Al Qooz Contracting LLC: Hazard Identification and Risk Assesment

The document identifies hazards and risks associated with backfilling work at a proposed factory site. It lists heat stress as a potential hazard, noting workers could be exposed to hot and humid conditions. It recommends various controls to mitigate the risk of heat stress, such as providing water, rest areas, and adjusting work hours.

Uploaded by

شاز إياس
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views

Al Qooz Contracting LLC: Hazard Identification and Risk Assesment

The document identifies hazards and risks associated with backfilling work at a proposed factory site. It lists heat stress as a potential hazard, noting workers could be exposed to hot and humid conditions. It recommends various controls to mitigate the risk of heat stress, such as providing water, rest areas, and adjusting work hours.

Uploaded by

شاز إياس
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

AL QOOZ CONTRACTING LLC

HAZARD IDENTIFICATION AND RISK ASSESMENT DATE


page 4
PAGE

TASK/JOB/OPERATION: BACK FILLING


PROJECT : PROPOSED FACTORY AND FACILITIES ON PLOT NO:KHIA5-14A_B
CREW/SUBCONTRACTORS:

DATE: Date next Review :


Recommended PPE: Hard hat,Safety shoes,Safety Harness overalls,Dust mask,Goggles,Gloves
EQUIPMENT REQUIRED: Excavator,shovel,skid steer loader(bobcat)

Legal compliance
harm/consequ
Risks Who

Control E/I/R
/Activities
Job steps

might be
/potential
identified

Hazards

Remarks
Risk Rating/Risk
Hazard

ences
Sl no

Mitigation action to be taken/Hazard/risk Residual Risk


level Control METHOD

L S R L S R
Tool box talks to be given before commencing the
activity,proper access shall be provide at required
location,,all personnel to HSE induction training from
safety department before entering the site,to ensure
proper use of PPE during entire work,Heat stress
Personal injury awareness campaign/tool box talk should be carried
Working in hot,humid
4 Heat stress property damage,loss No 3 5 High R out prior to start the work,Provide sufficient quantity 3 3 Med
environment of drinking water,juice and rest area,Allow the work
of life,deadth
force to have rest on frequent basis those who are
working direct exposure to sun,working hours to be
followed as per the UAE labour lae,Nearest assembly
point to be noted in advance and workers instructed
at TBT

1-Improbable 1-Negligible Likelihood X


Review by Main -Contractor Approved by Consultant
Severity

2-Remote 2-Minor Severity E -Eliminate


Control
Likely

Risk

3-Occassional 3-Reportable High 15-25 I- Isolate


COENGR Engineering
4-Probable 4-serious Medium 7-12 R-Reduce Al Qooz Contracting LLC
Consultancy
5-Frequent 5-Catastrophic Low 1-6