Commentary On Qualification Procedures: SSPC: The Society For Protective Coatings
Commentary On Qualification Procedures: SSPC: The Society For Protective Coatings
November 1, 2004
8-1
SSPC-QP COM
November 1, 2004
QP 2 is the basis for the QP 2 certification program, 2.4 SSPC-QP 4, “STANDARD PROCEDURE FOR
developed as a supplement to the QP 1 program in 1993 as EVALUATING THE QUALIFICATIONS OF CONTRACTORS
part of PCCP’s first expansion. As with QP 1, the consensus DISTURBING HAZARDOUS PAINT DURING DEMOLITION
qualification procedure formed the basis of an administrative AND REPAIR WORK”: SSPC-QP 4, developed by SSPC
program to evaluate whether a contractor, that met the require- technical committees C 5.3.B Removal of Hazardous Coatings
ments of QP 1, also had the capability to effectively manage the and C.3.5 on Applicator Prequalification, was issued by SSPC in
removal of hazardous (e.g. lead based) paints from industrial 1997. It is similar to QP 1, QP 2 and QP 3 in that it establishes
steel and marine structures. a consensus procedure to evaluate the capability of a general
QP 2 establishes several categories of qualification contractor to invoke appropriate worker and environmental
based on the contractor’s capability to remove, contain, and protection programs while disturbing hazardous (e.g. lead
properly handle and store hazardous paint debris. In addi- based) paint incidental to demolition or repair work.
tion to meeting the requirements of QP 1, five more function QP 4 is intended to evaluate contractors who are not paint-
areas of the contractor’s quality system are evaluated. They ing contractors but who disturb hazardous paint in conjunction
include: management of hazardous paint removal operations; with non-painting work such as bridge demolition or structural
technical capabilities; qualifications of competent persons; repair. A painting contractor certified to QP 2 also meets the
and site-specific safety, health and environmental compliance requirements of QP 4 and thus is also capable of performing
criteria as they relate to hazardous paint removal operations. such demolition and repair work.
QP 2 defines two categories of qualification, A and B, which QP 4 differs from QP 1, 2 and 3 in one important aspect:
are based on the use of negative air pressure in containment SSPC does not offer an administrative certification program to
structures. evaluate general contractors against the requirements of QP
As with QP 1, contractors seeking QP 2 certification 4. This is primarily because SSPC does not normally provide
must provide a series of submittals to SSPC for review and services to repair and structural demolition contractors who
acceptance and also undergo an audit at one of their active tend to belong to other trade or professional associations that
hazardous paint removel job sites. QP 2 is intended to be represent their interests.
used side by side with QP 1 to evaluate painting contractors The impetus for QP 4 came from bridge maintenance
who must remove hazardous paint in conjunction with surface authorities who asked SSPC to develop a procedure for such
preparation and maintenance repainting operations. work which they could then invoke in their contracts for repair
and demolition work. This would ensure that the repair con-
2.3. SSPC-QP 3, “STANDARD PROCEDURE FOR tractor was capable of implementing the same worker and
EVALUATING THE QUALIFICATIONS OF SHOP PAINTING environmental protection programs on site as the painting
CONTRACTORS”: QP 3 was developed by the SSPC techni- contractors are required to do under QP 2.
cal committee on Shop Coating Qualification and published in
1995. QP 3 defines a procedure for evaluating shop painting 2.5 SSPC-QP 6, “STANDARD PROCEDURE FOR
organizations (e.g. shipyard paint departments, structural EVALUATING THE QUALIFICATIONS OF CONTRACTORS
steel and miscellaneous metal parts fabrication shops; blast WHO APPLY THERMAL SPRAY COATINGS (METALLIZING)
and paint shops) that apply industrial protective coatings in a for CORROSION PROTECTION OF STEEL AND CONCRETE
permanent, stationary facility or shop. The requirements for QP STRUCTURES”: SSPC QP 6 was developed by technical
3 are similar to those for QP 1, except that QP 3 requirements committees C.3.5 on Applicator Prequalification and C.1.6.B
are applicable to shop coating operations. on Thermal Spray Coatings and issued in August 2004. Un-
SSPC also set up an administrative program in 1996 to less otherwise specified, QP 1 certification for field surface
evaluate shops against the requirements of QP 3. Facility preparation and coating application or QP 3 for shop surface
owners and others who contract for shop painting services preparation and coating application are required to supplement
use this program to evaluate the capabilities of the paint shop. the requirements of QP 6.. The QP 6 requirements are similar
QP 3 establishes several qualification categories based on the to QP 1 and QP 3 except that they define a quality system for
degree to which the shop can isolate coating operations from the thermal spray metallizing specialty process.
outdoor weather conditions and control ambient conditions. SSPC is introducing an administrative program in 2005 to
SSPC revised its QP 3 procedure and administrative cer- evaluate contractors and shops against the QP 6 standard.
tification program in 1999 to coordinate its program with that QP 6 defines two qualification categories, one for steel,
of the American Institute of Steel Construction (AISC) which and one for concrete. A contractor may be qualified for steel,
certifies structural steel fabrication shops that apply protective concrete, or both steel and concrete.
coatings in the shop after fabrication of new structural steel.
The AISC Sophisticated Paint Endorsement (SPE) program is 2.6 SSPC-QP 8, “STANDARD PROCEDURE FOR
recognized by SSPC as an equivalent to SSPC’s QP 3 program, EVALUATING THE QUALIFICATIONS OF CONTRACTING
with the exception of safety, health, and environmental compli- FIRMS THAT INSTALL POLYMER COATINGS OR SUR-
ance. AISC does not require evaluation of health, safety and FACINGS ON CONCRETE AND OTHER CEMENTITIOUS
environmental compliance in its SPE certfication program. SURFACES”: The QP 8 qualification procedure, issued in
July 2003, was developed by SSPC technical committee C.3.5
8-2
SSPC-QP COM
November 1, 2004
8-3