing of sediment
requires surplus water
the two streams - to river & to canal generates turbulence, bring sediment into suspension
and may enter canal; not suitable except during floods when water is surplus
3. Wedge-flow method:
When the stream carries high sediment load, close the canal itself
Barrage regulation methods have their limitations requiring either closure of canal or
surplus water. Therefore, sediment excluder/ejector and stilling basins are constructed.
Sediment excluders/ejectors take advantage of the fact that the bed load part of the
transported sediment in a stream moves near bed and the suspended load part is
distributed non-uniformly in the vertical with heavier concentrations near the bed.
Settling basins reduce the sediment transport capacity of the canal flow by enlarging the
flow cross-section over the length of the basin. The deposited sediment is suitably
removed.
curative measure; removes excess sediment load that has entered the canal
constructed in canal d/s of the canal head regulator
taking advantage of the concentration distribution, the near-bed water layers ejected
not too near the regulator - residual turbulence keeps the sediment in suspension
not too far from regulator - sediment deposits d/s of regulator and reduces canal capacity
reach up to the ejector to be wide to carry extra discharge for ejector
ejector spans the entire width of the canal ; divided into tunnels which, in turn, are
subdivided with gradually converging turning vanes to accelerate the escaping flow
main components - diaphragm, tunnels, control structure and an outfall channel
diaphragm so shaped as to cause least disturbance to sediment concentration u/s of it
diaphragm level = f(sediment size to be ejected, size of tunnels and u/s & d/s canal
levels)
lower side of u/s end of diaphragm is bell-mouthed/or made elliptical
escaping discharge - generally 10 to 20 per cent of full supply discharge
tunnel dimensions - resulting velocity is adequate to carry the sediment of desired size
about 20-25% depth of flow in the canal
tunnels further converged to increase the velocity further by 10-15%; range 2.5 - 6m/s
depth of tunnels; 1.8 - 2.2 m to facilitate inspection and repair
ejector discharge is controlled by regulator gates(near the outfall)
outflow led to natural drainage through outfall channel design to have self-cleansing
velocity
sufficient drop between FSL of the outfall channel and HFL of the drainage
proposed design model-tested
IU and ID are sediment concentration in the canal u/s and d/s of the ejector.
Settling Basin:
removal of sediment from flowing canal by reducing flow velocity through a long
expansion
reduces velocity, shear, turbulence which stops sediment movement and also deposition
of suspended sediment
material from the bed of the basin suitably removed and disposed of
Garde, Ranga Raju and Sujudi method for design of settling basin:
qsi & qse are amounts of sediment of a given size entering and leaving the basin
Guide banks to narrow down & restrict the course of the river so that it flows centrally
Approach embankments aligned with the weir axis and extend up to a point beyond the
range of the anticipated meander loop
Afflux embankments - earthen embankments extending from both approach
embankments connected to the u/s ground above the affluxed highest flood level
Spurs
Launching apron, Stone pitching etc.