1 CORE Consulting Engineers PLC
1 CORE Consulting Engineers PLC
Contents
1.0 INTRODUCTION..........................................................................................................................5
1.1 Introduction and Purpose................................................................................................5
1.2 Contract Data.......................................................................................................................7
1.3 Scope of Service and Objective.....................................................................................7
1.4 Purpose of the Engineering Design Report................................................................8
2.0 ENGINEERING STUDY.................................................................................................................9
2.1 Introduction................................................................................................................................9
2.2 Existing Road Condition...............................................................................................................9
2.2.1 Geometry of Existing Road...................................................................................................9
2.2.2 Existing Pavement Condition..............................................................................................11
2.2.3 Existing Drainage Condition................................................................................................13
2.3 Terrain Classification.................................................................................................................22
2.4 Geology and Geological Setting.................................................................................................23
2.5 Meteorology..............................................................................................................................23
2.5.1 Climate...............................................................................................................................23
2.5.2 Rainfall...............................................................................................................................23
2.5.3 Temperature......................................................................................................................24
2.6 Land use and Land cover...............................................................................................25
2.7 Soil Extension Survey.....................................................................................................25
3.0 FINAL ENGINEERING DESIGN..........................................................................................27
3.1 Design Standards.............................................................................................................27
3.2 Topographic Survey.........................................................................................................27
3.3 Geometric Design.............................................................................................................30
3.3.1 Design Controls.............................................................................................................30
3.3.2 Horizontal Alignment...................................................................................................33
3.3.3 Vertical Alignment........................................................................................................37
3.3.3 Vertical Curves...............................................................................................................38
3.3.4 Intersections...................................................................................................................40
3.3.5 Intersection at Grade..................................................................................................40
1
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
3.3.5.1 Introduction................................................................................................................40
3.3.5.2 General Design Considerations........................................................................42
3.3.5.3 Channelization........................................................................................................50
3.3.5.4 Auxiliary Lanes.......................................................................................................55
3.3.6 Interchange Design..................................................................................................57
3.3.6.1 Introduction............................................................................................................57
3.3.6.2 Interchange Design Element............................................................................58
3.3.6.3 Underpass versus Overpass Roadways.........................................................59
3.3.6.4 Roundabouts...........................................................................................................64
3.3.6.5. Summary of Intersections................................................................................66
3.3.7 Design Road Cross-Sections.................................................................................66
3.3.7.1 Design Cross Section and existing Right off way......................................68
3.4 Pavement Design..............................................................................................................75
3.4.1 Introduction..............................................................................................................................75
3.4.2 Sub grade Soils along the Alignment....................................................................................76
Introduction....................................................................................................................................76
Expansive Soils in the Project Area...........................................................................................76
Method of Treatment of Expansive Soils..................................................................................76
Determination of the design CBR...............................................................................................76
3.4.3 Traffic Survey and Analysis.........................................................................................................77
Traffic Count..................................................................................................................................77
Determination of Annual Average Daily Traffic........................................................................79
Traffic Forecasting........................................................................................................................83
Traffic Growth Rates....................................................................................................................83
Baseline AADT Computation.......................................................................................................84
Traffic Projection.........................................................................................................................85
3.4.4 Axle Load and OD Survey...........................................................................................................86
Axle Load Survey.........................................................................................................................86
Determination of Truck Factors...................................................................................................87
3.4.5 Design Traffic..............................................................................................................................88
3.4.6 Pavement Structure...................................................................................................................91
2
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
3
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
4
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
1.0 INTRODUCTION
1.1 Introduction and Purpose
Addis Ababa, the administrative and financial capital of Ethiopia, is
experiencing continued growth and change. Change is experienced in all
dimensions, peripheral areas are growing faster. Economically the city is
transforming from a predominantly administrative and service center into
an industrial and financial sector. In influence it is changing from a
national to an International city.
Now, therefore, the Addis Ababa city roads Authority hereby commits part
of its budget to finance for consultancy services for design, tender
document preparation and construction supervision of road upgrading
project. This study calls for an integrated design of road and LRT line to a
highest professional standard.
Currently this project designed two lines, the East-West route and the
North-South route.
The Initial design of the E-W LRT has weak Integration with the rest of
the traffic system; it could result into more traffic congestion and
confusion. The initial design also didn’t consider issues like Right off way,
Utility Lines, Lane & walkway widths for motor traffic & pedestrians.
One of the main achievement from the meetings is the decision for the
dislocation of the main water supply line from Megenagna to Mexico, in
addition different technical negotiations were made with Ethiopian
Railway Corporation and the Contractor of Light Rail Transport on the
type of Junctions and right off way.
6
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Along the route Megenagna RA- Torhailoch RA, 8 minor and 13 main
Junctions exist namely Megenagna, Lemhotel, 22Mazoria, WehaLimat,
Getahun Besha, Urael, Bambis, Maskel Square, Legehar, Mexico, Firdbet,
Cocacola and Torhailoch Roundabout, with the exception of Bambis and
Cocacola intersection it has been reached an agreement on all Junction
types with ERC. Although Bambis and Coca Junctions are found to be
important reliefs in connection with vehicular traffic the needs of other
stake holders (ERC) required closure of these two junctions.
ADMINISTRATION
• Minimizing delay to, and maximizing priority for the proposed LRT;
• Attempting to minimize negative effect to other road users – especially
delay and congestion;
• Ensuring ease of pedestrian access to and from the proposed stations;
• Producing an integrated LRT & Other traffic scheme which should bring
real benefit to the City and its residents; and
• Providing a design which will coordinate with LRT and other users of the
subject transport corridor.
8
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
At lowest point, the violent and torrential character of these rivers are
expressed by deep, abrupt banks, with steep sides, and are often invisible
from the east-west axis
Horizontal Alignment
The curve found at Awash wine factory where the project road
meets the newly constructed road is found sharp
9
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Vertical Alignment
22 Junction
TORHAILOCH Cocal Cola Lideta Mexico Gumruk Megenagna
Kidus Urael
The proposed design requires widening of the east-west axis from 30m
width to 40m and at Junctions wider width is required. The following
areas have critical right off way limitations due to existence of large
buildings in the East-West axis.
22 Mazoria
Legehar Area
Mexico
Existing Cross-Section
10
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
This section of the road is two directional bituminous surfaced road. The
carriage way width of this section is approximately 21m for the entire
length. However, the median varies from 1 - 4m near 4+000 and near
0+000 respectively.
This section is also two directional bituminous surfaced road. This section
of the road contains narrow as well as wide section of project road.
11
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Narrow carriage way encountered near Lagar area (5+330). Moreover the
outer lanes of each side are usually occupied as parking; resulting in two
lanes of effective pavement width that worsen the traffic jam. The widest
part along this section is found at Meskel Square area (4+000 – 4+700).
The width at this section is about 63m with seven lanes on each direction
along with the pedestrian walkway.
The pavement condition of this section; especially from the end of Meskel
Square Km4.70 to Mexico square Km6.37 is found to be in an inferior
condition. The existing pavement is affected by ruts, corrugations and
shoving of patches. On those sections where the vehicles are forced to
stop for a longer period ruts are seen to be severe and on some points
they are found to develop to deformations.
From Coca-Cola junction road Km8.04 to the end of the project Km8.90,
median of 11 meters wide is provided. As a result, the total road way
width including the median and 5m wide walk way width on each side is
42meters. In this section, distresses like potholes and undulation resulted
12
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Location 0+250
Type of super-structure Slab Culvert
Type of sub-structure Masonry Abutment & wing wall
Clear Span 3.00m
Clear height 3.20m
As it’s observed, the main part of the culvert is in good condition i.e. the
abutment masonry wall and the concrete slab are in good condition. At
the median, the culvert is open at top. At the upstream side the wing wall
is severely damaged and its backfill is eroded by the road’s side drainage
water that is not properly guided into the stream course. As widening of
this structure was found to be compulsory, retaining wall shall be
provided to maintain eroded river bank.
13
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
During the site visit, it’s learned that at times of rain, the road is usually
flooded at this section and the water overtops the side drainage manholes
and enters the stream course passing the inhabitants compound.
Figure 1: Damaged wing wall of upstream side of the Figure 2: Top opening of the culvert at median of the
culvert. road.
So, during the design stage, the design flood of the area was properly
estimated and provision of a larger diameter pipe than the existing 90cm
diameter pipe is provided as detailed on drawings.
Location 1+220
Type of super-structure Slab Culvert
Type of sub-structure Masonry Abutment
Clear Span 4.20m
Clear height 3.50m
The substructure shows some defects of losing jointing mortar that may
result in dislodgment of masonry units. Like the first culvert, this culvert
14
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
has an opening at the median of the road but covered with metal sheet.
The condition of the superstructure is good except there some damages
on the edge beams.
The third drainage structure or the first major structure comes at Km2.5.
This bridge composed of two skew bridges separated at the median of the
road to accommodate the water supply pipe of diameter 90cm supported
on steel structure.
Location 2+500
15
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
16
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
The second major structure is located at Km3.70 and it’s of type arch
bridge.
Location 3+700
Type of super-structure RC Arch Bridge with Masonry
Type of sub-structure Masonry wing wall
Clear Span (at bottom) 16.40m
Average Clear height 6.00m
The upstream course of this river extends parallel to the project road until
around Meskel Square some 250 of 300 meters away to the right and at
the back of Gion Hotel. So, the side drainages at around Meskel Square
can be discharged through it.
Figure 7: Upstream meandering river flow and Arch Figure 8: Water Supply pipe at median covered with
Bridge inlet. concrete protection.
17
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
The next structure comes after traveling about 3Kms from the previous
cross drainage which is at Km6.30 around Police Force Hospital. The
upstream inlet of this structure is located in the compound of Police Force
Hospital.
Location 6+300
Type of super-structure Slab Culvert
Type of sub-structure Masonry abutment
Clear Span 6.50m
Average Clear height 2.00m
During the visit, it was observed that the culvert is skew and its inlet is
located in Police Station compound and is completely inaccessible due to
vegetation and fences. The capacity of the culvert was checked and found
to be sufficient to accommodate incoming flood.
18
CORE Consulting Engineers Plc
Figure 9: Upstream of the culvert. Figure 10: Police Force Compound at the Upstream
side.
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
6. RC T-Girder at 7+500
Location 7+500
Type of super-structure RC T-Girder
Type of sub-structure Masonry abutment & wing wall
Clear Span 19.50m
Figure 11: Upstream side of the Bridge. Figure 12: Top of Bridge showing its wide median.
19
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
It is observed that in most section of the road, the side drainage is not
fully functional. Most of the stretch is clogged and out-of-order manholes
are observed. The size of the pipe is found to be 90cm as it is assessed
on different opened manholes. Capacity of manholes and pipes shall be
revised during detail design.
Figure 13: Completely out-of-order side drainage Figure 14: one of clogged manhole observed in the
around La-gare. road.
20
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
The project road mainly falls in flat terrain with intermittent rolling
sections. However, there will be heavy earthwork operations so as to
fulfill the geometrical requirements at intersections.
21
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
2.5 Meteorology
2.5.1 Climate
The project area is located on the higher part of the city, having altitude
of 2350 – 2405m above the mean sea level, which is considered as Dega.
The effective temperature is lower than 25 0c, which is good and most of
the time comfortable.
2.5.2 Rainfall
22
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Since the project area is located in Addis Ababa area, the rainfall of the
city is considered for the project area. Accordingly the mean annual
rainfall of the project area varies in the range of 918mm - 1567mm, and
the rainy period is between June through September, although occasional
shower is expected in the months of March, April, May, October and
November.
The mean monthly rainfall is maximum during the months of July and
August i.e. 250mm and 280mm and it is minimum during the months of
November and December i.e. 8mm and 9mm respectively.
Rainfall 17.6 39.7 68.5 91.3 77.3 119.2 253.6 279.6 172.9 39.2 8.1 9.2
(mm)
2.5.3 Temperature
For Addis Ababa area, the monthly temperature is maximum during the
months of March through May, about 27.5 0C, and it is minimum in the
months of November through January, 4.70C.
Max.
25.1 26.0 27.0 27.2 2709 24.4 22.3 21.3 23.1 24.4 24.7 24.4
(0C)
Min.
4.7 5.5 8.7 9.4 9.7 8.9 9.1 9.3 8.7 6.5 4.7 4.7
(0C)
23
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
The sub grade soil extension along the project length is presented in the
following table.
24
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
25
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
The Topographic survey of the project was totally carried out with Total
Station which directly records the alignment, profile and cross section
data on a memory stick. This system of data collection will render a
coherent approach to the design chain.
27
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Post processing
software (to tie to
National Grid
System)
Post processing
software (to tie to
GPS CONTROL
Leveling POINT)
28
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Basic design controls serve as the foundation for establishing the physical
form, safety and functionality of the facility. Some design controls are
inherent characteristics of the facility (e.g. its context and the
transportation demands placed upon it). Other basic design controls are
selected or determined in order to address a project’s purpose and need.
Selecting appropriate values or characteristics for these basic design
controls is essential to achieve a safe, effective, context sensitive
solution. Evaluate the following design controls to understand the factors
29
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
30
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
31
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
32
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Super elevation
When a vehicle travels on a horizontal curve, it is forced radially outward
by centrifugal force. This effect becomes more pronounced as the radius
of the curve is shortened. This is counterbalanced by providing roadway
super elevation and by the side friction between the vehicle tires and the
surfacing. Safe travel at different speeds depends upon the radius of
curvature, the side friction, and the rate of super elevation. When the
standard super elevation for a horizontal curve cannot be met, a design
exception will be required. However, the highest practical super elevation
should be selected for the horizontal curve design.
33
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
34
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
35
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Metric US Customary
Maximum Grade (%) for specified Maximum grade (%) for specified design
Type of terrain
design speed (Km/h) speed (mph)
50 60 70 80 90 100 30 35 40 45 50 55 60
Level 8 7 6 6 5 5 8 7 7 6 6 5 5
Rolling 9 8 7 7 6 6 9 8 8 7 7 6 6
Mountainous 11 10 9 9 8 8 11 10 10 9 9 8 8
36
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Metric US customary
Exhibit 3-76. Design Controls for Stopping Sight Distance and for Crest Vertical Curves.
37
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Metric US customary
Design Stopping Stopping
Design
speed sight sight
speed
(km/h) distance Calculated Design distance Calculated Design
(mph)
(m) (ft)
38
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
3.3.4 Intersections
The route from Megenagna-Torhailoch contains 13 Major Intersections
namely Megenagna, Lemhotel, 22Mazoria, WehaLimat, Getahun Besha,
Urael, Bambis, Maskel Square, Legehar, Mexico, Lideta, Cocacola and
Torhailoch. The use of Intersection at Grade almost on all Major
Intersections was impossible due to the implication of traffic analysis and
mainly due to the existence of LRT line with recurrence Interval of 6
minute which is going to be improved to 2 minutes on the East west
route.
3.3.5.1 Introduction
Although intersections have many common factors, they are not subject
to a set treatment, and must be looked upon on a case by case basis. In
varying degrees, four basic factors enter into the design of an
intersection. These factors are traffic, physical, economic, and human.
39
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
40
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Capacity Analysis
Capacity analysis is one of the most important considerations in the
design of intersections. This is especially true in the design of at-grade
intersections on urban streets and highways. Optimum capacities can be
obtained when intersections include auxiliary lanes, proper use of
channelization, and traffic control devices. Where these techniques are
under consideration, it is necessary to consider pedestrians Safety and
level of service.
Spacing
The spacing of intersections on major arterials is important to the
capacity and safety of the roadway. In urban areas, the capacity of the
arterial is determined by the capacity of the signalized intersections along
the roadway. Ideally, signalized intersections should be located no closer
than 400m apart.
Alignment and Profile
Intersections are points of conflict between motor traffics and
pedestrians. The alignment and grade of the intersecting roads should
41
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
1. Alignment
Regardless of the type of intersection, intersecting highways should meet
at or nearly at right angles. Roads intersecting at acute angles require
extensive turning roadway areas. Intersection angles less than 60
degrees normally warrant realignment closer to 90 degrees. Intersections
on sharp curves should be avoided wherever possible because the super
elevation and widening of pavements on curves complicate the
intersection design. Furthermore, since traffic stripes are not normally
carried through the intersection, there is no visual reference for the
guidance of the driver through the intersection curve during adverse
weather and visibility conditions.
2. Profile
Combinations of profile lines that make vehicle control difficult should be
avoided. Substantial grade changes should be avoided at intersections,
although it is not always feasible to do so. Adequate sight distance should
be provided along both highways and across corners, even where one or
both intersecting highways are on vertical curves.
The grades of intersecting highways should be as flat as practical on
those sections that are to be used for storage space for stopped vehicles.
A minimum storage space for 2 vehicles, approximately 15m, should be
provided for minor streets where stop sign control is employed and the
42
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
43
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
observe pedestrians and cyclists and carry out whatever maneuvers may
be required to negotiate the intersection. It is of equal importance that
pedestrians be able to view and react to potential conflicts with vehicles.
Any object within the sight triangle high enough above the elevation of
the adjacent roadways to constitute a sight obstruction should be
removed or lowered. Such objects include but are not limited to cut
slopes, hedges, bushes, tall crops, signs, buildings, parked vehicles, etc.
Also check the vertical curve on the highway to see if it obscures the line
of sight from the driver's eye (1.06m above the road) to the approaching
vehicle (1.06m above the road) as per the sight distance determined in
the next sections.
Stop Control on Cross Street
Intersection designs should provide sufficient sight distances to avoid
potential conflicts between vehicles turning onto or crossing a highway
from a stopped position and vehicles on the through highway operating at
the design speed.
As a minimum stopping sight distance must be provided. However, to
enhance traffic operations, the recommended sight distance along the
major roadway from the Figure shown below for various design vehicles
to turn left, right or cross should be provided.
44
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Yield Control
When an intersection is controlled by a yield sign, the sight triangle is
governed by the design speed on the main highway and that of the
approach highway or ramp.
Suggested approach speeds on the yield controlled approach are 30km/hr
for urban conditions. Where two major highways intersect and one leg is
45
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
47
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
48
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
3.3.5.3 Channelization
General
Where the inner edges of pavement for right turns at intersections are
designed to accommodate semi-trailer combinations, or where the design
permits passenger vehicles to turn at speeds of 30km/hr or more, the
pavement area at the intersection may become excessively large for
49
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
50
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
51
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
52
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
53
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
54
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
shall be in accordance with the figure shown below. The Engineering must
approve the addition of an auxiliary lane to improve capacity at signalized
intersections.
Auxiliary Lane Addition at Signalized Intersection
55
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
3.3.6.1 Introduction
(a) The location and standards of existing and proposed local streets
including types of traffic control.
(c) A traffic flow diagram showing average daily traffic and design
hourly volumes, as well as time of day (a.m. or p.m.), anticipated
on the freeway ramps and affected local streets or roads.
56
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Geometric design for all interchange roadways should follow the design
guides covered in the above section "Basic Geometric Design Elements."
Spacing
Sight Distance
Sight distance along the through roadways and all ramps should be at
least equal to the minimum safe stopping sight distance and preferably
longer for the applicable design speed.
57
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
A design that best fits the existing topography is the most pleasing and
economical to construct and maintain and this factor becomes the first
consideration in the design
Underpass Roadways
58
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Lateral Clearance
59
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Vertical Clearance
Megenagna Interchange
The topography and the Drainage path of Megenagna Interchange allows
for the through traffic to be underpass and the other crossings at grade
with Roundabout. The Interchange is designed to have a minimal effect
on the Right off way.
Width
Length of Width Width Round
Intersectio of Rwall & Total
Type Grade of Outer of Walk about
n Under/ Drainage width(m)
Separation(m) Lane(m) way(m) Diameter(m)
Over(m)
22 Mazoria Interchange
60
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
This Junction is one of the narrowest sections along the design route;
large buildings exist on both side of the road.
A shift of Master Plan Centerline towards Right from Megenagna is made
to protect large buildings. The LRT width of 11.0m is reduced to 9.50m
and a Lane & walkway width of 3.0m is also used. To obtain the minimum
Vertical clearance 5.40m and keep the longitudinal grade to a minimum
of 0.50% for drainage, the existing road (minor roads) require grade raising from 2 to
3m.
Width
Width
Length of Width Width Round of
Intersectio of Rwall & Total
Type Grade of Outer of Walk about Round
n Under/ Drainage width(m)
Separation(m) Lane(m) way(m) Diameter(m) About
Over(m)
(m)
22-Mazoria Under 730 21.5 12 8 1.8 41.3 50 14
URAEL INTERCHANGE
The topography of Urael allows for the major road to be underpass
Width
Width
Length of Width Width Round of
Intersectio of Rwall & Total
Type Grade of Outer of Walk about Round
n Under/ Drainage width(m)
Separation(m) Lane(m) way(m) Diameter(m) About
Over(m)
(m)
Urael Under 700 25 14 8 1.8 48.8 30/40 14
MEXICO INTERCHANGE
The East-West Line of Mexico is separated from the rest of traffic through underpass
Width
Width
Length of Width Width Round of
Intersectio of Rwall & Total
Type Grade of Outer of Walk about Round
n Under/ Drainage width(m)
Separation(m) Lane(m) way(m) Diameter(m) About
Over(m)
(m)
61
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
FIRDBET INTERSECTION
Minor Crossing road at Firdbet designed as Underpass
Width
Length of Width Width Rwall, Round
Intersectio of Total
Type Grade of Outer of Walk Med& about
n Under/ width(m)
Separation(m) Lane(m) way(m) Drainage Diameter(m)
Over(m)
OVERPASS ROADWAYS
The road way dimension design of an overpass bridge should be the same
as that of the basic road way
62
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
3.3.6.4 Roundabouts
63
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
The main constraint to use larger diameter of roundabout is right off way
limitation however it is tried to use medium size roundabouts that would
accommodate the traffic & has less right off way effect.
The Major axes of the elliptical roundabouts were aligned along with the
crossing roads and this will favor traffic along them as the through traffic
is at underpass.
The following Minimum Diameter of roundabouts has been used in the following Intersections
64
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Refer to Annex-5 for Junction details of Megenagna Tor Hailoch Road Project
A. Normal Sections
65
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
66
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
To protect buildings right side from megenagna, Master plan center line
shifted 1.31m towards left from megenagna
67
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
However, on the North -South direction where over Pass bridge Proposed
Matyas Building is in the design right off way by 1.91m as shown in the
drawing
68
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Golagol Building
69
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
AXUM HOTEL
The hotel is built inside the right off way limit of the master plan with
width ranging from 4.5m to 5.72m and is found critical in the project.
Around the area minimum widths has been used i.e. Lane width (3.0m),
and LRT width of 9.50m.
70
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
The Building falls within the design walkway, for length about 20m
BAMBIS BUILDING
The building is located inside the limit of Master Plan, to protect this
building and the new building near bambis a slight shift of Mp-Center Line
towards Right from Megenagna was made. However LRT designers
71
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Length from
Bulding
No. Station Rt off
Name
way/Design
8+400
Menged From
1 Transport Ayat 9.1m
North-
Derartu South
2 Bldg Direction 0.4m
1.91m (North-
3 Matias Bldg 0+320 South)
Centeral
4 Shoa Hotel 0+730 0.38m
Bldg Under
Constr St 1.83m (North-
5 800 0+820 South)
Golagol 0.82m (on East-
6 Bldg 1+300 West)
72
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
North-
South
12 Lex Plaza Direction 1.61m
Haile Alem
13 Bldg 2+860 1.93m
14 Bambis 3+050 -
New Bldg
near
15 Bambis 3+100 -
Zequala
Bldg (Abay
16 Bank) 3+520 1.77m
Bldg
17 Betezata 4+920 2.13m
Sport
18 Commission 5+080 6.75m
12.50m at Junction
& 4.31m at
19 Ayrese Bldg 5+110 Tangent
Tegbared
20 Bldg 6+220 0.50m
Helu Coffee
22 Bldg 7+200 3.46m
Refer to Annex-5 for Detail of buildings that are affected by the design
73
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
3.4.1 Introduction
The main function of a pavement is to provide a structural and economical
combination of materials to carry traffic in a given climate over the existing
soil conditions for a specified time interval (design period). In light of this,
analysis of the traffic characteristics of the project area was carried out so as
to determine the design traffic. And relevant data regarding the soil foundation
was collected to determine the design CBR. This helps to develop the most
economical combination of pavement layers (in relation to both thickness and
type of materials) that suit the underlying subgrade materials and the
cumulative traffic to be carried during the design life of the road.
The properties of the soil formations along the project route were also
assessed as they affect pavement structural design and performance. This
was carried out by conducting laboratory tests on soil samples collected at an
interval of 300m along the route alignment. Therefore, the design CBR for
homogeneous road sections was computed from the results of laboratory
CBR tests conducted on the collected soil samples.
This pavement design report has five chapters and three annexes. The first
part is the introduction which gives a brief highlight of the project. The second
chapter describes the subgrade soils along the alignment. The third chapter
discusses about the traffic survey and the analysis of these data. The fourth
chapter deals with the pavement design as per ERA manual. The last chapter
summarizes the whole topics covered in the conclusions and
recommendations part. The annexes contain the raw data collected for this
project. This includes the Traffic Count data, the Axle Load data and the
Origin – Destination Survey data.
74
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Introduction
The subgrade soils are of the upmost importance in the pavement design as
they carry the entire pavement structure and hence the total load. The
subgrade soils were first collected from the project site at 300m interval by
digging test pits of 1m depth. The samples were then logged, tagged,
sampled and transported to the head office for the test.
In order to determine the homogenous sections of the road soil extension
survey was conducted. This was presented in the Soils and Materials report.
Almost all of the project area is underlain by expansive soils. Majority of the
soils along the section have distinct features of low CBR values and high
Swell Indices.
Since the majority of the soil along the stretch has expansive nature, it shall
be removed and replaced by improved subgrade material having a minimum
CBR value of 8% and swell index less than 2% or rockfill material. As a result,
the design CBR value was taken to be 8%. Accordingly, the subgrade
strength class of the soil becomes S4.
75
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
The pattern and characteristics of traffic flow of the project area were
assessed so as to estimate the volume and damaging effect of the traffic that
will use the road within the design period. Thus, traffic surveys including traffic
count and origin – destination survey were conducted on the all major
intersections and crossings. The data collected from the study were compiled
and analyzed along with previous data so as to determine the design traffic.
Traffic Count
Manual classified traffic count was conducted for seven consecutive days at
14 counting stations divided in three phases. The traffic count data conducted
for seven days include a two days 24 hours traffic count, two days 16 hours
traffic count and a three days 12 hours count data.
The first phase of the count was from the 12th of December 2011 to 18th of
December 2011. The count stations include Legar, Kera Junction around
EEPCO, Higher Court and Coca Mazoria.
The second phase of the traffic count was from the 19th of December to the
25th of December 2011. The stations for this phase include: Bambis, Ureal,
Wuha Limat, Getahun Beshah, 22 Mazoria and Lem Hotel.
The third and final phase of the traffic count was conducted from the 26th of
December 2011 to the 1st of January 2012. The stations included in this final
count were: Megenagna, Estifanos, Stadium and Mexico Squares.
In carrying out the traffic surveys, the vehicle classification system of ERA
with slight modifications was used as shown in Table 2.1 below.
76
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
1. Passenger vehicles
2. Freight vehicles
77
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
It should be noted that the vehicles presented here are those that cause
considerable damage to the pavement.
Lem Hotel
Lem Hotel to
Megenegna 3438 613 267 130 25 14 4487
Megenegan to Lem
Hotel 3434 448 227 43 6 2 4161
22 Mazoria
78
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Getahun Beshah
Wuhalimat
Ureal
Estifanos
Legar
79
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Kera Junction
Lideta
Coca
80
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Table 3-3 Final Refined AADT on Torhyloch to Megenegna lane (West to East)
Direction One: Torhyloch to Megenegna (West to East)
Table 3-4 Final refined AADT on Megenegna to Torhyloch lane (East to West)
Direction Two: Megenegna to Torhyloch (East to West)
81
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
From the traffic data the average vehicle composition indicates that more than 75%
of the vehicles are small busses and truck trailers are less than 1%.
Traffic Forecasting
As the road to be constructed in very important road and located within the
city hub, the pavement structure was designed for 20 years design period. It
was anticipated that the road will be opened for traffic in 2016. The factors,
used for traffic forecasting, were detailed below.
The following traffic growth rates were determined by the traffic engineer
based on demand elasticity and GDP growth rate.
82
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
M. H.
S/Bus M/Bus L/Bus Truck Truck T-T Total
Traffic Projection
The annual average daily traffic anticipated within the design period i.e. 2016
– 2036 is projected by using the following relation (using year – to – year
growth rates):
83
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
The projected AADTs over the design period are presented in the table below.
84
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
A twelve hour axle load survey was conducted from 27th of February to 1st of March
2012 on two survey stations. The equipment used for the axle load survey was
INTERCOMP LP600 portable weighbridge obtained through the courtesy of ERA,
along with the operators.
As many as 436 vehicles were weighed on the first survey stations and 247
vehicles on the second survey station, covering all categories of buses (small,
medium and large) and trucks (small, heavy and truck – trailer) on both lanes.
Data from the axle load survey raw data is attached in Annex II of this report.
85
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
n
TF EF
i 1
AL = Axle Load
TF = Truck Factor
For the subject project axle load analysis was made on directional basis, i.e.
the truck factor of each commercial vehicle class was determined on each
direction and the maximum value for each vehicle type was taken. The truck
factors determined from the axle load survey data of the project road are
presented in the following table.
The truck factor of the truck and trailer is very small to represent the
damaging effect of articulated truck. Hence referring to the survey data of
other projects, truck factor of 7 was adopted to truck and trailer.
86
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
2029
CESA 365 * AADTi * TF * D * L
i2016
The directional split factor and lane distribution factor were taken to be 0.5
and 0.6 referring to the actual condition and AASHTO design guide
recommendation.
The cumulative equivalent standard axles on the design lane are presented in
the tables below.
87
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
2016 11,347 9,940 1,576 20,881 917 445,727 465 26,070 272 150,767 43 32,960 14,620 686,344
2017 12,164 10,656 1,678 22,233 977 474,891 501 28,088 293 162,407 47 36,026 15,660 734,299
2018 13,040 11,423 1,787 23,677 1,041 505,999 540 30,275 316 175,155 51 39,092 16,775 785,621
2019 13,979 12,246 1,903 25,214 1,109 539,052 582 32,629 341 189,013 56 42,924 17,970 841,077
2020 14,985 13,127 2,027 26,857 1,181 574,049 627 35,152 368 203,978 61 46,757 19,249 899,920
2021 15,974 13,993 2,149 28,473 1,252 608,560 668 37,451 392 217,281 66 50,589 20,501 956,348
2022 17,028 14,917 2,278 30,182 1,327 645,016 712 39,918 418 231,693 71 54,422 21,834 1,016,146
2023 18,152 15,901 2,415 31,998 1,407 683,901 759 42,553 446 247,213 77 59,021 23,256 1,080,586
2024 19,350 16,951 2,560 33,919 1,491 724,731 809 45,356 475 263,287 83 63,620 24,768 1,147,863
2025 20,627 18,069 2,714 35,959 1,580 767,991 862 48,327 506 280,470 89 68,219 26,378 1,219,036
2026 21,988 19,261 2,877 38,119 1,675 814,168 919 51,523 539 298,762 96 73,584 28,094 1,295,417
2027 23,439 20,533 3,050 40,411 1,776 863,261 980 54,943 575 318,716 103 78,950 29,923 1,376,813
2028 24,986 21,888 3,233 42,836 1,883 915,271 1,045 58,587 613 339,779 111 85,082 31,871 1,463,442
2029 26,635 23,332 3,427 45,406 1,996 970,197 1,114 62,455 653 361,951 120 91,980 33,945 1,555,321
2030 28,393 24,872 3,633 48,135 2,116 1,028,525 1,188 66,604 696 385,785 129 98,879 36,155 1,652,801
2031 30,267 26,514 3,851 51,024 2,243 1,090,256 1,266 70,977 742 411,282 139 106,544 38,508 1,756,597
2032 32,265 28,264 4,082 54,084 2,378 1,155,876 1,350 75,686 791 438,443 150 114,975 41,016 1,867,328
2033 34,394 30,129 4,327 57,331 2,521 1,225,384 1,439 80,676 843 467,266 162 124,173 43,686 1,984,958
88
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering
Design and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
2034 36,664 32,118 4,587 60,775 2,672 1,298,780 1,534 86,002 899 498,306 175 134,138 46,531 2,110,119
2035 39,084 34,238 4,862 64,419 2,832 1,376,552 1,635 91,665 958 531,009 189 144,869 49,560 2,242,750
2036 41,664 36,498 5,154 68,288 3,002 1,459,184 1,743 97,720 1,021 565,929 204 156,366 52,788 2,383,984
∑ 496,425 434,868 64,170 850,220 37,376 18,167,371 20,738 1,162,655 12,157 6,738,491 2,222 1,703,163 633,088 29,056,769
Accordingly, the design traffic value is 29,056,769, which falls in T8 traffic class Design of Pavement Structure
89
CORE Consulting Engineers Plc
Consultancy services for Detailed Engineering Design
and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Chart 5
150mm bituminous
surface
250mm granular road
base
Chart 7
50mm bituminous surface
200mm bituminous road
base
AC m3 4225.00
DBM m3 3436.40
GRB m3 429.84
GSB m3 103.00
The costs of the two structures per square meter in cubic meter were given in
the following table.
Chart 5 Chart 7
Unit Quantity Quantity
Material
Rate per sq.m Cost per sq.m Cost
[m3] [m3]
Bituminous road
3436.40 0.000 0.00 0.200 687.28
base
The cost comparison indicated that the pavement structure with 150mm Asphalt
Concrete, 250mm Granular Road base, and 275mm Granular Sub-base is more
Chart 5
150mm bituminous
surface
250mm granular road
base
3.4.8 Design of Walkways
175mm granular sub-
The foundation of the walkway shall
be shaped and base compacted to a
firm, even surface. Unsuitable
material shall be excavated to a
depth of 1m and removed, and replaced with approved materials.
The surface of the walkway shall be patterned concrete tiles with the following
structural components.
Borrow Material
The material requirements are taken from ERA’s Pavement Design Manual, Volume
1, Flexible Pavements and Gravel Roads, 2002 and ERA’s Standard Technical
Specification Manual, 2002.
The material shall have a maximum plasticity index and liquid limit
of 25 and 55, respectively.
Sub-base Material
- Sub – base material shall have a plasticity index of not more than 12 and the
plasticity product should not be greater than 75.
- The minimum soaked CBR of the sub-base materials shall be 30% when
determined in accordance with the requirements of AASHTO T-193. The CBR
shall be determined at a density of 95% of the maximum dry density when
determined in accordance with the requirements of AASHTO T-180 method D.
- The minimum in-situ dry density of the sub-base material shall be 97% of the
modified AASHTO density.
- The material shall have a Los Angeles Abrasion value of not more than 51% when
determined in accordance with the requirement of AASHTO T-96.
63.0 100
50.0 90-100
25.0 51-80
4.75 35-70
0.075 5-15
If crushed stone is utilized for sub base course construction, it shall fulfill the
requirements specified in clause 5105 of ERA Standard Technical Specification.
50.0 100
37.5 95 – 100
28 -
19 60 – 80
9.5 40 – 60
4.75 25 – 40
0.425 7 – 19
0.075 5 - 12
The grading of the crushed stone sub base shall comply with the grading limit-A of
Table 5105/1 of ERA Standard Technical Specification.
- The gradation of the base course material shall be smooth continuous curve
within the following envelop.
Table 5-14 Gradation Requirement for Crushed Stone Base Course Material
Percentage by mass of total
aggregate passing test sieve
37.5mm
50 100
37.5 95 – 100
19 60 – 80
9.5 40 – 60
4.75 25 – 40
2.36 15 – 30
0.425 7 – 19
0.075 5 – 12
Where crushed gravel is proposed for use as aggregate, not less than 90% by
weight of the crushed material retained on the 4.75mm sieve shall have at
least two fractured faces.
The coarse aggregates shall satisfy the physical requirements specified in the
following table.
Max. 5% passing
Cleanliness Grain size analysis BS 812, Part 103
0.075mm sieve
Aggregate Crushing
BS 812, Part 110 Max. 25%
Value
Water
Water Absorption ASTM C 127 Max. 2%
Absorption
coating 95%
The plasticity index of the fraction passing the 0.425mm sieve shall not
exceed 4 when tested in accordance with AASHTO T-90.
The fine aggregates shall satisfy the physical requirements specified in the
following table.
d. Filler: Filler (if required) shall consist of finely divided mineral matter such as rock
dust, hydrated lime or cement approved by the Engineer.
The filler shall be free from organic impurities and have a plasticity index not
greater than 4. The plasticity index shall not apply if the filler is cement or lime.
The filler shall be graded within the limits indicated in the table below.
0.6 100
0.3 95 – 100
0.075 85 – 100
e. Aggregate grading
When tested by wet sieving method, the combined grading of the coarse and fine
aggregates and added filler for the particular mixture shall fall within the limits
shown in the table below.
The combined aggregate grading shall not vary from the low limit on one sieve to
the high limit on the adjacent sieve.
Sand for mortar and concrete works shall fulfill the following requirements:
Percentage
Sieve Size (mm)
Passing by mass (%)
2.38 68 – 86
1.19 47 – 65
0.59 27 – 42
0.3 9 – 20
0.15
CORE CONSULTING ENGINEERS
0–7 99
0.075 0 – 2.5
Consultancy services for Detailed Engineering Design
and Tender Document Preparation for
Megenegan – Torhayloch Road Upgrading Project Final Engineering Report
Traffic
The existing road from Megenegan to Torhyloch is a major arterial road with a lot
of traffic. In order to know the exact traffic, traffic count was carried on 14 stations
for 7days each. Also to understand the amount of diverted traffic Origin –
Destination Survey was conducted on 7 major traffic stations. These data was
analyzed and from this the value for the existing traffic was determined.
Subgrade Soils
Pavement Structure
The pavement structure was determined as per the ERA design manual by taking
the subgrade strength class and the traffic category and matching this two in the
structural catalogue.
The traffic was analyzed and forecasted for a period of 20 years. In order to
determine the damaging effect of the vehicles axle load survey was conducted
and from this the appropriate truck factors were taken.
For the subgrade strength, test pits were dug at 300m interval and samples were
collected and the strength calculated.
By using this two values, the traffic class of T8 and subgrade strength of S4, the
recommended pavement structure has a 150mm Asphalt Concrete, 250mm
Granular Base Course and 175mm Granular Sub – Base.
3.5.1 INTRODUCTION
General
The life of roads and utilities depend on the drainage system installed in the area. Roads
surface which are poorly drain can have higher maintenance and operation cost. In addition
to this water can stay on the pavement surface and easily splashed on vehicles and
pedestrian, which can reduce visibility and increase road accident.
Water entering to the pavement structure can cause different distress and decrease ride
ability and also may result in higher maintenance and operation cost of roads.
If the drainage systems are not well designed to suit the specific site condition, the drainage
system can easily stop proper function.
Absence of proper drainage system can be the main cause for health hazard. Therefore,
during the design of the drainage system the life of the road with the utilities and the
environmental aspect were considered in detail.
The hydrological study was undertaken in order to compute and evaluate peak discharges
for all watercourses crossing the project road. Calculation of these peak discharge values
then enabled the determination of the hydraulic opening sizes and types of waterway
required for the roads projects.
Peak discharge is the maximum discharge in cubic meters per second of the watercourse at
its crossing of the project road during design peak flood.
The hydrological analysis was undertaken using available maps and aerial photographs
together with available data from Meteorological Services Agency. Additional hydrological
and geological information has been gathered from site visits to the area.
From the studies undertaken, it was found that there are some 34 catchments along the
three road projects. Of these, two of themare major stream crossings, whilst the remainder
is small streams and local flows.
All of the streams / rivers are un-gauged. For the evaluation of the flood discharge of the
watercourses crossing the road, available rainfall data and high flood marks have been
utilized
Storm sewers should be designed to avoid surcharging, i.e. the situation where flow is under
pressure and water is pushed up through inlets and other facilities. The Consultant has
Dimension of pipes
Spacing of inlets
Slope of pipes
The road project is situated in developed area of the city and for this reason it is treated
with the principle of urban hydrology.
In regard to the hydraulics the objective is to first carryout condition survey of the existing
drainage systems and to compute the opening requirement, which aims meeting the two
major objectives in the design of drainage of the road:
The terrain classification is made based on the specification, which is commonly used by
most manuals in the country, i.e. 0 - 10% for flat to rolling terrain, 10% - 20% for hilly terrain
and > 21% for mountainous terrain.
Based on the above terrain classification criteria, the project roadis classified into flat and
rolling terrains.
Land Use
The land use of most of the catchments in the road project is as follows:
All the minor crossings have urban catchments with mixed commercial and residential.
The land use of the major crossings are shown in the table below:
1 C1 0+080 70 30
2 C3 2+420 40 60
3 C5 3+640 60 40
4 C7 6+650 80 20
Longitudinally there is overland flow, which needs to be collected away from the road.
The land use along the road is commercial and business area
Climate
The project area is located on the highlands of the Ethiopian plateau, i.e. having altitude
over 2000. Therefore, the project area is considered Dega. The effective temperature is
lower than 250c, which is good and most of the time comfortable.
The project area gets mean annual rainfall in the range of 918 - 1567mm, and the rainy
period is between June through September, although occasional shower is expected in the
months of March, April, May, October and November.
The mean monthly rainfall is maximum during the months of July and August i.e. 250mm
and 280mm and it is minimum during the months of November and December i.e. 8mm and
9mm respectively.
Table 1-21: Mean Monthly rainfall (mm) of the Addis Ababa area
Mont Ja Feb Mar Apr Ma June July Aug Sept Oct No De
h n y v c
Rainfall 17.6 39.7 68.5 91.3 77.3 119. 253. 279. 172. 39.2 8.1 9.2
(mm) 2 6 6 9
For the Addis Ababa area, the monthly temperature is maximum during the months of
March through May, about 27.50c, and it is minimum in the months of November through
January, 4.70c.
Max. 25.1 26.0 27.0 27.2 27.9 24.4 22.3 21.3 23.1 24.4 24.7 24.4
Min. 4.7 5.5 8.7 9.4 9.7 8.9 9.1 9.3 8.7 6.5 4.7 4.7
For the big catchments delineation topographic maps of scale 1:50,000 as well as DEM of
3om are used.
Also Nortech maps of Addis Ababa are used in addition to the above maps listed.
Watersheds or Basins
The catchment area of the watershed upstream of the crossing point is an important
parameter in determining the peak discharge. Along the road project, there are some 7
catchments. Of these, 4 accommodate major stream crossings, whilst the remainders are
small streams. These catchments, showing the limits of the watersheds (or basins) were
delineated from the available topographic maps, aerial photos and digital elevation models
are presented in figure. All catchmentsdrain from North to south and finally toAwash River.
Soil type is one of the dominant factors for rainfall-runoff process however for urbanized
catchments it is mainly depends of the land cover/surface type.
The soil types of the watershed areas are examined in this section to classify the soil with
respect to infiltration and runoff i.e. to determine the runoff coefficient or curve number of
Field Surveys
Field surveys were carried out to gather hydrological and hydraulic data related to the
road’s drainage system. The following important data and information was gathered during
these visits.
Factors affecting the maximum discharge of a waterway are catchment area, slope, soil type
and vegetation (land cover and land use), intensity of rainfall and duration of storm. Various
methods of determining the peak or maximum discharge have been deployed; some being
more appropriate for larger catchments and others for smaller catchments. Therefore, in
the study of this particular project, the most appropriate method for each waterway
crossing has been applied.
Rainfall Analysis
In Section 1.3.2.1 probabilistic extrapolation is described of the available annual rainfall and
in Section 1.3.2.2 relationships determination is described between rainfall in mm and
rainfall duration in hours.
In order to apply the available rainfall data for the computation of discharges, the readily
available and collected rainfall data should be analyzed and processed.
The analysis and processing will be aimed at determination of appropriate intensity duration
relationship applicable for the project road. Using the short period data to be obtained for
the project will be used to establish intensity-duration curve. From rainfall data with
duration of 0.17, 0.33, 0.50, and 24 hours collected from the NMSA by developing the trend
line of the intensity-duration curve, the trend equation applicable for project is developed.
The rainfall depth computation for the specified return period of the respective rain gauge
stations is carried out using the following relationship:
hT X avg KT *
= Standard deviation
1 in
And X Xi
n i 1
1
1
Xi X 2 2
n 1
RAINFALL-DURATION RELATIONSHIP
For rainfall intensity duration curve computation, rainfall data of Bole MetrologicalStation is
used, which is closer to the project areas.
Table 1-23: Rainfall depth for different duration and different return period
Rainfall depth, h [mm]
Table 1-24: Rainfall intensity for different duration and different return period
Rainfall depth, h [mm]
Taking into account the values for the project area, the following relationships between
rainfall h (in mm) and duration T (in minutes) were determined for different return periods
(see figure Annex-1.5):
h50 = 6.891*T0.4827
h25 = 6.3581*T0.4829
h10 = 5.6354*T0.4834
h5 = 5.0591*T0.4839
The following relationships between rainfall intensity I (in mm/hour) and duration T (in
minutes) correspond to those above indicated (see figure Annex-1.4):
I25 = 380.71*T-0.5164
I10 = 338.05*T-0.5165
I5 = 304.24*T-0.5168
As per the AACRA Drainage Design Manual (2003) for computation of pick flood of minor
structures the return period shown in table 4.1 is recommended to be used for the roads
projects:
Table 1-25: Return period used for design of pick flood (AACRA’S Drainage Design
Manual)
Roadway Classification Exeedance Return Period
Probability
The stream crossings are generally designed to pass peak floods with up to 50 or 100 return
periods. However table 4.1 does not specifically give return period for different drainage
structures. For comparison ERA’s Drainage Design Manual (2002) is presented in table 4.2
for road class equivalent to the road projects (DS1/DS2).
For design of these road projects a combination of table 4.1 and 4.2 is used.
Table 1-7: Return period used for design of pick flood(ERA’S Drainage Design Manual)
Type of drainage structure Return period to be used
In the flood computation when the catchments area is less than 0.8km 2 as per AACRA
Drainage Design Manual, 2003, the Rational Formula will be used and if the catchments
areas are greater than 0.8 km2 SCS method will be used.
i) Rational Formula
This relationship is believed to provide adequate results for catchments less than 80ha as
per AACRA Drainage Design Manual, 2003. The main assumption in this formula is that the
maximum rate of flow results from a uniform rainfall intensity over the entire drainage area
where the rainfall has duration equal to the time of concentration.
The principal requirement for determining the time of concentration is to select the average
rainfall intensity for a selected frequency of recurrence.
QT 0.00278 CIA
The rational equation given above is applicable for return periods 5 to 10 years. For less
frequent flood computation the rational equation should be multiplied by 1.1, 1.2, and 1.25
for return periods 25, 50 and 100 years recurrence interval respectively.
Time of Concentration:
This method is used basically for overland flow with uniform slope and short distance not
exceeding 100m. The time of concentration can be computed using the following equation.
0.8
5.476 nL
tc 0.5
P2 S
The concentration time TC in hours is calculated with the help of Kirpich formula.
0.77
L 1
TC 0.0195
0 .5
H / L 60
b) Velocity Method
This method is applicable to sheet flow, shallow concentrated flow, pipe flow, or channel
flow.
L
TC
3600 * V
Taking in to account the terrain type, land use and soil condition of the project area, suitable
runoff coefficients will be determined. The dominate factor in the selection of rational
formula is land use/ percentage of area paved.
The US Soil Conservation Service developed this method, which is applicable for urban
environment. The inputs for peak discharge estimation includes variables reflect the size of
the contributing areas, the amount of rainfall, the potential watershed storage, and the
time-area distribution of the watershed.
The SCS runoff equation is a method of estimating direct runoff from 24-hour or 1-day storm
rainfall. The equation is:
P 0.8 S
The potential maximum soil water retention, S, is related to hydrologic soil properties, land
cover and management conditions as well as, the soil moisture status of the catchment’s
prior to rainfall event and expressed by a dimensionless response index termed the
catchment’s curve number (CN).
25400
S 254
CN
The CN number is selected according to the soil, moisture and the land cover of the
watershed area.
The SCS Unit Hydrograph method peak rate of flow is computed using the following
equation:
0.2083 A PC 0.2083 A PC
Q 0.5
0.5 TC 0.6 TC tp
The computed peak flood for the crossing streams are shown in Annex-2
3.5.4 HYDRAULICS
INTRODUCTION
In part I the pick flood for the waterway openings was calculated based on the Hydrology
characteristics of the catchments. In this Part (Part II) the design related to the hydraulics is
determined
Opening sizes were computed using hydraulic analysis of the computed discharges for the
corresponding discharges.
Safe opening is determined to safeguard against scour due to constriction and general
scour. In the hydraulic computations, important local hydrological and geomorphological
characteristics have been taken into consideration.
Stage discharge curve was developed for each major stream to determine the maximum
flood level.
Along the road to avoid spread of water gutter is designed on both side of the road. The
gutter is connected to curve inlet at a minimum spacing of 25m at grading section and 20m
at sag vertical curve and the inlets are connected to longitudinal drainage pipes (storm
sewers).
The size, location, type, and structural condition of existing structures on the stream under
study can be a valuable indicator when selecting the size and type for any new structure.
Therefore, the hydraulic capacity and structural conditions of the facilities has been
extensively surveyed.
The most challenging problem in urban drainage design is lack of well established drainage
master plan and as built drawing for utilities.
The longitudinal drainage designed from station 5+560 to 4+540 requires intensive follow
up and site adaption during construction, because it is very difficult to get detailed
information regarding junction road drainage conditions. Hence the design couldn’t consider
the connectivity of drainage pipes with the existing junctions’ longitudinal pipes.
OPENING REQUIREMENTS
In determining the opening sizes a detailed hydraulic analysis has been carried out. A stage-
discharge curve has been generated based on the river geometry, roughness coefficient and
the slope of the riverbed. After obtaining the stage-discharge curve, an appropriate stage
has been read from the graph that corresponds to the design discharge. A 100 year return
period was taken in the hydrological computation with the assumption that all the major
structures will be bridge with span greater than 15m.
Safe opening is determined/cheeked with existing size to safeguard against scour due to
constriction and general scour. In the hydraulic computation, important local hydrologic
and geomorphologic characteristics have been taken into consideration.
SCOUR CHECKS
A Manning formula has been used to compute the stage discharge of the river channel at
the crossings and determine the scouring velocity for all major bridges.
Maximum local scour depth under abutments and piers was determined using the method
derived from Laursen 1960 equation and prepared by Joseph H. Bradely, U.S. Department of
Transportation, for alluvial and incised rivers.
Since all of River bridge crossings have bed rock foundation, scouring is not serious problem.
To avoid localized scouring in the joint of the rock constriction of channel is avoided.
SIZE SELECTION
After computing the design discharge corresponding to the return period of the structure
using the available meteorological and topographic data, culvert size selection has been
carried out according to the Manning’s Formula based on the design discharge, roughness
coefficient, slope of the stream and geometrical data of the cross section.
Where:
= A/P
Q=V*A
Slab culverts are used up to 6-meter span. The minimum size of pipe culverts is 760 mm
(30 inch) diameter and 1500mm diameter has been taken as the largest size. When a single
1500 pipe culvert is insufficient for the design flow, box/slab culverts or multiple cell culverts
will be utilized.
Some of the typical decisions that are made in the design of the drainage are:
Dimension of pipes
Spacing of inlets
Slope of pipes
During the study stage the major crossings were observed consisting of urban catchment’s
and natural catchment’s. The area of the natural catchments is expected to reduce with
time as urban area expands, which will result in increase of impervious area. In the pick
discharge computation this is taken into consideration.
Side ditches/longitudinal pipes are an important part of the drainage system especially in
town sections and in cut areas. The major purpose of roadside channels/pipes is to collect
surface runoff from the road and adjacent areas which drain to the right of way and convey
the accumulated runoff to acceptable outlet points.
The longitudinal pipe design will be based on the Manning’s formula, given by:
Q = 1/nAR2/3S1/2
Where,
n = Manning’s roughness coefficient
A = Cross sectional area of the ditch/pipe
R = Hydraulic Radius
S = Longitudinal slope of the channel/pipe
Q = the design discharge
The design discharge will be determined by the rational formula. The discharge will be based
on the rainfall intensity 10 years return period for DS1. The rainfall duration will be based on
the time of concentration. The rainfall intensity will be derived from the IDF curve. The
Manning’s roughness coefficient for lined and unlined channels will be obtained from
standard tables of drainage design manuals.
GUTTER
Gutter flow calculations are necessary to establish the capacity of the gutter within the
spread and puddle depth criteria. Gutter capacity is determined based on a modified form
of Manning’s equation, the Izzard formulae, modified for triangular sections having a single
cross fall cross slope (AACRA Drainage Design Manual 2003).
Q 0.375 F d 8 / 3 S o Z / n
0.5
F = flow correction factor (0.9 for simple triangular sections and 0.8 for gutter
sections having different slope from the cross slope of roadway
Desirable gutter grades should not be less than 0.5%. Minimum pavement cross slope
should not be less than 2% for new construction/re-construction.
INLET
Types of Inlets:
Inlets are placed to intercept the concentrated flow of storm water. Three types of gulley
pit inlets are considered: Kerb or side entery openings, Grated opening and Combination
kerb opening and grate. Kerb or side entery opening type of inlet is selected due to the
suitability for Addis Ababa, where there is a lot of debris which can block the grate easily
and also the expected overlay might done negligently over the grate.
Inlets are located at the following critical locations of the road independent of hydraulic
calculations:
In most drainage design manuals the minimum spacing of the inlets is 90m (300 feet). In
Addis Ababa city there is higher proportion of unpaved access roads connected to the
Arterial or collector roads which results in higher sediment transport to the paved road. As
well as unexpected flood could come from junction this will force us to keep the minimum
spacing of inlets to lower value. For this design minimum spacing of inlets is taken 25m.
In locations where significant ponding may occur, such as at underpasses or sag vertical
curves in depressed sections, it is recommended practice to place supplemental inlets on
each side of the inlet at low point in the sag.
Capacity of Inlets:
a) On grade:
Flow interception by slotted inlets is side weir and the flow is subjected to lateral
acceleration due to the cross slope of pavement. Thus the equation with a straight cross
slope is expressed by:
Sx
a
LT KQ 0.42 S 0.3 1 / nS x
0.6
Where:
K = 0.817
The efficiency of slotted inlets shorter than the length required for total interception is
expressed by:
E 1 1 L / LT
1.8
Storm sewers should be designed such that velocities of flow will not be less than 0.91m/s
at design flow. For very flat grades, the general practice is to design components so that
flow velocities will increase progressively throughout the length of the pipe system. The
storm sewer system should be checked to be sure there is sufficient velocity in all of the
drains to deter settling of particles. Minimum slopes are given in table 2.2:
Pipe Size [mm] Pipe Size [inch] % Grade for self cleansing
760 30 0.15
915 36 0.12
1070 42 0.12
1220 48 0.10
In general, as the road ways are all widened the existing side drains need to be replaced. In
designing the side drains care should be taken to protect from blockage by foreign materials
as garbage and solid wastes by inhabitants to create water pools or blockage of the drains.
Because of this closed conduits are recommended in cities and big towns for side drains to
collect the water from the surroundings and direct to the cross drainage structures or other
out let.
In order to determine the capacity/size of longitudinal pipes, the areas that are
contributing/draining to the road corridor/ as well as pavement area has to be considered.
MANHOLE
The following general design guidance for location and spacing of manholes to be used:
For trunk sewers 36” (915mm) diameter and under, space approximately 100m
apart to facilitate maintenance.
For trunk sewers 42” (1070mm) diameter and over, space approximately 100
pipe diameters apart.
At angles in the main sewer
At points where the size of the sewer changes
At points where the grade of the sewer changes
At the junction of sewer lines
At street intersections or other points, such as connecting lines to catch basins
or inlets
Access manholes for sewer inspection on large tunnel sewers shall be spaced at
approximately 360m centers
At points where pipe material changes
3.5.5 Structures
3.5.5.1 SELECTION OF CONSTRUCTION MATERIALS
The possible types of construction materials required for the drainage and grade separation
bridges in the subject project are considered at the preliminary design stage. The use of
timber and similar construction materials is not feasible for bridges found in such a capital
city like Addis. Steel bridges and reinforced concrete bridges are two possible options of
which reinforced concrete is preferred as the most feasible option based on the following
reasons. The followings are some of the reasons considered while comparison is made
between steel bridges and reinforced concrete bridges.
Steel Structures are usually preferred for bridges whose services are needed
very urgently as their construction is very fast.
Steel bridges need continuous inspection and maintenance as damage or loss
of some members or bolts and nuts might result in collapse of the whole
structure.
Maintenance frequency and cost of steel structures is very high compared to
that of reinforced concrete structures.
The construction of reinforced concrete structures is more familiarized in the
country than that of steel structures. Steel may need to be imported.
It is difficult to find steel bridges from manufacturers which exactly satisfy the
entire cross sectional requirements of the subject road standard. And hence
results in delay and additional cost.
The required span of the bridge in this project is within the allowable range
for reinforced structures. (Table 4.1’Superstructure Type Selection Guide’ of
AACRA Bridge Design Manual.)
Based on the above reasons and other economic considerations, reinforced concrete is
preferred as the main construction material to be used in the design of superstructure and
substructure of the bridges. However, stone masonry shall also be used for retaining walls at
the edge of the road with lower heights.
The engineering properties of reinforcement steel, concrete and stone masonry utilized
during detail design are summarized as follows.
The steel and iron factories of the country produce steel with yield strength of 300Mpa for
diameters less than 20mm, and 420Mpa for bars larger than or equal to 20mm diameter.
Therefore the consultant shall use these practical data during the detail design of the
bridges.
As the height of abutment of drainage bridges are found to be very short it is recommended
to use stone masonry abutment and wing wall as construction material of the substructure
for the subjected bridge. The height of existing bridges at 2+500(18m RCDG) is 7m and at
3+700(16m concrete Arch) is 6m therefore there is no any requirement of using reinforced
concrete abutment hence stone masonry abutment and wing wall shall be provided.
Two options were available for the superstructure of the two drainage bridges. The first
option is extension of the existing 18m RCDG at 2+500 and 16m concrete arch bridge at
3+700 superstructure to meet the geometry requirement of the new road, while the second
option is provision of entirely new bridges. Considering conditions of these bridges the
consultant recommended extending both existing bridge considering the traffic disturbance
and soundness of the structure.
The only problem faced during the design of the subject project is the fact that the existing
bridge at 2+500 is dwarf becomes an obstacle to improve the vertical alignment of the road
as per the design requirement.
There were two option of solving the problem faced at this stage. The first option is to
utilize the existing bridge by widening to meet the new geometry requirement and improve
the approach through intensive earth work, while the second option is to abandon the
existing bridge and construct entirely a new bridge with raised finished level to solve the
vertical alignment problem. Therefore the consultant recommends using the existing
structure by extending to meet geometric width considering the difficulty of traffic
accommodation while demolishing the bridges and reconstruction activities. The consultant
may reconsider the options during construction stage if there are possible ways of traffic
accommodation.
ANNEX – I (PRIMARY
AND SECONDARY
CONTROL POINTS)
ANNEX – II
(HORIZONTAL
ALIGNMENT DATA)
ANNEX – III
(VERTICAL
ALIGNMENT DATA)
ANNEX – IV (SOIL
EXTENSION SURVEY)
ANNEX – VI
(HYDRAULIC
ANALYSIS SHEETS)
ANNEX – VII
(SAMPLE OF
STRUCTURAL
ANALYSIS )