Petroleum Production Technology Chapter 1
Petroleum Production Technology Chapter 1
1
INTRODUCTION
• Maximise the integrity and reliability of the completion over the envisaged life
of the completed well
• Minimise the total costs per unit volume of fluid produced or injected, i.e.
minimise the total costs of initial completion, maintaining production and
remedial measures
• Other criteria e.g. control sand production depending upon the particular reservoir
characteristics or development constraints.
The completion design involves four principal decision areas, that together provide
a conceptual design (Figure 1):
This conceptual design process is initiated on the basis of data from exploration wells.
Considerable uncertainty may exist as to the validity and accuracy of that data. Thus
a number of alternative designs for well completions will normally be selected and
contingency designs may be developed. The detailed design evaluation and costing
of the selected completion concept will then be undertaken to:
It is essential that an interactive approach is adopted at both the conceptual and detailed
design stages. This is necessary due to the diversity of design data, e.g. reservoir
rock and fluid properties, production constraints, etc. and the range of disciplines
which have inputs into the decision making process, e.g. drilling engineers, reservoir
engineers and production technologists.
Final Design(s)
Well Integrity is the process that sets the Standards and Policies which the completed
well should adhere to. The well should not only be constructed, but also operated and
maintained to these (company) standards and policies. These standards and policies
may be generally applicable, but may also be tailored according to the nature of the
field and the operating environment.
Sub Surface Safety Valve • Inability to isolate well Well safety and loss
failure • Inability to land flow of flow
control devices
The three alternative approaches for the completion of the reservoir zones are:
OPEN HOLE
Open hole completions can only be applied in consolidated formations as the borehole
may become unstable once a drawdown in applied to induce the well to flow. In
such cases either total collapse of the formation or the production of sand may occur.
6
Conventional Completions
1
The above characteristics of open hole completions explains why they are used in:
This system is also used in high angle angle wells to prevent major borehole collapse
or facilitate the passage of logging tools.
This technique shares the inability for zonal control of production or injection with
open hole completion. It may also only effectively control sand production over a
limited range of conditions. However, it is a (relatively) low cost technique. Use
of conventional sand screens restricts the technique's application to reservoir rock
CEMENTED AND
PERFORATED
LINER OR CASING
This type of completion involves considerably greater costs and time than the previous
options. The cost of a full length of casing from the surface to the base of the well
can be considerable, to which must be added the cost of perforating, cementing and
the additional rig time. The use of a liner helps to reduce the required length (and
cost) of casing. However the ability to control the depletion of individual zones,
isolate the inflow of undesirable produced fluids and control the injection of fluids
into zones are essential to a large number of developments. This has resulted in the
cemented and perforated liner or casing being the most widely applied bottom hole
completion technique.
8
Conventional Completions
1
2. SELECTION OF THE FLOW CONDUIT BETWEEN THE RESERVOIR
AND SURFACE
There are a number of options for fluid flow to surface in a production well, or to the
formation in an injection well. Considerations which may influence the choice include
cost, flow stability, ability to control flow and ensuring well safety and integrity of
the well by minimising corrosion or erosion.
TUBING COMPLETION
TUBINGLESS WITHOUT PACKER TUBING COMPLETION
COMPLETION (with optional WITH ANNULUS PACKER
annulus production)
This completion is rarely used due to these drawbacks. The tubingless completion, a
variant of this approach, is sometimes applied to multiple zones. Here the borehole
is drilled passed all the zones and individual tubing strings located opposite each
zone. The entire borehole is then cemented and each tubing string perforated with
orientated guns (see Figure 25). This is a simple a multi-zone completions but its
design precludes workovers if problems subsequently arise.
10
Conventional Completions
1
2.4 Tubing Flow with Annular Isolation
An open annulus can cause complications, as discussed in 2.3 above. Therefore, the
annulus is normally isolated by the installation of a packer and the produced fluid
flows to the surface via the tubing. The packer has a rubber element which, when
compressed or inflated, will expand to fill the annulus between the tubing and the
casing. The packer is normally located as close to the top of the reservoir as possible
to minimise the trapped annular volume beneath the packer. Hence the volume of gas
which can accumulate there is minimised; simplifying downhole pressure management
when the packer is released by the drilling rig during recovery operations. However,
packer installation removes the ability to U-tube or circulate kill fluid between the
tubing and annulus. The circulation capability can be restored via tubing accessory,
such as a sliding side door which allows annulus communication. Alternatively one can
perforate the tubing, which would need replacement prior to the recommencementing
production. In both cases, the circulation point is normally as deep in the well as
possible, but above the packer.
This completion system is by far the most widely used and offers maximum well
security and control.
There are many capabilities which can be included in the string design. Some of these
capabilities are essential, such as those providing operational security or safety, whilst
others provide improved performance or flexibility. However, an increased degree
of flexibility provided by the completion normally results in a complex completion
design with a large number of components. Such inbuilt complexity compromises the
reliability of the completion string. The design process should thus initially identify
the minimum functional requirements. Any additional options are then assessed on
the basis of incremental complexity versus incremental benefit.
The following (see also Figure 6) are considered to be the essential for the majority
of completion string installations to allow the well to be produced in a safe and
controlled manner:
(a) The ability to contain the expected flowing pressureas as well as the highest
hydraulic pressure which may be employed in well operations. Fluid should flow
to surface (production) or the reservoir (injection wells) with minimal flowing
pressure loss and optimal flow stability.
(c) The ability to affect downhole shut-in either by remote control or by automatically
activated by the changing well flowing conditions.
(d) A means to establish circulation between the annulus and the tubing.
(e) The ability to block the tubing by the installation of a plug. This allows pressure
testing of the tubing etc.
Surface Isolation
(wellhead / Xmas tree)
Circulation between
Annulus & Tubing (SSD)
The above allows the completion string to produce in a safe, controllable manner.
Consider each of the functions in turn:
Thus, both the casing and tubing should be designed to withstand the maximum
pressure expected in the wellbore. The production casing, packer and wellhead act
as a backup to contain fluids and pressures in the event of a tubing peak. Similarly,
the wellhead, from which each casing string is suspended will be rated for maximum
anticipated surface pressures. Overall control of fluid production from, or injection
into, the well is provided by the valve system located on top of the wellhead. This
Xmas tree usually comprises an in-line valve with a backup valve to shut in the well
12
Conventional Completions
1
and side outlets with valves for both choke and kill line attachment during well
killing procedures.
Annulus Isolation
Annulus isolation is required in the majority of production wells for reasons of tubing
flow stability and protection of the production casing from corrosion. It is frequently
necessary to isolate the annulus to prevent surface injection pressures being exerted
on the wellhead and possibly giving rise to burst of the production casing. This occurs
in injection wells and during well stimulation operations.
This annular isolation is normally achieved by installing a packer at the bottom of the
completion string which is lowered into the wellbore with an elastomeric element
in the retracted position. At the prescribed depth, the element is set by extrusion or
inflation to fill the annular space between the tubing and the annulus. To minimise
the volume below the packer and the length of casing exposed to well fluids, the
packer is normally set quite deep in the well.
Circulation Capability
One of the major limitations of using a production casing as the flow conduit (i.e.
without a production tubing) is the inability to kill the well by circulation. A coiled
tubing unit or snubbing unit could be used but is unlikely to be available at short notice
to carry out the well killing operation. Hence the majority of completions include
one of the following devices to provide circulation between the annulus and tubing:
They can all be opened when required and subsequently closed. An alternative is to
use a tubing punch or a perforation gun with a low power tubing perforator charge.
However, this is only used prior to a work over since the resulting hole is permanent.
Tubing Isolation
A further means of physical isolation of the reservoir is installed at one or more places
in the tubing. Thus the provision of isolation is deep within the wellbore, either just
above and/or just below the packer. The isolation is normally provided by lowering
a plug on wireline down the inside of the tubing string until it lands and locks into
a wireline nipple which was incorporated into the design of the tubing string at an
appropriate depth.
These stresses can be avoided by installing a moving seal system which allows expansion
and/or contraction of the tubing without mechanical failure or disengagement from
the packer or seal bore. Various systems are available. They all feature a concentric
sleeve approach where seals are located in a concentric annulus, one surface of which
moves while the other is stationary.
Another example is gas lift installations where gas a injected into the produced fluids
to lighten the hydrostatic head and maintain production at economic levels.
14
Conventional Completions
1
Artificial Lift
The selection of an electrical or hydraulically powered downhole pumping system or
of gas lift will require the inclusion of the pump or of multiple side pocket mandrels
in the completion string design. Important design issues will be:
• Installation depth of the side pocket mandrels for unloading and producing the well.
Safety Isolation
(SC) S.S.S.V.
Downhole
SLIDING SIDE
Tubing / Annulus
DOOR
Circulation
Accomodate
SEAL ASSEMBLY
Tubing Stress
Annular
PACKER
Isolation
Tubing
NIPPLE
Isolation
PERFORATED Alternative
JOINT Entry for Flow
Landing T and P
NIPPLE
Guages
W.E.G. Wireline
Re-Entry
The detailed design of the completion string involves the selection and specification
of all its component parts. There are many potential components available, each one
has numerous variants and each equipment supplier has their own particular designs.
In practice most companies use one supplier or have considerable experience with
specific types of components. Also, the equipment is specified as a certain size and
with a certain type of threaded coupling. Hence tubing completion equipment is of
necessity fairly standard and comparable between the different suppliers.
Equipment selection should be done on the basis that the component will provide a
specific facility necessary for the successful performance and operation of the well
under a range of operating scenarios. Each component adds undesirable complexity
to the completion. This must be compensated for by the fact that it is necessary or
provides desirable flexibility. One approach to discussing whether a particular
well completion is "fit-for-purpose" is to evaluate the facilities that each component
provides. The design is thus justified on a “needs” basis and the benefits of flexibility
can be assessed against the drawback of incremental complexity.
Each component in Figure 6 will now be discussed below in relation to its purpose
in production operations. It should be remembered at all times that the purpose of
well design is to minimise the wells "total life time cost" (i.e. the sum of the well
construction capital costs and the subsequent operating costs. Thus a range of reservoir
depletion scenarios should be considered during the above evaluation.
• Hydraulic access to the annuli between casing to allow cement placement and
between the production casing and tubing for well circulation
The Xmas tree valve provide flow control of the fluids produced from or injected
into the well. The Xmas tree is normally installed on the wellhead after installation
of the production tubing has been completed. The wellhead provides the facility for
all the casing strings and the production tubing are suspended from the well head
which is itself supported by the conductor, the foundation of the well. There are a
number of basic Xmas tree designs e.g. Figure 8. It has two wing valve outlets, one
for production and the other for injection, e.g. well killing. Additionally, the third
outlet (swab value) provides vertical access into the tubing for insertion of wireline
or coiled tubing tools into the well. The lower valve is the master valve. It controls
all hydraulic and mechanical access to the well. Well safety may require it to be
duplicated. All outlets have valves which may be manually operated or are remotely
controlled valves operated from a control room.
16
Conventional Completions
1
GAUGE VALVE
TOP CONNECTION
XMAS TREE
SWAB VALVE
FLOW FITTING
CHOKE
WING VALVE
MASTER VALVE
TUBING
CASING HANGER
WELLHEAD
CASING HAED
INNER CASING
INTERMEDIATE CASING
SEALING MEDIUM
CASING HANGER
CASING HEAD
OUTER CASING
Figure 8 Simple wellhead assembly including casing spools and Christmas tree.
(1) The inside diameter of the tubing must provide a produced fluid velocity to
minimise the total pressure loss (the tubing performance relationship).
(2) The tensile strength of the string (both tubing and coupling) must be high enough
to allow suspension of the complete string without tensile failure.
(3) The completion string must be able to withstand the maximum conceivable
internal (or burst) pressure.
(4) The completion string must be able to withstand the maximum concievable
external differential pressures between the annulus and the tubing (the collapse
pressure).
(5) The tubing must be resistant to chemical corrosion which may arise because of
fluid contact in the wellbore, and might ultimately accelerate string failure by
one of the loads and stresses mentioned above (2)-(4).
There are several standard grades of steel; H-40, J-55, C-75, L-80, N-80 and P-105.
The numbers after the letter grading signify the minimum yield strength in units of
a thousand psi. The letter grades indicate the manufacturing process or subsequent
treatment of the steel to modify its properties, e.g. the C and L grades are heat treated
to remove martensitic steels. In general, the higher the yield strength created by
working the steel, the more susceptible it is to embrittlement and failure by H2S.
The minimum yield strength defines the minimum tensile strength in psi. The tensile
load is carried by the plain end area or wall section area of the pipe, hence the weight/
foot of the pipe also affects the tensile load. The joints nearest surface are under the
greatest tensile load due to weight of the suspended pipe since each joint suspends
the joint immediately beneath it.
The threaded coupling has to provide two basic functions; firstly to transmit tensile
load up the tubing string and secondly to produce a connection which provides a seal
to retain internal pressure within the tubing.
The design of a completion string to withstand a given tensile load will obviously be
dependent upon the depth to which the completion string will be run but the following
aspects will also be considered.
(a) The minimum tensile strength of the pipe utilised for the design will be based
upon the manufacturers data or other specification. It will be reduced by the
application of a safety factor with a typical value of 1.6 to 2.0.
(b) The tensile load of a suspended string will cause it to become longer leading to
a reduction in the tubing's wall thickness. This will have to be taken into failure
conditions due to high external pressures by derating the nominal collapse resistance.
18
Conventional Completions
1
string is gas filled i.e. the tubing head pressure equals the reservoir pressure minus
the hydrostatic head of gas in the well.
A safety factor which varies from 1.0 to 1.33 is normally used to reduce the tubing
manufactures test data.
The published minimum tubing collapse data are derated by a safety factor of 1.0
to 1.125.
4.2.5 Corrosion
There are two principal types of corrosion encountered in oil and gas production
wells namely:
(1) Acidic Corrosion - due to the presence of carbonic acid (from CO2) dissolved
in the produced water or the organic acid content of the hydrocarbon fluid.
Most corrosion is selective (pitting) rather than an even reduction in wall thickness.
Corrosion inhibitor treatments will assist in minimising corrosion damage but must
be continiously applied. The alternative approach is to select a steel that is naturally
inert to the produced fluids for example, low grade steel is recommended for small H2S
partical pressures since these are less susceptible to embrittlement, e.g. 555 or N-80.
Figure 9 is an example of a completion metallurgy selection chart illustrating how
more complex and expensive alloys are required as the partial pressure of hydrogen
sulphide and carbon dioxide increases. Increasing reservoir temperature will further
complicate the selection process.
(3) Corrosion / erosion is also encountered due to the presence of produced solids
if the well is produced at a too high a flow velocity.
(1) Connections which require internal pressure to produce a pressure tight seal.
This type of coupling includes the API round thread and buttress connection whereby
a thread compound applied to the threads must be compressed by external pressure
acting on the coupling causing it to fill any void spaces within the coupling.
Other specialised couplings, such as resilient seal rings, are also used to provide an
additional seal system.
• An external coupling such as the VAM coupling (Figure 9a) requires that a male
thread be cut on each end of the tubing joints and while the coupling has two
female connection.
• An external coupling has a larger effective wall thickness in the coupling section
(Dc > D) giving it higher load capacity compared to an integral coupling. The
integral coupling (Figure 9b) has a male and female thread cut on opposite ends
of the pipe.
• An external upset coupling uses an increased wall thickness of pipe at one end
of the pipe allowing a female thread to be cut without sacrificing too much of
the tensile load carrying capacity.
• A flush joint is one in which there is a uniform Internal Diameter (d = dc) through
the make up connection (Figure 9a).
1.0E+06
1.0E+03
27 Cr - 31 NI - 3.5 Mo
22 Cr - 42 NI - 3 Mo
1.0E+02
13 Cr
20 Cr - 25 NI - 4 Mo
1.0E+01
1.0E+00
1.0E-02
1.0E-03
1.00E-03 1.00E-02 1.00E-01 1.00E+00 1.00E+01 1.00E+02 1.00E+03 1.00E+04 1.00E+05 1.00E+06
20
Conventional Completions
1
a) b)
D
D d
dc
dc
Dc Dc
The detailed design based upon the three mechanical conditions (tension, burst and
collapse) can be completed once the size is specified. The resulting specification for
the tubing is summarised as:
• Protection of the outer pressure containment system (the production casing and
the wellhead).
The most common method to provide an annular seal is the packer (Figure 10a). The
packer is anchored in position by the pushing the steel teeth of the slips into the casing
wall while the pack-off is accomplished by expanding or extending the elastomer
element outwards from the packer body until it seals against the casing wall (Figure 10b).
a) b)
Slips
Upper
Cone
Cone
Lower Slips
Lower
Slips
The characteristics that determine which type of packer is most appropriate for a
particular application are:
22
Conventional Completions
1
• A Retrievable Packer The packer can be run as an integral part of the tubing
string. It is run to the setting depth where the setting mechanism is actuated.
It can be easily retrieved after installation by pulling tension on the tubing and
shearing a set of (weak) screws. This reverses the setting process.
Packer Retrieval
• A retrievable packer is recovered by pulling tension on the tubing. This tension
shears a series of (weak) brass screws at a predetermined value that depends
on the number and strength of the screws. The packer setting action can now
be reversed. The slips disengage from the casing wall and the sealing element
collapses and the packer is released from the casing wall and can be pulled to
the surface.
• Retrieval of a permanent packer requires milling away the internal sleeve, which
holds the top slips in place. This releases the packer, which is now free and can
be pulled from the well. The milling operation normally takes between 3-6
hours. The mill head is guided onto the packer and maintained in place by a
guide rod, which passes through, the packer bore (Figure 11). The milling tool
is also fitted with a retrieval tool and catch sleeve which collects the remains
of the packer when the milling operation is complete, and the mill retrieved.
Packer
Mill
Catch sleeve prevents
Packer Milling packer falling into well,
Shoe allowing immediate
retrieval
Catch
Sleeve
Figure 11 Packer milling tool illustrating one trip milling and retrieval.
• Hydraulic set utilises hydraulic pressure inside the completion string. The
tubing string must be isolated or plugged below the packer to prevent pressure
being exerted on the formation or the annulus during setting.
• Electrical The packer (plus tailpipe) assembly is lowered into the casing on an
electrical conductor cable. A small explosive charge is detonated at the required
setting depth, actuating the setting mechanism.
• Compression and Tension Set Packers Packers that can withstand pressure
from either direction.
24
Conventional Completions
1
(a) (b) (c)
Locator
• Travel Joint (Figure 12e) This device is very similar to an inverted ELTSR.
A valve to shut off flow is located beneath the wellhead as part of the tubing system.
This Sub-Surface Safety Valve or SSSV is required when the Christmas trees valves
are not operational. These valves are based upon two different control philosophies:
(1) Direct Controlled SSSV which are designed to close when downhole well
conditions of pressure/flowrate vary from preset design values. These valves
are often refered to as "storm chokes".
Both valve systems provide a failsafe shutdown system for remote sub-surface isolation
e.g. in the event of a catastrophic failure of the Xmas tree.
• Tubing retrievable The valve is run as an integral part of the tubing string. It
can only be retrieved by pulling the tubing but the flow path can have the same
diameter as the tubing. A smaller flow diameter wireline retrievable valve can
be installed at the top of the valve. This allows well production to continue,
though possibly at a lower rate, if the tubing retrievable value fails.
• Wireline retrievable The valve nipple is run as an integral part of the tubing
the internal valve assembly being subsequently run and retrieved on wireline
cable. The flow path of the valve will have a smaller area that the production
tubing. It should always be evaluated if this will restrict production at some time
in the wells life. (This is especially important for gas wells).
26
Conventional Completions
1
Pressurised
control line
Landing
nipple
Depressurised
Sheer pin control line
Snap ring
Ball
Spring
Spring extended
compressed
OPEN CLOSED
Pressurised Depressurised
control line control line
Flapper Flapper
open closed
Open Closed
Annular safety values are installed at shallow depth for cases where it is required to
minimise the volume of annular gas released if wellhead assembly is damaged. This
is typically installed in offshore wells where gas lift is installed or where a downhole
packer has not been installed. An example completion is illustrated in Figure 28.
• Gas lift valves are set to open, shut or throttle the gas flow between the annulus
and the tubing at a preset pressure at valve depth. They can either respond to
the pressure of gas injected into the annulus or to the tubing pressure {see also
Chapter 5, (Gas Lift) of the Production Technology module}.
• Circulation of fluids or from the annulus into the tubing is achieved by installing
a valve with a bursting disc which can be sheared. Communication between the
annulus and the tubing can only be stopped by replacing the shear valve by wireline.
The installation and recovery of the valves from the side pocket mandrel is also described
in Chapter 5 (Gas Lift) of the Production Technology module.
(a)
Polish Bore
Valve body
Pocket Assembly
Figure 15a and 15b Side Pocket Mandrel with valve installed.
28
Conventional Completions
1
4.7 Sliding Side Door (SSD)
The sliding side door (Figure 16) permits communication between tubing and annulus.
It consists of two concentric sleeves, containing slots or holes, with elastomeric seals
between them. The inner sleeve can move up or down by wireline or coiled tubing.
This movement aligns the inner and outer openings. Its main application is to provide
access to the upper zones in multizone completions and for placement of fluids in
the tubing or annulus by circulation (often for well killing).
The SSD's design features external ports through the tubing wall within which is
located an inner mandrel with slots and seal rings above or below the slots (Figure
16). When closed, the inner mandrel or sleeve is located such that the ports in the
outer tubing wall are isolated by seals above and below on the inner mandrel (Figure
16b). Movement of the inner sleeve upwards (Figure 16a) allows circulation between
the tubing and annulus by aligning the slots in the inner mandrel with the ports in the
outer tubing. Moving the inner sleeve in the reverse direction returns the circulation
device to its closed position after completion of the circulation operation.
Movement of the inner sleeve requires the running of a shifting tool to open and
close the sleeve. The shifting tool lands in the top or bottom of the inner sleeve and
by jarring, the sleeve can be moved up or down. Normally movement of the sleeve
cannot be accomplished if a extremely high differential pressure exists across the
sleeve. Any number of sleeves of the same size can be run in the same completion.
Solids in the seal area or the effect of well deviation and the resultant inefficient
jarring can cause failure to close the sleeve. A separation sleeve can be run which
will land inside the sliding sleeve and seal in the seal bores above and below the
slotted section of the inner sleeve when it proves impossible to close the sliding side
door as described above.
Sliding (inner)
Sleeve
Seals
Inner ports
a) Open b) Closed
• Recess to mechanically lock the mandrel in place using a set of expandible keys
• Pressure seal between the internal bore of the nipple and the outer surface of
the mandrel.
The nipple therefore offers a landing / locking profile and a seal bore into which the
mandrel (a plug or other equipment) may be selectively installed.
Pressure Equalising
Sub allows retrieval
of mandrel
Subsurface
Flow Control
valve
(1) Isolation or plugging of the tubing string for well shut in, workover or for
hydraulically setting packers.
(2) A ported device which allows communication between the tubing and the
annulus.
(3) Emergency closure of the tubing or annular flow conduit by remote or direct
control.
30
Conventional Completions
1
(5) The installation of downhole pressure and temperature recording gauges.
The landing nipple maybe selective or non-selective. A selective nipple will only allow
the corresponding mandrel to lock into place e.g. seven or more different mandrels
of the same size can be selectively landed in the correct nipple installed in tubing.
There are three methods of obtaining selectivity in a landing nipple system:
Flow Coupling
with increased
wall thickness
Turbulence
generated
by landing
nipple’s profile.
Landing Nipple
Flow Coupling
with increased
wall thickness
5.1 Definition
Multiple zone completions are employed for reservoirs where more than one distinct
reservoir layer is intersected by a single well and there is the intention, or legal
requirement, to produce from or inject into these layers separately. Each reservoir
has, by definition, its own pressure regime and, if present, their own Gas-Oil-Contact
and Water-Oil-Contact.
• Alternate Zone Well Completion Strategy each well is completed on more than
one reservoir. However, only one reservoir is produced up one tubing string at
any particular time. The advantages and disadvantages of each of the above
techniques is discussed below.
Advantages
• The total number of wells and the capital investment, is minimised since each
well provides a drainage point in every reservoir
• The production plateaux for each the reservoir should be reached quickly since
the amount of drilling is minimised the number of wells and the time required to
execute the drilling programme. i.e. production should be accelerated compared
to the other optional strategies
Disadvantages
32
Conventional Completions
1
3. Hydrocarbon fluids with different compositions and hence differing economic
value.
4. Different water - oil - ratio (WOR and GOR). This will influence the vertical
lift performance of the total well system.
• A change in the production characteristics of one zone e.g. water coning and
the consequent increase in WOR will influence the total production from the
well. It may be difficult to remedy without closing in the well.
Advantages
• The production rate and duration of flow on each zone can be independently
controlled.
• Changes in the production characteristics of one zone will not influence the others.
Disadvantages
• Each zone requires its own tubing string; increasing the length of production
tubing and other completion equipment required. This requires an increase in
the capital expenditure, the individual well installation time and an increase in
the total time required to complete the drilling programme.
Advantages
• Effective control of all aspects of reservoir depletion and well control is provided.
• Each well is mechanically relatively simple minimising the risk of failure due
to complexity.
Disadvantages
• The field's lifetime and thus the unit production costs, will be increased unless
the number of wells is increased.
In addition, the flow potential of each zone might be impaired if too small a tubing
size has been installed, because of lack of space within the wellbore for a multiple
tubing completion.
34
Conventional Completions
1
5.3 Multiple Zone Completion Configurations
Wells can in priciple, be completed on any number of zones within the same well
bore by simply increasing the amount of completion equipment installed to provide
isolation and flow control capability. The benefits of using the same wellbore for
multizone production are significant.
The inherent advantage of the single wellbore completion are lost as the number
of zones their complexity, and hence the potential for malfunction, increases. The
optimum number of zones to be produced into any wellbore will depend on the
reservoir (e.g. the production rate), the well design (e.g. the deviation angle) and
the expected problems (e.g. completion component failure and expected operational
problems throughout the well's life).
Casing/Tubing Flow
In this case a single tubing string is run with a single packer installed to provide
isolation between zones. The lower zone will produce up the tubing whilst the upper
zone will produce up the casing-tubing annulus. The difficulty with this type of
completion is that under natural flow conditions it will have a live annulus perhaps
necessitating an annular safety valve. Also the produced fluid is in contact with the
casing and it may thus cause damage by corrosion or abrasion. In addition, pressure
limitations on the annulus with respect to casing burst may preclude stimulation of
the zone which produces via the annulus. These issues can be addressed by:
• Upper zone annular flow - applied where the upper zone fluid is non-corrosive,
non-abrasive and where casing pressure limitations do not preclude stimulation.
• Lower zone annular flow - this design can be considered in situations where
the upper zone would not be suitable for annular flow. The lower zone annular
flow system requires one long and one very short tubing and two packers and
a crossover tool. This design however, limits access to both zones for logging,
perforating etc.
Nipple
Sliding side door for Sliding side door for
upper zone production upper zone production
Nipple
Figure 19 Options for single and dual string, two zone completion without comingling.
• Dual Tubing
This completion has a separate tubing string for each zone. It requires two
packers, one to isolate between zones and the other to isolate the upper zone
from the upper casing annulus. The depletion of each zone can be accurately
monitored and controlled. In addition, the injection of fluids into each zone is
limited only by the tubing design criteria. The completion is also more suited
to the efficient production of problem well fluids. The tubing may be concentric
rather than the parallel configuration shown in Figure 21d. A concentric tubing
allows a greater area for flow of the produced fluids (for a given casing size);
but requires a more complex running procedure.
36
Conventional Completions
1
5.3.2 Completions for Three or More Zones
The options discussed for dual completions can be extended for wells to be completed
with or without some degree of zonal co-mingling on three or more zones.
Thus for Triple Zone Completions this can be accomplished with either:
• Three tubing string completion utilising separate zonal flow and having three
packers for isolation.
• Two string completion, whereby flow from two zones is co-mingled into one
of the tubing strings.
• Single zone annular flow and two tubing strings producing separately from two
zones.
• Two string completion where either or both of the strings are completed to
allow selectively production from two of the zones. This requires two tubing
strings and three packers.
Obviously the number of tubing strings will affect the completion procedure. The
size of the tubing and ancillary equipment will be dictated by the limitations imposed
by the casing inside diameter, tensile load and torque capabilities will not normally
be a significant problem for a completion rig.
Provision must also be made for the control lines for each tubing string and valve
system when using a surface controlled sub-surface safety valve.
Similar types of multiple string packers are available as these described for single
string packers, i.e. they can be either permanent or retrievable. In addition, they
can be set using a hydraulic or a mechanical setting procedure. The wireline setting
procedure, is frequently used to set the lower, single string packer.
All multiple string packers must offer a means of connecting tubing both above and
below the packer for each string. In some cases mechanical attachment exists e.g.
tubing screwed onto the base of the packer whilst, in other cases, the packer offers
a seal bore.
The tubing strings will have different lengths in multiple string completions in
any completion involving multiple strings. They are denoted as the long string, the
intermediate string and the short string. This terminology is crucial to the running
procedures for the completion e.g. a packer may be run into the well on the long
string which is landed off, and may be set using hydraulic pressure either by the
long string or by the short string after it has been run, located into the packer seal
bore and landed off in the tubing hanger.
38
Conventional Completions
1
fluid flowstream must quickly change through 90° to flow up the tubing. The fluid
entering the wellbore (e.g. high velocity gas flow) may have a significant impact force
on the tubing wall of the long string, leading to hydraulic erosion. The erosion rate
will drastically increase if sand or other solid fines are being produced.
A thick walled tubing section known as a blast point, is normally included in the long
string opposite the perforated intervals of the upper production zones to compensate
for the increased rate of erosion.
• Operation of downhole equipment to either divert or shut off fluid flow. e.g. open a
sliding side door or install a bridge plug
• Removal of materials, which have built up in the tubing string, such as wax or sand.
Wireline involves lowering a tool into the tubing to perform a specific function. The
tool forms part of a tool string suspended on either a single strand wire or, a braided
cable. Manipulation of the tool string, either by raising or lowering, will impart a
jarring effect on the tool and activate the setting or retrieval mechanism that will
carry out the required action. Alternatively, a cable with an electrical conductor to
generate an electric signal can be used to initiate the required action.
• Lowering and retrieval of the tool string to the (downhole) work location and
its subsequent retrieval.
• Handling and alignment pulleys so that the lubricator and the tool string
can be positioned vertically above the well prior for lowering through the Xmas
tree and into the tubing string.
• The ability to insert the tool string into the live well and to prevent pressurised well
fluid from escaping into the environment.
• A blowout preventor which will seal off the annulus around the cable
and, if required, cut the wireline.
Pulley
Stuffing Box
(Pressure Seal Around Wireline)
Wire
Odometer
measures length
Blow-Out Preventor of wire inserted
Connection to Xmas Tree into well
to Wireline Drum
Load Cell Measures Wireline Tension
Xmas Tree
40
Conventional Completions
1
6.1 The Wire
Conventional wireline, or “slick wireline”, utilises a single strand of wire. The wire
is normally made from high tensile steel so that the ratio of breaking strength (lbs)
to wire diameter (inches) is maximised. The minimum cable diameter is normally
used to reduce the weight of wire while still achieving the required breaking strength.
The wireline is normally wound onto a reel on a self contained skid which has its own
power supply for drum rotation and measurement of cable length and tension (Figure 22).
Work Platform
Wireline Unit
Portable Hoist
BOP Control
SC-SSV Control
The cable tension is continuously monitored to ensure that the breaking strength of
the cable is not exceeded. The cable tension will:
• Reduce as the tool string is lowered through restriction in the tubing string due
to fluid pressure. Hence cable tension can occationally give an approximate
indication of tool position.
• Conversely, during insertion of the tool string into the well, the tension will
reduce when it does not fall easily down the well due to increasing friction or
a downhole restriction.
The maximum well deviation angle for conventional wireline operates is 65º due to
the increasing friction of the wire and tool string against the tubing and production
casing or liner. Wireline servicing of such wells requires use of an electrically driven
tractor that pulls the tool string into the well. Tractors allow servicing of wells with
deviation angles greater than 90º; but they require substitution of the slick (solid)
wire by a (more expensive) electrical cable as well as hire of the tractor itself.
7. TUTORIALS
• Pressure.
• Productivity or injectivity index.
• Fluid properties.
• Rock properties and geological data.
• Geographical factors:
• Location.
• Water depth (if offshore).
• Weather conditions.
• Accessibility.
• Environmental regulations.
• Safety aspects.
A number of typical completion types are presented below. These designs have
been chosen to illustrate functional similarities and differences in a range of well
environments. They are all based on the concepts discussed in this chapter.
42