P FD File
P FD File
DEVELOPMENT CORPORATION
(KINFRA)
Detailed Project Report (DPR) for
Petrochemical Industrial Park at
Ambalamughal, Kochi, Kerala
PREPARED BY
QUALITY CONTROL
REVISED FINAL DETAILED PROJECT REPORT (DPR)
for Development of Petrochemical Park for at Ambalamughal, Kochi
SUBMITTED TO
Kerala Industrial Infrastructure Development Corporation (KINFRA)
KINFRA House, TC 31/2312, Sasthamangalam
Thiruvananthapuram - 695 010, Kerala
P a g e |i
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
TABLE OF CONTENTS
1. Salient Features ............................................................................................................................. 1
2. Executive Summary ...................................................................................................................... 7
2.1. Introduction .............................................................................................................................. 7
2.2. Demand Analysis ..................................................................................................................... 7
2.3. Site Master Plan .................................................................................................................... 10
2.4. Infrastructure Demand Assessment ...................................................................................... 11
2.5. Project Cost Estimate ............................................................................................................ 11
2.6. Environmental Impact Assessment ....................................................................................... 14
2.7. Project Viability and Sensitivity .............................................................................................. 14
2.7.1. Project Financing ......................................................................................................... 15
2.7.2. Park Revenues ............................................................................................................ 15
2.7.3. Expenses ..................................................................................................................... 16
2.7.4. Project Viability ............................................................................................................ 16
2.7.5. Economic Cost benefit analysis .................................................................................. 16
3. Introduction.................................................................................................................................. 19
3.1. Project Background ............................................................................................................... 19
3.2. Scope of Study ...................................................................................................................... 20
3.3. Objective of the Project.......................................................................................................... 20
3.4. Regional Setting .................................................................................................................... 20
3.4.1. Regional Location ........................................................................................................ 20
3.4.2. Regional Connectivity .................................................................................................. 22
3.4.3. Regional Profile ........................................................................................................... 23
3.4.4. Key Takeaways - Regional Context ............................................................................ 24
3.5. Site Analysis .......................................................................................................................... 24
3.5.1. Site location ................................................................................................................. 24
3.5.2. Site Connectivity .......................................................................................................... 25
3.5.3. Site Surroundings ........................................................................................................ 25
3.5.4. Approach and Access ................................................................................................. 27
3.5.5. Shape and Size ........................................................................................................... 28
3.5.6. Site Topography .......................................................................................................... 28
3.5.7. Climate ........................................................................................................................ 29
3.5.8. Elevation ...................................................................................................................... 29
3.5.9. Slope ........................................................................................................................... 31
3.5.10. Drainage ................................................................................................................ 31
3.5.11. Land Details .......................................................................................................... 32
3.5.12. Key Takeaways - Site Context .............................................................................. 33
3.5.13. On-site Infrastructure............................................................................................. 34
3.5.14. Off-site Infrastructure............................................................................................. 34
3.6. Environmental Considerations ............................................................................................... 34
3.7. Rehabilitation and Resettlement (R&R) issues ..................................................................... 35
3.8. SWOT Analysis ...................................................................................................................... 35
4. Status of Feasibility Studies ...................................................................................................... 37
5. Demand Analysis ........................................................................................................................ 38
5.1. Project Background ............................................................................................................... 38
5.2. Need for the Chemical Park in Kochi ..................................................................................... 38
5.3. Scope of the Market Study .................................................................................................... 39
5.4. Market Assessment for KINFRA Park ................................................................................... 40
5.4.1. Likely Feedstock available in the KINFRA Kochi Park catchment area including BPCL
refinery and propylene derivative petrochemical project (PDPP) .......................................... 40
5.4.2. Opportunities for Manufacture - KINFRA Park ............................................................ 41
P a g e |ii
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |viii
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
List of Tables
Table 1-1: Salient Features of Detailed Project Report (DPR) ............................................................... 1
Table 2-1: Likely available Feedstock in the Catchment area-Kochi Park ............................................. 7
Table 2-2: Potential Project Opportunities based on available feedstock in the Catchment area .......... 7
Table 2-3: Accessible market Potential of Land for KINFRA Park for target industry (Year 2017-27) ... 8
Table 2-4: Plotted Land Allocation by Product Categories – KINFRA Park (Acres) ............................... 9
Table 2-5: Proposed Land Use Break up for Entire Project Site Area .................................................. 11
Table 2-6: Summary of Project Cost Estimates .................................................................................... 13
Table 2-7: Overall Development Cost ................................................................................................... 14
Table 2-8: Impact of Petrochemical Park Usage .................................................................................. 17
Table 2-9: Annual Benefits of Proposed Project ................................................................................... 17
Table 2-10: Cost Benefit Ratio of Proposed Petrochemical Park ......................................................... 18
Table 3-1: Kerala State Profile .............................................................................................................. 21
Table 3-2: Land Details at Project Vicinity ............................................................................................ 32
Table 3-3: Environmental Sensitivity around the Project ...................................................................... 34
Table 5-1: Likely available Feedstock in the Catchment area-Kochi Park ........................................... 40
Table 5-2: Potential Project Opportunities based on available feedstock in the Catchment area ........ 42
Table 5-3: Forecasted Demand Supply Gap of Select/targeted Intermediates (possible from BPCL
Feedstock)-India 2017-27 ..................................................................................................................... 43
Table 5-4: Estimated market for targeted Specialty chemicals India ($ bn) ......................................... 46
Table 5-5: All India Land Area Demand Potential for target Petrochemicals and Chemicals (Year
2017-27) ................................................................................................................................................ 53
Table 5-6: Accessible Land area potential for KINFRA for Intermediates (2017-27) .......................... 56
Table 5-7: Accessible market Potential of Land for KINFRA Park for target Petrochemicals and
Chemicals (Year 2017-27) .................................................................................................................... 59
Table 5-8: Plotted Land Allocation by Product Categories –KINFRA Park (Acres) .............................. 61
Table 5-9: Comparison of salient features of Chemical Parks/Zones across the world ....................... 65
Table 5-10: Investors Wish List ............................................................................................................. 80
Table 5-11: Estimated Annual Sale Plan of Plotted Land-KINFRA Park .............................................. 81
Table 5-12: Market Proximity Advantage-KINFRA Park ....................................................................... 82
Table 5-13: Cost of Sellable Land in proposed KINFRA Petrochemical Park ...................................... 83
Table 5-14: Competitive Land Prices .................................................................................................... 84
Table 5-15: Land Prices in Urban cities with combination of refinery & Port facility ............................. 84
Table 5-16: Land Banks Available in preferred State in India ............................................................... 85
Table 5-17: Comparative Incentives for manufacturing units ............................................................... 85
Table 5-18: Electricity Charge per Unit by states.................................................................................. 86
Table 5-19: Comparative Water Tariff ................................................................................................... 86
Table 5-20: Target market & Regions ................................................................................................... 87
Table 5-21: Recommended Land Pricing by types of Units .................................................................. 89
Table 5-22: Tentative Promotion Plan- KINFRA Petrochemical Park .................................................. 92
Table 5-23: Estimated Budget for Marketing the Park .......................................................................... 92
Table 6-1: Proposed Population Estimation .......................................................................................... 98
Table 6-2: Proposed Length of Roads ................................................................................................ 100
Table 6-3: Proposed Land Use Break up for Entire Project Site Area ................................................ 102
Table 6-4: Proposed Plot Parcellation for Industrial Park ................................................................... 103
Table 7-1: Land use wise area and traffic population distribution....................................................... 117
Table 7-2: Modal Split & Occupancy ................................................................................................... 118
Table 7-3: Output Tonnage ................................................................................................................. 118
Table 7-4: Truck Movement ................................................................................................................ 118
Table 7-5: Number of Commercial Vehicles ....................................................................................... 119
Table 7-6: Generated Passenger Vehicles ......................................................................................... 119
Table 7-7: Distribution of Total Traffic ................................................................................................. 120
Table 7-8: Traffic Density in % age Gate Wise ................................................................................... 120
Table 7-9: Sub Division of Traffic Road Wise ..................................................................................... 121
Table 7-10: ECS of Vehicles ............................................................................................................... 123
Table 7-11: Parking Demand Assessment ......................................................................................... 123
Table 7-12: Generated Vehicles Due to Development ....................................................................... 123
Table 7-13: Total Daily Occupancy ..................................................................................................... 124
P a g e |ix
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Table 8-6: Development Cost Phasing (In Rs. Crore) ........................................................................ 240
Table 9-1: Cost to BPCL ..................................................................................................................... 241
Table 9-2: Land Absorption (Acres) .................................................................................................... 242
Table 9-3: Total Investment (in Rs. Crore - - Rounded off to nearest Integer) ................................... 244
Table 9-4: Working Results (Rs. Crore- Rounded off to nearest Integer) .......................................... 244
Table 9-5: Cash Flow (Rs. Crore- Rounded off to nearest Integer) .................................................... 245
Table 10-1: Economic Impact ............................................................................................................. 246
Table 10-2: KINFRA Petrochemical Park: Economic Benefit ............................................................. 247
Table 10-3: KINFRA Petrochemical Park: Economic Benefit ............................................................. 247
Table 10-4: KINFRA Petrochemical Park: CBA Economic Benefit (Rs. Crore) .................................. 248
Table 10-5: Risk Probabilities and its mitigation ................................................................................. 248
Table 11-1: The Details of the Categories .......................................................................................... 249
Table 11-2: EIA Report Structure ........................................................................................................ 250
Table 11-3: Site Information Summary ............................................................................................... 252
Table 11-4: Environmental Sensitivity Details..................................................................................... 253
Table 11-5: Environmental Monitoring Plan ........................................................................................ 255
Table 12-1: Potential Environmental Impacts ..................................................................................... 259
Table 12-2: Risk Probabilities and its Mitigation ................................................................................. 266
Table 13-1: Roles and Responsibilities of Developer and Member Industries ................................... 267
P a g e |xi
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
List of Figures
Figure 1-1: Project Management Organisation Strategy ........................................................................ 5
Figure 1-2: Implementation Schedule ..................................................................................................... 5
Figure 1-3: Brief Outlay of Project Control Systems ............................................................................... 6
Figure 3-1: Location Map of Ernakulam District and Project Site ......................................................... 21
Figure 3-2: Regional Location and Connectivity Map of the proposed site .......................................... 23
Figure 3-3: Kerala District Wise Population – Census 2011 ................................................................. 23
Figure 3-4: Map Showing nearby Settlements to Project Site .............................................................. 25
Figure 3-5: Site Surroundings ............................................................................................................... 26
Figure 3-6: Pictorial illustrations of the proposed project site region and environs .............................. 27
Figure 3-7: Site Dimensions of Petrochemical Park ............................................................................. 28
Figure 3-8: Elevation Analysis of Petrochemical Park .......................................................................... 29
Figure 3-9: Site Profile .......................................................................................................................... 30
Figure 3-10: Slope Analysis of Petrochemical Park .............................................................................. 31
Figure 3-11: Drainage Features at Petrochemical Park ....................................................................... 32
Figure 3-12: Map of Proposed Project Site ........................................................................................... 33
Figure 5-1: Specialty Chemical Market - India (2014). ......................................................................... 45
Figure 5-2: Polyurethane Market India by applications-2016 ............................................................... 51
Figure 5-3: Global Benchmarking Comparison “Chemical Sites' Success Factors .............................. 63
Figure 6-1: Principles for Sustainable Development ............................................................................. 94
Figure 6-2: Planning Concepts ............................................................................................................. 95
Figure 6-3: Existing Land use around the Project Area ........................................................................ 97
Figure 6-4: Zoning Plan......................................................................................................................... 99
Figure 6-5: Proposed Circulation Network Entry / Exit Plan ............................................................... 101
Figure 6-6: Proposed Land Use Distribution ....................................................................................... 101
Figure 6-7: Proposed Land Use Plan .................................................................................................. 102
Figure 6-8: Proposed Industrial Plots .................................................................................................. 103
Figure 6-9: Proposed Utilities .............................................................................................................. 104
Figure 6-10: Proposed Green / Open Area ......................................................................................... 105
Figure 6-11: Boundary Wall Layout Plan ............................................................................................ 115
Figure 7-1: Traffic Circulation Plan ..................................................................................................... 122
Figure 7-2: Typical ROW – 24m Wide (External Road) ...................................................................... 126
Figure 7-3: Typical ROW – 22m Wide (external Road) ...................................................................... 126
Figure 7-4: Typical ROW – 20m Wide (Internal Road) ....................................................................... 127
Figure 7-5: Typical ROW – 19m Wide (Internal Road) ....................................................................... 127
Figure 7-6: Site Levelling and Grading Work of Petrochemical Park Project ..................................... 131
Figure 7-7: Storm Water Network Drawing - 1 .................................................................................... 152
Figure 7-8: Storm Water Network Drawing - 2 .................................................................................... 152
Figure 7-9: Potable Water Network – 1 ............................................................................................... 168
Figure 7-10: Potable Water Network – 2............................................................................................. 168
Figure 7-11: Water Balance Sheet ...................................................................................................... 170
Figure 7-12: Recycled Water Network – 1 .......................................................................................... 176
Figure 7-13: Recycled Water Network – 2 .......................................................................................... 176
Figure 7-14: Sewergems Model .......................................................................................................... 185
Figure 7-15:Sewerage Network – 1 .................................................................................................... 198
Figure 7-16: Sewerage Network – 2 ................................................................................................... 199
Figure 7-17: Thematic View of Road Lighting ..................................................................................... 228
Figure 7-18: Waste Categories ........................................................................................................... 232
Figure 7-19: Safety Requirements in the Gas Supply Regulations .................................................... 235
Figure 15-1: Project Implementation Schedule ................................................................................... 275
P a g e |xii
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
List of Abbreviations
AADT : Annual average daily traffic
AASHTO : American Association of State Highway and Transportation Officials
ATF : Aviation Turbine Fuel
APIs : Active Pharmaceutical Ingredients
BC : Bituminous Concrete
BDPP : Brahmapuram Diesel Power Plant
BIS : Bureau of Indian Standard
BOQ : Bill of Quantity
BPCL : Bharat Petroleum Corporation Limited
BS : British Standards
BSNL : Bharat Sanchar Nigam Limited
c/way : Carriage Way
CAGR : Compounded Annual Growth Rate
CBR : California Bearing Ratio
CCTV : Closed Circuit TV
CDMA : Code Division Multiple Access
CETP : Common Effluent Treatment Plant
CFS : Container Freight Station
CPHEEO : Central Public Health and Environmental Engineering Organization
CPWD : Central Public Works Department
DBM : Dense Bitumen Macadam
DCI : Deliverables Control Index
DI : Ductile Iron
DLC : Dry Lean Concrete
DPR : Detailed Project Report
DSR : Delhi Schedule of Rates
DTA : Domestic Tariff Area
DTM : Digital Terrain Model
EHT : Extra High Tension
EIA : Environmental Impact Assessment
EO : Ethylene Oxide
EPDM : Ethylene Propylene Diene Monomer
ETP : Effluent Treatment Plant
FACT : Fertilizers and Chemicals Travancore Limited
FCC : Fluid Catalytic Cracking
FDI : Foreign Direct Investment
FRBL : FACT - RCF Building Products Ltd
FRL : Finished Road Levels
FRP : fibre-reinforced polymer
GDP : Gross Domestic Product
GIDC : Gujarat Industrial Development Corporation
GSB : Granular Sub-Base
GSM : Global System for Mobile Communications
P a g e |xiii
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
GSS : Grid-Substation
GVA : Gross Value Added
Ha : Hectare
HDPE : High Density Polyethylene
HFL : High Flood Level
HOCL : Hindustan Organic Chemicals Limited
HPSV : High-Pressure Sodium Vapour
HSD : High Speed Diesel
HT : High Tension
HVAC : heating, ventilation, and air conditioning
ICTT : International Container Transshipment Terminal
IDF : Intensity- Duration- Frequency
IEC : International Electro technical commission
IMD : Indian Meteorological department
IRC : Indian Road Congress
KEIL : Kerala Enviro Infrastructure Ltd
kg : Kilogram
KINFRA : Kerala Industrial Infrastructure Development Corporation
kmph : Kilo meter per hour
KSEB : Kerala State Electricity Board
KTA : Kilo Tons Per Anum
kV : Kilo Volt
kW : Kilo Watt
LED : Light Emitting Diode
LNG : Liquefied Natural Gas
LTE : Low Temperature Evaporation
LV : Low Voltage
M : Metre
m/s : Metre per Second
MCC : Mixed Commercial Centre
MED : Multiple-Effect Distillation
MEG : Mono Ethylene Glycol
MGD : Millions of Gallons per Day
MLD : Million Liter per Day
mm : Millimetre
MoEF : Ministry of Environment & Forests
MORTH : Ministry of Road Transport and Highways
MRSS : Main Receiving Sub-Station
MSA : Million Standard Axels
MSF : Multistage Flash
MSW : Municipal Solid Waste
MTO : Methane to Olefins
Mtr. : Metre
MVA : Mega Volt Amp
NH : National Highway
P a g e |xiv
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |xv
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
1. Salient Features
The salient features of the Final Detailed Project Report (DPR) for the development of
proposed Petrochemical Industrial Park at Ambalamughal, Kochi, Kerala is provided below.
Table 1-1: Salient Features of Detailed Project Report (DPR)
S.No Item Description
1. Title of the project Detailed Project Report (DPR) for Development
of Petro Chemical Park for at Ambalamughal,
Kochi, Kerala.
2. District Ernakulam
Thaluk (a). Kunnathunadu, (b). Kanayannur
Corporation/Municipality/Panchayath Vadavukode Puthencruz Panchayath
Assembly Constituency Kochi
3. Implementing agency / SPV Kerala Industrial Infrastructure Development
Corporation (KINFRA)
4. DPR prepared by Voyants Solutions Private Limited (VSPL).
5. Project outlay Rs.317 Crores
6. Budget provision No Provision
7. Budget speech reference Not Applicable
8. Administrative sanction DPR Yet to be Submitted.
9. Nature of the project (New / Existing / New
Upgradation)
10. Present status of existing Not Applicable
11. Need for the project (Brief) The chemical industry is the main stay of
industrial and agricultural development of the
country and provides building blocks for several
downstream industries, such as textiles, papers,
paints, soaps, detergents, pharmaceuticals,
varnish etc. It is one of the most diversified of all
industrial sectors covering thousands of
commercial products. Petrochemicals constitute
a very important segment of world chemicals
market, with a share of nearly 40 per cent. The
value additions in the petrochemicals chain offer
immense possibilities and cater to the need of
textiles and clothing, agriculture, packaging,
infrastructure, healthcare, furniture,
automobiles, information technology, power,
electronics and telecommunication, irrigation,
drinking water, construction and a host of other
articles of daily and specialized usage amidst
other emerging areas. The share of this sector in
the country’s GVA of manufacturing sector is
currently estimated at 13.60 %. The size of the
Indian Chemical industry in terms of market in
the year 2015-16 according to Department of
Chemicals and Petrochemical statistics was
P a g e |1 Salient Features
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |2 Salient Features
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |3 Salient Features
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |4 Salient Features
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |5 Salient Features
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |6 Salient Features
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
2. Executive Summary
2.1. Introduction
Kerala Industrial Infrastructure Development Corporation (KINFRA) is a statutory body formed
by the Government of Kerala in 1993, by an act of state legislature for facilitating the
development of industrial infrastructure in the State. KINFRA has played a pioneer role in
developing industrial infrastructure in the State of Kerala. KINFRA has a very successful track
record in setting up 22 industrial parks across Kerala for facilitating development of the
industry in the State.
KINFRA intends to develop a Petrochemical Park of international standards at Ambalamughal,
Ernakulum District, Kerala. The project is intended to create an Industrial Park with all modern
facilities exclusive for the Petrochemical Industry. The Petrochemical Park is proposed to be
established in approximately 489.46 acres of land in FACT premises at Ambalamughal, Kochi.
This land already has near to it, a large refinery, fertiliser and chemical factories, LNG Terminal
and Gas Pipeline Network being established, a Bulk Terminal and International Container
Transhipment Terminal (ICTT). The proposal assumes significance in view of the expansion
proposal of BPCL, nearness to the Port and Natural Gas infrastructure at the location. The
industrial units in the park will be provided with all infrastructure facilities.
Voyants Solutions Private Limited (VSPL)., India, has been appointed by KINFRA to prepare a
Detailed Project Report (DPR) for Petrochemical Industrial Park at Ambalamughal in
Ernakulum District, Kochi, Kerala.
P a g e |7 Executive Summary
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Specialty
1600 512(32%) 350 350
chemicals
P a g e |8 Executive Summary
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
End Products
Paints/Inks and
530 27 (5%) 95 95
adhesives
PU /Nylon
600 192 (32%) 200 200
Components
SAP based
300 96 (32%) 90 90
Hygiene products
The total land area of the Park is 489.46 acres. Excluding the 15.34 acres of land area for the
Road, the available land for the Park is 474.12 acres. Out of this BPCL will be allocated 150
acres land for their future projects. Accordingly, the balance land available with KINFRA to
carve out plots will be 304.12 acres. According to master plan the plotted land available in
KINFRA Petro Park is 206 acres (both for utilities and manufacturing units). The Plotted land
allocated for manufacturing units in targeted Petrochemicals and chemicals is 184 acres which
is around 17% of the total Land market accessible of 1060 acres.
Table 2-4: Plotted Land Allocation by Product Categories – KINFRA Park (Acres)
Specialty Chemicals 32 8 40
Pharmaceutical APIs 30 0 30
CETP (5)
Common Facilities 15 15 Central Utilities and
Water supply (2)
P a g e |9 Executive Summary
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Table 2-5: Proposed Land Use Break up for Entire Project Site Area
S. No Land Use Area in Sq. Mt Area in Ac. % of Total
Area
1 Petrochemical Plots 630862.06 155.889426 51.26%
2 Pharma Plots 116961.19 28.9017425 9.50%
3 Utilities / Amenities 69792.97 17.2462203 5.67%
4 Truck Terminal Warehouse 19711.23 4.87075152 1.60%
5 Road & Utility Corridor 113716.9157 28.1000648 9.24%
6 GREEN * 279685.481 69.1117947 22.73%
7 Sub Total 1230729.847 304.12 100.00%
8 Proposed for BPCL Plots 687965.52 170
Total 1918695.367 474.12
FACT Road 62078.8 15.34
Grand Total Site Area 1980774.167 489.46
*In addition, 10.27% of net industrial plotted area will be developed as green belt within the industrial
units.
The cost of providing the boundary wall including chain link fencing is estimated at Rs.4.80
Crores and cost for retaining wall is estimated at Rs. 43.95 crores.
The total cost estimates for the Development of Road works is estimated at Rs. 40.88 crores,
Junction’s development is estimated at Rs. 0.34 crores and traffic signs and markings are
estimated at Rs. 0.48 Crores.
Power Supply and Distribution
Along the RoW of internal roads, an underground power distribution network is proposed for
the project and the total cost of providing the power distribution network including
substations is about Rs.61.16 Crores and its including development of telecommunication
networks.
It is proposed to provide street lighting along the roads within the project. The cost of street
lighting system for the project is estimated to be Rs.5.69 Crores.
Water Supply, Treatment and Distribution Network
The cost for the proposed water supply, storage and distribution network including
firefighting system is estimated at Rs.23.57 Crores.
Stormwater Drainage
Storm water drains of various sizes are proposed in the storm water drainage network system.
The cost of the storm water drainage system for the project is estimated at Rs.18.46 Crores.
Recycle Water System
The cost for recycle water inclusive of Earthwork excavation, laying pipes, thrust blocks,
specials, sump, pumping system etc., is estimated at Rs. 4.93 Crores.
Effluent and Sewage Collection System
The cost for effluent and sewage collection which is inclusive of including mechanical and
electrical works is estimated is Rs. 42.81 crores including construction of 5 MLD capacities of
CETP’s.
Contaminated Storm Water System
The cost for contaminated Storm water network system including pumping mains, CETP’s is
estimated as Rs. 25.35 Crores.
Firefighting System
The cost for development of firefighting networks is estimated as Rs. 2.73 Crores.
Solid Waste Management
P a g e |12 Executive Summary
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The hazardous waste of units inside the petrochemical park can be treated at existing TSDF
and only need to provide a 5-10 industrial dustbins here the cost for establishing the solid
waste management system within the site works out to be Rs. 0.07 Crores.
Landscaping
Green belt is proposed at required places within the project site. In addition, landscaping is
proposed in the traffic islands to improve the aesthetics of the project site. Trees shall be
planted all along the road and the development of the same is proposed to be in the scope of
developer.
The total cost for development of green belt and landscaping works out to Rs.0.20 Crores.
Buildings
The cost of common and amenity buildings viz., admin building (G+1), Cantin (G), R&D Lab
(G+1), and 2 warehouses (G) are estimated at Rs. 10.37 Crores.
Proposed Entry / Exit Gates
There are five entry / exit gates were proposed for petrochemical industrial park and the cost
for the development of proposed entry / exit gates is estimated at Rs. 2.79 Crores.
Summary of Project Cost
The estimated project cost for the development of petrochemical park is around Rs.317
Crores and the summary of project cost is shown in the below table and cost estimates is
exclusive of all the taxes and levies.
Table 2-6: Summary of Project Cost Estimates
S. Project Component Total Cost as per DPR Amount in % Age of
No. Rs. Crores Total
(Amount in Rs. Lakhs) Cost
1 Site Levelling & Grading Works 28,46,90,115 28.47 8.98
2 Boundary Walls and Retaining Wall 48,74,19,858 48.74 15.38
3 Landscaping and Design 20,06,655 0.20 0.06
4 Architectural Building Works 10,36,84,602 10.37 3.27
5 Proposed Entry / Exit Gates 2,79,16,598 2.79 0.88
6 Road Improvement Works 41,69,75,845 41.70 13.16
7 Potable Water Supply System 23,56,74,180 23.57 7.44
8 Stormwater Drainage System 18,45,63,864 18.46 5.82
9 Recycle Water System 4,93,01,180 4.93 1.56
10 Sewage Collection System & CETPs 42,80,55,224 42.81 13.50
11 Contaminated stormwater system & CETPs 25,34,86,393 25.35 8.00
12 Firefighting network system 2,73,36,062 2.73 0.86
13 Power Supply & Distribution 66,85,39,222 66.85 21.09
TOTAL COSTS 3,16,96,49,799 316.96 100
Source: Voyants Analysis.
The annual operation and maintenance expenditure on different components of the project
have been estimated considering the life of the component, repair and maintenance
requirements, consumables, etc., from the consultant’s data base. The costs are estimated as
a percentage of the capital cost (indicative) and are as follows:
Roads - 3%
Power Distribution Network – 3%
Storm Water Drainage – 3%
Fire Fighting – 2%
CETP and STP – 7.5%
Effluent and Sewage Conveyance Network – 3%
Water Supply – 5%
Secured Landfill – 5%
Amenity Buildings – 2%
Street Lighting – 3%
Logistics and Packaging Complex – 3%
Green Belt and Landscaping – 3%
The power will be obtained from Kerala State Electricity Board (KSEB) and will be distributed
to all the tenants according to their needs at Rs. 5.80 per unit.
II. Water
The potable water will be obtained from the same source of BPCL and distribute water to its
tenants. at Rs. 70 per kilolitre.
III. Waste Water Treatment and Recycling of Water
A Central effluent Treatment plant (CETP) with zero liquid discharge technology (ZLD) will be
set up as per the needs of environment board. The tenants will be levied Rs. 110 per kilolitre.
C. Operations & Maintenance Fee
This cost is applicable for maintaining the park estate including the roads (Both Internal &
External), the park terrain, gardens, Administration and & amenities. A flat O&M fee of Rs. 4.5
Lakhs per acre per year will be levied to the tenants.
D. Plot Pricing
The following pricing is proposed to ensure low component of land cost (6.5%) in investment
and gradually pay for the land use with their earnings (.2% of turnover).
The land will be made available in the park on a lease renewable every 30 years. The
land ownership will be with KINFRA. The total land for lease will be 189 acres.
A onetime Rs. 1.5 Crore per acre will be levied as lease premium.
Every year a lease rental equivalent to 5% of the cost of the land will be payable
annually. (Rs. 30 Lakh per acre on a developed land price of Rs. 6.0 Crore).
2.7.3. Expenses
The expenses will be in terms of Operations & Maintenance of the utilities and estate, the
depreciation and income tax component.
a. Market Development
An amount of 80 lakhs annually will have to be the budget for the campaign annually for the
first 6 years
b. O&M expenses
A 5% is levied on all utility infrastructure (Power, Water and effluent treatment) and 3% on
roads, structures (Gates & Boundary Wall/Fencing), Administration Building and Estate on the
Capital Cost annually.
c. Depreciation
40% depreciation has been considered on written down value for all utilities, roads, building
and structures as applicable under the law.
d. Income Tax
A flat tax of 25% is levied along with a cess component of 15% amounting to 28.75%.
e. Escalation
A 6% escalation is likely both on the revenue as well on the expense side. This does not affect
while assessing the Internal Rate of Return and Net present value.
on import substitution and promote make in India as well ensure with the installation of zero
liquid discharge and recycling waste water precious water resource is conserved. The park
performance has considerable benefits and it outweighs the cost element multi-folds as is
clear in subsequent discussion.
Table 2-8: Impact of Petrochemical Park Usage
Particulars Unit Realisation
Area Usage Acres 189
Tonnage Produced Metric Tons 633400
Turnover Rs. Crore 9316
Import Substitution % 50%
Investment Rs. Crore 3988
Connected Power Load KVA 62110
Fresh water usage KLD 2100
Recycled Water Usage KLD 4410
GST earned for State (42%) Rs. Crore 700
Employment - Direct Numbers 3200
Employment - Indirect Numbers 4800
b. Benefits
The benefits in Rupee equivalent the project will generate to State of Kerala will be in terms
of Employment, tax Collection, Import Substitution and contribution to GDP.
Table 2-9: Annual Benefits of Proposed Project
Particulars Annual Benefits
(Rs.Crore )
TANGIBLE BENEFITS
Import Substitution (5% of 50% of turnover) 230
Saving in water with installation of Zero Liquid Discharge system 6
Direct Employment – New Wages 465
Indirect Employment – New Wages 70
Generation of taxes (42% of GST earned) 700
Total annual tangible Benefits 1471
INTANGIBLE BENEFITS
Contribution to State GDP 3,725
Creating a Chemical Hub -
c. Costs
The costs are in terms of land provided by the state and initial fund for development only. The
development cost of the project is completely recovered in three years and the land cost is
recovered in around 13 years with lease premium and lease rentals.
The annual tangible benefits are itself more than the overall project cost (Land + Development
cost), if you consider the intangible benefits it presents an excellent cost benefit.
d. Benefit / Cost Analysis
The cost benefit ratio is very healthy at all possible discount levels. The project is more than
viable.
Table 2-10: Cost Benefit Ratio of Proposed Petrochemical Park
Discounting rate (%)
Costs & Benefits
12% 10% 8% 6%
BENEFITS (Rs. Crore)
10 Years 4272 4812 5441 6178
3. Introduction
3.1. Project Background
Kerala Industrial Infrastructure Development Corporation (KINFRA) is a statutory body formed
by the Government of Kerala in 1993, by an act of state legislature for facilitating the
development of industrial infrastructure in the State. KINFRA has played a pioneer role in
developing industrial infrastructure in the State of Kerala. KINFRA has a very successful track
record in setting up 22 industrial parks across Kerala for facilitating development of the
industry in the State.
KINFRA intends to develop a Petrochemical Park of international standards at Ambalamughal,
Ernakulum District, Kerala. The project is intended to create an Industrial Park with all modern
facilities exclusive for the Petrochemical Industry. The Petrochemical Park is proposed to be
established in approximately 489.46 acres of land in FACT premises at Ambalamughal, Kochi.
This land already has near to it, a large refinery, fertiliser and chemical factories, LNG Terminal
and Gas Pipeline Network being established, a Bulk Terminal and International Container
Transhipment Terminal (ICTT). The proposal assumes significance in view of the expansion
proposal of BPCL, nearness to the Port and Natural Gas infrastructure at the location. The
industrial units in the park will be provided with all infrastructure facilities.
The Industrial Park location is presented as below figure.
The proposed components of the project broadly are:
A. Common Infrastructure Facilities
a. Internal Roads, culverts and drainage
b. Water supply and distribution including water treatment plant.
c. Dedicated Sub-station and Power Distribution System
d. Street lighting
e. Telecom and Communication systems
f. Sewerage network
g. Common Effluent Treatment Plant (CETP) for Industrial Wastewater treatment;
i. Rainwater harvesting
j. Greenery etc.
B. Social Amenities
a. Canteen
b. Clinic
c. Recreational facilities
d. Bank / ATM
e. Logistics movement support etc.
Voyants Solutions Pvt. Ltd., India, has been appointed by KINFRA to prepare a Detailed Project
Report (DPR) for Petrochemical Industrial Park at Ambalamughal in Ernakulum District, Kochi,
Kerala.
P a g e |19 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |20 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
by Trichur district on the north, Idukki on the east and south east, Kottayam and Alappuzha
districts on the south and the Lakshadweep Sea on the west. It lies between North latitudes
090 47’ 13” and 100 10’44” and East longitudes 760 10’ 05” and 770 05’ 24. The Muvattupuzha
River and a branch of Chalakkudy River flow through the district.
The district headquarters is located at Kakkanad, a suburb of Kochi city. It is known as the
commercial capital of Kerala as it is the most industrially advanced and flourishing district of
Kerala compared to the other districts. Ernakulam district also hosts the highest number of
international and domestic tourists in Kerala state. The district has a moderate climate, and
mostly falls within the Malabar Coast moist forests eco region, while the highlands are part of
the South-Western Ghats moist deciduous forests eco region. Cochin International Airport is
located in northern part of the district at Nedumbasheri village in Angamaly. Owing to the
international airport, water ways, railways, and road ways, Ernakulam is one of the most
connected districts in the state.
NORTH PARAVUR
2
PERIYAR NAGAR
PROPOSED SITE
KAKKANAD
ERNAKULAM
MUVATTUPUZHA
3
KOCHI
ERNAKULAM RAILWAY STATION 1
LEGEND
P a g e |21 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |22 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
NORTH PARAVUR
2
PERIYAR NAGAR
PROPOSED SITE
KAKKANAD
ERNAKULAM
NH 85 MUVATTUPUZHA
3
KOCHI 10 KM
1
20 KM
30 KM
Figure 3-2: Regional Location and Connectivity Map of the proposed site
Source: Voyants using base data from Google Earth
4,500,000
Population (in lakh)
4,000,000
3,500,000
3,000,000
2,500,000
2,000,000
1,500,000
1,000,000
500,000
0
Districts
P a g e |23 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |24 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |25 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |26 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Figure 3-6: Pictorial illustrations of the proposed project site region and environs
Source: Voyants based on Google images
P a g e |27 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Kakkanad Karimughal road is further connected to the FACT Road which runs inside the site
and also acts as the major access to and from the site.
P a g e |28 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
3.5.7. Climate
The proposed site features a tropical monsoon climate with annual temperatures range
between 23°C to 31°C (73°F to 88°F) and average annual rainfall is 2,978 mm (117.24 in)
primarily during the period from June to September.
The predominant flow of wind in the region is from South-west to North-east direction.
3.5.8. Elevation
Being a coastal district majority of the Kochi region is within the low land regions of the state.
The average altitude towards the eastern fringes is about 7.5 m above MSL1, and towards the
west the altitude is less than one metre on an average. The whole of the land slopes gradually
from east to west.
The site is undulating and ground elevation in the project area varies from a maximum of
49.79 m to -2m. The central part is at higher elevation than the rest of the site. The total
elevation difference between the highest and lowest points of the site is 51.79 m. The highest
point 49.79 meters lies on the central location of the site while the lowest elevation of -2.00
meters is towards the river edge of the site.
1
Source: Development Plan for Kochi City Region – 2031.
P a g e |29 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |30 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
3.5.9. Slope
The site gradually slopes towards the Chithra Puzha River. Approximately 88.3% of the site
area is under slope ranging between 0° to 15° which indicates that site is buildable. 10% of
the total site area has slope between 15° to 30° and only 1.7% of land is under slope greater
than 30° which is not buildable.
3.5.10. Drainage
The major drainage features in the area are Chithra Puzha River which flows in close proximity
to the western boundary of the site and Ambalamedu Lake in the eastern side of the site.
There natural drainage of the site is from east to west towards the Chithra Puzha River. Due
to the topography of site there is a low-lying area at the west side of the site.
P a g e |31 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The proposed project site having an area of approximately 489.46 acres belongs to the FACT.
The rest of the land belongs to Bharat Petroleum Corporation Ltd. (BPCL), Kerala Enviro
Infrastructure Ltd. (KEIL), FACT - RCF Building Products Ltd (FRBL) which is a joint venture of
M/s Fertilisers & Chemicals Travancore Ltd, Kochi (FACT) and others.
The site has a close proximity and connection to three major national highways passing
through Ernakulam District - the Cochin-Mumbai Highway (NH-66), Salem-Kanyakumari
(NH-544 part of NSEW corridor) and Cochin - Dhanushkodi Highway (NH-49). This NH-544
runs inland from Kanyakumari and joins at Salem. The NH-544 also connects at Trichur
with NH- 66, which runs northwards along the coast to Mumbai.
The nearest small railway station is located at Tripunithura at about 4 km in the eastern
direction from the project site. Other major railway stations within the vicinity of the
Petrochemical Park are Ernakulam Junction and Ernakulam Town and there is a railway
siding at Irumpanam.
The project site is also connected through Vytila-Kakkanad boat service (City Water Bus)
under Kerala State Water Transport Department (SWTD) which is the governmental
agency who provides inland water transport facilities in the district.
P a g e |33 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Site will benefit from the growth corridor Kochi-Palakkad National Investment and
Manufacturing Zone (NIMZ) which will connect Kochi and Bengaluru through
Ambalamughal.
For preventing the effects of earthquake, design and construction methods suitable for
seismic zone III should be considered.
Considering the fragile ecosystem of the site surroundings, safety and pollution control
are the main concerns of the project. Best standards in environment management as per
law will be implemented with the directions of the authorities concerned. A Greenbelt
should be developed in a phase wise manner right from the construction phase of the
proposed project.
P a g e |34 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |35 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Strong manufacturing base built around Shape of the site is serpentine and
major seaport, international airport, IT Hub, is creating unusable pockets/
logistics, oil and petrochemicals. corners thereby reducing efficiency
The site is well connected in terms of air in use of land.
(Cochin International Airport), sea (Cochin Large part (54%) of the Site has
Port) and rail (Cochin – Ernakulam Town trees.
Station and Ernakulam Junction Station) The proposed industries i.e.
facilities. petrochemical and pharma are Red
Proximity to NH and SH will help in easy category industry. So,
movement of trucks in and out of the site. Environmental Impact Assessment
Land available for acquisition from FACT. (EIA) needs to be carried out.
Proposed single window clearance facility Deficient petrochemical industrial
for units in its Parks for obtaining regulatory structure with poor capacity to
licenses and clearances. create inter-industry demand and
Availability of skilled manpower from agglomeration economies.
surrounding areas.
The site is located in a proposed industrial
development zone as per Development
Plan for Kochi City Region – 2031.
The site at Kochi has a strong base with
modern infrastructure and availability of
feedstock from BPCL refinery for setting up
of industries.
OPPORTUNITIES THREATS
Expansion (existing 9.5 MMTPA to 15.5 Presence of other thriving industrial
MMTPA) of BPCL-KR adjacent to the project areas in the region (e.g. proposed
site will provide for feedstock supply, Cochin - Coimbatore Industrial
utilities, offsite and other support facilities Corridor (CCIC) and Kochi-Palakkad
Potential spill over benefits from the Cochin National Investment and
Shipyard Limited, Fertilisers and Chemicals Manufacturing Zone) giving
Travancore Limited (FACT), Kochi-Palakkad competition to the proposed
National Investment and Manufacturing petrochemical industrial node.
Zone and Hindustan Organic Chemicals
(HOC) and Cominco Binani.
The proximity of the site to the Airport, Sea
Port and Railway Station will be an
advantage for the tenants in terms of cost
effectiveness and access to Global and
Indian markets.
Good terrain to develop an efficient
drainage system.
It can be observed that the proposed project has got amble strengths and opportunities to
develop as a petrochemical hub. Such development should be planned in such a manner to
optimum sustainable utilization of resources to ensure diversification of economic activity to
the secondary and tertiary activity to create better job opportunities with due regard to ways
and measures to increase productivity, value addition and optimum utilization of resources to
promote local economic growth to nullify the weaknesses and reduce the risk of threats.
P a g e |36 Introduction
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
5. Demand Analysis
5.1. Project Background
KINFRA is proposing to set up a Petrochemical Park in Ambalamughal – Kochi, to be developed
next to BPCL refinery on an area of 474.12 acres. The main motivation for setting up the Park
in the region has been activated due to proposed expansion of BPCL- Kochi plant which is
expanding its refining capacity from 9.5 mn tons to 15 mn ton through FCC route together
with setting up a large petrochemical complex. The products and by products from proposed
petrochemical complex and refinery will offer wide ranging feedstock for setting up various
downstream petrochemical units in the region that will spur the economic development of
the entire area.
After this increase the refinery will produce about 5 lakh tons of Propylene, in addition to the
routine products like Motor spirit, HSD, Kerosene, ATF, Pet Coke, Bitumen, Benzene, Toluene,
MTO, Naphtha etc. Around 2.5 Lakh tons of Propylene will be utilized to set up large
Petrochemical intermediate projects like Acrylic acid, Oxo Alcohols and Acrylates which are
slated to be in production form 2019 2nd quarter. Apart from this around 1 Lakh tons of
ethylene will be extracted from FCC off gases that may be used for producing Ethylene Oxide
and MEG etc. The refinery also has plans for utilizing balance propylene to set up Propylene
Oxide and Polyol ether units by 2023 which can further spur the development of Polyurethane
industry in the region. The range of possibilities in fact is huge considering availability of both
Ethylene and Propylene, the basic building blocks, at the same location. The marketable
surpluses of the feedstock can provide major fillip for the development petrochemical sector
in South India.
has been shortage of basic feed stocks in the country for manufacturing the various chemicals
and Petrochemicals. There is thus huge potential for attracting investments in Chemical
industry in the country with increased availability of feed stocks. BPCLs proposed venture in
petrochemical industry with diverse end products and feedstock will provide attractive
investment opportunities for development of Petrochemical downstream industry close to
BPCL refinery. Much of the feed stocks that will be produced by refinery and Petrochemical
plant by their very nature will be difficult to transport and have to be preferably consumed
next the source of supply and hence KINFRA Park accordingly has every chance of attracting
future investments in this sector. Moreover, South India which accounts for almost 30% share
of Indian GDP accounts for meager share of the production of chemicals and Petrochemicals
in the country, which is mostly concentrated around Gujarat and Maharashtra. The proposed
KINFRA Park can play big role in bridging this demand supply gap of chemicals in South India.
Chemical Parks have been seen to be the best method of attracting investments in chemical
sector world over in all major countries and regions. Investments in chemical parks benefit
investors in several ways providing Optimal economic conditions, Professional settlement
support, Investment benefits through state of art infrastructure, flexibilization and
optimization of business model, Focusing on core business, Time and cost benefits through
offered individual services, Synergy potentials resulting from optimum structures (e.g. links to
supply chain, connections to research institutes) and Benefits from integrated know-how
structures. In successful Chemical Parks like Jurong Singapore and German chemical parks the
investors save up to 15 to 20% in capital and operation costs. It thus makes great sense to set
up an integrated KINFRA Chemical Park in Kochi which will have tremendous economic impact
in the region.
its value addition possibilities and ease of marketing the land with overall objective of
ensuring diversity of operations.
Carry broad benchmarking exercise of similar successful parks/zones in the country
and abroad with a view to define the concept of the KINFRA Park in terms of
infrastructure, facilities, services and revenue models.
Determine the likely time line for land absorption in the KINFRA park by various
product categories.
Recommend appropriate Market strategies and Policy/incentive framework for
attracting the investors to the Park and achieving the time lines of absorption.
5.4.1. Likely Feedstock available in the KINFRA Kochi Park catchment area including
BPCL refinery and propylene derivative petrochemical project (PDPP)
One of the most important considerations for siting Petrochemical and Chemical projects is
the availability of feedstock in its vicinity. The BPCL refinery expansion near the KINFRA park
and its plans to enter petrochemical sector will result in availability of several important basic
feedstock’s and intermediates that can propel the development of chain of downstream
petrochemical industry in the proposed Park. As a first step we have tried to compile a list of
various feedstocks’ that will be made available in the catchment area in general and from
BPCL project in particular. The Petrochemical feedstock that is likely to be made available from
BPCL Kochi and neighbourhood units will include the following products as illustrated in Table
5-1 by time frame.
Table 5-1: Likely available Feedstock in the Catchment area-Kochi Park
Propylene; Iso butylene; n Butene; Toluene; Benzene; Acrylic Acid; Butanol /Iso
butanol; 2 Ethyl Hexanol; Butyl Acrylate; 2 Ethyl-Hexyl Acrylates; and other BPCL
2019 - 2022
refinery products/by products – Kerosene, Pet Coke, Bitumen, Benzene, Toluene,
MTO, Naphtha etc.
2022 onwards Ethylene; EO; MEG; SAP, Propylene Oxide; Propylene Glycol; Polyol Ethers;
Source: BPCL
Essentially one will have access to some surplus Propylene and Ethylene from BPCLs FCC unit
besides other refinery by products for further value addition. Also, one will have access to first
and second level intermediates like Acrylic Acid, Oxo Alcohols, Acrylates, SAP, Ethylene Oxide,
Ethylene Glycols, Propylene Oxides, Polyol Ethers and Propylene Glycol in phases from
proposed petrochemical projects being planned by BPCL. Opportunities may also be there
based on Caprolactum, Phenol and Acetone produced / to be produced by HOCL and FACT in
the catchment.
In addition, Kochi Port offers scope for easy imports of several other chemicals and
Petrochemicals from cost effective region of Middle East for subsequent value addition.
P a g e |40 Demand Analysis
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
There are wide ranging possibilities for manufacturing different Petrochemical intermediate
as well as downstream specialty chemicals and end products with the kind of feedstock
available in the catchment and possible to import. The opportunities for manufacturing have
been broadly categorized under following main classes;
a) Intermediates are defined as products which are first- or second-generation bulk
petrochemicals derived from basic petrochemicals / building blocks like Methane,
Ethane, Propane; Olefins like Ethylene, Propylene, Butylene’s etc., and Aromatics like
Benzene, Toluene and Xylenes etc. There could also be second level of intermediates
possible from first level intermediate downwards. There are possibilities of setting
several intermediate units in KINFRA based on surplus availability of Propylene,
Ethylene, Butenes and first level intermediates like EO, PO, MEG, Oxo Alcohols,
Acrylic Acid etc proposed in the BPCLs PDPP project. Many of these feed stocks / first
level intermediates are difficult to transport (immovable) which may provide
excellent opportunities for attracting investments in producing next level of
intermediates within KINFRA Park and these may themselves find use within the park
for further value addition through production of down-stream products/specialty
chemicals.
b) Specialty Chemicals, also known as performance chemicals, are low volume but
high value compounds. Specialty chemicals can be sub-divided based on end-user
industries. In addition to end-use driven segments, there are a few categories of
specialty chemicals which are used across several end-user segments for similar
applications. End-use driven segments comprise agrochemicals, personal care
ingredients, polymer additives, water chemicals, textile chemicals and construction
chemicals and application-driven segments include surfactants, flavors and
fragrances and dyes and pigments. These all put together are the largest
constituents of the specialty chemicals industry and cumulatively constitute over
80% of the specialty chemicals universe. There are large opportunities for several
types of specialty chemical units in the Park based on available feedstock, possible
easy imports and large markets in the Southern India.
c) Drugs and Pharmaceuticals: Usually manufactured using several types of specialty
chemicals / intermediates etc. in smaller quantities. These exhibit similar
characteristics as specialty chemicals but are considered as separate category due
to its size and its distinct regulatory regime. These mainly consist of APIs (Active
Pharmaceutical ingredients) and formulations. The Drug and Pharma units are wide
spread in the country and generally prefer to locate units in areas which are either
close to markets or feedstock sources or areas that offer high level of Plug and Play
infrastructure facilities in cluster format with good incentives. KINFRA Park will be
in a position to offer some of the feed stocks (Pharma grade Solvents) and incentives
as well as presumably high level of infrastructure support facilities in cluster format
close to a major urban center for attracting some of APIs and formulation units.
d) End Products: This is large category of consumer facing value added end items
which are produced after reacting / mixing / processing various specialty chemicals
and intermediates etc. They include products like Cosmetics, Paints, Emulsions,
While several opportunities (Annexure 1) are there in intermediates, the limited surplus
availability of Basic building blocks like Propylene, Ethylene and Butylene from BPCL would
render very few feasible intermediates that can be manufactured with economic capacity as
covered in above table. In the case of specialty chemicals and end products however large
opportunities exist in the Park. Some specialty chemicals and end products are possible from
acrylic acid, acrylates and Oxo Alcohols that will be produced by BPCL in phase 1. The possible
production of SAP and Polyol ethers in phase 2 will open more project opportunities in the
form of hygiene products and Poly urethane-based components. Similarly, likely production
of EO, MEG and PO in phase 2 by BPCL will open potential for some other intermediate and
specialty chemical units as mentioned in table above. Overall the feedstock and products in
the catchment and Park can add tremendous value within the Park itself to the benefit of local
economy of the region.
5.4.3.1. Intermediates
The current and forecasted Capacity and demand for select intermediates that can come up
in the Park is expressed in Table 5-3. More details are provided in Annexure 2b.
Table 5-3: Forecasted Demand Supply Gap of Select/targeted Intermediates (possible from BPCL Feedstock)-India
2017-27
As can be seen from the table, majority of the intermediates that have been considered are
being currently imported in the country (with existing nil capacity) and there is large demand
supply gap. The demand supply gap is expected to widen in future over the next 10 years, thus
offering very good potential for manufacturing the same in the country. Units located in
proposed KINFRA Park will have good scope for setting these units due to close proximity to
BPCL refinery which can supply feedstock for producing these intermediates in economically
viable size capacities.
As stated earlier the specialty chemical industry include agrochemicals, personal care
ingredients, polymer additives, water chemicals, textile chemicals and construction chemicals,
surfactants, flavours and fragrances and dyes and pigments. The total specialty chemical
market in India is estimated at US$ 18.2 bn in 2014 against global market of almost $ 800bn.
The breakup of market by sub segments is illustrated in Figure 5-1.
Over the years, growth drivers in the chemicals industry (including specialty chemicals) have
shifted and evolved. The US was the original home to innovation and production of chemicals
and specialty chemicals. The industry then gradually transitioned to Europe, followed by
developing countries such as China. India is now positioned to take centre stage in production
of specialty chemicals in future. We believe the drivers for specialty chemicals are: (1)
domestic availability of raw material at competitive prices, (2) strong demand growth in
consumer industries and a domestic industry that supports ‘premiumisation’ of products, (3)
competitive manufacturing costs, (4) investment in R&D and (5) an ecosystem that supports
the industry and innovation. Our analysis indicates that India has all these drivers required to
‘Make in India’ and become the top destination for specialty chemicals.
Despite the demand side growth drivers, several challenges still remain. While some are
segment specific issues, there are three systemic challenges the sector is confronted with –
fragmentation and lack of scale, commoditization and regulations.
• Fragmented industry structure with few scaled up Indian players: Most players
operating in India are still small in scale. At the global level, however, there is significant
level of concentration. Most segments in India witness a dominating presence of a few
global leaders. This has implications on the competitiveness of Indian players. Only a
few Indian players have the scale or capabilities to compete with the global giants on
product development and innovation. As the global companies enter and strengthen
their presence in the Indian market, they will also invest in marketing, distribution and
production systems that local companies may struggle to match.
According to our analysis the segments that may enjoy maximum advantage at KINFRA Park
will include Personal care ingredients, Polymer additives, Water chemicals, Textile chemicals,
Construction chemicals, Surfactants and Flavours and fragrances. As they are characterized by
high growth potential, high product differentiation and low-to medium penetration levels and
will have some of the basic feedstock available in the catchment at competitive prices. The
estimated future market for the targeted sub segments is illustrated in Table below.
Table 5-4: Estimated market for targeted Specialty chemicals India ($ bn)
The overall market for targeted specialty chemicals is estimated at $ 11.6 bn in 2017
equivalent to 2.7 mn tons. The overall target specialty chemical market, as per various reports,
is expected to grow at about 13% by value and 10% by volume over the next 10 years.
The global pharmaceutical market, has grown at a CAGR of 6% over the last 5 years from a
value of US$ 887 in 2010 to US$ 1,187 in 2015. The global market is expected to slow down
owing to slowing growth in developed markets and lower levels of spending expected in some
of the major economies like USA. The key growth drivers in future for the global
pharmaceutical industry would be:
Strong growth in emerging markets like India, China, Brazil and Russia
Aging population and rising life expectancy
Increasing access to modern healthcare
Increase in healthcare awareness
Improvement in medical practices
The global market is expected to grow at 4.5% to reach a value of US$ 1,479 Bn by 2020. Indian
market accounts for 1.3% of the global market for pharmaceuticals by value and 10% by
volume.
The Indian pharmaceuticals market witnessed growth at a CAGR of 17.90 per cent, during
2005-16, with the market increasing from USD6 billion in 2005 to USD33.4 billion in 2016
(about 1 mn tons by volume). The domestic pharmaceutical market in India is estimated at $
17 Bn in FY16, having grown at a CAGR of 7.2% from $ 10 Bn in FY11. The balance ($ 16.4 bn)
is exports. Cumulative FDI inflows worth USD14.53 billion were made during April 2000 to
December 2016. The Indian pharma industry, which is expected to grow over 15 per cent per
annum by value between 2015 and 2020, will outperform the global pharma industry, which
is set to grow at an annual rate of 5 per cent between the same periods. The total market in
India is expected to grow to US$ 55 billion by 2020, thereby emerging as the sixth largest
pharmaceutical market globally by absolute size.
By 2020, India is likely to be among the top three pharmaceutical markets by incremental
growth and sixth largest market globally in absolute size. India’s cost of production is
significantly lower than that of the US and almost half of that of Europe. It gives a competitive
edge to India over others. Increase in the size of middle-class households coupled with the
improvement in medical infrastructure and increase in the penetration of health insurance in
the country will also influence in the growth of pharmaceuticals sector.
With 70 per cent of market share (in terms of revenues), generic drugs form the largest
segment of the Indian pharmaceutical sector.
In the case of formulations, about 70% of the total formulations sold are for acute illness and
remaining 30% for chronic illness (prolonged duration). This is true for most developing
countries as compared to developed markets where the growth is led by chronic ailments.
Currently, Anti-infective drugs command the largest share of the Indian pharma market,
followed by Cardio vascular & Gastro-intestinal, Respiratory and Vitamins & Minerals. The top
5 segments contribute to nearly 57% of the entire market in 2015.
India is also a major exporter of pharmaceuticals to more than 200 countries with US, Europe
and Africa accounting for more than 50% of India's exports of pharmaceuticals. Drugs for
cholesterol control, pain management, anti-coagulant, respiratory problems, liver disorders,
depression and lipid regulators are highly prevalent in the global market.
While the Indian Pharmaceutical market is expected to grow at double-digit levels over the
next five years, it faces certain challenges as highlighted below:
Compliance with global cGMP standards involving continuous improvement in systems
& processes and workforce training.
High level of fragmentation in the industry with top 10 companies contributing to 41%
of total sales, next 10 companies contributing to 22% and remaining companies
contributing to 37% of total sale.
Government control on prices of pharmaceutical products.
Lower spend on Research and Development resulting in lack of innovation.
Lack of skilled manpower especially in Research and Development of Novel molecules.
Consolidation among customers in US market.
The Indian growth drivers are such that the Indian market is expected to grow at 12% over
the next 5 years to reach revenues of almost US$ 55bn by 2020 driven majorly by following
factors:
India's huge population and growing number of stress-related diseases due to change
in lifestyle.
Increasing incomes leading to increase in affordability of healthcare facilities and drugs.
Availability of better diagnostic facilities.
Increase in government spending on social sectors with a focus on healthcare.
Increased penetration of health insurance (Provision of Rs.1 lakh insurance cover per
family by GOI).
India’s cost of production is nearly 60 per cent lower than that of the US and almost half of
that of Europe. Labour costs are 50-55 per cent cheaper than in Western countries. The cost
of setting up a production plant in India is 40 per cent lower than in Western Countries Cost-
efficiency continues to create opportunities for Indian companies in emerging markets and
Africa. India also has a skilled workforce as well as high managerial and technical competence
in comparison to its peers in Asia resulting in India emerging as major hub for manufacture of
Drugs and Pharma in the world. Also, economic prosperity would improve affordability for
generic drugs in the market and improve per capita sales of pharmaceuticals in India.
The DoP (Department of Pharmaceutical) seeks to implement Cluster Development
Programme for Pharma Sector (CDP-PS) to enhance Quality, Productivity & Innovative
capabilities of the SME Pharma sector in the country. Cluster based approach is increasingly
being recognized as an effective and sustainable strategy for competitive enhancement of
Pharmaceutical Industry in India. Such an approach, which leverages the geographical
proximity of the enterprises on ‘collaborating while competing’ principle, is participatory and
cost effective. As it provides critical mass for customization of interventions. The vision of the
Department of Pharmaceutical (DoP), Ministry of Chemicals & Fertilizers is to catalyse and
encourage quality, productivity and innovation in pharmaceutical sector and to enable the
Indian pharmaceutical industry to play a leading role in a competitive global market. KINFRA
Park will be state of art Park for promoting chemical industry with common facilities and
infrastructure that can be leveraged by drug and pharma sector which display similar
characteristics as that of specialty chemicals by their very nature of manufacturing and
requirement of feedstock. Since these units are uniformly spread across the country, KINFRA
Park by being a cluster can offer tremendous advantages to local and international investors
proposing to enter this sector in India.
refinishers, furniture finishing and road marking paints, and their demand is linked to the
growth and performance of the industrial equipment sectors, automotive industry and
appliance industries. Paints and coatings find wide range of application in buildings &
construction, automotive, aerospace & defence, aerospace, marine, consumer durables,
oil & gas, refinery & petrochemical and industrial coatings industries. The architecture &
decorative paints and coatings segment accounted for 70.53 percent of the India paints
and coatings market in terms of revenue as of 2015. The segment under technology
includes powder coatings, water-borne coatings and solvent-borne coatings. The solvent-
borne technology accounted for 59 percent of the India paints and coatings market in
term of revenue as of 2015.
The India paints and coatings industry are growing at faster pace with the new skills and
technological development in recent past. Many companies for different market
opportunities and coatings applications have upgraded the production process.
Moreover, companies are looking for better technology to produce eco-friendly paints
and coatings with natural raw materials like bio-based polyurethane or biodegradable
materials. These production processes with new technology will have better
opportunities in paints and coatings market in near future.
b) Inks
India is among the fast-growing printing ink markets globally spurred by the rapid
expansion of the domestic print markets. Backed by a strong demand from key end user
segments such as package printing, newsprint, publishing and other commercial printing,
the printing ink market in India has registered strong growth in the recent years. The
printing ink industry is fragmented with over 400 manufacturers and a large number of
players in the unorganised sector. Printing ink sector in India is estimated at 360,000
tonnes for 2017, valued at around $ 1 billion; the market witnessed a growth of
around 7.5% per annum during the last 10 years. Printed packaging accounts for around
27% of the demand for printing inks in India followed by newspapers at 20%. Commercial
printing/ promotional and printed advertising together account for around 19% of the
demand. Other key end user segments for printing inks include books and stationery.
With the print sector forecast to grow at around 8% per annum, over the next 5 years,
printing ink segment is expected to grow strongly during the same period. Micro Inks
(Huber group), DIC India, Sakata, Siegwerk, Flint and Toyo are the leading manufacturers
of printing ink in India. The top six players comprising domestic players and established
multinational players account for around 75% of the market. Printing inks has a well-
entrenched presence of multinational players who have entered the market either
through a direct subsidiary or through Joint Ventures with existing domestic players.
Going forward, the printing ink market is set to benefit from rapid urbanization, increasing
literacy rates and growth of FMCG sector.
c) Adhesives and sealants
The India Adhesives market is expected to value USD 921.90 million in 2018 and is likely to
reach USD 1,464.10 million by 2023, growing at a CAGR of 9.69% during the forecast
period, 2018 to 2023. The Indian sealants market is expected to value USD 150.37 million
in 2018, and is likely to reach USD 237.16 million by 2023, growing at a CAGR of 9.54%,
during the forecast period 2018-2023. The current overall market volume for adhesives
and sealants in India (2017) is estimated at 3,20,000 tons. The growth in volume is
expected to be 6% annually.
Adhesives and sealants are often grouped together, as they both are applied to the
surfaces of materials to adhere and seal them together. They are generally available in
the liquid form, which is viscous in nature, with no or little flow characteristics. Adhesives
are majorly chosen for their bonding and holding power and have high tensile and shear
strength. Adhesives are of two varieties, namely structural adhesives (strength is vital for
the success of the assembly) and non-structural adhesives (generally have low strength,
are used to bond weak substrates and for temporary fastening). However, sealants are
majorly selected for their ability to resist relative movement of the substrates, to fill gaps,
and to contain or exclude another material. They have less strength compared to
adhesives but are more flexible in nature. This market is driven by a number of factors,
such as the increasing demand from the packaging industry, growth of automotive
production in the country, growing consumer focus towards interior designing, and
others. However, this market faces certain drawbacks, such as the increase in the raw
material prices, and others. These factors may act as a roadblock to the growth of the
market.
The Indian adhesives market, based on technology, can be broadly segmented into water-
borne adhesives, solvent-borne adhesives, reactive adhesives, hot melts adhesives, and
others. These are again segmented according to the sub-segmentations on the basis of
resins used. The water-borne adhesives dominate the market with ~45% share followed
by hot-melts and reactive adhesives. The hot-melt adhesives are also the fastest growing
with a CAGR of ~11% followed by reactive adhesives with a CAGR of ~10%. The Indian
sealants market, based on product type, can be broadly segmented into silicone sealants,
polyurethane sealants, plastisol, emulsion, butyl, polysulfide, silyl modified and others.
The silicone-based sealants dominate the market with ~30% share followed by
polyurethane and plastisol sealants. Silyl modified sealants is the fastest growing with a
CAGR of more than 10% during the forecast period. This is followed by silicon and
polyurethane sealants with a CAGR of ~9.5%.
On the basis of end-user industry, the market is segmented into building & construction,
paper, board & packaging, woodworking & joinery, transportation, footwear & leather,
healthcare, electronics and others (textiles, consumer goods, etc.). Paper, board &
packaging industry dominates the consumption of adhesive & sealants with ~30% share.
This is followed by transportation and building & construction industry with 22% and 17%
respectively. The electronics industry which is comparatively a smaller segment is
expected to be the fastest growing end-user industry with a CAGR of ~13% during the
forecast period.
Furthermore, the increasing electronics assembly operations in India and growth of
defence manufacturing in the country will offer numerous opportunities for the growth
of the Indian adhesives and sealants market. Some of the major companies dominating
this market for its products, services, and continuous product development are Pidilite
Industries Limited, 3M, Henkel AG & Co. KGaA, H.B. Fuller, Anabond, Sika AG, Dow Corning
Corporation, and Arkema (Bostik AG), among others.
TPU
CASE
1%
5%
Shoe Sole
Slabstock Foam
20%
27%
The demand for polyurethane is expected to increase manifold in the country, which
produces 4 million cars and 9 million refrigerators annually. With a population estimated
at 1.3 billion people and GDP growth rate of 7 percent or above, India offers a huge
potential to global polyurethane players. By expanding their manufacturing capabilities,
MNCs are aiming to capture larger share of PU market pie in the country. The PU market
is expected to reach 2.15 mn tons over the next 10 years with CAGR of 13%, opening
immense scope for new units to come up in this field.
e) SAP based Products
Synthetic SAP based products include polyacrlyamide copolymer, sodium polyacrylate,
polyvinyl alcohol copolymers, and ethylene maleic anhydride copolymer. All these
products types are used in numerous applications such as diapers, adult incontinence and
feminine hygiene products. Polyacrylamine copolymer is likely to witness fastest growth
rate owing to properties such as non-toxicity, high water retaining and absorption. Since
its development in 1978, the use of SAP has revolutionized the diaper industry because of
its unique ability to absorb and retain aqueous solutions up to 60 times its volume and
500 times its weight and diaper manufacturers soon began to design diapers that were
thinner, more absorbent and more comfortable than ever before.
Global super absorbent polymer market size was estimated at 2.07 million tons in 2014
and is likely to exceed 3.1 million tons by 2023 growing with an expected CAGR of over
5.5%. Application segments include baby diapers, adult incontinence products, feminine
hygiene products and others. Among these, baby diapers are primarily expected to boost
demand for superabsorbent polymers in the market. The baby diaper industry accounted
for more than a 74% share of the global superabsorbent market and the market for adult
incontinence products was the second largest, which accounted for 224.3 kilotons.
Among the countries, China, Japan and Europe are the major production centres of SAP
products. China's annual capacity is 740,000 tons/year (23% share); Japan's annual
capacity is 660,000 tons/year (20% share); Europe's annual capacity is 542,000 tons/year
(17% share); the U.S.'s annual capacity is 501,000 tons/year (16% share); Korea's annual
capacity is 360,000 tons/year (11% share); and others are 434,000 tons/year (13% share).
Increasing baby diapers demand owing to growth in population and consumer awareness
towards infant’s hygiene is likely to drive super absorbent polymer market growth.
Agricultural applications are likely to witness highest gains with an estimated CAGR of
over 5.8% by 2023 owing to superior water retention properties required for crops in
rainfall water scarce area. Super absorbent polymer market revenue is likely to be valued
at over USD 11 billion by 2023. Europe was the dominant region and accounted for more
than 30% of SAP demand in 2014. Asia Pacific is likely to witness highest growth rates over
the forecast period owing to populations expansion coupled with growing hygiene
awareness among consumers.
Global super absorbent polymer market share is consolidated with few companies
catering to large part of the demand. Major companies are taking initiatives to increase
their production capacity and enhance product portfolio. Key companies involved in this
market include BASF, Nippon Shokubai, Evonik, Sumitomo, and LG Chemical. Other
prominent companies include Formosa Plastics, KAO Corporation, SDP Global
Corporation, Yixing Danson Technology and Songwon Industrial Corp. Ltd. The top three
companies today, BASF AG, Nippon Shokubai and Evonik Industries, occupy 51% of the
production, and the output of each company exceeds 500,000 tons/year.
India is emerging as major market for SAP products. In recent years, India, with a 1.3 billion
population and booming economy, has become a hot investment destination for global
investors. According to India Diaper Market Overview, 2016-2022, diaper market in India
is growing with more than 20% CAGR over last seven years. Diaper industry has mainly
two segments, one is baby diaper segment and the other is adult diaper segment. Baby
diapers are the most widely used products whereas adult diaper is still at a nascent stage
in India.
From international giants to Chinese manufacturers, industrial players from a wide range
of markets have expanded their footprints in India, and the disposable hygiene market is
no exception. All the big international hygiene product brands like Procter &
Gamble, Johnson & Johnson, Kimberly-Clark and Unicharm have established facilities or
operated branches in India. The entire SAP at present is being imported in the country.
India’s current consumption of SAP is estimated at 50,000 tons per yr. ($ 1bn) which is
very small in comparison to other countries but has vast potential for growth. India is
expected to conservatively grow at 15% annually in volume over next 10 years. BPCL plans
to produce super absorbent Polymer (SAP) in future for the first time in India which is
likely to open opportunities for downstream diaper industry in the KINFRA Park.
Intermediates 938
End Products
TOTAL 7,718
Source: Based on Secondary Data and Analysis (Refer Annexure 2 a & b for basis and sources of Information)
The detailed working of demand supply gap (10 years), land absorption norms and land
requirement by each intermediate and product category is provided in Annexure 2 a & b. The
information on current capacity, past and future growth rates etc. of markets have been
compiled from reliable Government sources, Industry associations and publications of
reputed consultants and our own industry experience as consultants. Some of the sources are
given under Annexure 2 a and b.
S T R E N G T H W E A K N E S S
• Assured supply of Basic building blocks like • High marketing Logistic Cost of end products
Ethylene and Propylene from BPCL and several to reach other parts of the country- East, West
other petrochemical intermediates /feedstocks in and North India.
the catchment. • Poor perception of potential investors about
• Proximity to Major Gateway port for seamless Industry culture in Kerala especially labour
connectivity to major international destinations related issues.
for exports and imports of chemicals. • Small size Local market.
• Excellent social and Urban infrastructure at • Comparatively much Higher Land cost
doorstep – help attracting managerial talent. compared to other established hubs in west
• Ready availability of trained manpower due to India and other proposed PCPIRs and chemical
presence of large Refinery and other chemical zones.
units in close proximity- BPCL, HOCL, FACT etc.
• Presence of LNG terminal offering low cost, clean
and efficient energy source to the units.
• Low Feedstock logistics cost.
• Ample availability of water – lifeline for chemical
plants.
• Lower logistics cost for finished goods to Southern
region compared to supplies from Gujarat and
Maharashtra (major hub).
• The Government of India has launched the Draft
National Chemical Policy, which aims to increase
the share of chemical sector in the country’s GDP.
O P P O R T U N I T Y T H R E A T
• Strong growth drivers of the industry- Rise in GDP • Environment Issues may delay the time frame
and purchasing power, Low cost manufacturing, • Reliance – Mega Investment for same
World class engineering and strong R&D derivatives may offer competition.
Capability; Government policy support. • Gujarat – Maharashtra offer considerable
• South India accounts for almost 25 to 30% share advantage of established hubs in attracting
of the chemical end products consumption but potential investments.
account for limited production. • Possible dumping by China with Global
Capacities in range of products.
• Rapid growth in end consuming Markets (10 -20%) • FTA agreements with several neighbouring
offer scope for end product manufacturing for countries also may pose challenge in negating
domestic market in general and local markets in advantages of manufacturing vis a vis imports
particular. due to inverted duty structures.
• Possibility of Contract Production by large end • Likely competition from PCPIRs in the state of
product manufacturers. Gujarat, AP and Orissa which are pitching
• Critical size of domestic market ensuring viability aggressively for investments from
of setting globally economic size capacities for Petrochemical and Chemical sector and
various petrochemicals. also/are venturing into integrated
• Surplus Propylene and Ethylene available from Petrochemical refineries-IOCL/HPCL.
BPCL for planning medium size Petrochemical
Intermediate Projects in the Park.
• During the period of 2014-2020, products worth $
6.3 Bn are expected to go off-patent which will
provide Indian generic product manufacturers an
opportunity to expand their market presence and
grow organically.
• Potential to attract NRIs and other native
industrialist located in other parts of the country
• Possibility to create a first of its kind chemical
cluster like China, Singapore and Germany giving
tremendous advantages on operating and capital
costs and wide-ranging services to the
incumbents.
Source: Primary survey
The major advantage of KINFRA proposed petrochemical Park is the availability of surplus
Basic building blocks of Petrochemicals like Ethylene and Propylene and large quantities of
other petrochemical intermediates in the neighbourhood for value additions. This is one of
the most important requirements for attracting investors who generally prefer to either locate
plants close to source of feedstock or consumption centres. Analysis of the SWOT indicates
that while there are huge opportunities for setting up the Park there will be equal challenges
for attracting investments due to competition from other states/PCPIRs who are aggressively
pitching for investments. The main challenge would be for attracting investors who generally
have perceived poor image of the Kerala as manufacturing destinations and may prefer to
locate the units in Gujarat or Maharashtra where there is major concentration of
manufacturing industry as well as end markets. However, the perceived strength of location,
wide demand supply gaps of several products, availability of critical feed stocks together with
attractive policy / incentive package and well-designed marketing strategy should ensure
investments coming here.
Considering the situation as it exists, we have determined the accessible market potential for
KINFRA Park for each of the product categories using detailed analysis.
a) Intermediates:
The critical factors responsible for attracting investments in intermediates are the
proximity to feedstock and markets. KINFRA Park has the dual advantage of being next to
BPCL refinery, the source of feedstock and also has access to the entire Indian market
which is currently importing all of these intermediates. Thus the 100% land market
potential for India for these intermediates is accessible to KINFRA. The total land that can
P a g e |55 Demand Analysis
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Ethylene
Ethylene Oxide
Ethanol Amines; Glycol Ethers;
35 1 X 10 Acres
~10 KTA Ethylene carbonate; others
Propylene Oxide
Iso – propanolamine Propylene
Glycol ethers na na
na (BPCL not clear on supply)
Propylene Carbonate; others
The likely quantity of intermediates that can be produced out of surplus feedstock is
estimated based on conversion factors varying between 0.3 tons to 0.75 tons of feedstock
per ton of intermediates. Based on the average norm of 4000 tons/yr of intermediates
production per acre of land, around 95 acres of land is accessible to KINFRA Park based on
available surplus immoveable feedstock and 40 Acres based on movable feedstock. As can
be seen this still leaves lot of all India land demand potential to be absorbed by competition
and other clusters that are in existence or may come up in future.
b) Specialty Chemicals
Specialty chemicals projects are sensitive to proximity to feedstock and markets as well as
quality of infrastructure support. The industry together needs large number of feedstock
in small quantities to produce end chemicals which further are used in other fine chemicals,
drugs or in end products. KNFRA Park will have access to some of the critical feedstock
from BPCL that are used in specialty chemicals like Oxo Alcohols, Acrylic Acid, Acrylates,
Benzene, Toluene etc as well as from other intermediates that are likely to be produced
within the Park based on available feedstock from BPCL. The Specialty chemicals normally
find applications in end consuming markets like Packaging, Food, Textiles, Construction,
Drug intermediates, Personal care products, automobiles etc which are wide spread across
the country. The accessible market potential for KINFRA Park for these chemicals has been
assumed based on its geographical reach of consumption markets. The entire South Indian
consumption can be catered from KINFRA Park which is currently sourcing the specialty
chemicals from Gujarat and Maharashtra. We have accordingly taken accessible market
share as 32% which is assumed based on overall GDP share of South Indian states in total
GDP of the country. The overall land market accessible to specialty chemicals to KINFRA
Park over the next 10 years period is accordingly estimated at 32% of the total All India
land requirement of 1600 acres (Table 3) or 512 Acres. The KINFRA has excellent chance of
capturing good market share. The intermediates that are expected to be produced within
the Park and those like Oxo Alcohols etc. available from BPCL itself can be used to produce
large number of specialty chemicals. Assuming that around 4.5 Lakh tons of available
intermediates produced within the Park and available from BPCL can possibly be converted
into specialty chemicals, it is estimated that about 0.9 mn tons/yr of specialty chemicals
can overall be produced at input norm of 50%. Accordingly, a total land requirement of
almost 350 acres may be accessible for specialty chemicals over the next 10 years at
absorption rate of 2500 tons/yr /acre of land as observed in these chemicals.
Table 5-7: Accessible market Potential of Land for KINFRA Park for target Petrochemicals and Chemicals (Year 2017-
27)
End Products
Paints/Inks and
530 27 (5%) 95 95
adhesives
PU /Nylon
600 192 (32%) 200 200
Components
For Drugs and Pharma, the accessible land required based on feedstock availability is
taken same as the market accessible land as locations are not very sensitive to feedstock
proximity.
It can be seen that Land Demand based on market and feedstock access varies from product
to product category. The actual land requirement in the Park demand will be dictated either
by available feedstock’s while in others where feedstock is not an issue it will be dictated by
market access. In intermediates the surplus feedstock availability from BPCL will be the prime
consideration and can result in maximum land demand of 135 acres (95 acres for immoveable
feedstock and 45 acres for moveable feedstock) against large all India accessible market (938
Acres) over next 10 years. In the case of specialty chemicals almost 350 acres of land can be
accessed based on the feedstock that will be available in the catchment in future (2017-27).
The drug and pharmaceutical market is actually more sensitive to infrastructure availability
and proximity to major metro based on GDP share of the state and accordingly 190 acres can
be accessed to the Park over next 10 years based on market accessibility. Based on similar
logic the land accessed to end products based on markets and feedstock available has been
worked out. It is feedstock availability that will largely dictate the overall land market potential
accessible to KINFRA which works out to almost 1,060 acres over the next 10 years. This works
out to almost 13% share of the all India land market potential of almost 7,718 acres (refer
Table 5-5) over the corresponding period.
The land has to be judiciously allocated to each product category depending on its importance
in terms of availability of Feedstock, the investment it can bring and the value addition it can
create, its ease of marketing and the competition from other similar Parks. Some share may
have to be left for other competing zones and PCPIRs being prosed in the Southern region.
o Intermediates: Based on the limitations of supply of the feedstock from BPCL, a very
conservative saleable land of 96 acres has been allocated only for the immovable feedstock
from BPCL for the next level of intermediates. Since there is wide choice of intermediates
that can be manufactured out of the surplus feedstock, this land has good chance of being
marketed.
o Specialty Chemicals: These chemicals are manufactured in smaller quantities but are wide
ranging and bring in high value addition. Some of the feedstock and key solvents for these
chemicals will be met from BPCL and next level of intermediates proposed to be
manufactured in the Park. Also ease of imports due to Cochin Port can lead to investments
in wide ranging specialty chemicals including Surfactants; Polymer additives like
Plasticizers, heat stabilizers, flame retardants, and antioxidants; personal care ingredients,
Construction chemicals like concrete admixtures, super plasticizers, flooring chemicals;
Water chemicals like flocculants, defoamers, and disinfectants, Detergent additives and
Textile finishing chemicals etc. Even though 350 acres of land is accessible to KINFRA based
on marketing study, we have proposed a nominal of 33 acres of plotted area (10% share
of the accessible market) due to constraint of the land availability and need to represent
diversity of sectors to mitigate risks.
o Drugs and Pharmaceuticals: A plotted area of only 30 acres (out of total 190 acres of easily
market accessible land area) has been allocated in the park for this sector over the next 10
years, which is 15% of the accessible market. A very small area has been considered again
due to land area constraints.
o End Products: A plotted area of only 38 acres has been taken for end products like Paints,
Coatings, Emulsions, Adhesives, Inks, SAP, PU products etc. This again is small 9 to 10%
share of the total accessible Land market potential of almost 385 acres as per Table 5-5.
o Ancillary and Support Industries for BPCL and the Park: These include manufacture of
packaging materials, Industrial Gas etc., besides other related industries which can use the
infrastructure and services at the location. A nominal 4 acres have been allocated towards
them on adhoc basis.
o Common Facilities: As per the requirement of the various industries that will come up in
the area, around 15 acres of land has been allocated for this purpose.
It may be mentioned that that there is large flexibility in allocating land for various sub sectors
as mentioned above. The proposed allocation is only one way of allocating based on informed
judgment. Depending on the future trends in investment the allocation by sub sectors may
undergo change. The proposed saleable/plotted land as allocated by categories is summarized
in Table below. The land sales will be in Phases depending on the time schedule of feedstock
availability from BPCL for different category of target Products.
Table 5-8: Plotted Land Allocation by Product Categories –KINFRA Park (Acres)
Next 5
Now Till 5 Years
Product Category Years Total Plot Sizes (Acres)
2019-2022
2023++
Specialty Chemicals 32 8 40
Pharmaceutical APIs 30 0 30
CETP (5)
Central Utilities and
Water supply (2)
Technical center &
Common Facilities 15 15
Administration (2)
Warehouse, Logistics
and trading Hub
including Parking (6)
It can be seen that while there is demand for the land, its absorption will take its own time.
The time frame will depend on the feedstock availability schedule which will be supplied in
Phases. According to our informed judgment the total land can conservatively be absorbed in
about 7 to 8 years through proper marketing efforts as indicated in table 5-8 above. Some of
the feedstock’s like Propylene, Acrylic Acid, Oxo Alcohols, Acrylates, Iso butylene and refinery
P a g e |61 Demand Analysis
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
by products can be made available by first half of 2019 and accordingly the land demand for
the products based on them can come in the phase 1 in first 5 years. Products based on
Ethylene, Ethylene oxide, Polyols, SAP may be likely by 2022/23 and the land absorption for
these downstream products may come towards 2023.
The plot area/sizes are illustrative of typical units and have to be flexible to meet the varied
requirement of the investors.
The most important and still valid conclusion drawn from this benchmarking of the worlds'
leading chemical industry parks is that the "ideal chemical site for all kinds of investments with
best-in-class chemical production conditions" does not exist. Instead, each site offers a
portfolio of favourable and less favourable factors to be evaluated according to the projects'
specific requirements. The challenge for globally operating chemical companies is to find the
best-fit investment location facing the heterogeneity of chemical production locations. At the
same time, it is an opportunity for chemical industry parks and their operators to present
themselves at their best. The Global Site Benchmarking is key to both, identifying optimization
levers for increased competitiveness for the own site and having a detailed and structured set
of information regarding strengths and weaknesses of other worldwide leading chemical
Industry Parks.
a) Chemical Industry Parks in Europe
European chemical production sites provide very stable production conditions thanks to
their long production history and highly professional site operators as seen in German Park.
They are one of the best when it comes to protecting intellectual property, Environment
safety and health, site services and project handling aspects. Here, site service providers
offer a very comprehensive site service portfolio and reliable infrastructure for chemical
production companies according to the Plug & Play principle, leading to a high degree of
customer satisfaction. A further main advantage of European sites is the availability of well-
qualified personnel on all levels as well as reasonable Environment Safety and Health (ESH)
regulations. In general, investment cost levels are higher than at the Asian sites because of
higher material, construction and engineering costs, but far lower than expected cost
levels in the Middle East.
European chemical industry faces a context that is overall quite favorable to strong cluster
initiatives. But there are specific challenges that cluster initiatives need to react to, either
through appropriate organizational choices or through launching targeted activities.
Regional governments tend to be well developed, widely engaged in economic
P a g e |63 Demand Analysis
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
development activities, and in most cases open to collaboration with companies. National
governments and European institutions share the overall interest in economic
development but in the past, there has also often been, especially at EU level, a tension
between cluster mobilization and other policy goals.
Environmental regulations have been a strong focus of EU policies. The regulation of
chemical substances through REACH has been a major effort with significant impact on
chemical companies operating in Europe. The dialogue between industry and government
agencies has been problematic, undermining the mutual trust necessary for cluster
initiatives to work.
Table 5-9: Comparison of salient features of Chemical Parks/Zones across the world
Year of
2004 2001 2008 1990 1990
Establishment
Germany has 35 chemical parks
Total Area located all over the Country with
12500 Ha 2940 Ha 640 Ha 3000 Ha
(in Acres) areas generally ranging between
200 to 600 hectares
Location is not so good from the Located in the south Strategic location 15 kms Jurong Island is linked to Each park has excellent location
point of view of proximity to of the Shanghai city at North of Mangalore next to the main island by a and connectivity via road, air and
social and urban infrastructure about 60 kms from refinery. Good Road, Rail 2.3 km causeway known good access to ports to reach any
and connectivity by Air and Rail the main city. and Air connectivity with as the Jurong Island part of the world. Each of the park
Main rail head 50 kms away and Excellent location rest of the country. Located Highway, several public is connected additionally to a
nearest Airport 140 kms at close to major midway between Cochin - bus services run between network of pipelines for natural
Baroda. consuming center of Mumbai on NH - 66. Jurong Island and the gas, naphtha, hydrogen, carbon
China. mainland, operated by monoxide and technical gases
Port connectivity is also poor. Very well connected Mangalore International Woodlands Transport. available from all over Europe.
Location & The current Dahej port is poorly to international and Airport is just 5 kms away
Connectivity equipped to handle cargo and domestic markets from MSEZ. Jurong has Excellent sea Investment is being made all the
dependence is mostly on JNPT Very well connected and Air connectivity to rest time to improve provision across
and Mundra which are far through expressways New Mangalore Port a of the world. the existing logistics
away. and rail to various deep draft major port is infrastructure.
parts of the country., just 8 kms from MSEZ,
connecting well-developed
The nearest airport countries across the globe.
Pudong International
Airport) is about 50
kms away
Located in Gujarat state which Easy access to large Close proximity to Jurong’s major advantage The product offerings and
is hub of chemical industries in Chinese domestic excellent social is its location and product infrastructure at
India, providing easy access to markets. educational and urban offerings. Jurong island is parks and the
markets in close proximity. infrastructure at model of industry market
Large amount of Mangalore city. integration. Companies attractiveness of
Feedstock Advantage: Raw assured feedstock share common facilities Germany itself is
material available in plenty from large no of Quick Start Advantage: and infrastructure and can the major draw for
from companies within Dahej Petrochemical Plug-n-play infrastructure buy and sell feedstock and investments. The
SEZ & from companies in DTA projects present with graded plots, power, products literally over the investors see
area and the huge chemical within the Park. water and drainage fence. following benefits
cluster in Ankleshwar.in specific connections up to the in the parks
and Gujarat in general Relatively large area doorsteps and zone level By leveraging the large Optimal economic conditions
of the Park provides Environment Clearance base of manufacturers Professional settlement
SEZ related fiscal incentives are economy of scales for offer a Quick Start present. Companies in support
available to units operating in common Advantage. Jurong island are able to Investment benefits through
Key strategic
Dahej SEZ apart from duty free infrastructure and reduce capital costs and existing infrastructure
advantages
imports, and income tax facility providers. Well Connected: By Air, operating costs by Flexibilization and
exemptions on exports income; Sea, Rail and Road to outsourcing their optimization of business
no specific incentives in DTA Financial incentives various parts of the country manufacturing needs to model
area for R&D, like letting and abroad specialized third-party Focusing on core business
companies take tax providers on the island Time and cost benefits
deductions for R&D Feedstock Advantage: Raw who supply utilities like through offered individual
costs material available in plenty steam, hydrogen, cooling services
from companies within water, storage DM water, Synergy potentials resulting
Incentives for MSEZ from neighboring 15 effluent treatment, from optimum structures
innovative products, mn ton refinery & from industrial gasses ports and (e.g. links to supply chain,
such as government Companies within 5 kms terminal facilities and connections to research
subsidies radius of MSEZ. even emergency services institutes)
with all benefiting from Benefits from integrated
All major common Possibility to import low economy of scales. know-how structures
facilities available in cost feedstock from Gulf
the zone through through Mangalore Port Presence of large no of Availability of various
private which is just 10 kms away refineries and cracker feedstocks from all over
concessionaire from the zone. projects provide wide Europe through pipeline
models ranging feedstock to network connecting each
SEZ related fiscal incentives potential downstream Park
are available to units investors to invest in large
operating in Mangalore SEZ range of end products.
apart from duty free
imports, and income tax
exemptions on exports
income
Range of investments drawn Investments in Aromatic complex, PTA, Refining, Crackers, Petrochemical intermediates,
from Crackers, Polymers, Ethylene crackers, PET, Specialty chemicals, petrochemical Agrochemicals, Basic chemicals,
Petrochemical intermediates, polyester chips, APIs, Indian strategic intermediates and Bio-based Chemicals,
specialty chemicals, Pharma, Engineering petroleum reserves ltd - specialty chemicals Biotechnology, Catalysts,
Allied chemical industries, polymers-MMA, Industrial Gases, Packaging,
Engineering and Ancillary Polycarbonates, Investments exceeding $50 billion worth of Pharmaceuticals, Polymers,
industries Petrochemical USD $2.5 billion investments Refinery/Petrochemicals,
Type of
Intermediates – Bis- Specialty and Fine Chemicals
investments,
Total aggregate investments of phenol, Isocynates
$ 22 bn till now Formaldehyde etc.,
Specialty chemicals,
Aggregate investment
of USD 10.56 billion.
Current SEZ Land completely sold out; Being large area land Almost 70% of the SEZ land Land still available as it is a Land in various parks available to
Occupancy in DTA large parcels sold out is still available has been leased over last 5 large format project different extents. Some parks
Details but land still available years fully occupied
Low Modest
INR 1730 per sqm Average INR 1.5 Cr per Acre
O&M Charges - INR 15 per sqm lease premium;
Public relations
Crisis communication
Training (vocational /
advanced)
Medical services
Technical and maintenance
services
Warehousing and logistics
Engineering and planning
Facilities management
Analytical services
Event management
Safety/quality/environmental
control
Power grid services
Roads Waterworks & Island houses Pulau Seraya Parks are interconnected via
Graded plots
RCC Roads with Street lights waste water Power Station. numerous pipelines, as well as
Infrastructure Pipeline-cum-road
Strom Water Disposal treatment plant being linked to neighboring
offered connectivity to
(SWD) facility alongside by Sino-French Island has a network of countries.
Mangalore Seaport
road Water pipelines that allows for
Water Development Co., Well planned wide seamless integration Well-developed network of
Water distribution network Ltd, roads network for among companies. pipelines connects the Chemical
for 10 MGD water supply. internal and external Parks to the European
Water Reservoirs, Pumping Waste incinerator connectivity Two major cargo jetties on transshipment centers for
Stations and ESRs in both by Swire SITA Seamless power supply Jurong Island, namely mineral oil, natural gas, ethylene,
parts of SEZ. Waste Services from State Grid through Sakra Jetty and Banyan Propylene and naphtha.
A Desalination project is Ltd. robust power Jetty. Sakra Jetty is
being set up to meet infrastructure managed and controlled All common facilities are being
additional water Heating and Complete water by ExxonMobil. provided for Utilities, waste and
requirement of SEZ units. power station management from effluent management etc.
Drainage / Effluent Disposal with cogeneration drawing water from Central utility facilities
Underground pipeline for by Singapore rivers to purification to supplying steam, DM
collection of treated SembCorp distribution Water, cooling water, ETPs
effluent. Collection Sump Utilities. Waste water collection, etc., through multiple
and Guard Pond in both part process and disposal suppliers
of SEZ. Dock and tank system
Power storage facilities 24/7 security
33/11 KV Two sub-stations – by Vopak of surveillance and
one each in Part I & Part II Holland. emergency
are set up. Power management system
distribution network is in Sinopal, a JV
place. between Air
Power Project of 1200 MW Liquide and
is under implementation in Praxair, supplies
SEZ. industrial gases
Gas Supply
Gujarat State Petronet Ltd.
(GSPL) is co-developer for
gas distribution within SEZ.
Properties; Fugitive be expanded to 6 mld ̇ Halogens and their vacuum pumps, leaks, spills,
Waste Water/Effluents: emissions from capacity. Besides OMPL compounds (Cl2, Br2, HF, spent/used solvents,
various equipment (Aromatic complex) has its HCl, HBr) housekeeping (pad wash-down),
Waste water contains high own treatment facility for waste oils /lubricants from
̇ Incomplete combustion
COD, BOD, Dissolved solids, 10 mld of waste water. maintenance. Process water may
compounds, such as CO
Organic chemicals, heavy Waste water/ include chemicals like Methanol,
Solid wastes: and CxHy
metals, and cyanides etc effluents: Ethanol, Acetone, Isopropanol,
Currently only 19 small to Municipality wastes: ̇ Volatile organic Toluene etc .
Waste waters consist
medium units are using CETP Organic waste from compounds (VOC) which
of Inorganic Solid wastes: (non-hazardous
facility which together generate canteen, pantry etc; might encompass
sulphides, and hazardous) wastes are
13.3 mld of effluent. Inorganic and paper waste; compounds with
mercaptans, soluble generated.
Proposed 40 MLD capacities STP Sludge
hydrocarbons, carcinogenic potential
CETP in two stages factoring for These wastes can include off-
polymerised product, Hazardous waste: Used /
future needs and 90 MLD ̇ Particulate matter (such spec or obsolete raw materials or
phenolic compounds, spent Oil; Chemical sludge
submarine pipelines to carry as dust, soot, alkali, heavy products, spent solvents,
sulphide, cyanide, from ETP; Salt from MEE;
treated waste water of all the metals) with possible reaction residues, used
heavy oils, coke, Discarded containers /
plants in Dahej. (including the barrels / liners; Process carcinogenic
spent caustic, SOx, filter media, still bottoms, used
larger one’s not using CETP) NOx, hydrocarbons, residues and waste; Spent Properties. The main chemical reagents, dusts from
catalyst; Spent carbon; category of air pollutants
particulates, water filtration or air pollution control
Solid and hazardous wastes: Distillation Residues are combustion
borne waste equipment, raw material
Three categories of hazardous containing BOD, COD, emissions, VOCs and acid packaging wastes, laboratory
wastes generated from Suspended solid, oil, gases wastes, spills, as well as wastes
proposed CETP including ETP TSS, pH, Turbidity, generated during packaging of
Waste water/effluents
Sludge from Common Effluent and detergents etc. the formulated Product.Filter
Treatment Plant, Used oil from Include process and Non cakes and spent raw materials,
lubrication of Equipment and Currently 39.2 MLD Process waste waters Spent catalysts, spent filters,
Discarded Containers. of waste water is including spent solvents, sludges, wastewater treatment
being treated in the oil and grease, catalysts, biological sludge, contaminated
complex. Ultimate reactants; pump seal soil, old equipment/insulation,
Non-Processing
Waste:
Non processing
waste:
Sources: Chemical Parks in Europe and China by Chemlot Management Consultants, German Chemical Parks website, Chemical Industry Parks in China by Achema World wise news, Role of
clusters in Chemical Industry by EPCA.
Note: It should be recognized that in case of environmental impact is concerned, the Chemical and Petrochemicals industry generate considerable air and water pollution but can be mitigated
through proper technologies. The exact information on pollution loads and characteristics is very difficult to obtain for each park separately as limited information is available for each separate
park in literature. Most of sources and type of Air and water pollutants for typical refineries, Crackers, Intermediates, Organic chemicals and Pharmaceuticals are mostly same, the values may
vary though. We have determined the type of pollutants generated for each park based on composition and type of projects existing in each of the Park and typical pollutants and its range for
each separate type of industry as available in literature. For large Parks like Jurong and Shanghai, the pollutant types are more akin to refineries, crackers and large intermediate projects,
whereas the German parks are more dealing in production of specialty chemicals and pharmaceuticals etc hence pollutant types are more related to those kinds of industries.
Competition law is another key pillar of EU policy. Limitations to state aid and the risks of
joint activities between companies being found in violations of competition law have been
perceived as a barrier for launching cluster initiatives.
The leading chemical clusters in Europe have strong market positions and a rich set of supporting
and related industries.
While the maturity of the European clusters provides clear advantages, it can make the
launch of a cluster initiative more complex. The legacy of relations can turn out to be a barrier
for effective collaboration. The presence of many competing companies can make it less
likely for any individual company to take the initiative and contribute to a common goal.
Clusters with a dominating anchor firm, like BASF in Ludwigshafen, seem to work well but
might also have less potential for cluster effects.
The lower rate of market growth in Europe has a dampening effect on investment, leaving
European clusters with an aging capital stock. Only 16% of all investment projects in the
chemical industry occur in Europe compared to 35% in South East Asia and 27% in the Middle
East.
world-class level. In addition, labor costs are approximately on the same level as in Europe,
whereas labor productivity is very high in comparison with the rest of the world. When
considering the economic and administrative environment, a rather high-income tax up to 39.5%,
due to high federal tax, has to be considered.
d) Chemical Industry Parks in Southeast Asia -Singapore
Investments in chemical industry parks in Southeast Asia, especially in Singapore, benefit from a
world-class administrational environment that offers very favorable tax incentives and shows a
very effective site commercialization and clearly defined site development strategy. They are the
best when it comes to site positioning strategy and production networks. Tax holidays up to 10
years and reduced income taxes are other important aspects. Site service provision and project
handling are considered as advanced as the Asian sites, but do not always meet high European
levels. Located close to one of the world's largest seaports, the region's leading chemical site
Jurong Island is well connected to the global customer and sourcing markets. Major disadvantages
are the electrical energy prices that are as high as at several chemical sites in Europe, e.g.,
chemical cluster Antwerp, but double the price of other Southeast Asian chemical sites.
Concerning qualified employees, comparable to the Middle East and China, there is a strong need
for internal company training on the job, because of missing dual education system. The German
education system still functions as a role model for several initiatives started in Asia and
elsewhere.
The chemical industry in Singapore faces a context that is also strong, notwithstanding the clear
structural differences between Singapore and Europe. Governments play a strong active role in
economic development in Singapore. The Singaporean government has developed a global
reputation for extreme efficiency and professionalism. The country views economic development
in partnership between government and companies as a national priority. The general business
environment is very strong in Singapore while the situation in China is more mixed. Singapore
benefits from a very efficient infrastructure, high openness to foreign companies, availability if
skilled local and expatriate labor, and the presence of many world-class companies in supporting
and related industries.
Singapore has developed a strong chemical cluster as the result of a determined strategy that has
persisted over many years. The Singaporean chemical cluster continues to receive major
investment commitments from foreign companies. Supporting logistical and financial services are
widely available, and the growing investments into biopharmaceuticals could present an
interesting future opportunity.
e) Chemical Industry Parks in China
Especially the large and dynamic customer market for chemicals as well as low investment and
labor costs put Chinese chemical industry parks in a favorable position when compared with other
sites. Labor cost levels amount to less than 10% to 20% compared with European sites.
Nevertheless, intellectual property protection remains an issue in China, although legislation has
been adjusted to international standards. Furthermore, the low degree of production integration
at the considered sites is not really addressed by a proactive intercompany production network
planning and site commercialization by the Chinese site operators. In addition, there are
monopolistic structures of site services supply; however, in total they have no influence on
favorable production costs for electrical energy, wastewater treatment and maintenance services.
The context for the chemical industry in China is not quite as strong but improving. Governments
play a strong active role in economic development in China like in case of Singapore.
China has invested tremendously in physical infrastructure, boasts large numbers of graduates in
many technical disciplines, and has been interested to attract foreign companies. Many industrial
parks have been created, some - like Changzhou Park in the Ningbo Chemical Industry Zone south
of Shanghai - with a particular focus on chemical products. But many weaknesses persist and
China still ranks low on aggregate measures of competitiveness such as the Global
Competitiveness Report.
Especially when considering more rural chemical sites compared with a very developed and
professionally managed park like the Shanghai Chemical Industry Park, the sites are at very early
stages of development in becoming a chemical park. The heterogeneity in the Chinese chemical
sites' landscape is still extensive concerning, among other things, site strategies, production
network development plans, availability of qualified labor, satisfying labor productivity level and
site services as well as infrastructure provision.
The Chinese chemical clusters are emerging around the sites of major new investments, like the
joint venture between SINOPEC and BASF in Nanjing. Many clusters in China are focused on a
relatively narrow set of activities, even if they reach large scale in those areas.
In China both the national and the regional governments are important partners for cluster
initiatives. Government agencies in China can suffer from low efficiency and corruption, despite
their clear focus on economic growth. There can also be inconsistencies between the decisions of
different government agencies.
f) Chemical Industry Parks in India
Chemical clusters in India are very recent phenomena. It started with SEZ and PCPIR policies of
Government of India. Besides some of the government departments have recently come out with
Industry Park /cluster development schemes like Plastic Parks and Pharma Parks to give fillip to
investments in chemical and related industries. Cluster based approach is increasingly being
recognized as an effective and sustainable strategy for competitive enhancement of specific
Industries by providing common infrastructure and support services and exploit the benefits
arising due to optimization of resources and economies of scale. There have been successful
examples of integrated Textile Parks in the country.
PCPIR scheme experiences merit discussions to give lessons for new chemical parks. A PCPIR is
supposed to be combination of production units, public utilities, logistics, environmental
protection mechanisms, residential areas and administrative services to be set up on very large
land areas of about 250 sqm kms. It is supposed to have a processing area, where the
manufacturing facilities, along with associated logistics and other services, and required
infrastructure will be located, and a non-processing area, to include residential, commercial and
other social and institutional infrastructure. The minimum processing area for the PCPIR will be
about 40% of the total designated area, i.e., around 100 sq.km. The processing area may or may
not be contiguous. The PCPIR may include one or more Special Economic Zones, Industrial Parks,
Free Trade & Warehousing Zones, Export Oriented Units, or Growth Centers, duly notified under
the relevant Central or state legislation or policy. PCPIRs are infrastructure-driven projects where
the Centre provides support for development of external physical infrastructure linkages such as
rail, road, port, airport, telecom through Viability Gap Funding (VGF).
Touted as game-changer for Indian chemical and petrochemicals industry, the PCPIR policy was
launched with an aim to attract investments worth around $ 100 billion in these regions. PCPIRs
were to be formed specifically to attract investments for establishing production facilities for
petroleum, chemicals and Petrochemicals. However, the policy has failed to deliver desired results.
Of the five approved PCPIRs, only Dahej (Gujarat) PCPIR has made progress, while rest have failed
to take off for various reasons.
The main challenges have been non-availability of basic feedstock for the downstream industries
from refineries and crackers, other challenges have included Land Acquisition and getting
environmental clearances in PCPIRs due to protests and other delays. The land areas of 250 sq.km
for PCPIRs are huge for managing. The timely development of supporting infrastructure and
external linkages is also vital for the successes of these major investments which have recorded a
very slow pace. The chemical industry has not been able to attract top class talent which has
created severe shortage of skilled manpower in the industry thus impacting its productivity and
growth. There are also issues related to multiple legislations in chemical industry and fall under
the purview of different industries making it very cumbersome to get environmental clearances.
Indian PCPIRs have to constantly compete with countries in the Middle East and South East Asia
for attracting investments in the chemicals and petrochemicals sector. Even in Dahej, the most
successful of PCPIRs, the chemical industries face several issues related to water, roads, power
availability and environmental clearances. There are not very many common facilities in the Dahej
and individual units have to make arrangements for effluent treatment. Dahej besides have limited
port capacity and poor access to Urban and social infrastructure. The connectivity by Rail and Air
is big challenge. Besides water supply is an issue due to limited supply.
Mangalore Petrochemical despite excellent infrastructure in SEZ format has faced major
constraints which are to do more with SEZ policy constraints which restrict the sales of
petrochemical in domestic area which happens to be the major growth areas. Also, it has faced
similar problems as PCPIRs in assuring feedstock supply from refineries for the downstream
industries.
Under the new plastic and Pharma Parks schemes the government of India is giving grants for
setting up common facilities subject to certain conditions. Government has given approval for
setting up 10 plastic parks in different states with total grant of appx. Rs 400 crores. The success
of the scheme will have to be watched. As many as six pharma clusters are similarly planned to be
developed across the country under the cluster development programme, which was launched in
2015. Among other things, common infrastructure facilities such as roads, water supply, Power,
Effluent treatment, waste management etc will be created for the companies willing to put up
their units. The success of these units has to be seen.
including quality water and Power supply apart from warehousing etc. to reduce their capital costs.
The investors from other states generally were found to have poor perception of industry culture of
Kerala and were somewhat apprehensive of labour related issues. The wish list of the potential
investors has been summarized below in order of criticality.
Table 5-10: Investors Wish List
VITAL ESSENTIAL
• Long Term Feedstock Security. • Warehousing and 3 PL Services.
• Quality Power and Water. DESIRABLE
• CETP and Solid and Hazardous waste • Arrangement for other Raw Materials (not
management. available from BPCL).
• Competitive Land Pricing. • DM water and Steam.
• Incentives (Comparable / better to • Testing Laboratory.
other states).
• Natural Gas Supply.
• Ensure Moratorium on Labor unrest.
• Handholding Services.
Source: Primary Survey
In order to give shape to the above sales Plan one need to formulate appropriate marketing strategies
for the Park in lieu of its competitive advantages and strategy dictates.
location for overall viability. The factors that the investors look at while deciding locations are the
following:
Availability of Critical Feedstock / Raw material
Market Proximity
Land Prices and availability
The incentives available
The Utility Costs (Power & water)
Access to Infrastructure support
Skilled Manpower availability
Social & Urban infrastructure
Attractiveness scores
Prospective Project Market Catchment Sensitivity w.r.t to on Market Proximity
Categories Ares Market Proximity out of Max 5
(1 poor and 5 excellent)
Within the Park for Least sensitive to
downstream product products sold within the
manufacture or Park and for Exports
INTERMEDIATES exports or sales in through Kochi Port; but 2.5/5
Gujarat and sensitive w.r.t to end
Maharashtra markets in Gujarat and
Maharashtra
The disadvantage of market proximity in certain products like Intermediates is largely negated by
feedstock proximity and for Specialty chemicals and Pharmaceuticals it is negated due to high
value-added product.
The Park location is optimal for the range of products it is envisaged to produce.
c) Land Prices and Availability
The cost of the land in the park per Acre will work out to Approximately Rs. 4.22 Crore. The detail
is summarized in Table below.
Table 5-13: Cost of Sellable Land in proposed KINFRA Petrochemical Park
Sale of Undeveloped land to BPCL carved out from the Park (150 acres +
portion of road extension Area 4.5 acres) @ Rs2.72 Cr. Per acre including Rs. 420 Cr.
PMC and other costs of 10%
Total Usable Land for Industrial Use leaving green space +non-utilizable
218 acres
Land due to terrain and HT lines.
Total available land for Sale (which excludes area for administration,
210 Acres
Water supply, CETP etc)
The cost as worked out is far higher than the favoured areas in India where land is still available.
The land cost in these areas is far lower than the estimated cost of the Land in KINFRA
Petrochemical Park as indicated in Table below. The land cost at the best is a maximum of Rs. 2
Crore per acre. The land prices in Kerala too in other KINFRA parks between Rs. 1.0 - 2.5 Crore.
Please refer Annexure 4 A and b for the land cost comparisons for different states and within Kerala
respectively.
Table 5-14: Competitive Land Prices
Maharashtra 0.04-0.83
Gujarat 0.38-1.68
Orissa 0.1-.6
Telangana 0.41-0.97
Kerala Maximum 2.5
Basis: Secondary data and Analysis obtained for State Government Parks Detailed in Annexure 4 a
However, the locations lack advantages of what the KINFRA Park provides like feedstock’s & Port
proximity as well as access to good urban infrastructure at its doorstep. A comparative analysis of
locations with more or less similar advantages shows that Kochi KINFRA Petrochemical is quite
competitively placed as in Table 5-15. The details are provided in Annexure 5.
Table 5-15: Land Prices in Urban cities with combination of refinery & Port facility
The Kochi KINFRA Petrochemical Park is competitive considering that the Feedstock especially
immovable feedstock is available at its doorstep. However, for feedstock, which are movable and are
freely imported into India there would certainly be an issue of land cost as the units can be set up
closer to markets than feedstock. The pricing of the land for such units would have to be accordingly
worked out keeping the prevailing prices in favourable states where there is surplus land available.
Many of the states have large Land banks available for attracting units to their states as can be seen
from Table below.
Table 5-16: Land Banks Available in preferred State in India
Chem
Open
Pharma
Chem
Open
Pharma
Chem
Open
(Land in Acres)
Maharashtra 441 88 4032 212 Large land Bank is being created 653 88
Source: Web sites of various industry and infrastructure authorities of various states
Our proposed market strategy has to factor competition that may arise from other states for
drawing investments in similar industries that we plan to target in our Park.
d) The incentives available
The states which are favoured and house chemical and Pharmaceutical manufacturing hubs also
provide considerable Incentives, which are not present in Kerala. The incentives prevailing in these
favoured states are detailed in Table below. A comparative analysis of incentives offered by select
states has been provided in Annexure 6.
Table 5-17: Comparative Incentives for manufacturing units
Andhra
Details of Incentives Kerala Karnataka Orissa
Pradesh
Power Subsidy
Stamp Duty Subsidy
Capital Subsidy
Interest Subsidy
SGST Reimbursement
Environment Related
*
incentives
Employment Related
incentives
Technology up gradation
Incentives
Training fee Reimbursement
Source: State Incentive Structures (Details obtained from website sources and provided details in Annexure 6)
It may be mentioned that almost all other states have attractive industry sector wise policies and
incentive schemes for attracting investments. KOCHI KINFRA PETROCHEMICAL PARK will be at a
disadvantage on incentive offerings. The government has to devise an incentive package
comparable to the preferred states for the manufacture of Petrochemical derivatives, specialty
chemicals, Pharmaceuticals and other related products.
e) The Utility Costs (Power, water and Fuel)
i) Power
The Power cost in Kerala is one of the lowest in India barring Gujarat which is Rs. 1.2 / unit
lower as seen in Table below.
Table 5-18: Electricity Charge per Unit by states
Gujarat is a hub for manufacture of Chemicals and petrochemical derivatives and investor’s
first preference and offers better Power tariff than Kerala (even though it is one of the lowest).
Since energy cost is of prime interest to units the Park may be at disadvantage compared to
Gujarat on this count.
ii) Water
Water is lifeline for Chemical projects. KOCHI KINFRA PETROCHEMCIAL PARK is in much
advantageous position compared to all other competing locations in the country (Refer Table
19). Dahej which currently seem to have lower water cost actually has deficit in water supply
and with proposed commissioning of desalination plant the cost of water may considerably go
up.
Table 5-19: Comparative Water Tariff
Name of SEZ Water Charges (Rs. Per KL)
Dahej SEZ, Gujarat 24 (Rationed supply)
Mangalore SEZ, Karnataka ~ 40
JNPC Parwada, Vizag, Andhra Pradesh 50
The overall cost works out economical compared to other parks in India.
iii) Fuel
GAIL will make LNG supply available to all the industry in the complex including for KOCHI
KINFRA PETROCHEMCIAL PARK. Very few industry locations in the country currently have
natural gas available as fuel. The natural gas is clean fuel preferred by industry and brings down
the carbon emissions and accordingly the cost of environmental compliances. KINFRA has
distinct advantages compared to many other locations in the country.
f) Common Industrial Infrastructure
As discussed in the earlier sections the Park will be designed to meet the standards set by similar
parks across the world and in India as well as per the needs enunciated by sample of investors. It
will be one of the best in its category in the country and factor the needs of the potential investors.
g) Skilled Manpower
Kerala is the most literate state in India and has large number of technical colleges. They are
endowed with large available educated manpower and comparable to other states.
h) Social & Urban infrastructure
Kochi is one of the most cosmopolitan and vibrant cities in India and is endowed with all social and
urban infrastructures and comparable to international standards.
of feedstock would need to be subsidized to attract them. The recommended pricing for the land
is summarized in Table 5-21.
Table 5-21: Recommended Land Pricing by types of Units
Note: This proposed price will actually be finalized/further revised on financial evaluation of the
Project.
The pricing will have an escalation of 5% every year.
b. Operation and Maintenance (O&M) Charges
Charges towards operation of maintenance of the gated Park including provision of street lighting
and its maintenance, Road and its maintenance, Green Space and its maintenance, Sewage
treatment & Disposal, Drinking and water for sanitation supply and maintenance, Security,
Communication lines, maintenance of firefighting facilities etc. will form as O&M Charges which
will be levied on a Quarterly basis. The proposed O&M Charges are estimated at Rs.15 / Sq.mtr /
Quarter.
c. Waste Management Charges
This will include charges towards use of Zero Liquid discharge central effluent Treatment Plant,
Solid waste collection and disposal and recycling of treated waste water. The charges will be fixed
based on the specification of effluent generated.
d. Electricity
The charges will be as levied by Kerala Electricity Board.
e. Water, DM Water, Steam
A provision for special Central utility facility will be provided for a concessionaire to provide
specialized utility services including supply of Demineralized Water, Steam (at various pressures),
and any other special utility required.
The pricing will be based on pay per use plan.
o An integrated high-quality Park with plug and Play facility of utilities and Feedstock.
o Non-stop availability of assured quality power, Water and other utilities.
o Common infrastructure of 3PL Logistics & Warehousing, Central waste management
Support.
o Compression of environment clearance time frame on account of Umbrella clearance for
the Park.
o Handholding services to investors to effectively settle down in the park.
o A Park with international gateway and connectivity to Cochin Port and well-connected road
network.
o A Complex, which ensures low investment per unit of production and transaction cost.
o A Park with facilities which works round the clock. And much more.
These advantages will be clearly translated in the form of Brochure, video presentation, web site
for dissemination.
c. Park Promotion
A multi-pronged market development plan will be followed. The Promotion will be jointly taken
up by KINFRA and BPCL wherever necessary.
o Advertisement
Advertisement will be released in various prospective industry association newsletters,
and Industry journals. Wherever required prominent local media will be targeted.
o Generate publicity
Organize inauguration and foundation stone laying events Make media announcements,
go for interviews in electronic media, publish write ups.
Invite all major entrepreneurs in the region to the inauguration and foundation stone
laying events.
o Direct Marketing
Identify major marketers looking for contract producers (sanitary napkins, diapers,
Paints, adhesives etc.), companies looking for expansion in various regions. Go for direct
mailers to them by electronic media.
o Road Shows
Have special road shows in Kerala to attract local entrepreneurs and other industrial hubs
of the perspective industries – Mumbai, Ahmedabad, Baroda and Bangalore etc.
o Seminars & Participation in Exhibitions
Participate in the industry associations run seminars and exhibitions, industry specific
seminars / exhibitions in prospective locations.
o Facilitation at the Site
The prospective investors will be taken for a site visit and meeting with BPCL officials and
KINFRA officials to generate confidence and remove any apprehension they have on the
support that will be provided and the availability of feedstock. The visit itinerary will be
chalked out to provide complete confidence to the prospective.
The tentative promotion Program is indicated in Table 5-22.
P a g e |91 Demand Analysis
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Phase I Phase II
# Activity
2018-2022 2023++
1 Web Site / maintenance X X
2 Presentation Videos 1 1
3 Brochures
On Park 1 1
On Opportunity 1 1
4 Advertisement
In End user association Magazine in 8 4
Selective Media
5 Road Shows: (Cochin, Ahmedabad, Baroda,
18 6
Coimbatore, Mumbai, Bangalore)
6 End user Industry Conferences / Exhibitions
12 4
(Numbers)
7 Marketing Interaction / Due Diligence Support With every With every
Meeting and travelling for the above as well as prospective prospective
for prospective investors and finalization Investor Investor
Source: Consultant Assessment
d. Marketing Cost
The overall marketing budget is estimated at Rs 5.00 crores over the life of the project which
is broadly summarized in Table 5-23.
Table 5-23: Estimated Budget for Marketing the Park
Phase I Phase II
TOTAL
# Activity 2018-2022 2023++
(Rs. Lakhs)
(Rs. Lakhs) (Rs. Lakhs)
1 Web Site
2 Presentation Video 30 10 40
Brochures
3
Park & End user Opportunity brochures
Advertisement
4 In End user association Magazine and 5 5 10
Selective Media
Road Shows: (Cochin, Ahmedabad,
5 Baroda, Coimbatore, Mumbai, 40 20 60
Bangalore)
End user Industry Conferences /
6 30 10 40
Exhibitions
Marketing Interaction / Due Diligence
7 30 20 50
Support
6. Functional Design
6.1. Surveys and Investigations2
6.2. Preamble
Greenfield projects such as this have to be effective in appropriate physical planning to harness the
complete potential of the site. A state-of-the-art Master Plan incorporating holistic and sustainable
industrial development concepts shall include:
Long term vision with focus on international competence
Focus on integrated infrastructure
Optimal utilisation of available land and flexibility in plot division
Optimal use of natural resources including energy conservation measures
Traffic management
Inclusion of social infrastructure and allied requirements
Integration of operation and management aspects
Social Wellbeing: To improve the level of physical and mental health of the community by
providing basic necessities and amenities in the community and also by creating different
employment opportunities in the area.
Economic Development: To ensure the economic growth in the area by providing key
economic sectors and by reducing the cost of the essential goods and services. This will
increase the economic activity and productivity to promote growth in the community.
2Detailed topographic survey and geotechnical investigations were carried out and the same has been
enclosed as Annexure 8.
P a g e |93 Functional Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
SOCIAL ENVIRONMENT
DEVELOPMENT PROTECTION
ECONOMIC
GROWTH
The planning concepts considered for the development of Petrochemical Park is based on the following
principles:
Optimum
resource
utilization for
maximum
Create salebility
opportunities SEZ Acts and
for better Policies
public realm
Provision for
Planning common
Flexibility
Concepts facilities and
open spaces
Minimum
length of
Product Mix Road with
provision for
redundancy
Surrounding
Landuse
Factor Remarks
Wind Influence
Prominent wind direction is from south-west to north-east. The prevailing wind
direction plays a major role to reduce the impact on surrounding natural and physical
environment.
Land Use The site is part of land earmarked for industrial land use.
Need for phased The Petrochemical Park is envisaged to be developed over 10 years. This calls for a
development phased approach to development and flexibility in terms of layout and provision of
services.
All the above aspects were taken into consideration for planning the processing area, support services,
utilities and amenities.
Proposed zoning of the petrochemical park is based on site context and derived from site potentials
and constraints.
The broad proposed zones in the petrochemical park are as follows:
Industrial Zones
Logistics and Warehousing Zone
Support Facility Zone
6.10.2. Transportation
Total length of 22 mt ROW road connecting sites, outside the boundary = 2830 mt.
6.10.2.2. Parking
The proposed Petrochemical park will have an integrated facility for truck terminal warehousing and
parking. As the site is separated by BPCL land the location of parking facilities have been proposed
close to the entry point of the two land parcels. Proposed location of parking is shown in Figure 6-5.
23%
51%
9%
2%
6%
9%
Table 6-3: Proposed Land Use Break up for Entire Project Site Area
S. No Land Use Area in Sq. Mt Area in Ac. % of Total
Area
1 Petrochemical Plots 630862.06 155.889426 51.26%
2 Pharma Plots 116961.19 28.9017425 9.50%
3 Utilities / Amenities 69792.97 17.2462203 5.67%
4 Truck Terminal Warehouse 19711.23 4.87075152 1.60%
5 Road & Utility Corridor 113716.9157 28.1000648 9.24%
6 GREEN * 279685.481 69.1117947 22.73%
7 Sub Total 1230729.847 304.12 100.00%
8 Proposed for BPCL Plots 687965.52 170
Total 1918695.367 474.12
FACT Road 62078.8 15.34
Grand Total Site Area 1980774.167 489.46
*In addition, 10.27% of net industrial plotted area will be developed as green belt within the industrial
units.
6.11.5. Trees
Reference
S.NO. Botanical name Common name Type Spacing images
(in
metres)
6.11.6. Shrubs
This landscape represents an amalgamation of green, paved and contoured area. The diverse use of
landscape surfaces and vegetation material creates a composite scheme of the landscape abutting the
river.
All detailed cost estimates, Bill of Quantities (BOQ’s) and engineering drawings related to Boundary
Wall, Site Grading, Landscaping and Detailed Master Plan drawing has been included as Annexure 9
and Annexure 10.
7. Engineering Design
7.1. Traffic and Transportation
This section presents the traffic and transportation studies carried out in order to assess the adequacy
of the circulation network (both internal and external) of the project site and to arrive at the proposed
traffic management plan. The section presents the estimated Trip Generation of the project site (from
commercial as well as passenger traffic), followed by estimation of Peak Hour Trips and assumptions
taken on Trip Distribution. Based on this, Lane Adequacy checks are presented for the existing and
proposed road network within and around the project site. The analysis of critical junctions in the
study area is also presented along with appropriate recommendations for each junction. The chapter
concludes with recommendations concerning traffic management of the project site.
The road network is the most important infrastructure development in any industrial area. Road
network planning includes the fixing of right of way, geometric design of roads, design of typical cross-
sections to ensure adequacy of carriageway widths and utility corridors, selection and design of
pavement type, design of intersections, interchanges, location & provision of appropriate facilities.
7.1.1.2. Assumptions
To calculate the design capacity of compatible roads, junctions, parking and public transport facilities
following assumptions have been made which are based on standard practice of Industrial Park / SEZ
development: -
Traffic Population per day – Considering industrial norms the detailed calculated population for
development area is given in Table 7-1.
All required detailed engineering drawings, cost estimates and bill of quantities (BOQ’s) related to
Road Network Plan, Traffic Circulation Plan, Road Plan and Profiles, Typical Cross Sections has been
enclosed as Annexure 9 and Annexure 10.
Table 7-1: Land use wise area and traffic population distribution
Sl. Land Use Land parcel Area Population
No. Acre Sq.m. BUA Working Population Floating Population Working + Floating Population
(Sq.m.)
A INDUSTRIES
A.1 Ancillary 3.68 14760 10332 91 137 228
A.2 Intermediate Chemicals 85.80 347229 243060 429 644 1073
A.3 Specialty Chemical 34.27 138695 97087 857 1285 2142
A.4 End Products (Paints/ Adhesives / Inks, etc.) 21.42 86676 60673 535 803 1339
A.4 End Products (Based on Polyurethane And SAP) 10.78 43612 30528 431 647 1078
Sub-Total 155.95 630972 441680 2343 3516 5860
B COMMON FACILITIES
Truck Terminal and Warehouse 4.87 19711 13798 73 110 183
C UTILITY
Admin &Tech Center 1.37 5543 11086 21 31 51
Contract, R&D Lab 1.96 7915 15831 29 44 73
Water Works 1.19 4805 4805 18 27 45
ZSS 0.58 2333 2333 9 13 22
MRSS 1.59 6424 6424 24 36 60
Sub-Total 6.68 27019 40477 100 150 250
D CETPs 10.57 42774 42774 159 238 396
F GREEN AREA 69 279685
G ROAD 28 113717
H PHARMA PARK PLOT 28.90 116961 81873 1156 1734 2890
I FACT ROAD 15.34 62079
TOTAL 319.46 1292817 620602 3731 5597 9328
BPCL PLOTS 170
GRAND TOTAL AREA 489.49
Modal Split & Occupancy – On the basis of similar projects, past experience and market analysis
has been considered as mentioned in the table below:
Table 7-2: Modal Split & Occupancy
Modal Split of Population
Land Use IPT/ TW Car Taxi Traveler/ Mini Bus Bus
NMT/ HOV
Walk
WP FP WP FP WP FP WP FP WP FP WP FP WP FP
Industries 30% 5% 25% 20% 10% 30% 5% 20% 5% 5% 15% 10% 10% 10%
Source: Voyants
WP – Working Population, FP – Floating Population, IPT – Intermediate Public Transport, NMT
– Non-motorized Transport, HOV – High Occupancy Vehicles.
Peak Hour Traffic – 65% passengers’ traffic considering that full traffic consumes in 2 office
hours.
For commercial vehicles average tonnage per day - 0.01 Tonnes/sq.m/day.
Total processing area for total tonnage calculation – 2409841 sqm
Load Sharing & General weight of commodity for Commercial Vehicles – As per market study.
Considering that the northern gate A will ingress the maximum part of the area so maximum traffic
which is about 70% of the whole traffic will circulate through this gate only. Total peak hour traffic is
considered 65% which can be accommodated by 4 lanes.
Considering that the southern gate B will ingress mainly the southern part of the area so maximum
southern part industries traffic which is about 30% of the whole traffic will circulate through this gate.
Total peak hour traffic is considered 65% which can be accommodated by 4 lanes.
Considering all factors demand has been arrived for full development of area is given detail in below
table.
Table 7-11: Parking Demand Assessment
Built Area of New Development (in Sqm) 673572
Number of Employees 3983
Visitors 5975
Source: Voyants
XI. Landscaped plazas with designated spaces for hawkers along with parking lots for NMT, other
IPT and service vehicles as well private vehicles shall be provided in the detailed design.
The typical cross sections for various types of RoW are presented in figure below.
7.3.1.3. Intersections
Since anticipated traffic volume is high in this kind of area development project the smooth traffic
movement prevails over high speed, all the intersections are kept at grade only. Thus, the basic
P a g e |128 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
requirements for the design of intersections in this case was to cater to safe movements for the traffic
and to provide them full traffic information by way of traffic signs, pavement markings and traffic
signals, if required in future. Further, simplicity and uniformity has been considered as the guiding
principles for intersection design and to ensure the safe passage of movements.
Though IRC-SP: 41-1994 give the monogram for warrants for the different types of at-grade or grade
separated intersections, these warrants are based upon the traffic volumes on each of the two
intersecting roads. The type of intersection to be provided shall be based on these IRC guidelines.
Similarly warrants given in the “Type Designs for Intersections on National Highways” published by
the MORT&H has also been taken into consideration for the design of intersections. However, looking
at the very high level of traffic the at-grade intersections have been categorized in two types:
Intersections within the sub-links
Intersections of sub-links with the main link.
All required cost estimates cum BOQ’s and detailed engineering drawings w.r.t road network plans,
road plan and profiles has been enclosed as Annexure 9 and Annexure 10.
Table 7-17: Summary of Estimated Cut & Fill Volume for Fact Road
Description 2D Area (sqm) Cut (Cu.M) Fill (Cu.M) Net (Cu.M) Cut-Fill
Plot area 56914 17074 79680 -62605 Fill
14.06 Acre
All required detailed engineering drawings, cost estimates, bill of quantities (BOQ’s) w.r.t site
grading and levelling, boundary wall, landscape plan, buildings and proposed gates and also a
detailed master plan has been enclosed as Annexure 9 and Annexure 10.
Figure 7-6: Site Levelling and Grading Work of Petrochemical Park Project
1. Storm water drains are aligned to the carriageways following the proposed road gradients,
draining into the water bodies.
2. Proposed plot grading and direction of plot outfall has been considered in estimating the
runoff generation in a particular road stretch.
All required detailed engineering drawings w.r.t potable water supply, recycle water supply,
sewerage networks, storm water networks, fire water networks, cost estimates cum BOQ’s has
been enclosed as Annexure 9 and Annexure 10.
The figure below gives schematic diagram of the process of Storm Water network design followed.
7.5.3.3. Imperviousness
The percentage of drainage area can be obtained from the records of a particular drainage basin or
City. In the absence of such data, standards can be followed.
Based on the land use, adopted coefficient of imperviousness for various land use of this project is
given in Table 7-18.
Coefficient of
Sl. No. Parameters
Imperviousness
1 Commercial and Industrial area 0.8
2 Residential area 0.6
3 Parks & Undeveloped areas including agricultural areas
0.2
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
Elevation Elevation
Length Cover Ground Ground Invert Invert Depth Slope
Start Stop (Scaled) (Average) (Start) (Stop) (Start) (Stop) (Normal) / (Calculated)
Label Node Node (m) Size (Display) (m) (m) (m) (m) (m) Rise (%) (1/S)
CO-1 N-327 N-46 28.32 0.6 X 0.6 0.06 36.11 36.03 35.51 35.32 5.30 146.61
CO-2 N-63 N-328 19.44 0.6 X 0.6 0.11 26.55 26.42 25.85 25.70 27.50 129.60
CO-3 N-168 N-328 30.56 0.9 X 0.9 0.86 26.30 26.42 24.85 24.35 32.40 61.12
CO-4 N-328 O-7 7.20 1.05 X 1.05 1.15 26.42 26.54 24.35 24.20 43.30 47.99
CO-5 N-264 N-329 13.99 0.6 X 0.6 1.04 26.39 26.35 25.01 24.45 1.10 25.00
CO-6 N-7 N-8 5.95 1.05 X 1.05 0.16 3.09 3.15 1.91 1.90 79.10 500.00
CO-7 N-278 N-329 36.01 1.05 X 1.05 0.76 26.30 26.35 24.57 24.45 55.30 300.09
CO-8 N-329 N-328 10.84 1.05 X 1.05 0.93 26.35 26.42 24.45 24.35 37.80 108.36
CO-9 N-330 N-100 46.71 0.6 X 0.6 0.00 26.51 26.33 25.91 25.73 28.40 255.30
CO-10 N-331 N-109 46.75 0.6 X 0.6 0.00 26.82 26.63 26.22 26.03 16.70 242.47
CO-11 N-15 N-16 10.15 0.6 X 0.6 0.02 36.08 36.10 35.48 35.46 16.30 500.00
CO-12 N-10 N-17 40.10 0.9 X 0.9 0.15 23.34 23.43 22.44 22.22 79.70 179.62
CO-13 N-177 N-334 47.08 0.6 X 0.6 0.03 24.54 24.11 23.94 23.45 73.60 96.55
CO-14 N-19 N-20 10.90 0.9 X 0.75 0.12 29.10 29.10 28.24 28.22 71.60 500.00
CO-15 N-334 N-21 46.53 0.75 x 0.75 0.05 24.11 23.94 23.36 23.10 60.90 176.37
CO-16 N-18 N-7 10.90 1.05 X 1.05 0.09 3.09 3.09 1.99 1.91 29.90 146.77
CO-17 N-22 N-21 10.90 0.9 X 0.9 0.22 24.23 23.94 23.18 22.74 39.40 25.00
CO-18 N-333 N-335 56.21 0.6 X 0.6 0.00 33.16 32.53 32.56 31.93 40.00 88.53
P a g e |137 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-19 N-336 N-19 36.68 0.6 X 0.6 0.16 30.79 29.10 29.92 28.45 27.90 25.00
CO-20 N-335 N-336 51.99 0.6 X 0.6 0.14 32.53 30.79 31.93 29.92 27.70 25.87
CO-21 N-30 O-14 11.97 0.6 X 0.6 0.07 15.23 15.15 14.58 14.46 80.00 97.16
CO-22 N-332 N-337 57.94 0.6 X 0.6 0.01 33.48 32.63 32.88 32.00 8.50 65.46
CO-23 N-25 N-26 14.53 0.6 X 0.6 0.16 23.82 24.10 23.22 23.19 32.00 500.00
CO-24 N-338 N-20 35.87 0.6 X 0.6 0.17 30.77 29.10 29.88 28.45 21.40 25.00
CO-25 N-28 N-27 16.09 0.6 X 0.6 0.00 37.08 36.76 36.48 36.16 31.20 50.83
CO-26 N-337 N-338 52.87 0.6 X 0.6 0.16 32.63 30.77 32.00 29.88 20.70 25.00
CO-27 N-29 N-41 32.03 0.6 X 0.6 0.04 24.97 23.68 24.33 23.05 21.70 25.00
CO-28 N-37 N-339 41.90 0.75 x 0.75 0.00 28.19 27.55 27.44 26.80 55.30 65.39
CO-29 N-340 N-35 54.93 0.75 x 0.75 0.15 26.64 25.63 25.89 24.58 47.70 41.90
CO-30 N-339 N-340 47.42 0.75 x 0.75 0.00 27.55 26.64 26.80 25.89 51.20 52.10
CO-31 N-31 N-32 16.88 0.75 x 0.75 0.01 8.26 8.25 7.51 7.47 55.60 500.00
CO-32 N-26 N-1 18.82 0.75 x 0.75 0.08 24.10 23.48 23.19 22.73 59.20 40.68
CO-33 N-324 N-341 45.56 0.6 X 0.6 0.00 28.20 27.48 27.60 26.88 5.60 63.35
CO-34 N-33 N-34 17.35 0.9 X 0.9 0.08 3.80 3.92 2.90 2.86 76.30 500.00
CO-35 N-342 N-36 52.16 0.6 X 0.6 0.00 26.59 25.63 25.99 25.03 13.20 54.45
CO-36 N-341 N-342 49.50 0.6 X 0.6 0.00 27.48 26.59 26.88 25.99 9.80 55.14
CO-37 N-36 N-35 17.70 0.6 X 0.6 0.01 25.63 25.63 25.03 25.00 70.50 613.13
CO-38 N-343 O-11 14.60 1.2 X 1.2 0.10 23.56 23.30 22.15 22.10 65.10 274.92
CO-39 N-94 N-122 45.41 0.6 X 0.6 0.29 24.89 23.56 24.25 22.43 20.80 25.00
CO-40 N-20 N-37 20.37 0.75 x 0.75 0.06 29.10 28.19 28.22 27.44 39.20 26.28
CO-41 N-38 N-19 20.71 0.6 X 0.6 0.13 28.88 29.10 28.28 28.24 80.00 500.00
CO-42 N-122 N-343 16.59 0.6 X 0.6 0.57 23.56 23.56 22.43 22.35 58.30 207.37
P a g e |138 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-43 N-39 N-40 21.02 0.6 X 0.6 0.08 28.88 27.89 28.13 27.29 13.50 25.00
CO-44 N-42 N-24 22.95 0.6 X 0.6 0.00 15.37 15.23 14.77 14.63 23.60 163.68
CO-45 N-344 N-142 50.10 0.6 X 0.6 0.26 41.84 41.35 41.24 40.23 6.20 49.85
CO-46 N-43 N-30 24.41 0.6 X 0.6 0.02 15.39 15.23 14.79 14.58 21.30 119.83
CO-47 N-14 N-15 28.86 0.6 X 0.6 0.00 37.08 36.08 36.48 35.48 4.70 28.93
CO-48 N-345 N-138 48.60 0.6 X 0.6 0.26 41.34 41.28 40.74 40.15 6.80 83.02
CO-49 N-44 N-18 27.70 0.9 X 0.75 0.29 3.03 3.09 2.04 1.99 66.70 500.00
CO-50 N-68 N-6 48.23 0.75 x 0.75 0.11 13.34 11.30 12.43 10.50 60.00 25.00
CO-51 N-45 N-30 29.63 0.6 X 0.6 0.02 15.34 15.23 14.74 14.58 45.20 189.45
CO-52 N-21 O-8 30.80 1.2 X 1.2 0.00 23.94 23.76 22.74 22.56 64.90 171.08
CO-53 N-47 N-24 31.31 0.6 X 0.6 0.00 15.36 15.23 14.76 14.63 51.20 248.63
CO-54 N-48 N-39 31.53 0.6 X 0.6 0.08 29.60 28.88 29.00 28.13 14.80 36.31
CO-55 N-49 N-38 31.79 0.6 X 0.6 0.00 29.60 28.88 29.00 28.28 21.30 44.33
CO-56 N-24 N-30 16.87 0.6 X 0.6 0.02 15.23 15.23 14.63 14.58 79.50 373.96
CO-57 N-50 N-34 17.79 0.75 x 0.75 0.16 3.67 3.92 2.92 2.86 67.50 332.13
CO-58 N-346 N-122 27.89 0.6 X 0.6 0.38 23.43 23.56 22.59 22.43 24.00 169.44
CO-59 N-51 N-33 34.77 0.9 X 0.9 0.00 4.44 3.80 3.54 2.90 33.20 54.43
CO-60 N-5 N-346 27.71 0.6 X 0.6 0.15 23.30 23.43 22.65 22.59 35.40 500.00
CO-61 N-32 N-52 49.96 0.75 x 0.75 0.09 8.25 6.86 7.47 5.96 38.60 33.05
CO-62 N-347 N-5 17.72 0.6 X 0.6 0.03 23.34 23.30 22.74 22.65 21.90 208.06
CO-63 N-53 N-31 34.60 0.6 X 0.6 0.07 8.92 8.26 8.32 7.51 33.80 42.73
CO-64 N-348 N-347 48.58 0.6 X 0.6 0.00 23.85 23.34 23.25 22.74 16.90 94.89
CO-65 N-3 N-23 35.96 0.6 X 0.6 0.09 26.52 26.49 25.92 25.70 2.00 164.06
CO-66 N-27 N-55 36.83 0.6 X 0.6 0.00 36.76 35.81 36.16 35.21 29.10 38.77
P a g e |139 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-67 N-349 N-348 50.54 0.6 X 0.6 0.00 24.77 23.85 24.17 23.25 11.00 54.73
CO-68 N-56 O-12 39.01 2 X 1.5 -0.02 1.50 1.40 0.05 -0.10 49.60 260.05
CO-69 N-325 N-349 43.82 0.6 X 0.6 0.00 25.58 24.77 24.98 24.17 11.00 54.13
CO-70 N-1 N-10 28.01 0.9 X 0.75 0.07 23.48 23.34 22.73 22.44 69.30 99.17
CO-71 N-389 N-50 11.19 0.6 X 0.6 0.08 3.82 3.67 3.22 2.92 46.00 36.81
CO-72 N-35 O-2 41.07 1.05 X 1.05 0.00 25.63 25.50 24.58 24.45 61.10 318.69
CO-73 N-52 N-161 10.97 0.9 X 0.9 0.15 6.86 6.84 5.96 5.64 27.50 34.12
CO-74 N-57 N-32 42.56 0.6 X 0.6 0.09 9.09 8.25 8.49 7.47 38.40 41.88
CO-75 N-161 O-15 27.69 1.2 X 1.2 0.00 6.84 6.55 5.64 5.35 50.90 95.00
CO-76 N-16 N-58 43.90 0.6 X 0.6 0.02 36.10 34.43 35.46 33.83 21.30 26.89
CO-77 N-59 N-7 44.83 0.9 X 0.75 0.33 2.99 3.09 2.00 1.91 67.90 500.00
CO-78 N-60 N-11 47.42 0.6 X 0.6 0.04 26.83 26.81 26.23 26.13 24.20 500.00
CO-79 N-62 N-61 50.00 0.9 X 0.75 1.04 26.99 27.34 25.42 25.32 78.20 500.00
CO-80 N-11 N-63 47.27 0.6 X 0.6 0.09 26.81 26.55 26.13 25.85 23.40 168.45
CO-81 N-61 N-64 50.00 0.9 X 0.75 1.27 27.34 27.24 25.32 25.22 78.40 500.00
CO-82 N-65 N-59 50.00 0.9 X 0.75 0.12 2.85 2.99 2.10 2.00 66.50 500.00
CO-83 N-66 N-67 50.00 0.6 X 0.6 0.03 18.18 17.09 17.58 16.43 68.90 43.47
CO-84 N-70 N-69 50.00 0.75 x 0.75 0.05 2.99 3.00 2.24 2.14 77.60 500.00
CO-85 N-71 O-10 48.55 1.5 X 1.2 0.00 3.79 3.70 2.59 2.50 70.70 500.00
CO-86 N-73 N-72 50.00 0.6 X 0.6 0.00 14.65 14.25 14.05 13.65 39.90 122.47
CO-87 N-75 N-74 50.00 0.75 x 0.75 0.02 26.49 26.42 25.74 25.62 79.80 442.49
CO-88 N-69 N-44 50.00 0.9 X 0.75 0.17 3.00 3.03 2.14 2.04 65.90 500.00
CO-89 N-76 N-62 50.00 0.9 X 0.75 0.60 26.65 26.99 25.52 25.42 77.60 500.00
CO-90 N-78 N-77 50.00 0.6 X 0.6 0.16 14.89 14.66 14.06 13.96 68.00 500.00
P a g e |140 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-91 N-79 N-22 49.19 0.75 x 0.75 0.15 24.40 24.23 23.65 23.18 57.40 104.63
CO-92 N-67 N-80 50.00 0.6 X 0.6 0.17 17.09 15.31 16.43 14.43 56.50 25.00
CO-93 N-82 N-81 50.00 1.2 X 1.2 0.00 7.68 7.57 6.48 6.37 70.80 474.37
CO-94 N-83 N-84 50.00 1.5 X 1.2 0.20 2.10 1.85 0.66 0.49 79.70 300.19
CO-95 N-86 N-87 49.32 0.6 X 0.6 3.48 30.38 29.12 26.66 24.69 47.40 25.00
CO-96 N-88 N-89 50.00 0.6 X 0.6 0.00 33.15 32.44 32.55 31.84 33.40 70.54
CO-97 N-74 N-76 50.00 0.9 X 0.75 0.21 26.42 26.65 25.62 25.52 76.80 500.00
CO-98 N-4 N-90 50.24 0.6 X 0.6 0.00 33.47 32.77 32.87 32.17 17.40 71.89
CO-99 N-92 N-91 50.00 0.6 X 0.6 0.00 5.23 4.86 4.63 4.26 62.00 134.75
CO-100 N-93 N-94 50.00 0.6 X 0.6 0.02 26.81 24.89 26.21 24.25 19.90 25.52
CO-101 N-95 N-83 50.00 1.2 X 1.2 0.12 2.15 2.10 0.95 0.66 79.80 171.23
CO-102 N-97 N-96 50.00 0.9 X 0.9 0.02 5.43 5.08 4.48 4.18 50.00 163.32
CO-103 N-98 N-99 50.00 0.6 X 0.6 0.53 27.08 25.48 26.15 24.15 21.10 25.00
CO-104 N-100 N-101 50.00 0.6 X 0.6 0.00 26.33 25.97 25.73 25.37 34.20 139.56
CO-105 N-6 N-102 51.74 0.75 x 0.75 0.03 11.30 9.18 10.50 8.43 60.30 25.00
CO-106 N-103 N-104 50.00 0.6 X 0.6 0.00 30.84 29.51 30.24 28.91 29.10 37.75
CO-107 N-106 N-105 49.89 1.05 X 1.05 1.36 27.50 27.17 24.97 24.87 58.80 500.00
CO-108 N-107 N-108 50.00 0.6 X 0.6 0.00 29.24 28.40 28.64 27.80 37.80 59.30
CO-109 N-109 N-110 50.00 0.6 X 0.6 0.00 26.63 26.30 26.03 25.70 21.80 150.29
CO-110 N-111 N-107 50.00 0.6 X 0.6 0.00 30.96 29.24 30.36 28.64 28.20 28.99
CO-111 N-104 N-112 50.00 0.6 X 0.6 0.00 29.51 28.52 28.91 27.92 39.50 50.52
CO-112 N-113 N-82 50.00 1.2 X 1.2 0.00 7.84 7.68 6.64 6.48 53.00 312.03
CO-113 N-81 N-114 50.00 1.2 X 1.2 0.03 7.57 7.54 6.37 6.27 73.40 500.00
CO-114 N-116 N-115 50.00 0.6 X 0.6 0.45 27.41 24.74 26.02 24.02 14.30 25.00
P a g e |141 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-115 N-64 N-117 50.00 0.9 X 0.75 1.13 27.24 26.86 25.22 25.12 79.30 500.00
CO-116 N-118 N-21 50.00 0.75 x 0.75 0.23 23.99 23.94 23.24 22.74 29.70 99.42
CO-117 N-17 N-343 33.46 1.2 X 1.2 0.11 23.43 23.56 22.22 22.15 65.10 500.00
CO-118 N-120 N-119 50.00 0.6 X 0.6 0.71 27.58 25.28 26.12 24.12 14.60 25.00
CO-119 N-121 N-22 50.00 0.9 X 0.75 0.17 24.27 24.23 23.48 23.18 54.00 166.31
CO-120 N-110 N-123 50.00 0.6 X 0.6 0.00 26.30 25.82 25.70 25.22 27.70 103.45
CO-121 N-101 N-124 50.00 0.6 X 0.6 0.00 25.97 25.68 25.37 25.08 39.20 169.90
CO-122 N-126 N-125 50.00 0.9 X 0.9 0.07 8.23 8.13 7.33 7.08 52.00 202.52
CO-123 N-125 N-127 50.00 1.05 X 1.05 0.00 8.13 8.04 7.08 6.98 60.90 500.00
CO-124 N-129 N-128 50.00 0.6 X 0.6 1.77 41.85 40.93 40.02 38.02 5.50 25.00
CO-125 N-130 N-126 50.00 0.75 x 0.75 0.08 8.37 8.23 7.62 7.33 52.20 170.41
CO-126 N-99 N-343 50.00 0.6 X 0.6 0.77 25.48 23.56 24.15 22.15 21.80 25.00
CO-127 N-131 N-79 50.00 0.75 x 0.75 0.00 24.65 24.40 23.90 23.65 72.50 196.47
CO-128 N-133 N-132 50.00 0.6 X 0.6 1.25 41.27 40.67 40.12 38.12 5.30 25.00
CO-129 N-102 N-134 50.00 0.75 x 0.75 0.00 9.18 7.27 8.43 6.52 63.30 26.18
CO-130 N-84 N-135 50.00 1.5 X 1.2 0.23 1.85 1.78 0.49 0.28 79.60 236.47
CO-131 N-136 N-121 50.00 0.75 x 0.75 0.02 24.35 24.27 23.60 23.48 80.00 404.78
CO-132 N-117 N-137 50.00 0.9 X 0.9 0.74 26.86 26.57 25.12 25.02 66.80 500.00
CO-133 N-139 N-118 50.00 0.6 X 0.6 0.08 24.32 23.99 23.72 23.24 46.90 105.34
CO-134 N-119 N-140 50.00 0.6 X 0.6 0.28 25.28 22.72 24.12 22.12 15.80 25.00
CO-135 N-115 N-141 50.00 0.6 X 0.6 0.06 24.74 22.62 24.02 22.02 15.30 25.00
CO-136 N-90 N-111 50.00 0.6 X 0.6 0.00 32.77 30.96 32.17 30.36 26.80 27.62
CO-137 N-144 N-143 50.00 0.6 X 0.6 0.00 32.88 31.04 32.28 30.44 18.60 27.12
CO-138 N-2 N-145 50.00 0.6 X 0.6 0.00 24.99 24.64 24.39 24.04 70.60 143.59
P a g e |142 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-139 N-8 N-146 50.00 1.05 X 1.05 0.11 3.15 2.85 1.90 1.77 80.00 371.98
CO-140 N-147 N-97 50.00 0.9 X 0.9 0.02 5.48 5.43 4.58 4.48 76.10 500.00
CO-141 N-80 N-68 50.00 0.6 X 0.6 0.30 15.31 13.34 14.43 12.43 56.40 25.00
CO-142 N-149 N-148 50.00 0.6 X 0.6 0.00 25.01 24.66 24.41 24.06 45.20 145.12
CO-143 N-150 N-151 50.00 0.6 X 0.6 0.03 19.74 19.00 19.09 18.40 7.50 72.32
CO-144 N-152 N-153 50.00 0.6 X 0.6 0.03 19.74 19.01 19.09 18.41 7.50 73.89
CO-145 N-89 N-103 50.00 0.6 X 0.6 0.00 32.44 30.84 31.84 30.24 26.20 31.15
CO-146 N-154 N-155 50.00 0.6 X 0.6 1.66 36.67 34.16 34.15 32.15 14.30 25.00
CO-147 N-156 N-92 50.00 0.6 X 0.6 0.00 5.48 5.23 4.88 4.63 67.00 201.96
CO-148 N-153 N-157 50.00 0.6 X 0.6 0.00 19.01 18.09 18.41 17.49 9.30 54.08
CO-149 N-158 N-159 50.67 0.6 X 0.6 1.60 36.67 34.17 34.23 32.21 11.80 25.00
CO-150 N-151 N-160 50.00 0.6 X 0.6 0.00 19.00 18.06 18.40 17.46 9.30 53.36
CO-151 N-96 N-51 50.00 0.9 X 0.9 0.00 5.08 4.44 4.18 3.54 38.00 78.21
CO-152 N-114 N-161 50.00 1.2 X 1.2 0.03 7.54 6.84 6.27 5.64 37.70 79.29
CO-153 N-91 N-162 50.00 0.6 X 0.6 0.00 4.86 4.40 4.26 3.80 61.40 108.70
CO-154 N-163 N-120 50.00 0.6 X 0.6 0.91 29.69 27.58 28.12 26.12 13.40 25.00
CO-155 N-159 N-164 50.02 0.6 X 0.6 1.14 34.17 31.72 32.21 30.21 13.40 25.00
CO-156 N-155 N-165 50.00 0.6 X 0.6 1.15 34.16 31.66 32.15 30.15 16.20 25.00
CO-157 N-166 N-2 50.00 0.6 X 0.6 0.00 25.33 24.99 24.73 24.39 58.30 143.92
CO-158 N-167 N-149 50.00 0.6 X 0.6 0.00 25.35 25.01 24.75 24.41 40.40 144.60
CO-159 N-170 N-169 50.00 0.6 X 0.6 0.00 31.45 30.53 30.85 29.93 19.40 54.23
CO-160 N-171 N-172 50.00 0.6 X 0.6 0.00 27.59 26.78 26.99 26.18 49.80 61.74
CO-161 N-173 N-174 50.00 0.6 X 0.6 0.00 27.61 26.79 27.01 26.19 51.50 61.62
CO-162 N-175 N-116 50.00 0.6 X 0.6 1.05 29.93 27.41 28.02 26.02 13.10 25.00
P a g e |143 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-163 N-148 N-139 50.00 0.6 X 0.6 0.00 24.66 24.32 24.06 23.72 49.30 144.39
CO-164 N-176 N-177 50.00 0.6 X 0.6 0.00 25.17 24.54 24.57 23.94 65.20 79.63
CO-165 N-123 N-167 50.00 0.6 X 0.6 0.00 25.82 25.35 25.22 24.75 32.20 108.37
CO-166 N-178 N-131 50.00 0.6 X 0.6 0.03 25.18 24.65 24.58 24.00 76.10 85.99
CO-167 N-180 N-179 50.00 0.6 X 0.6 0.00 30.69 28.84 30.09 28.24 32.90 26.95
CO-168 N-182 N-181 50.00 1.05 X 1.05 0.75 26.67 26.37 24.77 24.67 61.20 500.00
CO-169 N-183 N-75 50.00 0.6 X 0.6 0.08 27.40 26.49 26.80 25.74 46.10 47.00
CO-170 N-185 N-184 69.53 0.75 x 0.75 3.80 27.28 27.15 24.06 21.28 37.20 25.00
CO-171 N-145 N-136 50.00 0.6 X 0.6 0.08 24.64 24.35 24.04 23.60 76.20 114.50
CO-172 N-112 N-173 50.00 0.6 X 0.6 0.00 28.52 27.61 27.92 27.01 41.90 54.43
CO-173 N-124 N-166 50.00 0.6 X 0.6 0.00 25.68 25.33 25.08 24.73 48.20 144.30
CO-174 N-134 N-186 50.00 0.75 x 0.75 0.08 7.27 5.90 6.52 5.00 69.50 32.87
CO-175 N-187 N-48 50.00 0.6 X 0.6 0.00 30.52 29.60 29.92 29.00 14.10 54.03
CO-176 N-188 O-9 50.00 0.75 x 0.75 0.07 4.11 4.05 3.36 3.16 80.00 241.65
CO-177 N-189 N-188 50.00 0.75 x 0.75 0.00 4.66 4.11 3.91 3.36 53.80 91.58
CO-178 N-108 N-171 50.00 0.6 X 0.6 0.00 28.40 27.59 27.80 26.99 46.70 61.67
CO-179 N-190 N-191 50.00 0.6 X 0.6 0.00 32.75 31.69 32.15 31.09 35.30 46.99
CO-180 N-143 N-192 50.00 0.6 X 0.6 0.00 31.04 29.18 30.44 28.58 19.90 26.95
CO-181 N-193 N-53 50.00 0.6 X 0.6 0.00 9.89 8.92 9.29 8.32 34.40 51.56
CO-182 N-184 O-5 43.13 0.75 x 0.75 5.95 27.15 27.07 21.28 19.55 59.40 25.00
CO-183 N-197 N-196 50.00 0.6 X 0.6 2.54 37.40 34.92 34.02 32.02 8.90 25.00
CO-184 N-199 N-198 50.00 0.6 X 0.6 0.00 29.16 27.63 28.56 27.03 72.30 32.84
CO-185 N-200 N-57 50.00 0.6 X 0.6 0.00 10.06 9.09 9.46 8.49 40.50 51.56
CO-186 N-202 N-201 50.00 0.6 X 0.6 0.00 5.95 5.80 5.35 5.20 53.90 320.14
P a g e |144 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-187 N-203 N-95 50.00 1.05 X 1.05 0.07 2.35 2.15 1.30 0.95 63.10 142.86
CO-188 N-205 N-204 50.00 0.6 X 0.6 0.00 6.20 5.95 5.60 5.35 20.70 198.79
CO-189 N-206 N-202 50.00 0.6 X 0.6 0.00 6.21 5.95 5.61 5.35 44.90 193.31
CO-190 N-208 N-207 52.39 0.9 X 0.75 1.25 26.99 27.47 25.28 25.18 71.80 500.00
CO-191 N-210 N-209 50.00 0.6 X 0.6 0.00 20.02 18.76 19.42 18.16 21.70 39.73
CO-192 N-179 N-211 50.00 0.6 X 0.6 0.00 28.84 27.14 28.24 26.54 35.40 29.37
CO-193 N-160 N-212 50.00 0.6 X 0.6 0.00 18.06 17.13 17.46 16.53 11.30 53.71
CO-194 N-213 N-113 50.00 1.2 X 1.2 0.00 7.94 7.84 6.74 6.64 61.30 500.00
CO-195 N-41 N-214 50.00 0.6 X 0.6 0.02 23.68 21.66 23.05 21.05 33.20 25.00
CO-196 N-216 N-215 50.00 0.6 X 0.6 0.00 14.87 14.76 14.27 14.16 61.30 470.86
CO-197 N-217 N-218 50.00 0.6 X 0.6 0.01 21.97 19.95 21.35 19.35 46.60 25.00
CO-198 N-219 N-216 50.00 0.6 X 0.6 0.00 14.98 14.87 14.38 14.27 57.50 451.38
CO-199 N-393 N-220 36.01 0.6 X 0.6 0.00 3.80 3.50 3.20 2.90 6.30 120.20
CO-200 N-221 N-389 11.88 0.6 X 0.6 0.00 3.94 3.82 3.34 3.22 68.20 103.16
CO-201 N-222 N-144 50.00 0.6 X 0.6 0.00 34.62 32.88 34.02 32.28 12.60 28.72
CO-202 N-224 N-223 50.00 0.6 X 0.6 0.00 15.63 15.24 15.03 14.64 33.00 129.65
CO-203 N-225 N-47 50.00 0.6 X 0.6 0.00 16.28 15.36 15.68 14.76 28.40 53.93
CO-204 N-226 N-163 50.00 0.6 X 0.6 1.21 32.18 29.69 30.12 28.12 12.10 25.00
CO-205 N-227 N-228 50.00 0.6 X 0.6 0.00 19.65 17.93 19.05 17.33 46.30 29.10
CO-206 N-142 N-229 49.97 0.6 X 0.6 1.07 41.35 40.45 40.23 38.23 7.10 25.00
CO-207 N-231 N-230 50.00 0.6 X 0.6 0.18 19.87 19.49 18.97 18.83 12.00 367.03
CO-208 N-204 N-232 50.00 0.6 X 0.6 0.07 5.95 5.79 5.35 5.04 26.80 163.30
CO-209 N-234 N-233 50.00 0.6 X 0.6 0.00 15.63 15.24 15.03 14.64 33.00 129.65
CO-210 N-235 N-189 50.00 0.75 x 0.75 0.00 4.88 4.66 4.13 3.91 75.20 224.21
P a g e |145 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-211 N-236 N-152 50.00 0.6 X 0.6 0.03 20.04 19.74 19.44 19.09 5.20 142.31
CO-212 N-237 N-43 50.00 0.6 X 0.6 0.00 16.23 15.39 15.63 14.79 15.30 59.54
CO-213 N-238 N-239 50.00 0.6 X 0.6 0.08 5.93 5.15 5.33 4.40 66.40 53.36
CO-214 N-240 N-98 50.00 0.6 X 0.6 0.37 29.16 27.08 28.15 26.15 19.50 25.00
CO-215 N-242 N-241 50.00 0.6 X 0.6 0.00 17.56 17.17 16.96 16.57 23.70 129.61
CO-216 N-243 N-242 50.00 0.6 X 0.6 0.00 17.94 17.56 17.34 16.96 21.40 129.61
CO-217 N-244 N-245 50.00 0.6 X 0.6 1.93 40.45 38.91 38.15 36.15 10.20 25.00
CO-218 N-246 N-225 50.00 0.6 X 0.6 0.00 17.54 16.28 16.94 15.68 24.60 39.73
CO-219 N-220 N-247 50.00 0.6 X 0.6 0.00 3.50 3.24 2.90 2.64 17.50 187.00
CO-220 N-249 N-248 50.00 0.6 X 0.6 0.00 17.56 17.17 16.96 16.57 23.70 129.61
CO-221 N-172 N-250 50.00 0.6 X 0.6 0.00 26.78 25.97 26.18 25.37 52.80 61.68
CO-222 N-252 N-251 50.00 0.6 X 0.6 2.50 39.27 37.16 36.12 34.12 7.60 25.00
CO-223 N-253 N-197 50.00 0.6 X 0.6 2.80 39.44 37.40 36.02 34.02 7.30 25.00
CO-224 N-254 N-187 50.00 0.6 X 0.6 0.00 31.45 30.52 30.85 29.92 12.20 53.83
CO-225 N-256 N-255 50.00 0.6 X 0.6 0.00 17.50 16.24 16.90 15.64 24.00 39.73
CO-226 N-218 N-66 50.00 0.6 X 0.6 0.00 19.95 18.18 19.35 17.58 49.50 28.20
CO-227 N-257 N-178 50.00 0.6 X 0.6 0.00 25.98 25.18 25.38 24.58 65.80 62.38
CO-228 N-258 N-71 50.00 1.2 X 1.2 0.05 4.85 3.79 3.54 2.59 38.00 52.68
CO-229 N-137 N-259 50.00 0.9 X 0.9 0.59 26.57 26.35 25.02 24.92 67.50 500.00
CO-230 N-260 N-237 50.00 0.6 X 0.6 0.00 17.16 16.23 16.56 15.63 13.20 53.71
CO-231 N-207 N-261 52.40 0.9 X 0.9 1.54 27.47 27.67 25.18 25.07 69.30 500.00
CO-232 N-263 N-262 50.00 0.6 X 0.6 0.00 12.16 11.03 11.56 10.43 30.70 44.39
CO-233 N-194 N-185 82.94 0.6 X 0.6 1.40 28.15 27.28 27.37 24.06 44.90 25.00
CO-234 N-23 N-264 50.17 0.6 X 0.6 0.27 26.49 26.39 25.69 25.45 2.10 209.03
P a g e |146 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-235 N-265 N-93 50.00 0.6 X 0.6 0.21 29.23 26.81 28.21 26.21 17.50 25.00
CO-236 N-251 N-266 50.00 0.6 X 0.6 2.20 37.16 34.67 34.12 32.12 9.30 25.00
CO-237 N-267 N-254 50.00 0.6 X 0.6 0.00 32.38 31.45 31.78 30.85 4.60 53.92
CO-238 N-186 N-268 50.00 0.9 X 0.9 0.08 5.90 5.13 5.00 4.08 64.30 54.43
CO-239 N-270 N-269 50.00 0.6 X 0.6 0.00 21.32 20.06 20.72 19.46 21.00 39.73
CO-240 N-140 N-270 50.00 0.6 X 0.6 0.00 22.72 21.32 22.12 20.72 18.90 35.63
CO-241 N-135 N-271 50.00 1.5 X 1.5 0.00 1.78 1.65 0.28 0.15 77.00 384.62
CO-242 N-273 N-272 50.00 0.6 X 0.6 0.00 18.71 18.33 18.11 17.73 17.00 129.61
CO-243 N-250 N-176 50.00 0.6 X 0.6 0.00 25.97 25.17 25.37 24.57 56.50 62.52
CO-244 N-157 N-260 50.00 0.6 X 0.6 0.00 18.09 17.16 17.49 16.56 11.30 53.71
CO-245 N-239 N-235 50.00 0.75 x 0.75 0.00 5.15 4.88 4.40 4.13 69.40 188.86
CO-246 N-275 N-274 50.00 0.6 X 0.6 0.00 11.94 10.86 11.34 10.26 31.10 46.40
CO-247 N-276 N-208 50.01 0.75 x 0.75 0.58 26.34 26.99 25.38 25.28 79.60 500.00
CO-248 N-277 N-175 50.00 0.6 X 0.6 1.56 32.43 29.93 30.02 28.02 11.80 25.00
CO-249 N-181 N-278 50.00 1.05 X 1.05 0.66 26.37 26.30 24.67 24.57 67.30 496.07
CO-250 N-279 N-210 50.00 0.6 X 0.6 0.00 21.28 20.02 20.68 19.42 20.40 39.73
CO-251 N-196 N-277 50.00 0.6 X 0.6 2.05 34.92 32.43 32.02 30.02 10.40 25.00
CO-252 N-280 N-246 50.00 0.6 X 0.6 0.00 18.80 17.54 18.20 16.94 23.30 39.73
CO-253 N-72 N-281 50.00 0.6 X 0.6 0.00 14.25 13.24 13.65 12.64 29.80 49.76
CO-254 N-223 N-282 50.00 0.6 X 0.6 0.00 15.24 14.98 14.64 14.38 39.80 189.27
CO-255 N-241 N-283 50.00 0.6 X 0.6 0.00 17.17 16.78 16.57 16.18 25.70 129.61
CO-256 N-284 N-276 52.70 0.75 x 0.75 0.10 26.24 26.34 25.49 25.38 69.70 500.00
CO-257 N-255 N-45 50.00 0.6 X 0.6 0.00 16.24 15.34 15.64 14.74 28.10 55.44
CO-258 N-245 N-154 50.00 0.6 X 0.6 2.04 38.91 36.67 36.15 34.15 12.30 25.00
P a g e |147 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-259 N-127 N-213 50.00 1.05 X 1.05 0.08 8.04 7.94 6.98 6.74 51.10 203.70
CO-260 N-146 N-203 50.00 1.05 X 1.05 0.02 2.85 2.35 1.77 1.30 49.80 107.07
CO-261 N-229 N-285 50.00 0.6 X 0.6 1.85 40.45 38.91 38.23 36.23 8.90 25.00
CO-262 N-262 N-200 50.00 0.6 X 0.6 0.00 11.03 10.06 10.43 9.46 39.60 51.54
CO-263 N-286 N-234 50.00 0.6 X 0.6 0.00 16.01 15.63 15.41 15.03 31.20 129.61
CO-264 N-209 N-256 50.00 0.6 X 0.6 0.00 18.76 17.50 18.16 16.90 22.80 39.73
CO-265 N-287 N-263 50.00 0.6 X 0.6 0.00 13.46 12.16 12.86 11.56 28.20 38.31
CO-266 N-288 N-286 50.00 0.6 X 0.6 0.00 16.40 16.01 15.80 15.41 29.40 129.61
CO-267 N-192 N-183 50.00 0.6 X 0.6 0.00 29.18 27.40 28.58 26.80 37.10 28.04
CO-268 N-214 N-227 50.00 0.6 X 0.6 0.01 21.66 19.65 21.05 19.05 34.10 25.00
CO-269 N-128 N-253 50.00 0.6 X 0.6 2.57 40.93 39.44 38.02 36.02 5.50 25.00
CO-270 N-211 N-284 50.00 0.6 X 0.6 0.08 27.14 26.24 26.54 25.49 44.00 47.83
CO-271 N-282 N-289 50.00 0.6 X 0.6 0.00 14.98 14.87 14.38 14.27 57.50 451.38
CO-272 N-212 N-290 50.00 0.6 X 0.6 0.00 17.13 16.20 16.53 15.60 13.20 53.71
CO-273 N-274 N-193 50.00 0.6 X 0.6 0.00 10.86 9.89 10.26 9.29 33.40 51.56
CO-274 N-105 N-182 50.05 1.05 X 1.05 1.05 27.17 26.67 24.87 24.77 59.80 500.00
CO-275 N-77 N-287 50.00 0.6 X 0.6 0.05 14.66 13.46 13.96 12.86 28.90 45.42
CO-276 N-271 N-56 50.00 2 X 1.5 -0.02 1.65 1.50 0.15 0.05 63.00 500.00
CO-277 N-40 N-291 49.28 0.6 X 0.6 0.03 27.89 26.01 27.29 25.35 27.60 25.48
CO-278 N-215 N-73 50.00 0.6 X 0.6 0.00 14.76 14.65 14.16 14.05 63.80 470.87
CO-279 N-55 N-292 50.00 0.6 X 0.6 0.00 35.81 34.35 35.21 33.75 30.10 34.08
CO-280 N-261 N-106 51.94 0.9 X 0.9 1.66 27.67 27.50 25.07 24.97 79.60 500.00
CO-281 N-326 N-199 50.00 0.6 X 0.6 0.00 29.92 29.16 29.32 28.56 49.50 65.26
CO-282 N-141 N-279 50.00 0.6 X 0.6 0.00 22.62 21.28 22.02 20.68 18.60 37.25
P a g e |148 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-283 N-293 N-147 50.00 0.75 x 0.75 0.08 5.64 5.48 4.89 4.58 46.60 164.33
CO-284 N-165 N-240 50.00 0.6 X 0.6 0.66 31.66 29.16 30.15 28.15 17.80 25.00
CO-285 N-132 N-252 50.00 0.6 X 0.6 2.25 40.67 39.27 38.12 36.12 5.30 25.00
CO-286 N-294 N-180 50.01 0.6 X 0.6 0.00 32.56 30.69 31.96 30.09 31.60 26.79
CO-287 N-296 N-295 50.00 0.6 X 0.6 0.00 19.10 18.72 18.50 18.12 14.50 129.61
CO-288 N-297 N-217 50.00 0.6 X 0.6 0.03 23.99 21.97 23.35 21.35 44.70 25.00
CO-289 N-87 N-298 52.54 0.6 X 0.6 4.19 29.12 27.74 24.69 22.59 50.90 25.00
CO-290 N-394 N-205 44.77 0.6 X 0.6 0.00 6.77 6.20 6.17 5.60 5.90 77.91
CO-291 N-201 N-299 50.00 0.6 X 0.6 0.00 5.80 5.64 5.20 5.04 53.60 320.14
CO-292 N-162 N-221 50.00 0.6 X 0.6 0.00 4.40 3.94 3.80 3.34 67.40 107.12
CO-293 N-232 N-293 50.00 0.75 x 0.75 0.00 5.79 5.64 5.04 4.89 56.30 320.14
CO-294 N-283 N-288 50.00 0.6 X 0.6 0.00 16.78 16.40 16.18 15.80 27.50 129.61
CO-295 N-291 N-297 50.00 0.6 X 0.6 0.05 26.01 23.99 25.35 23.35 39.60 25.00
CO-296 N-285 N-158 50.00 0.6 X 0.6 1.96 38.91 36.67 36.23 34.23 10.30 25.00
CO-297 N-300 N-150 50.00 0.6 X 0.6 0.03 20.04 19.74 19.44 19.09 5.20 142.31
CO-298 N-302 N-301 50.00 0.6 X 0.6 0.00 16.79 16.40 16.19 15.80 27.50 129.61
CO-299 N-301 N-303 50.00 0.6 X 0.6 0.00 16.40 16.02 15.80 15.42 29.40 129.61
CO-300 N-266 N-226 50.00 0.6 X 0.6 1.70 34.67 32.18 32.12 30.12 10.80 25.00
CO-301 N-174 N-257 50.00 0.6 X 0.6 0.00 26.79 25.98 26.19 25.38 58.70 61.68
CO-302 N-164 N-265 50.00 0.6 X 0.6 0.67 31.72 29.23 30.21 28.21 15.30 25.00
CO-303 N-268 N-304 50.00 1.05 X 1.05 0.07 5.13 4.88 4.08 3.68 64.50 123.27
CO-304 N-290 N-42 50.00 0.6 X 0.6 0.00 16.20 15.37 15.60 14.77 15.40 60.36
CO-305 N-306 N-305 50.00 0.6 X 0.6 0.15 20.05 19.87 19.45 18.97 4.00 104.94
CO-306 N-259 N-168 50.00 0.9 X 0.9 0.54 26.35 26.30 24.92 24.85 78.20 679.54
P a g e |149 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-307 N-281 N-275 50.00 0.6 X 0.6 0.00 13.24 11.94 12.64 11.34 28.20 38.28
CO-308 N-248 N-302 50.00 0.6 X 0.6 0.00 17.17 16.79 16.57 16.19 25.70 129.61
CO-309 N-307 N-231 50.00 0.6 X 0.6 0.15 20.05 19.87 19.45 18.97 4.00 104.94
CO-310 N-138 N-244 50.00 0.6 X 0.6 1.11 41.28 40.45 40.15 38.15 7.80 25.00
CO-311 N-272 N-243 50.00 0.6 X 0.6 0.00 18.33 17.94 17.73 17.34 19.30 129.61
CO-312 N-198 N-308 50.00 0.6 X 0.6 0.00 27.63 25.99 27.03 25.39 70.20 30.42
CO-313 N-395 N-206 43.33 0.6 X 0.6 0.00 6.78 6.21 6.18 5.61 5.80 76.65
CO-314 N-299 N-156 50.00 0.6 X 0.6 0.00 5.64 5.48 5.04 4.88 78.30 314.18
CO-315 N-309 N-273 50.00 0.6 X 0.6 0.00 19.10 18.71 18.50 18.11 14.50 129.61
CO-316 N-295 N-310 50.00 0.6 X 0.6 0.00 18.72 18.33 18.12 17.73 17.00 129.61
CO-317 N-311 N-296 50.00 0.6 X 0.6 0.03 19.49 19.10 18.84 18.50 12.20 149.82
CO-318 N-304 N-258 50.00 1.2 X 1.2 0.05 4.88 4.85 3.68 3.54 80.00 375.82
CO-319 N-269 N-280 50.00 0.6 X 0.6 0.00 20.06 18.80 19.46 18.20 22.30 39.73
CO-320 N-312 N-249 50.00 0.6 X 0.6 0.00 17.94 17.56 17.34 16.96 21.40 129.61
CO-321 N-303 N-224 50.00 0.6 X 0.6 0.00 16.02 15.63 15.42 15.03 31.20 129.61
CO-322 N-233 N-219 50.00 0.6 X 0.6 0.00 15.24 14.98 14.64 14.38 39.80 189.27
CO-323 N-305 N-311 50.00 0.6 X 0.6 0.18 19.87 19.49 18.97 18.84 12.00 367.03
CO-324 N-310 N-312 50.00 0.6 X 0.6 0.00 18.33 17.94 17.73 17.34 19.30 129.61
CO-325 N-313 N-78 50.00 0.6 X 0.6 0.11 14.76 14.89 14.16 14.06 65.30 500.00
CO-326 N-230 N-309 50.00 0.6 X 0.6 0.03 19.49 19.10 18.83 18.50 12.20 149.82
CO-327 N-289 N-313 50.00 0.6 X 0.6 0.00 14.87 14.76 14.27 14.16 61.30 470.87
CO-328 N-314 N-315 50.01 0.6 X 0.6 0.00 15.20 13.36 14.60 12.76 47.20 27.20
CO-329 N-58 N-190 50.39 0.6 X 0.6 0.00 34.43 32.75 33.83 32.15 24.40 30.05
CO-330 N-316 N-170 50.00 0.6 X 0.6 0.00 32.38 31.45 31.78 30.85 5.90 54.15
P a g e |150 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Elevation Elevation
Length Cover Invert Invert Depth Slope
Start Stop Ground Ground
Label (Scaled) Size (Display) (Average) (Start) (Stop) (Normal) / (Calculated)
Node Node (Start) (Stop)
(m) (m) (m) (m) Rise (%) (1/S)
(m) (m)
CO-331 N-292 N-294 50.00 0.6 X 0.6 0.00 34.35 32.56 33.75 31.96 29.90 28.00
CO-332 N-315 N-317 50.19 0.6 X 0.6 0.00 13.36 11.50 12.76 10.90 47.80 26.95
CO-333 N-318 N-86 50.37 0.6 X 0.6 2.43 31.03 30.38 28.68 26.66 42.10 25.00
CO-334 N-46 N-222 50.03 0.6 X 0.6 0.06 36.03 34.62 35.32 34.02 13.70 38.66
CO-335 N-317 N-319 50.32 0.6 X 0.6 0.00 11.50 9.54 10.90 8.93 47.70 25.54
CO-336 N-320 N-238 50.21 0.6 X 0.6 0.00 7.44 5.93 6.84 5.33 54.60 33.38
CO-337 N-169 N-49 50.58 0.6 X 0.6 0.00 30.53 29.60 29.93 29.00 21.00 54.03
CO-338 N-298 N-184 32.86 0.6 X 0.6 4.91 27.74 27.15 22.59 21.28 54.50 25.00
CO-339 N-319 N-320 52.35 0.6 X 0.6 0.00 9.54 7.44 8.93 6.84 48.10 25.00
CO-340 N-321 N-7 65.00 0.6 X 0.6 0.29 3.26 3.09 2.66 1.91 15.80 87.32
CO-341 N-247 N-18 59.36 0.6 X 0.6 0.25 3.24 3.09 2.64 1.99 15.30 91.42
CO-342 N-34 N-95 63.27 0.9 X 0.9 0.23 3.92 2.15 2.86 0.95 39.20 33.08
CO-343 N-392 N-321 81.33 0.6 X 0.6 0.00 3.66 3.26 3.06 2.66 21.20 202.75
CO-344 N-228 N-314 79.87 0.6 X 0.6 0.00 17.93 15.20 17.33 14.60 48.70 29.29
CO-345 N-308 N-26 66.51 0.6 X 0.6 0.16 25.99 24.10 25.39 23.19 79.70 30.22
CO-346 N-322 N-29 75.48 0.6 X 0.6 0.02 27.91 24.97 27.31 24.33 18.10 25.33
CO-347 N-191 N-318 92.23 0.6 X 0.6 0.87 31.69 31.03 31.09 28.68 45.20 38.29
CO-348 N-323 N-25 94.91 0.6 X 0.6 0.38 25.57 23.82 24.22 23.22 15.00 94.66
Area
Land use Plots
Acres Sq. m Assumptions
IC-10 1.97 7975.5
IC-11 2.15 8710.3
IC-12 2.14 8673.8
IC-13 3.25 13134.9
IC-14 17.07 69074.7
IC-15 9.29 37585.1
IC-16 8.07 32648.1
IC-17 4.17 16868.1
IC-18 3.15 12750.6
IC-19 6.30 25489.0
IC-20 4.82 19507.5
IC-21 4.80 19425.8
Sub-Total
(Intermediate 85.80 347228.68
Chemicals)
Specialty 1.Potable water requirement for working 45 lpcd & 15
Chemical lpcd for visitors,
SC-1 1.47 5943.8 2.Processing water 75KL/Acre,
SC-2 1.93 7810.9 3. Effluent @ 45% of Process Water
4.Horticulture demand @ 4 ltr./sqm of 40% of open
SC-3 1.16 4699.0
area
SC-4 1.25 5062.0 5.10ltr Water for HVAC cooling with 20% of BUA
SC-5 2.86 11581.3
SC-6 1.22 4942.2
SC-7 1.19 4802.0
SC-8 4.80 19426.2
SC-9 1.52 6161.9
SC-10 1.01 4090.6
SC-11 0.93 3775.6
SC-12 1.13 4555.7
SC-13 1.11 4498.9
SC-14 1.21 4896.6
SC-15 1.31 5307.0
SC-16 1.41 5710.8
SC-17 1.19 4797.7
SC-18 3.18 12887.3
SC-19 1.25 5070.3
SC-20 1.40 5663.2
SC-21 1.10 4468.8
SC-22 0.63 2543.3
Sub-Total
(Specialty 34.27 138695.01
Chemical)
Area
Land use Plots
Acres Sq. m Assumptions
End Products 1.Potable water requirement for working 45 lpcd & 15
(Paints/ lpcd for visitors,
Adhesives / 2. Processing water 50KL/Acre,
Inks, etc.) 3. Effluent @ 25% of Process Water
EP-1 0.94 3801.7 4.Horticulture demand @ 4 ltr./sqm of 40% of open
EP-2 0.99 4004.3 area
EP-3 0.95 5.10ltr Water for HVAC cooling with 20% of BUA
3857.2
EP-4 0.94 3815.0
EP-5 0.95 3845.8
EP-6 3.11 12589.0
EP-7 3.47 14062.5
EP-8 2.87 11600.0
EP-9 2.41 9754.0
EP-10 2.21 8952.2
EP-11 2.57 10394.5
Sub-Total (End
Products
(Paints/ 21.42 86676.26
Adhesives /
Inks, etc.)
End Products 1.Potable water requirement for working 45 lpcd & 15
(Based on lpcd for visitors,
Polyurethane 2.Processing water 20KL/Acre,
And SAP) 3. Effluent @ 20% of Process Water
EP-12 1.13 4570.7 4.Horticulture demand @ 4 ltr./sqm of 40% of open
EP-13 1.98 8014.5 area
EP-14 1.66 5.10ltr Water for HVAC cooling with 20% of BUA
6724.9
EP-15 3.88 15691.7
EP-16 2.13 8609.9
Sub-Total (End
Products
(Based on 10.78 43611.64
Polyurethane
And SAP))
Common 1.Potable water requirement for working 45 lpcd & 15
Facilities lpcd for visitors,
Truck Terminal 2.Horticulture demand @ 4 ltr./sqm of 50% of open
4.87
and 19711.2 area
Warehouse 3.10ltr Water for HVAC cooling with 10% of BUA
Sub-Total
(Common 4.87 19711.23
Facilities)
UTILITY
Admin & Tech 1.Potable water requirement for working 45 lpcd & 15
Centre 1.37 5543 lpcd for visitors,
Area
Land use Plots
Acres Sq. m Assumptions
2. Horticulture demand @ 4 ltr./sqm of 50% of open
Contract, R&D area
& Lab 1.96 7915 3.10ltr Water for HVAC cooling with 60% of BUA
Water Works 1.19 4805 1.Potable water requirement for working 45 lpcd & 15
ZSS 0.58 2333 lpcd for visitors,
2. Horticulture demand @ 4 ltr./sqm of 30% of open
MRSS 1.59 6424
area
Sub-Total
3.10ltr Water for HVAC cooling with 10% of BUA
(Utility) 6.68 27019.31
CETP
CETP-1 6.96 28149.1
CETP-2 3.61 14624.5
Sub-Total
(CETP) 10.57 42773.65
GREEN AREA 69.11 279685.5 Horticulture demand @ 4 ltr./sqm
ROAD 28.10 113716.92 Road washing @ 2 litres/sq.m. of ROW area
PHARMA PARK
PLOT 28.90 116961
FACT ROAD 15.34 62078.80
V = Velocity in m/s
Manning’s formula:
V = 1/r2/3 S1/2
Where
r = Hydraulic radius in m
S = Slope of hydraulic gradient line
= Manning’s coefficient of roughness
V = velocity in m/s
The above comparison indicates that, HDPE and DI pipes are more suitable than other alternatives for
the pipe diameter range in the Industrial Area. Refer the table below for cost comparison of various
pipe materials for water supply.
From the above table it is clear that, HDPE pipes are cheaper up to a diameter of 300mm and then DI
pipes are cheaper for larger diameter pipes. HDPE pipes have been recommended for distribution
system upto 315 mm dia and above DI Pipes are adopted for the design.
Table 7-27: Pipe materials used for the water supply system
Class of
Component of the System Pipe Material Applicable Code
Pipe
Transmission system Ductile Iron (DI) K9
Ductile Iron (D.I.) pipes as per
Distribution system above
Ductile Iron (DI) K7 IS:8329
300mm
Distribution system upto 300mm HDPE HDPE pipes as per IS: 4984
7.6.3.12. Anchorage
Anchorages are required for one or more of the following reasons:
• To resist the tendency of pipe to pull apart at bends and other points when unbalanced
pressure occurs this exceeds the resistance of their joints to their longitudinal stresses.
• When the resistance of the joints to longitudinal stresses are inadequate and the pipes have
the tendency to pull apart when pipe is laid on steep ground.
These are provided at bends, tees, and crosses to protect the pipe from unbalanced forces.
Detailed Estimate for Pumping Main 500mm dia. DI K-9 from Clear
6 732951.00
water sump to all ELSRs in length - 100m
Construction of 2 numbers of ELSR Capacity of 13LL & 12LL capacity
7 39717300.00
Staging: 15m
8 Proposed Portable water distribution system 57536079.00
Sub Total - I 235674180.00
B GST
9 Provision towards Works Contract GST @ 12% 28280902.00
Sub Total - II 263955082.00
C Other L.S provisions
10 Unforeseen items @ 2% 5279102.00
11 PS & Contingencies- @ 1.50% 3959326.00
12 Quality Control @ 0.75% 1979663.00
13 Price Escalation @ 5% 13197754.00
14 Tender Premium @ 5% and rounding off 13197754.00
Grand Total in Rs. 301568681.00
Grand Total in Lakhs 3015.69
Headloss
Start Length Diameter Velocity
Label Stop Node Material Gradient
Node (m) (mm) (m/s)
(m/km)
P-23 J-19 J-3 12 66.8 HDPE 0.01 0.002
P-24 J-109 J-19 69 350 DI 0.89 2.256
P-25 J-114 J-32 22 143.4 HDPE 0.63 3.406
P-26 J-32 J-33 14 66.8 HDPE 0.04 0.042
P-27 J-32 J-86 15 143.4 HDPE 0.62 3.327
P-28 J-112 J-113 21 98.6 HDPE 0.01 0.001
P-29 J-138 J-112 57 179.4 HDPE 0.78 3.934
P-30 J-112 J-66 46 179.4 HDPE 0.78 3.915
P-31 J-66 J-102 15 143.4 HDPE 0.82 5.501
P-32 J-66 J-67 9 143.4 HDPE 0.41 1.524
P-33 J-126 J-73 26 224.4 HDPE 0.65 2.123
P-34 J-73 J-118 23 179.4 HDPE 0.67 2.921
P-35 J-73 J-74 10 143.4 HDPE 0.54 2.558
P-36 J-126 J-137 63 179.4 HDPE 0.77 3.793
P-37 J-75 J-76 10 66.8 HDPE 0.29 1.978
P-38 J-60 J-61 8 66.8 HDPE 0.19 0.885
P-39 J-135 J-64 41 155.7 PVC 0.37 1.154
P-40 J-93 J-27 100 300 DI 0.73 1.865
P-41 J-64 J-107 19 155.7 PVC 0.36 1.081
P-42 J-64 J-65 8 72.8 PVC 0.06 0.092
P-43 J-27 J-130 30 107 PVC 0.44 2.476
P-44 J-27 J-121 30 224.4 HDPE 1.08 5.494
P-45 J-27 J-28 8 107 PVC 0.5 3.112
P-46 J-83 J-134 36 107 PVC 0.57 3.994
P-47 J-83 J-84 10 107 PVC 0.51 3.262
P-48 J-83 J-131 45 300 DI 0.85 2.504
P-49 J-54 J-97 32 107 PVC 0.45 2.544
P-50 J-54 J-55 14 107 PVC 0.46 2.667
P-51 J-97 J-98 14 66.8 HDPE 0.02 0.014
P-52 J-140 J-54 120 224.4 HDPE 0.79 3.052
P-53 J-97 J-108 20 107 PVC 0.44 2.463
P-54 J-54 J-20 75 194.7 PVC 0.77 3.473
P-55 J-48 J-49 7 72.8 PVC 0.01 0.004
P-56 J-49 J-111 21 107 PVC 0.45 2.598
P-57 J-106 J-91 49 500 DI 0.81 1.247
P-58 J-49 J-91 25 107 PVC 0.46 2.653
P-59 J-58 J-59 8 155.7 PVC 0.29 0.748
P-60 J-58 J-87 24 155.7 PVC 0.32 0.895
P-61 J-87 J-119 23 107 PVC 0.47 2.737
P-62 J-87 J-88 12 107 PVC 0.22 0.668
P-63 J-95 J-127 26 72.8 PVC 0.44 3.892
P-64 J-95 J-96 13 72.8 PVC 0.41 3.365
Headloss
Start Length Diameter Velocity
Label Stop Node Material Gradient
Node (m) (mm) (m/s)
(m/km)
P-65 J-58 J-95 182 450 DI 0.86 1.576
P-66 J-11 J-12 4 72.8 PVC 0.41 3.408
P-67 J-8 J-45 7 107 PVC 0.35 1.622
P-68 J-89 J-90 12 107 PVC 0.42 2.241
P-69 J-8 J-89 108 450 DI 0.77 1.297
P-70 J-13 J-14 4 107 PVC 0.36 1.678
P-71 J-46 J-47 7 107 PVC 0.33 1.472
P-72 J-81 J-101 14 107 PVC 0.3 1.21
P-73 J-124 J-103 25 155.7 PVC 0.57 2.572
P-74 J-103 J-104 17 107 PVC 0.36 1.712
P-75 J-103 J-136 44 155.7 PVC 0.4 1.331
P-76 J-116 J-133 33 107 PVC 0.35 1.623
P-77 J-116 J-117 23 155.7 PVC 0.67 3.472
P-78 J-123 J-30 25 155.7 PVC 0.34 0.972
P-79 J-30 J-70 10 107 PVC 0.34 1.557
P-80 J-30 J-31 5 107 PVC 0.37 1.792
P-81 J-116 J-123 313 350 DI 0.73 1.565
P-82 J-62 J-85 11 107 PVC 0.57 3.994
P-83 J-62 J-63 8 300 DI 0.82 2.364
P-84 J-43 J-44 6 66.8 HDPE 0.25 1.545
P-85 J-43 J-9 131 300 DI 0.76 2.016
P-86 J-79 J-80 12 155.7 PVC 0.33 0.92
P-87 J-91 J-79 45 500 DI 0.78 1.187
P-88 J-79 J-58 120 500 DI 0.75 1.099
P-89 J-77 J-78 10 72.8 PVC 0.41 3.323
P-90 J-95 J-77 86 450 DI 0.83 1.501
P-91 J-77 J-11 82 450 DI 0.82 1.465
P-92 J-131 J-132 31 107 PVC 0.48 2.907
P-93 J-131 J-93 85 300 DI 0.79 2.18
P-94 J-34 J-35 6 72.8 PVC 0.43 3.624
P-95 J-11 J-34 73 450 DI 0.81 1.43
P-96 J-7 J-40 6 72.8 PVC 0.41 3.323
P-97 J-34 J-7 59 450 DI 0.8 1.394
P-98 J-7 J-8 3 450 DI 0.79 1.36
P-99 J-71 J-72 10 107 PVC 0.39 1.956
P-100 J-89 J-71 54 450 DI 0.75 1.224
P-101 J-71 J-13 54 450 DI 0.72 1.158
P-102 J-38 J-39 6 107 PVC 0.33 1.441
P-103 J-13 J-38 51 450 DI 0.7 1.099
P-104 J-38 J-46 57 450 DI 0.69 1.046
P-105 J-56 J-57 8 107 PVC 0.28 1.043
P-106 J-46 J-56 63 450 DI 0.67 0.993
Headloss
Start Length Diameter Velocity
Label Stop Node Material Gradient
Node (m) (mm) (m/s)
(m/km)
P-107 J-56 J-81 76 400 DI 0.82 1.687
P-108 J-82 J-100 14 107 PVC 0.45 2.571
P-109 J-81 J-82 10 400 DI 0.8 1.606
P-110 J-63 J-68 9 107 PVC 0.44 2.41
P-111 J-63 J-43 206 300 DI 0.77 2.078
P-112 J-9 J-10 4 66.8 HDPE 0.17 0.719
P-113 J-9 J-142 146 300 DI 0.75 1.975
P-114 J-115 J-29 33 155.7 PVC 0.69 3.666
P-115 J-20 J-50 15 107 PVC 0.5 3.067
P-116 J-20 J-21 5 194.7 PVC 0.62 2.331
P-117 J-21 J-22 16 155.7 PVC 0.28 0.703
P-118 J-21 J-115 22 155.7 PVC 0.69 3.666
P-119 J-29 J-15 7 155.7 PVC 0.69 3.666
P-120 J-15 J-16 7 155.7 PVC 0.46 1.755
P-121 J-15 J-23 24 107 PVC 0.48 2.892
P-122 J-23 J-24 5 107 PVC 0.48 2.892
P-123 J-5 J-41 37 98.6 HDPE 0.39 2.176
P-124 J-25 J-26 5 98.6 HDPE 0.22 0.749
P-125 J-41 J-42 6 66.8 HDPE 0.37 3.143
P-126 J-41 J-25 27 98.6 HDPE 0.22 0.749
P-127 J-121 J-122 25 224.4 HDPE 0.9 3.937
P-128 J-121 J-135 237 155.7 PVC 0.37 1.154
P-129 J-60 J-36 12 179.4 HDPE 0.56 2.136
P-130 J-120 J-60 145 179.4 HDPE 0.59 2.323
P-131 J-114 J-138 283 300 DI 0.92 2.888
P-132 J-138 J-126 237 300 DI 0.64 1.469
P-133 J-91 J-92 13 72.8 PVC 0.01 0.007
P-134 J-106 J-105 17 500 DI 1.08 2.166
P-135 J-128 J-106 129 600 DI 1.31 2.491
P-136 J-82 J-124 226 400 DI 0.77 1.489
P-137 J-124 J-116 212 400 DI 0.68 1.194
P-138 J-36 J-75 93 143.4 HDPE 0.4 1.436
P-139 J-75 J-5 60 143.4 HDPE 0.33 1.041
P-140 J-105 J-140 253 500 DI 0.73 1.037
P-1 J-141 J-109 2,798 350 DI 1.16 3.74
P-2 J-19 J-145 31 350 DI 0.89 2.255
7.7.1. Population
The land use of the Master Plan, the proposed built-up area (BUA), density of development dictates
the estimation of population in the proposed development. This is further segregated into working
population, resident population and floating population based on which the demand assessment for
all infrastructure requirements has been prepared. The demand assessment of main power receiving,
Water supply system, sewerage system etc. is arrived on the basis of the estimated population and
land use.
The potable water demand for Petrochemical Park area is estimated based on proposed land use,
built-up area, the population proposed and process water demand.
The non-potable demand comprising of horticulture demand and commercial cooling can be met from
the recycled water. The water demand for the Non-Processing Area has been calculated separately
due to variation in standards and requirements. Below figures shows the water balance sheet of
Petrochemical Park area for total area in single phase. The horticulture demand and cooling demand
will be fed through recycled water from proposed Common Effluent Treatment Plant (CETP) for
Petrochemical Park area. For proposed project, the portion of horticulture demand and cooling
demand will be fed through recycled water from proposed CETP and additional quantity of water shall
draw from potable water.
Distribution and transmission system have been efficiently managed, making unaccounted for Water
(UFW) and other water losses included.
Distribution and transmission system have been efficiently managed, making unaccounted for Water
(UFW) and other water losses included. As the development will happen in various phases, the phase
wise process and domestic water demand requirements are shown in below table.
Table 7-30: Recycle Water Output
Headloss
Start Length Diameter Velocity
Label Stop Node Material Gradient
Node (m) (mm) (m/s)
(m/km)
Headloss
Start Length Diameter Velocity Gradient
Label Node Stop Node (m) Material (mm) (m/s) (m/km)
P-1 J-134 R-3 13 DI 250 0.65 1.893
P-2 J-104 J-134 33 DI 250 0.63 1.779
P-3 J-102 J-47 165 DI 250 0.67 1.989
P-4 J-98 J-102 50 DI 250 0.63 1.791
P-5 J-81 J-98 81 DI 250 0.62 1.725
P-6 J-104 J-112 44 DI 200 0.31 0.638
P-7 J-112 J-148 243 DI 200 0.28 0.505
P a g e |170 Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Headloss
Start Length Diameter Velocity
Label Stop Node Material Gradient
Node (m) (mm) (m/s)
(m/km)
P-8 J-82 J-51 68 DI 200 0.63 2.277
P-9 J-81 J-82 15 DI 200 0.79 3.533
P-10 J-51 J-135 63 DI 200 0.61 2.178
P-11 J-135 J-33 165 DI 200 0.56 1.864
P-12 J-33 J-28 45 DI 200 0.54 1.719
P-13 J-28 J-56 128 DI 200 0.51 1.547
P-14 J-56 J-17 78 DI 200 0.5 1.506
P-15 J-17 J-92 72 DI 200 0.49 1.465
P-16 J-92 J-70 57 DI 200 0.49 1.423
P-17 J-70 J-83 64 DI 200 0.48 1.384
P-18 J-83 J-122 48 DI 200 0.47 1.335
P-19 J-122 J-58 56 DI 200 0.46 1.278
P-20 J-58 J-39 54 DI 200 0.45 1.226
P-21 J-39 J-13 49 DI 200 0.44 1.179
P-22 J-13 J-79 58 DI 200 0.43 1.136
P-23 J-79 J-85 66 DI 200 0.42 1.094
P-24 J-85 J-35 75 DI 200 0.41 1.059
P-25 J-41 J-104 101 DI 150 1.16 9.955
P-26 J-35 J-11 150 DI 150 0.72 4.152
P-27 J-77 J-118 64 DI 150 0.99 7.388
P-28 J-78 J-41 77 DI 150 1.15 9.804
P-29 J-77 J-78 15 DI 150 0.99 7.388
P-30 J-11 J-53 94 DI 150 0.7 3.932
P-31 J-148 J-125 239 DI 150 0.3 0.799
P-32 J-53 J-109 187 DI 150 0.64 3.367
P-33 J-21 J-81 142 DI 150 0.29 0.777
P-34 J-118 J-119 25 DI 150 0.99 7.388
P-35 J-20 J-21 8 DI 150 0.26 0.608
P-36 J-75 J-20 87 DI 150 0.26 0.609
P-37 J-109 J-22 275 DI 150 0.56 2.613
P-38 J-125 J-147 62 DI 100 0.29 1.215
P-39 J-22 J-113 160 DI 150 0.55 2.466
P-40 J-142 R-2 16 DI 300 0.58 1.227
P-41 J-141 J-142 37 DI 300 0.55 1.117
P-42 J-138 J-141 39 DI 250 0.79 2.714
P-43 J-107 J-75 21 DI 100 0.46 2.896
P-44 J-107 J-15 105 DI 100 0.46 2.895
P-45 J-47 J-138 259 DI 250 0.78 2.613
P-46 J-119 J-30 165 DI 100 2.08 47.289
P-47 J-15 J-16 6 DI 100 0.4 2.224
P-48 J-16 J-9 74 DI 100 0.27 1.112
P-49 J-118 J-144 43 DI 100 0 0
Headloss
Start Length Diameter Velocity
Label Stop Node Material Gradient
Node (m) (mm) (m/s)
(m/km)
P-50 J-30 J-67 156 DI 100 1.91 40.222
P-51 J-113 J-114 24 DI 100 0.08 0.102
P-52 J-125 J-68 28 DI 100 0.38 2.024
P-53 J-119 J-100 26 DI 100 0.14 0.309
P-54 J-9 J-31 61 DI 100 0.19 0.589
P-55 J-102 J-120 45 DI 100 0.16 0.427
P-56 J-148 J-60 56 DI 100 0.44 2.691
P-57 J-113 J-127 73 DI 100 1.05 13.45
P-58 J-127 J-90 156 DI 100 1.05 13.45
P-59 J-68 J-149 68 DI 100 0.25 0.936
P-60 J-60 J-65 49 DI 100 0.29 1.254
P-61 J-67 J-7 14 DI 100 0.17 0.467
P-62 J-109 J-110 23 DI 100 0.15 0.358
P-63 J-104 J-105 19 DI 100 0.08 0.102
P-64 J-142 J-152 6 DI 100 0 0
P-65 J-31 J-32 10 DI 100 0.13 0.282
P-66 J-53 J-94 25 DI 100 0.13 0.265
P-67 J-67 J-24 35 DI 100 1.73 33.767
P-68 J-75 J-76 15 DI 100 0.12 0.224
P-69 J-90 J-96 155 DI 100 1.01 12.394
P-70 J-120 J-137 34 DI 100 0.09 0.138
P-71 J-65 J-87 16 DI 100 0.2 0.592
P-72 J-100 J-140 37 DI 100 0.04 0.03
P-73 J-7 J-8 4 DI 100 0.12 0.241
P-74 J-30 J-5 9 DI 100 0.1 0.16
P-75 J-100 J-101 19 DI 100 0.1 0.167
P-76 J-33 J-34 11 DI 100 0.1 0.16
P-77 J-113 J-126 28 DI 100 0.1 0.158
P-78 J-9 J-10 5 DI 100 0.08 0.113
P-79 J-135 J-43 35 DI 100 0.09 0.139
P-80 J-28 J-63 35 DI 100 0.09 0.139
P-81 J-94 J-106 20 DI 100 0.09 0.137
P-82 J-21 J-62 13 DI 100 0.08 0.116
P-83 J-111 J-112 24 DI 100 0.15 0.358
P-84 J-30 J-45 28 DI 100 0.08 0.107
P-85 J-24 J-25 9 DI 100 0.07 0.079
P-86 J-120 J-121 27 DI 100 0.07 0.1
P-87 J-68 J-69 14 DI 100 0.13 0.276
P-88 J-47 J-72 30 DI 100 0.6 4.7
P-89 J-72 J-73 15 DI 100 0.07 0.085
P-90 J-96 J-97 18 DI 100 0.07 0.084
P-91 J-16 J-50 12 DI 100 0.07 0.079
Headloss
Start Length Diameter Velocity
Label Stop Node Material Gradient
Node (m) (mm) (m/s)
(m/km)
P-92 J-47 J-48 12 DI 100 0.07 0.081
P-93 J-102 J-103 19 DI 100 0.07 0.081
P-94 J-98 J-99 18 DI 100 0.08 0.112
P-95 J-31 J-3 24 DI 100 0.06 0.075
P-96 J-3 J-4 4 DI 100 0.06 0.075
P-97 J-63 J-88 16 DI 100 0.06 0.071
P-98 J-5 J-6 4 DI 100 0.06 0.069
P-99 J-126 J-133 31 DI 100 0.06 0.066
P-100 J-15 J-49 12 DI 100 0.06 0.069
P-101 J-43 J-44 11 DI 100 0.06 0.067
P-102 J-16 J-108 23 DI 100 0.06 0.064
P-103 J-51 J-52 13 DI 100 0.06 0.065
P-104 J-65 J-66 14 DI 100 0.1 0.164
P-105 J-7 J-74 15 DI 100 0.05 0.05
P-106 J-11 J-12 5 DI 100 0.05 0.042
P-107 J-96 J-37 29 DI 100 0.94 10.891
P-108 J-37 J-38 11 DI 100 0.05 0.039
P-109 J-90 J-91 17 DI 100 0.05 0.04
P-110 J-122 J-123 27 DI 100 0.04 0.037
P-111 J-45 J-89 17 DI 100 0.04 0.036
P-112 J-58 J-59 13 DI 100 0.04 0.032
P-113 J-1 J-2 2 DI 100 0.02 0.008
P-114 J-94 J-95 18 DI 100 0.04 0.028
P-115 J-24 J-1 26 DI 100 0.02 0.008
P-116 J-22 J-129 29 DI 100 0.04 0.03
P-117 J-83 J-84 15 DI 100 0.04 0.027
P-118 J-39 J-40 11 DI 100 0.04 0.028
P-119 J-109 J-130 29 DI 100 0.04 0.027
P-120 J-126 J-132 30 DI 100 0.04 0.026
P-121 J-5 J-19 7 DI 100 0.04 0.025
P-122 J-79 J-80 15 DI 100 0.03 0.024
P-123 J-45 J-46 11 DI 100 0.03 0.024
P-124 J-13 J-14 6 DI 100 0.03 0.024
P-125 J-92 J-93 17 DI 100 0.03 0.019
P-126 J-35 J-36 11 DI 100 0.03 0.02
P-127 J-56 J-57 13 DI 100 0.03 0.018
P-128 J-17 J-18 6 DI 100 0.03 0.018
P-129 J-28 J-29 9 DI 100 0.03 0.018
P-130 J-70 J-71 14 DI 100 0.03 0.017
P-131 J-85 J-86 16 DI 100 0.03 0.017
P-132 J-43 J-117 25 DI 100 0.03 0.017
P-133 J-63 J-64 14 DI 100 0.03 0.015
Headloss
Start Length Diameter Velocity
Label Stop Node Material Gradient
Node (m) (mm) (m/s)
(m/km)
P-134 J-60 J-131 30 DI 100 0.15 0.361
P-135 J-41 J-42 11 DI 100 0.02 0.01
P-136 J-22 J-23 8 DI 100 0 0
P-137 J-26 J-27 32 DI 100 0 0
P-138 J-53 J-54 13 DI 100 0 0
P-139 J-20 J-55 13 DI 100 0 0
P-140 J-60 J-61 13 DI 100 0 0
P-141 J-115 J-116 30 DI 100 0 0
Availability of re-cycled water is estimated based on the assumption that, about 20 to 45% of the
wastewater generated from the industries.
The recycled water supply distribution system is designed as per the manual of Central Public Health
and Environmental Engineering Organisation (CPHEEO).
Plots
Amount Amount
S.No Component
Phase I Phase II
P a g e |176
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
7.8.1.1. Introduction
Wastewater network is designed to minimize number of pumping/ lift stations and at the same time
to avoid deep sewers. The total length of wastewater network proposed for the petrochemical park
area is about 6.3 km. The total numbers of pump/ lift stations proposed is 2 and maximum depth of
excavation is limited to 3m. In catchment of CETP 1, ground profile is falling and again raising for about
4m due to which depth is envisage to 7m at two places.
The values of Manning’s Roughness Coefficient (n) for various pipeline materials are given in the table
7-33.
Table 7-33 : Manning’s Coefficient
P a g e |177
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |178
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |179
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
7.8.1.3.9. Manholes
Manholes are to be provided to facilitate cleaning and inspection of sewers. Table 7-36 gives the type
and size of various manholes to be employed for different diameter of sewers and for different depths.
The selection of types of manhole shall also be based on the economic and construction factors.
Table 7-36: Manholes sizes
Types of Manholes Description Size of manholes
Circular Manholes For depth up to 1.65m 900 mm diameter
Circular Manholes For depth from 1.66m to 2.30m 1200 mm diameter
Circular Manholes For depth from 2.31m to 9.0m 1500 mm diameter
Circular Manholes For depth above 9.0m 1800 mm diameter
P a g e |180
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
3 Peak Factor 3
B Hydraulic Design
D Sewer Material
P a g e |181
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
E Limiting Velocities
F Bedding
G Earth Cover
I Manhole Construction
P a g e |183
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |184
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |185
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
5 500 37 1.53
Total 6218
P a g e |186
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P-2 MH-226 MH-227 27.00 5.98 0.00 34.63 33.71 150 0.74 32.69 32.51 200 RCC NP3 0.01 0.00 0.02 1.01 31.65 0.00 1.94 1.20 1.74 1.00
P-3 MH-227 MH-228 30.00 9.30 0.00 33.71 32.63 150 0.88 31.63 31.43 200 RCC NP3 0.01 0.00 0.03 1.01 31.65 0.00 2.08 1.20 1.88 1.00
P-4 MH-228 MH-229 36.00 15.61 0.16 32.63 31.86 150 0.53 30.90 30.66 200 RCC NP3 0.01 0.16 0.55 1.01 31.65 0.00 1.73 1.20 1.53 1.00
P-5 MH-229 MH-230 32.00 19.21 0.16 31.86 31.59 150 0.05 30.61 30.39 200 RCC NP3 0.01 0.16 0.55 1.01 31.65 0.00 1.25 1.20 1.05 1.00
P-6 MH-230 MH-231 30.00 22.56 0.16 31.59 31.50 250 30.39 30.27 200 RCC NP3 0.01 0.18 0.46 0.78 24.52 0.01 1.20 1.23 1.00 1.03
P-7 MH-231 MH-232 27.00 25.53 0.16 31.50 31.46 250 30.27 30.16 200 RCC NP3 0.01 0.18 0.46 0.78 24.52 0.01 1.23 1.30 1.03 1.10
P-8 MH-232 MH-233 28.00 31.50 0.17 31.46 31.37 250 0.26 29.90 29.79 200 RCC NP3 0.01 0.19 0.46 0.78 24.52 0.01 1.56 1.58 1.36 1.38
P-9 MH-233 MH-234 30.00 34.81 0.17 31.37 30.92 250 29.79 29.67 200 RCC NP3 0.01 0.19 0.46 0.78 24.52 0.01 1.58 1.25 1.38 1.05
P-10 MH-234 MH-235 34.00 38.45 0.17 30.92 30.15 150 0.50 29.17 28.95 200 RCC NP3 0.01 0.17 0.56 1.01 31.65 0.01 1.75 1.20 1.55 1.00
P-11 MH-235 MH-236 30.00 42.70 0.17 30.15 29.26 150 0.63 28.32 28.06 200 RCC NP3 0.01 0.17 0.56 1.01 31.65 0.01 1.83 1.20 1.63 1.00
P-12 MH-236 MH-237 30.00 47.39 0.17 29.26 28.07 150 0.90 27.16 26.87 200 RCC NP3 0.01 0.17 0.56 1.01 31.65 0.01 2.10 1.20 1.90 1.00
P-13 MH-237 MH-238 30.00 53.65 0.17 28.07 27.21 150 0.60 26.27 26.01 200 RCC NP3 0.01 0.17 0.56 1.01 31.65 0.01 1.80 1.20 1.60 1.00
P-14 MH-239 MH-238 30.00 26.45 1.49 26.94 27.21 250 25.72 25.57 200 RCC NP3 0.01 0.62 0.84 0.78 24.52 0.06 1.22 1.64 1.02 1.44
P-15 MH-240 MH-239 30.00 22.40 1.49 27.07 26.94 250 25.87 25.72 200 RCC NP3 0.01 0.62 0.84 0.78 24.52 0.06 1.20 1.22 1.00 1.02
P-16 MH-241 MH-240 30.00 18.25 1.49 27.55 27.07 150 26.09 25.87 200 RCC NP3 0.01 0.53 1.03 1.01 31.65 0.05 1.46 1.20 1.26 1.00
P-17 MH-242 MH-241 30.00 14.55 1.49 27.71 27.55 250 26.35 26.22 200 RCC NP3 0.01 0.62 0.84 0.78 24.52 0.06 1.36 1.33 1.16 1.13
P-18 MH-243 MH-242 30.00 10.82 1.49 27.85 27.71 250 26.50 26.35 200 RCC NP3 0.01 0.62 0.84 0.78 24.52 0.06 1.35 1.36 1.15 1.16
P-19 MH-224 MH-243 39.00 4.61 0.00 27.86 27.85 250 26.66 26.50 200 RCC NP3 0.01 0.00 0.02 0.78 24.52 0.00 1.20 1.35 1.00 1.15
P-20 MH-25 MH-141 19.00 1.60 0.11 25.43 25.47 250 24.22 24.27 200 RCC NP3 0.01 0.15 0.41 0.78 24.52 0.00 1.21 1.20 1.01 1.00
P-21 MH-198 MH-85 36.00 29.11 0.44 27.16 26.58 150 25.62 25.38 200 RCC NP3 0.01 0.27 0.74 1.01 31.65 0.01 1.54 1.20 1.34 1.00
P-22 MH-197 MH-198 30.00 25.13 0.44 27.65 27.16 150 26.16 25.96 200 RCC NP3 0.01 0.27 0.74 1.01 31.65 0.01 1.49 1.20 1.29 1.00
P-23 MH-68 MH-197 30.00 21.80 0.44 28.13 27.65 150 26.65 26.45 200 RCC NP3 0.01 0.27 0.74 1.01 31.65 0.01 1.48 1.20 1.28 1.00
P-24 MH-151 MH-68 34.00 14.84 0.33 28.69 28.13 150 27.16 26.93 200 RCC NP3 0.01 0.23 0.68 1.01 31.65 0.01 1.53 1.20 1.33 1.00
P-25 MH-58 MH-151 30.00 11.06 0.33 29.18 28.69 150 27.69 27.49 200 RCC NP3 0.01 0.23 0.68 1.01 31.65 0.01 1.49 1.20 1.29 1.00
P-26 MH-90 MH-58 20.00 4.17 0.13 29.74 29.18 150 28.11 27.98 200 RCC NP3 0.01 0.15 0.52 1.01 31.65 0.00 1.63 1.20 1.43 1.00
P-27 MH-89 MH-213 30.00 107.68 6.49 28.88 28.28 670 21.40 21.35 400 RCC NP3 0.01 0.67 0.84 0.76 95.09 0.07 7.48 6.93 7.08 6.53
P-28 MH-5 MH-6 5.00 13.95 0.78 4.15 4.15 250 1.16 1.14 200 RCC NP3 0.01 0.42 0.72 0.78 24.52 0.03 2.99 3.01 2.79 2.81
P-29 MH-8 MH-87 18.00 41.99 1.22 24.13 24.48 250 22.56 22.49 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 1.57 1.99 1.37 1.79
P-30 MH-13 MH-11 9.00 22.69 5.27 29.29 28.94 250 27.58 27.54 300 RCC NP3 0.01 0.70 1.15 1.02 72.28 0.07 1.71 1.40 1.41 1.10
P a g e |187
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P-31 MH-12 MH-11 9.00 66.94 1.22 28.34 28.94 250 21.66 21.62 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 6.68 7.32 6.48 7.12
P-32 MH-9 MH-7 7.00 39.34 1.22 23.94 23.89 250 22.61 22.59 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 1.33 1.30 1.13 1.10
P-33 MH-7 MH-8 6.00 40.03 1.22 23.89 24.13 250 22.59 22.56 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 1.30 1.57 1.10 1.37
P-34 MH-50 MH-17 34.00 152.43 7.26 17.95 17.12 300 15.83 15.72 400 RCC NP3 0.01 0.55 1.18 1.13 142.10 0.05 2.12 1.40 1.72 1.00
P-35 MH-17 MH-110 31.00 155.91 7.26 17.12 16.36 300 0.65 15.07 14.96 400 RCC NP3 0.01 0.55 1.18 1.13 142.10 0.05 2.05 1.40 1.65 1.00
P-36 MH-139 MH-50 25.00 2.81 0.17 17.61 17.95 250 16.41 16.31 200 RCC NP3 0.01 0.19 0.47 0.78 24.52 0.01 1.20 1.64 1.00 1.44
P-37 MH-138 MH-40 19.00 1.66 0.18 21.34 21.34 250 20.14 20.08 200 RCC NP3 0.01 0.20 0.47 0.78 24.52 0.01 1.20 1.26 1.00 1.06
P-38 MH-52 MH-25 15.00 1.66 0.12 25.36 25.43 250 24.16 24.10 200 RCC NP3 0.01 0.16 0.42 0.78 24.52 0.00 1.20 1.33 1.00 1.13
P-39 MH-41 MH-40 15.00 1.66 0.10 21.26 21.34 250 20.06 20.00 200 RCC NP3 0.01 0.15 0.40 0.78 24.52 0.00 1.20 1.34 1.00 1.14
P-40 MH-51 MH-50 15.00 1.66 0.09 17.87 17.95 250 16.67 16.61 200 RCC NP3 0.01 0.14 0.39 0.78 24.52 0.00 1.20 1.34 1.00 1.14
P-41 MH-1 O-2 37.00 190.82 8.94 6.87 6.90 830 5.42 5.37 450 RCC NP3 0.01 0.73 0.83 0.74 116.95 0.08 1.45 1.53 1.00 1.08
P-42 MH-111 MH-110 25.00 2.78 1.40 16.29 16.36 250 15.09 14.99 200 RCC NP3 0.01 0.59 0.83 0.78 24.52 0.06 1.20 1.37 1.00 1.17
P-43 MH-47 MH-1 21.00 186.76 8.93 7.56 6.87 300 5.54 5.47 400 RCC NP3 0.01 0.63 1.23 1.13 142.10 0.06 2.02 1.40 1.62 1.00
P-44 MH-48 MH-47 15.00 1.66 0.27 8.03 7.56 150 6.46 6.36 200 RCC NP3 0.01 0.21 0.64 1.01 31.65 0.01 1.57 1.20 1.37 1.00
P-45 MH-134 MH-81 15.00 1.69 0.00 30.37 30.35 250 29.17 29.11 200 RCC NP3 0.01 0.03 0.14 0.78 24.52 0.00 1.20 1.24 1.00 1.04
P-46 MH-34 MH-189 15.00 67.25 1.09 7.45 7.56 250 5.24 5.18 200 RCC NP3 0.01 0.51 0.79 0.78 24.52 0.04 2.21 2.38 2.01 2.18
P-47 MH-135 MH-77 20.00 2.00 0.14 32.89 32.99 250 31.69 31.62 200 RCC NP3 0.01 0.18 0.45 0.78 24.52 0.01 1.20 1.37 1.00 1.17
P-48 MH-245 MH-174 22.00 2.39 0.00 6.75 6.51 150 5.46 5.31 200 RCC NP3 0.01 0.00 0.02 1.01 31.65 0.00 1.29 1.20 1.09 1.00
P-49 MH-78 MH-77 15.00 1.69 0.16 32.55 32.99 250 31.35 31.29 200 RCC NP3 0.01 0.19 0.46 0.78 24.52 0.01 1.20 1.70 1.00 1.50
P-50 MH-247 MH-12 7.00 0.82 0.00 28.83 28.34 150 27.19 27.14 200 RCC NP3 0.01 0.03 0.17 1.01 31.65 0.00 1.64 1.20 1.44 1.00
P-51 MH-120 MH-58 20.00 1.93 0.04 29.52 29.18 150 28.09 27.98 200 RCC NP3 0.01 0.08 0.36 1.01 31.65 0.00 1.43 1.20 1.23 1.00
P-52 MH-248 MH-89 32.00 12.65 0.00 29.44 28.88 150 27.90 27.68 200 RCC NP3 0.01 0.03 0.17 1.01 31.65 0.00 1.54 1.20 1.34 1.00
P-53 MH-59 MH-58 15.00 1.66 0.16 29.82 29.18 150 28.08 27.98 200 RCC NP3 0.01 0.17 0.55 1.01 31.65 0.01 1.74 1.20 1.54 1.00
P-54 MH-249 MH-248 30.00 9.09 0.00 30.01 29.44 150 28.44 28.24 200 RCC NP3 0.01 0.03 0.17 1.01 31.65 0.00 1.57 1.20 1.37 1.00
P-55 MH-113 MH-68 20.00 1.97 0.04 28.06 28.13 250 26.86 26.79 200 RCC NP3 0.01 0.10 0.30 0.78 24.52 0.00 1.20 1.34 1.00 1.14
P-56 MH-250 MH-249 44.00 5.74 0.00 30.82 30.01 150 29.10 28.81 200 RCC NP3 0.01 0.03 0.17 1.01 31.65 0.00 1.72 1.20 1.52 1.00
P-57 MH-69 MH-68 15.00 1.66 0.07 28.34 28.13 120 27.03 26.93 200 RCC NP3 0.01 0.11 0.43 1.13 35.38 0.00 1.31 1.20 1.11 1.00
P-58 MH-251 MH-250 8.00 0.90 0.00 31.11 30.82 120 29.67 29.62 200 RCC NP3 0.01 0.03 0.17 1.13 35.38 0.00 1.44 1.20 1.24 1.00
P-59 MH-117 MH-85 20.00 1.97 0.04 26.50 26.58 120 25.30 25.21 200 RCC NP3 0.01 0.09 0.32 1.13 35.38 0.00 1.20 1.37 1.00 1.17
P-60 MH-252 MH-228 21.00 2.29 0.16 32.68 32.63 120 31.48 31.40 200 RCC NP3 0.01 0.18 0.46 1.13 35.38 0.00 1.20 1.23 1.00 1.03
P-61 MH-109 MH-16 20.00 2.03 0.04 25.25 25.33 120 24.05 23.98 200 RCC NP3 0.01 0.10 0.31 1.13 35.38 0.00 1.20 1.35 1.00 1.15
P-62 MH-253 MH-62 39.00 4.33 1.66 36.00 34.92 120 33.98 33.72 200 RCC NP3 0.01 0.56 1.06 1.13 35.38 0.05 2.02 1.20 1.82 1.00
P-63 MH-136 MH-101 20.00 1.94 0.04 24.36 24.44 120 23.16 23.09 200 RCC NP3 0.01 0.10 0.30 1.13 35.38 0.00 1.20 1.35 1.00 1.15
P-64 MH-3 MH-112 21.00 2.08 0.13 24.05 23.97 120 22.69 22.77 200 RCC NP3 0.01 0.17 0.43 1.13 35.38 0.00 1.36 1.20 1.16 1.00
P a g e |188
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P-65 MH-119 MH-92 21.00 2.02 0.15 23.92 23.99 120 22.72 22.65 200 RCC NP3 0.01 0.18 0.45 1.13 35.38 0.00 1.20 1.34 1.00 1.14
P-66 MH-255 MH-232 26.00 2.88 0.01 31.20 31.46 120 30.00 29.90 200 RCC NP3 0.01 0.05 0.20 1.13 35.38 0.00 1.20 1.56 1.00 1.36
P-67 MH-106 MH-105 22.00 1.95 0.14 24.18 24.26 120 22.98 22.91 200 RCC NP3 0.01 0.17 0.44 1.13 35.38 0.00 1.20 1.35 1.00 1.15
P-68 MH-256 MH-237 22.00 1.88 0.01 28.36 28.07 120 26.99 26.87 200 RCC NP3 0.01 0.04 0.20 1.13 35.38 0.00 1.37 1.20 1.17 1.00
P-69 MH-99 MH-118 21.00 1.94 0.13 24.68 24.72 120 23.45 23.52 200 RCC NP3 0.01 0.17 0.43 1.13 35.38 0.00 1.23 1.20 1.03 1.00
P-70 MH-238 O-4 9.00 81.86 1.66 27.21 27.58 100 25.57 25.51 200 RCC NP3 0.01 0.67 0.86 1.23 38.76 0.04 1.64 2.07 1.44 1.87
P-71 MH-125 MH-124 21.00 1.83 0.12 25.07 25.04 100 23.87 23.81 200 RCC NP3 0.01 0.16 0.42 1.23 38.76 0.00 1.20 1.23 1.00 1.03
P-72 MH-260 MH-182 10.00 1.16 0.01 3.39 3.46 100 2.19 2.15 200 RCC NP3 0.01 0.04 0.17 1.23 38.76 0.00 1.20 1.31 1.00 1.11
P-73 MH-115 MH-114 20.00 1.84 0.12 25.38 25.35 100 24.18 24.11 200 RCC NP3 0.01 0.16 0.42 1.23 38.76 0.00 1.20 1.24 1.00 1.04
P-74 MH-261 MH-191 31.00 3.48 0.39 6.71 6.04 100 5.05 4.84 200 RCC NP3 0.01 0.26 0.72 1.23 38.76 0.01 1.66 1.20 1.46 1.00
P-75 MH-129 MH-128 19.00 1.90 0.10 25.81 25.89 250 24.61 24.54 200 RCC NP3 0.01 0.15 0.40 0.78 24.52 0.00 1.20 1.35 1.00 1.15
P-76 MH-160 MH-262 20.00 0.78 0.01 33.94 33.80 250 32.58 32.60 200 RCC NP3 0.01 0.04 0.17 0.78 24.52 0.00 1.36 1.20 1.16 1.00
P-77 MH-131 MH-130 12.00 1.34 0.11 26.10 26.48 80 24.90 24.86 200 RCC NP3 0.01 0.15 0.41 1.38 43.34 0.00 1.20 1.62 1.00 1.42
P-78 MH-108 MH-107 10.00 1.13 0.16 26.41 26.89 80 25.21 25.17 200 RCC NP3 0.01 0.19 0.46 1.38 43.34 0.00 1.20 1.72 1.00 1.52
P-79 MH-265 MH-243 45.00 2.24 1.49 28.38 27.85 80 26.78 26.65 200 RCC NP3 0.01 0.53 1.03 1.38 43.34 0.03 1.60 1.20 1.40 1.00
P-80 MH-43 MH-42 15.00 1.66 0.30 26.46 26.42 80 25.26 25.18 200 RCC NP3 0.01 0.24 0.60 1.38 43.34 0.01 1.20 1.24 1.00 1.04
P-81 MH-54 MH-53 15.00 1.66 0.13 26.73 26.71 80 25.53 25.47 200 RCC NP3 0.01 0.17 0.43 1.38 43.34 0.00 1.20 1.24 1.00 1.04
P-82 MH-37 MH-36 15.00 1.66 0.13 27.30 27.33 80 26.10 26.04 200 RCC NP3 0.01 0.17 0.43 1.38 43.34 0.00 1.20 1.29 1.00 1.09
P-83 MH-57 MH-56 4.00 0.41 0.13 27.57 27.52 100 26.34 26.32 200 RCC NP3 0.01 0.15 0.52 1.23 38.76 0.00 1.23 1.20 1.03 1.00
P-84 MH-67 MH-66 5.00 0.53 0.12 31.00 30.99 100 29.80 29.78 200 RCC NP3 0.01 0.16 0.43 1.23 38.76 0.00 1.20 1.21 1.00 1.01
P-85 MH-63 MH-62 5.00 0.55 0.20 34.83 34.92 100 33.63 33.61 200 RCC NP3 0.01 0.21 0.49 1.23 38.76 0.01 1.20 1.31 1.00 1.11
P-86 MH-4 O-3 12.00 236.34 4.88 24.03 24.27 80 22.38 22.36 350 RCC NP3 0.01 0.71 0.78 2.00 192.73 0.03 1.65 1.91 1.30 1.56
P-87 MH-11 MH-89 19.00 91.70 6.49 28.94 28.88 80 21.42 21.40 400 RCC NP3 0.01 0.67 0.84 2.19 275.17 0.02 7.52 7.48 7.12 7.08
P-88 MH-74 MH-73 15.00 1.69 0.08 33.25 33.46 250 31.95 31.89 200 RCC NP3 0.01 0.13 0.37 0.78 24.52 0.00 1.30 1.57 1.10 1.37
P-89 MH-137 MH-90 20.00 1.94 0.13 29.66 29.74 250 28.46 28.39 200 RCC NP3 0.01 0.17 0.43 0.78 24.52 0.01 1.20 1.35 1.00 1.15
P-90 MH-23 MH-22 12.00 1.37 0.17 29.71 29.46 150 28.34 28.26 200 RCC NP3 0.01 0.17 0.56 1.01 31.65 0.01 1.37 1.20 1.17 1.00
P-91 MH-116 MH-22 25.00 2.78 0.21 29.28 29.46 250 28.08 27.98 200 RCC NP3 0.01 0.21 0.50 0.78 24.52 0.01 1.20 1.48 1.00 1.28
P-92 MH-61 MH-29 15.00 1.66 0.16 27.44 26.97 150 25.87 25.77 200 RCC NP3 0.01 0.16 0.55 1.01 31.65 0.00 1.57 1.20 1.37 1.00
P-93 MH-121 MH-29 25.00 2.78 0.17 26.90 26.97 250 25.70 25.60 200 RCC NP3 0.01 0.19 0.47 0.78 24.52 0.01 1.20 1.37 1.00 1.17
P-94 MH-60 MH-10 15.00 1.66 0.01 24.65 24.16 150 23.06 22.96 200 RCC NP3 0.01 0.04 0.20 1.01 31.65 0.00 1.59 1.20 1.39 1.00
P-95 MH-132 MH-97 25.00 2.78 0.16 24.50 24.71 250 23.30 23.20 200 RCC NP3 0.01 0.19 0.46 0.78 24.52 0.01 1.20 1.51 1.00 1.31
P-96 MH-103 MH-79 16.00 1.76 0.11 8.44 8.38 250 7.24 7.17 200 RCC NP3 0.01 0.15 0.41 0.78 24.52 0.00 1.20 1.21 1.00 1.01
P-97 MH-126 MH-26 15.00 1.70 0.05 8.29 8.48 250 7.09 7.03 200 RCC NP3 0.01 0.10 0.31 0.78 24.52 0.00 1.20 1.45 1.00 1.25
P-98 MH-70 MH-26 15.00 1.66 0.07 8.48 8.48 250 7.28 7.22 200 RCC NP3 0.01 0.12 0.35 0.78 24.52 0.00 1.20 1.26 1.00 1.06
P a g e |189
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P-99 MH-21 MH-96 18.00 5.76 0.77 2.79 2.86 250 1.47 1.40 200 RCC NP3 0.01 0.42 0.72 0.78 24.52 0.03 1.32 1.46 1.12 1.26
P-100 MH-83 MH-21 11.00 1.23 0.52 2.79 2.79 250 1.59 1.55 200 RCC NP3 0.01 0.34 0.64 0.78 24.52 0.02 1.20 1.24 1.00 1.04
P-101 MH-15 MH-21 23.00 2.57 0.26 2.80 2.79 175 1.60 1.47 200 RCC NP3 0.01 0.22 0.60 0.93 29.30 0.01 1.20 1.32 1.00 1.12
P-102 MH-62 MH-160 30.00 8.21 1.86 34.92 33.94 150 32.94 32.74 200 RCC NP3 0.01 0.61 1.08 1.01 31.65 0.06 1.98 1.20 1.78 1.00
P-103 MH-160 MH-148 30.00 12.32 1.87 33.94 32.85 150 0.89 31.85 31.65 200 RCC NP3 0.01 0.61 1.08 1.01 31.65 0.06 2.09 1.20 1.89 1.00
P-104 MH-148 MH-94 29.00 15.58 1.87 32.85 31.78 150 0.87 30.78 30.58 200 RCC NP3 0.01 0.61 1.08 1.01 31.65 0.06 2.07 1.20 1.87 1.00
P-105 MH-94 MH-66 21.00 17.94 1.87 31.78 30.99 150 0.65 29.93 29.79 200 RCC NP3 0.01 0.61 1.08 1.01 31.65 0.06 1.85 1.20 1.65 1.00
P-106 MH-66 MH-162 30.00 21.80 1.99 30.99 29.88 150 0.91 28.88 28.68 200 RCC NP3 0.01 0.63 1.10 1.01 31.65 0.06 2.11 1.20 1.91 1.00
P-107 MH-162 MH-161 30.00 25.13 1.99 29.88 28.76 150 0.92 27.76 27.56 200 RCC NP3 0.01 0.63 1.10 1.01 31.65 0.06 2.12 1.20 1.92 1.00
P-108 MH-161 MH-56 35.00 29.03 1.99 28.76 27.52 150 1.01 26.55 26.32 200 RCC NP3 0.01 0.63 1.10 1.01 31.65 0.06 2.21 1.20 2.01 1.00
P-109 MH-56 MH-163 30.00 32.77 2.12 27.52 26.81 150 0.51 25.81 25.61 200 RCC NP3 0.01 0.66 1.11 1.01 31.65 0.07 1.71 1.20 1.51 1.00
P-110 MH-163 MH-165 30.00 36.10 2.12 26.81 26.48 150 0.13 25.48 25.28 200 RCC NP3 0.01 0.66 1.11 1.01 31.65 0.07 1.33 1.20 1.13 1.00
P-111 MH-104 MH-4 24.00 174.90 4.20 23.98 24.03 450 22.48 22.43 300 RCC NP3 0.01 0.74 0.86 0.76 53.87 0.08 1.50 1.60 1.20 1.30
P-112 MH-165 MH-210 30.00 39.48 2.12 26.48 26.43 360 25.23 25.14 250 RCC NP3 0.01 0.60 0.81 0.75 37.04 0.06 1.25 1.29 1.00 1.04
P-113 MH-210 MH-209 30.00 42.85 2.12 26.43 26.52 360 25.14 25.06 250 RCC NP3 0.01 0.60 0.81 0.75 37.04 0.06 1.29 1.46 1.04 1.21
P-114 MH-209 MH-205 30.00 46.18 2.12 26.52 26.67 360 25.06 24.97 250 RCC NP3 0.01 0.60 0.81 0.75 37.04 0.06 1.46 1.70 1.21 1.45
P-115 MH-205 MH-178 30.00 49.51 2.12 26.67 26.84 360 24.97 24.89 250 RCC NP3 0.01 0.60 0.81 0.75 37.04 0.06 1.70 1.95 1.45 1.70
P-116 MH-178 MH-177 31.00 52.94 2.12 26.84 27.13 360 24.89 24.80 250 RCC NP3 0.01 0.60 0.81 0.75 37.04 0.06 1.95 2.33 1.70 2.08
P-117 MH-177 MH-122 31.00 56.39 2.12 27.13 27.36 360 24.80 24.72 250 RCC NP3 0.01 0.60 0.81 0.75 37.04 0.06 2.33 2.64 2.08 2.39
P-118 MH-122 MH-88 30.00 62.54 2.63 27.36 27.37 360 24.72 24.63 250 RCC NP3 0.01 0.69 0.84 0.75 37.04 0.07 2.64 2.74 2.39 2.49
P-119 MH-123 MH-122 25.00 2.72 0.50 27.31 27.36 250 26.11 26.01 200 RCC NP3 0.01 0.33 0.64 0.78 24.52 0.02 1.20 1.35 1.00 1.15
P-120 MH-88 MH-36 18.00 64.60 2.63 27.37 27.33 360 24.63 24.58 250 RCC NP3 0.01 0.69 0.84 0.75 37.04 0.07 2.74 2.75 2.49 2.50
P-121 MH-36 MH-208 30.00 69.59 2.75 27.33 27.08 360 24.58 24.50 250 RCC NP3 0.01 0.72 0.85 0.75 37.04 0.07 2.75 2.58 2.50 2.33
P-122 MH-208 MH-217 30.00 72.93 2.75 27.08 26.88 360 24.50 24.41 250 RCC NP3 0.01 0.72 0.85 0.75 37.04 0.07 2.58 2.47 2.33 2.22
P-123 MH-217 MH-53 31.00 76.41 2.75 26.88 26.71 360 24.41 24.33 250 RCC NP3 0.01 0.72 0.85 0.75 37.04 0.07 2.47 2.38 2.22 2.13
P-124 MH-53 MH-143 30.00 81.41 2.88 26.71 26.53 360 24.33 24.24 250 RCC NP3 0.01 0.74 0.85 0.75 37.04 0.08 2.38 2.29 2.13 2.04
P-125 MH-143 MH-42 28.00 84.48 2.88 26.53 26.42 360 24.24 24.17 250 RCC NP3 0.01 0.74 0.85 0.75 37.04 0.08 2.29 2.25 2.04 2.00
P-126 MH-42 MH-203 30.00 89.47 3.18 26.42 26.35 450 0.05 24.12 24.05 300 RCC NP3 0.01 0.61 0.82 0.76 53.87 0.06 2.30 2.30 2.00 2.00
P-127 MH-203 MH-202 30.00 92.80 3.18 26.35 26.34 450 24.05 23.98 300 RCC NP3 0.01 0.61 0.82 0.76 53.87 0.06 2.30 2.36 2.00 2.06
P-128 MH-202 MH-164 30.00 96.13 3.18 26.34 26.48 450 23.98 23.92 300 RCC NP3 0.01 0.61 0.82 0.76 53.87 0.06 2.36 2.56 2.06 2.26
P-129 MH-164 MH-159 30.00 99.46 3.18 26.48 26.69 450 23.92 23.85 300 RCC NP3 0.01 0.61 0.82 0.76 53.87 0.06 2.56 2.84 2.26 2.54
P-130 MH-159 MH-158 30.00 102.79 3.18 26.69 26.84 450 23.85 23.78 300 RCC NP3 0.01 0.61 0.82 0.76 53.87 0.06 2.84 3.06 2.54 2.76
P-131 MH-158 MH-107 31.00 106.19 3.18 26.84 26.89 450 23.78 23.72 300 RCC NP3 0.01 0.61 0.82 0.76 53.87 0.06 3.06 3.17 2.76 2.87
P-132 MH-107 MH-181 30.00 110.66 3.34 26.89 26.86 450 23.72 23.65 300 RCC NP3 0.01 0.63 0.83 0.76 53.87 0.06 3.17 3.21 2.87 2.91
P a g e |190
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P-133 MH-181 MH-180 30.00 114.00 3.34 26.86 26.74 450 23.65 23.58 300 RCC NP3 0.01 0.63 0.83 0.76 53.87 0.06 3.21 3.16 2.91 2.86
P-134 MH-180 MH-130 41.00 118.54 3.34 26.74 26.48 450 23.58 23.49 300 RCC NP3 0.01 0.63 0.83 0.76 53.87 0.06 3.16 2.99 2.86 2.69
P-135 MH-130 MH-212 30.00 123.21 3.45 26.48 26.29 450 23.49 23.42 300 RCC NP3 0.01 0.64 0.83 0.76 53.87 0.06 2.99 2.87 2.69 2.57
P-136 MH-212 MH-128 39.00 127.58 3.45 26.29 25.89 450 23.42 23.34 300 RCC NP3 0.01 0.64 0.83 0.76 53.87 0.06 2.87 2.55 2.57 2.25
P-137 MH-128 MH-153 30.00 132.82 3.55 25.89 25.57 450 23.34 23.27 300 RCC NP3 0.01 0.65 0.84 0.76 53.87 0.07 2.55 2.30 2.25 2.00
P-138 MH-153 MH-114 30.00 136.13 3.55 25.57 25.35 450 23.27 23.20 300 RCC NP3 0.01 0.65 0.84 0.76 53.87 0.07 2.30 2.15 2.00 1.85
P-139 MH-114 MH-124 45.00 142.93 3.67 25.35 25.04 450 23.20 23.10 300 RCC NP3 0.01 0.67 0.84 0.76 53.87 0.07 2.15 1.94 1.85 1.64
P-140 MH-100 MH-99 23.00 150.66 3.78 24.83 24.68 450 23.04 22.99 300 RCC NP3 0.01 0.68 0.85 0.76 53.87 0.07 1.79 1.69 1.49 1.39
P-141 MH-124 MH-100 30.00 148.09 3.78 25.04 24.83 450 23.10 23.04 300 RCC NP3 0.01 0.68 0.85 0.76 53.87 0.07 1.94 1.79 1.64 1.49
P-142 MH-99 MH-150 30.00 155.98 3.91 24.68 24.46 450 22.99 22.92 300 RCC NP3 0.01 0.70 0.85 0.76 53.87 0.07 1.69 1.54 1.39 1.24
P-143 MH-150 MH-105 30.00 159.28 3.91 24.46 24.26 274 22.92 22.81 300 RCC NP3 0.01 0.59 1.04 0.98 69.04 0.06 1.54 1.45 1.24 1.15
P-144 MH-105 MH-93 30.00 164.54 4.05 24.26 24.06 450 22.81 22.74 300 RCC NP3 0.01 0.72 0.86 0.76 53.87 0.08 1.45 1.32 1.15 1.02
P-145 MH-93 MH-92 21.00 166.81 4.05 24.06 23.99 403 22.74 22.69 300 RCC NP3 0.01 0.69 0.90 0.81 56.93 0.07 1.32 1.30 1.02 1.00
P-146 MH-92 MH-104 30.00 172.19 4.20 23.99 23.98 450 0.14 22.55 22.48 300 RCC NP3 0.01 0.74 0.86 0.76 53.87 0.08 1.44 1.50 1.14 1.20
P-147 MH-3 MH-4 4.00 60.15 0.69 24.05 24.03 250 22.69 22.68 200 RCC NP3 0.01 0.39 0.70 0.78 24.52 0.03 1.36 1.35 1.16 1.15
P-148 MH-102 MH-3 30.00 57.61 0.56 24.21 24.05 207 22.99 22.85 200 RCC NP3 0.01 0.33 0.71 0.86 26.94 0.02 1.22 1.20 1.02 1.00
P-149 MH-101 MH-102 24.00 54.28 0.56 24.44 24.21 250 23.09 22.99 200 RCC NP3 0.01 0.35 0.66 0.78 24.52 0.02 1.35 1.22 1.15 1.02
P-150 MH-187 MH-101 30.00 49.65 0.52 24.76 24.44 150 23.44 23.24 200 RCC NP3 0.01 0.30 0.78 1.01 31.65 0.02 1.32 1.20 1.12 1.00
P-151 MH-17 MH-187 30.00 46.32 0.52 25.15 24.76 150 23.76 23.56 200 RCC NP3 0.01 0.30 0.78 1.01 31.65 0.02 1.39 1.20 1.19 1.00
P-152 MH-16 MH-17 12.00 42.99 0.52 25.33 25.15 250 23.98 23.93 200 RCC NP3 0.01 0.34 0.65 0.78 24.52 0.02 1.35 1.22 1.15 1.02
P-153 MH-176 MH-16 30.00 39.67 0.48 25.81 25.33 150 24.33 24.13 200 RCC NP3 0.01 0.28 0.76 1.01 31.65 0.02 1.48 1.20 1.28 1.00
P-154 MH-85 MH-86 17.00 33.01 0.48 26.58 26.30 150 25.21 25.10 200 RCC NP3 0.01 0.28 0.76 1.01 31.65 0.02 1.37 1.20 1.17 1.00
P-155 MH-86 MH-176 30.00 36.33 0.48 26.30 25.81 150 0.29 24.81 24.61 200 RCC NP3 0.01 0.28 0.76 1.01 31.65 0.02 1.49 1.20 1.29 1.00
P-156 MH-73 MH-77 31.00 5.12 4.96 33.46 32.99 250 31.71 31.59 300 RCC NP3 0.01 0.67 1.13 1.02 72.28 0.07 1.75 1.40 1.45 1.10
P-157 MH-77 MH-173 30.00 12.18 5.26 32.99 32.10 250 0.77 30.82 30.70 300 RCC NP3 0.01 0.70 1.15 1.02 72.28 0.07 2.17 1.40 1.87 1.10
P-158 MH-173 MH-82 30.00 15.51 5.26 32.10 31.01 250 0.97 29.73 29.61 300 RCC NP3 0.01 0.70 1.15 1.02 72.28 0.07 2.37 1.40 2.07 1.10
P-159 MH-81 MH-13 24.00 21.64 5.27 30.35 29.29 250 27.99 27.89 300 RCC NP3 0.01 0.70 1.15 1.02 72.28 0.07 2.36 1.40 2.06 1.10
P-160 MH-82 MH-81 16.00 17.33 5.26 31.01 30.35 250 29.01 28.95 300 RCC NP3 0.01 0.70 1.15 1.02 72.28 0.07 2.00 1.40 1.70 1.10
P-161 MH-186 MH-12 30.00 65.15 1.22 27.81 28.34 250 21.78 21.66 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 6.03 6.68 5.83 6.48
P-162 MH-152 MH-186 30.00 61.82 1.22 27.25 27.81 250 21.90 21.78 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 5.35 6.03 5.15 5.83
P-163 MH-145 MH-152 30.00 58.49 1.22 26.68 27.25 250 22.02 21.90 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 4.66 5.35 4.46 5.15
P-164 MH-144 MH-145 29.00 55.18 1.22 26.15 26.68 250 22.13 22.02 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 4.02 4.66 3.82 4.46
P-165 MH-185 MH-144 30.00 51.98 1.22 25.59 26.15 250 22.25 22.13 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 3.34 4.02 3.14 3.82
P-166 MH-188 MH-185 30.00 48.65 1.22 25.04 25.59 250 22.37 22.25 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 2.67 3.34 2.47 3.14
P a g e |191
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P-167 MH-87 MH-188 30.00 45.32 1.22 24.48 25.04 250 22.49 22.37 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 1.99 2.67 1.79 2.47
P-168 MH-10 MH-9 7.00 38.64 1.22 24.16 23.94 250 22.67 22.64 200 RCC NP3 0.01 0.55 0.81 0.78 24.52 0.05 1.49 1.30 1.29 1.10
P-169 MH-97 MH-10 23.00 36.24 1.22 24.71 24.16 250 22.95 22.86 200 RCC NP3 0.01 0.54 0.81 0.78 24.52 0.05 1.76 1.30 1.56 1.10
P-170 MH-183 MH-97 30.00 30.94 1.05 25.57 24.71 250 23.53 23.41 200 RCC NP3 0.01 0.50 0.78 0.78 24.52 0.04 2.04 1.30 1.84 1.10
P-171 MH-28 MH-183 30.00 27.61 1.05 26.55 25.57 250 24.39 24.27 200 RCC NP3 0.01 0.50 0.78 0.78 24.52 0.04 2.16 1.30 1.96 1.10
P-172 MH-29 MH-28 13.00 24.28 1.05 26.97 26.55 250 25.30 25.25 200 RCC NP3 0.01 0.50 0.78 0.78 24.52 0.04 1.67 1.30 1.47 1.10
P-173 MH-184 MH-29 30.00 18.40 0.72 27.96 26.97 250 25.79 25.67 200 RCC NP3 0.01 0.40 0.71 0.78 24.52 0.03 2.17 1.30 1.97 1.10
P-174 MH-95 MH-184 30.00 15.07 0.72 28.91 27.96 250 26.78 26.66 200 RCC NP3 0.01 0.40 0.71 0.78 24.52 0.03 2.13 1.30 1.93 1.10
P-175 MH-22 MH-95 21.00 11.74 0.72 29.46 28.91 250 27.69 27.61 200 RCC NP3 0.01 0.40 0.71 0.78 24.52 0.03 1.77 1.30 1.57 1.10
P-176 MH-84 MH-22 30.00 5.24 0.35 29.93 29.46 250 28.28 28.16 200 RCC NP3 0.01 0.27 0.57 0.78 24.52 0.01 1.65 1.30 1.45 1.10
P-177 MH-32 MH-84 17.00 1.90 0.35 29.99 29.93 250 28.69 28.62 200 RCC NP3 0.01 0.27 0.57 0.78 24.52 0.01 1.30 1.31 1.10 1.11
P-178 MH-25 MH-199 30.00 122.31 6.72 25.43 24.22 670 21.24 21.20 400 RCC NP3 0.01 0.69 0.84 0.76 95.09 0.07 4.19 3.02 3.79 2.62
P-179 MH-40 MH-201 30.00 136.89 7.00 21.34 20.12 300 18.82 18.72 400 RCC NP3 0.01 0.54 1.17 1.13 142.10 0.05 2.52 1.40 2.12 1.00
P-180 MH-110 MH-194 31.00 162.08 8.66 16.36 15.17 300 13.87 13.77 400 RCC NP3 0.01 0.62 1.23 1.13 142.10 0.06 2.49 1.40 2.09 1.00
P-181 MH-213 MH-195 30.00 111.01 6.49 28.28 27.15 670 21.35 21.31 400 RCC NP3 0.01 0.67 0.84 0.76 95.09 0.07 6.93 5.84 6.53 5.44
P-182 MH-195 MH-24 30.00 114.34 6.49 27.15 25.93 670 21.31 21.26 400 RCC NP3 0.01 0.67 0.84 0.76 95.09 0.07 5.84 4.67 5.44 4.27
P-183 MH-24 MH-25 12.00 115.71 6.49 25.93 25.43 670 21.26 21.24 400 RCC NP3 0.01 0.67 0.84 0.76 95.09 0.07 4.67 4.19 4.27 3.79
P-184 MH-199 MH-206 30.00 125.64 6.72 24.22 23.01 670 21.20 21.15 400 RCC NP3 0.01 0.69 0.84 0.76 95.09 0.07 3.02 1.86 2.62 1.46
P-185 MH-206 MH-40 41.00 130.24 6.72 23.01 21.34 300 1.08 20.07 19.94 400 RCC NP3 0.01 0.53 1.16 1.13 142.10 0.05 2.94 1.40 2.54 1.00
P-186 MH-201 MH-204 30.00 140.22 7.00 20.12 18.98 300 17.68 17.58 400 RCC NP3 0.01 0.54 1.17 1.13 142.10 0.05 2.44 1.40 2.04 1.00
P-187 MH-204 MH-50 35.00 144.12 7.00 18.98 17.95 300 0.92 16.66 16.55 400 RCC NP3 0.01 0.54 1.17 1.13 142.10 0.05 2.32 1.40 1.92 1.00
P-188 MH-194 MH-146 30.00 165.41 8.66 15.17 13.99 300 12.69 12.59 400 RCC NP3 0.01 0.62 1.23 1.13 142.10 0.06 2.48 1.40 2.08 1.00
P-189 MH-146 MH-147 29.00 168.68 8.66 13.99 12.77 300 1.12 11.47 11.37 400 RCC NP3 0.01 0.62 1.23 1.13 142.10 0.06 2.52 1.40 2.12 1.00
P-190 MH-147 MH-200 31.00 172.08 8.66 12.77 11.44 300 1.23 10.14 10.04 400 RCC NP3 0.01 0.62 1.23 1.13 142.10 0.06 2.63 1.40 2.23 1.00
P-191 MH-200 MH-192 30.00 175.41 8.66 11.44 10.17 300 1.17 8.87 8.77 400 RCC NP3 0.01 0.62 1.23 1.13 142.10 0.06 2.57 1.40 2.17 1.00
P-192 MH-192 MH-193 30.00 178.75 8.66 10.17 8.96 300 1.11 7.66 7.56 400 RCC NP3 0.01 0.62 1.23 1.13 142.10 0.06 2.51 1.40 2.11 1.00
P-193 MH-193 MH-47 36.00 182.73 8.66 8.96 7.56 300 1.28 6.28 6.16 400 RCC NP3 0.01 0.62 1.23 1.13 142.10 0.06 2.68 1.40 2.28 1.00
P-194 MH-80 MH-79 16.00 4.36 0.06 8.46 8.38 250 6.98 6.91 200 RCC NP3 0.01 0.11 0.34 0.78 24.52 0.00 1.48 1.47 1.28 1.27
P-195 MH-72 MH-71 15.00 1.66 0.12 8.03 8.10 250 6.83 6.77 200 RCC NP3 0.01 0.16 0.42 0.78 24.52 0.00 1.20 1.33 1.00 1.13
P-196 MH-140 MH-71 16.00 1.77 0.05 8.12 8.10 250 6.92 6.86 200 RCC NP3 0.01 0.11 0.33 0.78 24.52 0.00 1.20 1.24 1.00 1.04
P-197 MH-39 MH-38 15.00 1.66 0.15 7.99 8.06 250 6.79 6.73 200 RCC NP3 0.01 0.18 0.45 0.78 24.52 0.01 1.20 1.33 1.00 1.13
P-198 MH-127 MH-38 16.00 1.72 0.03 8.07 8.06 250 6.87 6.80 200 RCC NP3 0.01 0.08 0.27 0.78 24.52 0.00 1.20 1.26 1.00 1.06
P-199 MH-45 MH-44 11.00 1.21 0.13 7.87 7.94 250 6.67 6.63 200 RCC NP3 0.01 0.17 0.43 0.78 24.52 0.01 1.20 1.31 1.00 1.11
P-200 MH-46 MH-30 15.00 1.66 0.34 8.25 8.00 150 6.90 6.80 200 RCC NP3 0.01 0.24 0.68 1.01 31.65 0.01 1.35 1.20 1.15 1.00
P a g e |192
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P-201 MH-19 O-1 6.00 179.49 4.42 5.86 5.81 360 -0.83 -0.84 300 RCC NP3 0.01 0.71 0.96 0.85 60.23 0.07 6.69 6.65 6.39 6.35
P-202 MH-49 MH-20 8.00 0.88 0.39 5.80 5.82 245 4.60 4.57 200 RCC NP3 0.01 0.29 0.60 0.79 24.76 0.02 1.20 1.25 1.00 1.05
P-203 MH-65 MH-64 9.00 1.01 0.34 3.16 3.06 150 1.93 1.86 200 RCC NP3 0.01 0.24 0.69 1.01 31.65 0.01 1.23 1.20 1.03 1.00
P-204 MH-76 MH-75 10.00 1.14 0.66 2.82 2.89 250 1.62 1.58 200 RCC NP3 0.01 0.38 0.69 0.78 24.52 0.03 1.20 1.31 1.00 1.11
P-205 MH-79 MH-27 30.00 9.44 0.16 8.38 8.26 250 6.91 6.79 200 RCC NP3 0.01 0.19 0.46 0.78 24.52 0.01 1.47 1.47 1.27 1.27
P-206 MH-222 MH-80 23.00 2.59 0.06 8.37 8.46 250 7.07 6.98 200 RCC NP3 0.01 0.11 0.34 0.78 24.52 0.00 1.30 1.48 1.10 1.28
P-207 MH-27 MH-26 13.00 10.91 0.16 8.26 8.48 250 6.79 6.74 200 RCC NP3 0.01 0.19 0.46 0.78 24.52 0.01 1.47 1.74 1.27 1.54
P-208 MH-26 MH-155 30.00 17.60 0.27 8.48 8.23 250 6.74 6.62 200 RCC NP3 0.01 0.24 0.54 0.78 24.52 0.01 1.74 1.61 1.54 1.41
P-209 MH-155 MH-154 30.00 20.92 0.27 8.23 8.17 250 6.62 6.50 200 RCC NP3 0.01 0.24 0.54 0.78 24.52 0.01 1.61 1.67 1.41 1.47
P-210 MH-154 MH-71 33.00 24.61 0.27 8.17 8.10 250 6.50 6.37 200 RCC NP3 0.01 0.24 0.54 0.78 24.52 0.01 1.67 1.73 1.47 1.53
P-211 MH-71 MH-38 21.00 30.33 0.44 8.10 8.06 250 6.37 6.29 200 RCC NP3 0.01 0.31 0.62 0.78 24.52 0.02 1.73 1.77 1.53 1.57
P-212 MH-38 MH-179 30.00 37.05 0.62 8.06 8.00 250 6.29 6.17 200 RCC NP3 0.01 0.37 0.68 0.78 24.52 0.03 1.77 1.83 1.57 1.63
P-213 MH-179 MH-98 30.00 40.38 0.62 8.00 7.94 250 6.17 6.05 200 RCC NP3 0.01 0.37 0.68 0.78 24.52 0.03 1.83 1.89 1.63 1.69
P-214 MH-98 MH-44 23.00 42.90 0.62 7.94 7.94 250 6.05 5.95 200 RCC NP3 0.01 0.37 0.68 0.78 24.52 0.03 1.89 1.99 1.69 1.79
P-215 MH-44 MH-149 30.00 47.39 0.75 7.94 8.01 250 5.95 5.84 200 RCC NP3 0.01 0.41 0.71 0.78 24.52 0.03 1.99 2.17 1.79 1.97
P-216 MH-149 MH-31 30.00 50.75 0.75 8.01 8.03 250 5.84 5.72 200 RCC NP3 0.01 0.41 0.71 0.78 24.52 0.03 2.17 2.31 1.97 2.11
P-217 MH-31 MH-30 13.00 52.24 0.75 8.03 8.00 250 5.72 5.66 200 RCC NP3 0.01 0.41 0.71 0.78 24.52 0.03 2.31 2.34 2.11 2.14
P-218 MH-30 MH-216 30.00 57.23 1.09 8.00 7.95 250 5.66 5.54 200 RCC NP3 0.01 0.51 0.79 0.78 24.52 0.04 2.34 2.41 2.14 2.21
P-219 MH-216 MH-215 30.00 60.58 1.09 7.95 7.80 250 5.54 5.42 200 RCC NP3 0.01 0.51 0.79 0.78 24.52 0.04 2.41 2.38 2.21 2.18
P-220 MH-35 MH-34 15.00 65.60 1.09 7.47 7.45 250 5.30 5.24 200 RCC NP3 0.01 0.51 0.79 0.78 24.52 0.04 2.17 2.21 1.97 2.01
P-221 MH-215 MH-35 30.00 63.94 1.09 7.80 7.47 250 5.42 5.30 200 RCC NP3 0.01 0.51 0.79 0.78 24.52 0.04 2.38 2.17 2.18 1.97
P-222 MH-189 MH-190 30.00 70.58 1.09 7.56 6.97 250 5.18 5.06 200 RCC NP3 0.01 0.51 0.79 0.78 24.52 0.04 2.38 1.91 2.18 1.71
P-223 MH-190 MH-174 30.00 73.91 1.09 6.97 6.51 250 5.06 4.94 200 RCC NP3 0.01 0.51 0.79 0.78 24.52 0.04 1.91 1.57 1.71 1.37
P-224 MH-174 MH-175 30.00 79.62 1.09 6.51 6.20 250 4.94 4.82 200 RCC NP3 0.01 0.51 0.79 0.78 24.52 0.04 1.57 1.38 1.37 1.18
P-225 MH-175 MH-191 30.00 82.95 1.09 6.20 6.04 250 4.82 4.70 200 RCC NP3 0.01 0.51 0.79 0.78 24.52 0.04 1.38 1.34 1.18 1.14
P-226 MH-191 MH-142 30.00 89.77 1.48 6.04 5.95 250 4.70 4.58 200 RCC NP3 0.01 0.62 0.84 0.78 24.52 0.06 1.34 1.37 1.14 1.17
P-227 MH-142 MH-19 27.00 92.82 1.48 5.95 5.86 250 4.58 4.47 200 RCC NP3 0.01 0.62 0.84 0.78 24.52 0.06 1.37 1.39 1.17 1.19
P-228 MH-20 MH-19 12.00 85.97 2.93 5.82 5.86 360 -0.74 -0.78 250 RCC NP3 0.01 0.75 0.86 0.75 37.04 0.08 6.56 6.64 6.31 6.39
P-229 MH-172 MH-20 30.00 83.76 2.54 5.73 5.82 360 -0.66 -0.74 250 RCC NP3 0.01 0.67 0.84 0.75 37.04 0.07 6.39 6.56 6.14 6.31
P-230 MH-170 MH-172 30.00 80.43 2.54 5.63 5.73 360 -0.58 -0.66 250 RCC NP3 0.01 0.67 0.84 0.75 37.04 0.07 6.21 6.39 5.96 6.14
P-231 MH-171 MH-170 30.00 77.10 2.54 5.54 5.63 360 -0.49 -0.58 250 RCC NP3 0.01 0.67 0.84 0.75 37.04 0.07 6.03 6.21 5.78 5.96
P-232 MH-156 MH-171 30.00 73.77 2.54 5.51 5.54 360 -0.41 -0.49 250 RCC NP3 0.01 0.67 0.84 0.75 37.04 0.07 5.92 6.03 5.67 5.78
P-233 MH-157 MH-156 30.00 70.44 2.54 5.46 5.51 360 -0.33 -0.41 250 RCC NP3 0.01 0.67 0.84 0.75 37.04 0.07 5.79 5.92 5.54 5.67
P-234 MH-219 MH-157 30.00 67.12 2.54 5.31 5.46 360 -0.24 -0.33 250 RCC NP3 0.01 0.67 0.84 0.75 37.04 0.07 5.55 5.79 5.30 5.54
P a g e |193
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P-235 MH-218 MH-219 30.00 63.79 2.54 4.95 5.31 360 -0.16 -0.24 250 RCC NP3 0.01 0.67 0.84 0.75 37.04 0.07 5.11 5.55 4.86 5.30
P-236 MH-207 MH-218 30.00 60.44 2.54 4.55 4.95 360 -0.08 -0.16 250 RCC NP3 0.01 0.67 0.84 0.75 37.04 0.07 4.63 5.11 4.38 4.86
P-237 MH-6 MH-207 32.00 57.09 2.54 4.15 4.55 360 0.01 -0.08 250 RCC NP3 0.01 0.67 0.84 0.75 37.04 0.07 4.14 4.63 3.89 4.38
P-238 MH-182 MH-5 28.00 13.44 0.78 3.46 4.15 250 1.28 1.16 200 RCC NP3 0.01 0.42 0.72 0.78 24.52 0.03 2.18 2.99 1.98 2.79
P-239 MH-96 MH-182 30.00 9.14 0.77 2.86 3.46 250 1.40 1.28 200 RCC NP3 0.01 0.42 0.72 0.78 24.52 0.03 1.46 2.18 1.26 1.98
P-240 MH-211 MH-6 29.00 39.62 1.76 3.85 4.15 250 0.18 0.06 200 RCC NP3 0.01 0.70 0.87 0.78 24.52 0.07 3.67 4.09 3.47 3.89
P-241 MH-166 MH-211 30.00 36.43 1.76 3.70 3.85 250 0.30 0.18 200 RCC NP3 0.01 0.70 0.87 0.78 24.52 0.07 3.40 3.67 3.20 3.47
P-242 MH-167 MH-166 30.00 33.10 1.76 3.48 3.70 250 0.42 0.30 200 RCC NP3 0.01 0.70 0.87 0.78 24.52 0.07 3.06 3.40 2.86 3.20
P-243 MH-214 MH-167 30.00 29.77 1.76 3.32 3.48 250 0.54 0.42 200 RCC NP3 0.01 0.70 0.87 0.78 24.52 0.07 2.78 3.06 2.58 2.86
P-244 MH-168 MH-214 30.00 26.44 1.76 3.22 3.32 250 0.66 0.54 200 RCC NP3 0.01 0.70 0.87 0.78 24.52 0.07 2.56 2.78 2.36 2.58
P-245 MH-169 MH-168 30.00 23.11 1.76 3.15 3.22 250 0.78 0.66 200 RCC NP3 0.01 0.70 0.87 0.78 24.52 0.07 2.37 2.56 2.17 2.36
P-246 MH-196 MH-169 30.00 19.78 1.76 3.08 3.15 250 0.90 0.78 200 RCC NP3 0.01 0.70 0.87 0.78 24.52 0.07 2.18 2.37 1.98 2.17
P-247 MH-91 MH-196 30.00 16.45 1.76 3.02 3.08 250 1.02 0.90 200 RCC NP3 0.01 0.70 0.87 0.78 24.52 0.07 2.00 2.18 1.80 1.98
P-248 MH-64 MH-91 20.00 13.11 1.76 3.06 3.02 250 1.10 1.02 200 RCC NP3 0.01 0.70 0.87 0.78 24.52 0.07 1.96 2.00 1.76 1.80
P-249 MH-75 MH-64 41.00 9.84 1.42 2.89 3.06 250 1.27 1.10 200 RCC NP3 0.01 0.60 0.84 0.78 24.52 0.06 1.62 1.96 1.42 1.76
P-250 MH-220 MH-75 36.00 4.01 0.76 2.71 2.89 250 1.41 1.27 200 RCC NP3 0.01 0.41 0.72 0.78 24.52 0.03 1.30 1.62 1.10 1.42
P a g e |194
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Inlet Chamber
Screen Chamber
Wet Well
Valve Chamber
P a g e |195
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |196
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |197
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |198
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Distribution and transmission system have been efficiently managed, making unaccounted for Water
(UFW) and other water losses included.
2. Industrial Contaminated Storm Water: primarily runoffs from the industrial processing
area
The waste water generated from other areas of the petrochemical park area would be collected
and treated at the common facility.
ii.) the wet weather contaminated wastewater (primarily run off from open processing areas)
- 10% of the pollutants load for dissolved pollutants like COD, phenols, sulphides, heavy
metals etc.
- 200 % of the pollutant load for suspended pollutants primarily suspended solids
On the above basis the wastewater has been quantified and its quality accessed - the detailed
analysis will be done next stage once more clarity on industrial type.
P a g e |200
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
pH 7.5 - 9.0
VSS/ TSS % 60 55 – 65
P a g e |201
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
pH 7.5 – 8.5
P a g e |202
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Domestic Wastewater Treatment Plant is to be treated to a water quality as good as raw water. In
India at the present juncture there are no formal standards for reuse of previously used water,
however there are standards for discharge of treated wastewater into nalas / water bodies.
Domestic wastewater shall to be treated and discharged conforming to the following standards if
being discharged into inland surface waters
- pH 5.5 to 9.0
- Suspended Solids less than 30 mg/l
For water reuse generally, the guidelines laid down by US EPA would be followed. The abstract of the
same is attached as Exhibit –I. The standards are based on the use of water and recommend a water
quality as well as levels of treatment. The standards recommended for non-direct human water use
such as unrestricted landscape irrigation including toilet flushing would be secondary treatment
followed by disinfection and tertiary treatment i.e. physico chemical flocculation and filtration to
achieve the quality standards specified in below table.
Table - Domestic Wastewater Quality Standards for reuse
- pH 6.5 to 9.0
- Suspended Solids less than 2 mg/l
- Turbidity less than 2 NTU
- BOD 5 day at 20 deg C, less than 10 mg/l
- Fecal Coliforms Not detectable # /100 ml
- Residual Chlorine at least 1.0 mg/l
The standards and treatment requirement would be different if the water is to be used industrial reuse
then softening or demineralization would be required.
The domestic wastewater treatment plant shall be designed for achieving the quality.
P a g e |204
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Typical treatment scheme for Dry and Wet Weather Industrial Wastewater:
3 Gravity oil separators 3 Nos gravity separators designed for a flow of 5 mld
designed to remove oil of
free oil 150 microns (the
gravity separator shall be
designed as per guidelines
of API Manual)
4 Flow equalisation Capacity = 1 day’s flow
designed as 2 number equal capacity earthen basins
lined with impermeable membranes and with slow
speed submersible mixers for mixing the material
and with variable level oil skimmers
5 TPI / CPI Oil separators to 3 Nos TPI / Laminar oil water separators
remove oil of up to 50
microns
6 Mixed Flow Equalisation Flow equalization tank for wet & dry weather flow
Tank
P a g e |205
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |206
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
11.2 Wastewater Quality after After the Fixed film Biological treatment, the
Aerobic Stage –I wastewater will meet the treatment standards
for costal water discharge ie with a
Oil & Grease: less than 20 mg/l
BOD: less than 100 mg/l
COD: less than 250 mg/l
Phenols: less than 5 mg/l
However, as mention in chapter 4 in case standards
conforming to column 3 (a) have to be achieved i.e.
Oil & Grease: less than 10 mg/l
BOD: less than 30 mg/l
COD: less than 250 mg/l
Phenols: less than 2 mg/l
Then a second stage biological treatment will be
required
12 Aerobic Bio Reactor Stage – The SBR will have a hydraulic retention time of to
II achieve the required standards with Nitrification &
Proposal is a Sequential Bio denitrification the units in a SBR will comprise of
Reactor (SBR) with i.) Bio reactor tanks 3 numbers
automatic control ii.) Aeration with diffusers & Blowers
SBR is being selected iii.) Submersible mixer / excess sludge
because of better process recirculation and associated pumps as per
control and its ability to technology
operate at all flow The wastewater after the second stage biological
conditions and nitrification treatment will conform to the following quality
as well as denitrification can Oil & Grease: less than 10 mg/l
occur in the same reactor BOD: less than 10 mg/l
The SBR will generate high Suspended Solids less than 10 mg/l
quality of treated effluent COD: less than 250 mg/l
as compared to Phenols: less than 2 mg/l
7.9.1.12. Utilities & Residuals: Chemicals (dry & wet weather flow conditions)
- H2O2
- Polyelectrolyte
ii.) Residuals
- Slop Oil (with 80-90 % water)
Denitrification 60 % 60 – 70 % 60 – 70 % 60 – 70 %
The above typical figures are those commonly achievable for the above-mentioned technologies
without any additional tertiary treatment like chemical aided clarification chlorination or filtration. As
it is intended to reuse the treated water, we would recommend the SBR technology considering its
distinct advantages offered by the SBR. The Sequencing Batch Reactor (SBR) is an activated sludge
process designed to operate under non-steady state conditions. An SBR operates in a true batch mode
P a g e |208
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
with aeration and sludge settlement both occurring in the same tank. The major differences between
SBR and conventional continuous-flow, activated sludge system is that the SBR tank carries out the
functions of equalization aeration and sedimentation in a time sequence rather than in the
conventional space sequence of continuous-flow systems. In addition, the SBR system can be designed
with the ability to treat a wide range of influent volumes whereas the continuous system is based
upon a fixed influent flowrate. Therefore, there is a degree of flexibility associated with working in a
time rather than in a space sequence
SBRs produce sludges with good settling properties providing the influent wastewater is admitted into
the aeration in a controlled manner. Controls range from a simplified float and timer-based system
with a PLC to a PC based SCADA system using either flow proportional aeration or dissolved oxygen-
controlled aeration to reduce aeration to reduce energy consumption and enhance the selective
pressures for BOD, nutrient removal, and control of filaments microbes. An appropriately designed
SBR process is a unique combination of equipment and software. Working with automated control
reduces the number of operators required:
SBR reactors require a few equipment’s namely;
1. Inlet controls
2. Diffused aeration with power saving based on feed quantity and DO level
3. Submersible mixers & sludge recirculation, excess sludge withdrawal pumps
4. Decanter for decanting the treated water
5. PCL for controlling the sequence in a time space with interlocks to level and dissolved oxygen
All technologies will need a dewatering system to dewater the biological treatment process
residuals i.e. excess sludge.
The recommended is Mechanical sludge dewatering using a centrifuge with some stand by
sludge dewatering beds 2 numbers for use as stand by.
The electric load does not include power for pumping of raw effluent any pumped disposal
of the same
ii.) Chemicals (at average dry & wet weather flow conditions)
- Polyelectrolyte 3 to 4 Kg/day
iii.) Residuals
About 3 persons will be needed to be deployed in the operation and maintenance. This
number is with a high level of automatic controls. The level of automation needs to be
discussed with the end user
7.10.1.3. Imperviousness
The percentage of drainage area can be obtained from the records of a particular drainage basin or
City. In the absence of such data, standards can be followed.
Based on the land use, adopted coefficient of imperviousness for various land use of this project is
given in the below Table.
P a g e |210
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |211
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |212
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |213
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |214
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |215
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |216
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |217
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |218
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |219
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |220
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
7.11.2. Study of the Existing Power System around the Project Area
Petro Chemical Park and its vicinity has a well laid out system of power transmission and distribution.
Electrical network is available in near vicinity:
• 220/110kV Electric Substation is located at Brahmapuram Diesel Power Plant (i.e. BDPP) a
Distance of 0.8 km from Project site.
• 66kV Overhead transmission line (already shifted) passing besides the project boundary.
• 220/110 kV electric substation is located at FACT premises.
*BPCL has their own CPP hence the load has not been considered in load calculation for Main Receiving
Sub-station (MRSS).
For the other development area, the following load norms are considered to get the total power
demand of the Petro Chemical Park:
Table 7-50: Design Assumptions for Other Development Area
Sl. No. Description Power Requirement
1 Utility 40kVA/Acre
2 CETP 80 kVA/Acre
3 Road Calculated Load
4 Green / Open Space 1.2 kVA/Acre
5 FACT Road Calculated Load
Source: Voyants
P a g e |221
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
i. Total load of the project area is 33.36 MVA without considering BPCL Kochi Refineries (170
Acre) as it already has a substation of 220/33KV and other adjacent plots/amenities, outside
of the project area the client has informed that BPCL will arrange the supply for their load and
therefore the load has not been considered in load calculation for MRSS.
ii. The total maximum demand load to Main Receiving substation should be 110/33kV voltage
level, proposed to be constructed in plot near water works during development of 319.46
Acres project area.
iii. Considering the provision of single circuit 11kV line overhead Line from any nearby substation
is proposed only to feed temporary/construction load under electrical Substation.
iv. All industrial plots will be fed by the 11kV UG Distribution network (except plots IC-14 - 33kV)
running through the utility corridor of the road network with a tee off breaker from Ring Main
Unit and 11kV power supply as well as the stepping down circuits.
v. Stepping down to L.T supply for Utility pockets/commercial/facility use will be made available
by 11/0.415kV Transformer near the load Centre of suitable ratings as required.
vi. Reticulation of emergency power supply is economically infeasible for 100% power back-up
for the all industrial areas. Our recommendation is that emergency power shall be only for
street lighting, utility areas etc. Because all the commercial & industrial units have own
standby generator for emergency power requirement of individual. Meanwhile, in case of
100% central AMF (Automatic mains failure) standby power supply tariff problem is also an
issue. Moreover, the KSEB is responsible as O&M for all electrical infrastructures as developed
and handed over. The O&M of generator sets may not viable with them. So, 100% power back
up for the complete industrial area is not recommended.
vii. Ducting network will be proposed for laying of Telecom & Data network in both side/ either
side of the utility corridor.
viii. Provision of Rooftop Photovoltaic system shall be proposed as per the availability of space
upon the roof of buildings and other available space; to meet partial power demand of the
development area. Solar Panel & inverter cum rectifier unit will be placed along with the LT
panel. It will be mandatory for every plot holder.
ix. Energy efficient smart LED lighting will be considering for entire petrochemical park and all
outdoor lighting system shall be connected to automatic controls. Automatic controls can be
either time based or photo sensor based.
All required detailed engineering drawings, cost estimates and bill of quantities (BOQ’s) w.r.t
electrical MV distribution system, external illumination system, data and telecommunication
system has been enclosed as Annexure 9 and Annexure 10.
P a g e |222
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
For proper distribution and working of electrical system, the Site is being divided in 2 zones,
Each zone has its own Zonal Substation (ZSS). The Load distribution for each zone is been summed up
in following table: -
Table 7-53: Zonal Substation Details
Sl. Zonal Max. Demand Load
Network Details
No. Substation (MVA)
From MRSS 2nos. 33kV I/C through UG cable & 1nos
1 ZSS 1 13.28
33kV UG cable between ZSS-1 & ZSS-2
P a g e |223
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
For Zonal Division kindly refer Drawing No. VSPL/KINFRA/1718_064/ED/MV/01 under title “Zonal
Distribution Layout” as enclosed.
Table 7-54: Main Receiving Station Details
Main Receiving Max. Demand
Sl. No. Network Details
Switching Station Load (MVA)
1 MRSS (2X16MVA, 33.36 Option-1, 110kV UG Cable tapping from 110kV
110/33kV) FACT Line from Brahamapuram Substation.
OR
Option-2, 110kV OH Line with UG Cable tapping
from 110kV FACT Line from Brahamapuram
Substation.
Source: Voyants
There are several ways to design any electrical supply network, but only one of these alternatives will
give an optimum solution considering the above factors and practicability of implementation of
theoretical design. It is extremely complex to determine the overall economies, as many variables are
involved. So Complete Electrical system is proposed and decided to be as under-ground.
P a g e |224
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
documents/drawings will have to be approved from KSEB / approval agency before execution to avoid
any problem at time of commissioning & handing over etc.
7.11.5.3. MV Reticulation
19/33 kV (E) will be 3-core Aluminum Armoured TR-XLPE type in accordance with IEC 60502-2. The
MV cable will be installed underground at a minimum depth of 1050mm below ground level. The cable
will terminate at MRSS & ZSS. The cables will be run through the RCC Masonry Cable Trenches.
6.35/11kV (E) will be 3-core Aluminum Armoured XLPE type in accordance with IEC 60502-2. The MV
cable will be installed underground at a minimum depth of 900mm below ground level. The cable will
terminate at each Ring main unit. The Ring main unit is proposed with 3/4nos. Outgoings as required
with SF6/Vacuum circuit breaker arrangement for Tee-Off. The cable will be laid underground at a
minimum level of 900mm below ground level in tier formation according to the voltage level. The
cables will be run through the RCC Masonry Cable Trenches.
Drawing showing the MV Power distribution is enclosed as drawing no.
VSPL/KINFRA/1718_064/ED/MV/04 under title “33 & 11kV UNDER GROUND POWER DISTRIBUTION
LAYOUT”.
The typical cross section of RCC Masonry cable trenches will be as follows:
P a g e |226
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
7.11.5.4. LV Reticulation
LV cable will be buried at a minimum depth of 750mm below ground and will connect the distribution
transformer as per the L.T Load requirement. LV cables shall be installed a minimum of 300 mm apart
from other 11kV cables.
P a g e |227
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
2 Pole Mounting pole Double arm pole on the Single arm pole on Single arm pole on
detail median of the road. both side of the road. one side of the road.
3 Lighting Fixture 2x60W, LED lamp with 2x45W, LED lamp with 60W, LED lamp with
fixture of IP-65. fixture of IP-65. fixture of IP-65.
P a g e |228
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
communication power, no electricity bills; DC power supply and control; It has the advantages of good
stability, long life, high luminous efficiency, simple installation and maintenance, high safety
performance, energy-saving and environmental protection, economical and practical. It can be widely
used in urban main, secondary road, residential area, factory, tourist attraction, parking lot and other
places. Product parts lighting rod structure: GI lamp pole and bracket, surface spray treatment, the
panel connection adopts special anti-theft stainless steel screws.
Solar street lamp principle of work: during the day under the control of the intelligent controller of
solar energy street lamp, solar panels after the illuminate of sunshine, absorb the solar energy light
into electrical energy, solar battery components to the battery charge during the day, night batteries
to provide electricity to power a LED light source, lighting functions. The dc controller ensures that the
battery pack is not damaged by over-charging or over-discharge, and also has the functions of light
control, time control, temperature compensation and lightning protection and anti-polarity
protection.
Drawing showing the Road Lighting arrangement is enclosed as drawing no.
VSPL/KINFRA/1718_064/ED/RL/01 under title “Proposed Road Lighting Layout”.
P a g e |231
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |232
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |233
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |234
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
A gas appliance should not be installed in premises without testing the connection for gas tightness,
ascertaining that all the gas safety controls are in proper working order, ensuring that there is proper
ventilation and the operating pressure is as recommended by the manufacturer.
Table 7-61: Natural Gas requirement in Tons/yr @ 100% of the fuel on Natural Gas for Petro Chemical Park
Products 2019 2020 2021 2022 2023 2024
Intermediate Chemicals 62400 114400 145600 145600 176800 197600
Specialty Chemicals 6400 16000 21120 21120 25600 25600
Pharmaceutical APIs 960 1920 2880 2880 2880 2880
End Products Paints/ Adhesives /
9600 19200 24960 24960 25160 25360
Inks / Polyurethane etc.
Total 79360 151520 194560 194560 230440 251440
Table 7-62: Natural Gas requirement in Tons/yr @ 50% of the fuel on Natural Gas for Petro Chemical Park
Products 2019 2020 2021 2022 2023 2024
Intermediate Chemicals 31200 57200 72800 72800 88400 98800
Specialty Chemicals 3200 8000 10560 10560 12800 12800
Pharmaceutical APIs 480 960 1440 1440 1440 1440
End Products Paints/ Adhesives /
4800 9600 12480 12480 12580 12680
Inks / Polyurethane etc.
Total 39680 75760 97280 97280 115220 125720
Source: Market Research and Consultant Analysis.
P a g e |235
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |236
Engineering Design
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
C. Bare Land Acquisition cost per acre (A/B) Rs. crore 2.03
P a g e |237
Financial Estimates & Cost Projection’s
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The yield from the parcel of land puts lot of pressure on the cost of land, which alone works out to
around Rs. 3.77 Crores per acre of sellable / processing area.
The basic cost includes development of the parcel of land (319.46 acres) into a gated enclave
effectively designed with graded plots with effective security fencing, internal roads with street lights,
well designed drains, entrance gates and an external connecting road with the city of Cochin.
Table 8-3: Cost of Basic Development elements
Landscaping 0.20
b) Essential Services
The park will have three distinct services to support the manufacturing units namely power supply &
distribution, Water Supply and distribution, Central Effluent treatment plant with treated waste water
recycling network to the units. Each of these services will supply their services to meet each diverse
manufacturing unit’s needs. The estimated cost will be Rs.157.83 crores.
Water Supply
i. Potable water system 23.57
Wastewater collection and treatment plant, CETP's etc.
i. Sewerage system 42.81
ii. CETP of required capacity 25.35
iii. Recycle Water 4.93
Power Supply
i. Power supply (including sub-stations) 61.17
Total Cost of Essential Service 157.83
In addition to these services plots are made available for investors to provide shared services including
Trucking, Warehouse & Logistics, Specialised process utilities, Technical Services if the demand from
the tenants justifies such services.
c) Overall Costs
The overall cost of Development including all contingency expenses will be around Rs. 332.46 Crores.
The development cost per sellable land of 189 acres will be Rs. 1.76 Crores.
Table 8-5: Overall Development Cost
Development Elements Rs. Crores
P a g e |239
Financial Estimates & Cost Projection’s
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The total cost of sellable land works out to Rs. 5.19 crores.
The Goods & Services Tax (GST) applicable on Plant & Machinery for utilities (18% for power & Water
P&M and 5% on CETP P&M) and on developing physical infrastructure (GST as applicable)
implication has not been factored, as it will be set off from the GST earned in operations through
Lease Premium & Lease rentals, water, & Power distribution, Effluent treatment and O&M services.
The benefit is passed on to the Tenants.
d) Development Phasing
The development will have to be phased based on the prospective investors interest. The cost of
development will be phased keeping the time of procession of the plot and the actual time of their
coming into production. The development cost distribution is detailed:
Table 8-6: Development Cost Phasing (In Rs. Crore)
Years >>> 0 1 2 3 4 5 6 7 Total
Preliminary &
Preoperative 2.00 2.00
Cost
Basic
60.38 64.71 9.76 11.06 6.33 0 0 152.24
Development
Water supply
0 7.07 9.43 7.07 0 23.57
CETP
0 14.61 14.61 10.96 10.96 10.97 10.98 73.09
Power supply
21.41 21.41 18.35 61.17
Contingency (5%)
4.09 5.39 2.61 1.45 0.86 0.55 0.55 15.50
PMC (1.5%)
1.29 1.70 0.82 0.46 0.27 0.17 0.18 4.89
Total 2.00 87.66 115.42 55.66 31.09 18.48 11.68 11.68 332.46
P a g e |240
Financial Estimates & Cost Projection’s
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
9. Revenue Streams
9.1. Revenues & Expenses
9.1.1. Revenues
i. Sale to BPCL
The KINFRA Petrochemical Park envisaged a considerable parcel of land to be reserved for BPCL
activities, which will feed its feedstock to the downstream manufacturers in the Park.
The park planned earmarked a large parcel of land in the middle flanked by prospective downstream
units and effectively connected with external road developed for the park. BPCL activity will be the
first tenant for the park having a plot of 170 Acres. KINFRA will sell the land to BPCL at a virtual cost
price. A total of Rs. 400 Crores will be the cost of the land.
Table 9-1: Cost to BPCL
A. Total plot size of BPCL Acres 170
B. Add: Apportioned area of External connectivity area for BPCL @36% Acres 5.52
(Acres)
C. Total land to BPCL Acres 175.52
The power will be obtained from Kerala State Electricity Board (KSEB) from their 110 KV line at a cost
of Rs. 5.10 per unit and a charge of Rs. 290 per KVA collected Load. KINFRA will be a licenced
distributor to KSEB. Then will distribute to all the tenants according to their needs. On the basis of the
infrastructure create for the distribution a fee of Rs. 0.70 will be levied per unit of consumption. The
power cost per unit will be Rs. 5.80.
Water
P a g e |241
Revenue Streams
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The potable water will be obtained from the same source of BPCL at a cost of Rs. 40 per Kilolitre.
KINFRA will store and distribute water to its tenants. The water works will also distribute recycled
wastewater received from the Central Effluent treatment Plant. Considering the cost of infrastructure
and the cost of Recycled wastewater Rs. 70 per kilolitre will be levied.
Waste Water Treatment and Recycling of Water
A Central effluent Treatment plant (CETP) with zero liquid discharge technology (ZLD) will be set up as
per the needs of environment board. The wastewater / sludge will be pumped in from each of tenants
and treated. The dry sludge will be disposed of in the specified landfill near the park and water
retrieved (near 90%) will be distributed back to the tenants to meet their process needs.
The cost of managing and processing costs are between Rs. 150 to Rs. 200. Considering the cost of
infrastructure Rs. 110 per kilolitre will be levied.
iii. Operations & Maintenance Fee
This cost is applicable for maintaining the park estate including the roads (Both Internal & External),
the park terrain, gardens, Administration and & amenities. On the basis of the incurred towards O&M
a flat Rs. 4.5 Lakhs per acre per year will be levied to the tenants. This rate is comparable to other
parks across the country especially the petrochemical park in Mangalore.
iv. Plot Pricing
The bare cost of the KINFRA parkland is around Rs. 5.2 Crore, which under any stretch is far removed
from the cost of industrial land across India including those designed and developed for petrochemical
and pharmaceutical industry. The prevailing prices are discussed in the marketing section of this
report.
Kerala is not a natural choice for any investor to set up petrochemical and pharmaceutical industry
compared to state of Gujarat, Maharashtra, Telangana (Hyderabad), which are hub of such activities.
Besides Kerala has a very small local demand to cater to. Most of the demand of petrochemical
industry is in Gujarat and Maharashtra. Kerala is also perceived not very industry friendly and the level
of industrialisation is also very low.
Kerala suffers from several negative factors which is to a large extent is offset by BPCL project
promising availability of feedstock which is normally and available and their derivatives are mostly
imported. The situation holds a promise but investors and more so with the low investment climate
prevailing in India the land price will be a critical issue. The park will have to provide more than
competitive pricing.
The land absorption considered based on market assessment as discussed earlier to arrive at the
revenues are provided below table.
Table 9-2: Land Absorption (Acres)
Years 1 2 3 4 5
Total (Acres) 65 68 14 27 15
The success of this project will have a considerable economic impact to the state in terms of industrial
turnover, high investment, generation of GST and employment both direct and indirect.
P a g e |242
Revenue Streams
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The following pricing is proposed to ensure low component of land cost (6.5%) in investment and
gradually pay for the land use with their earnings (.2% of turnover).
The land will be made available in the park on a lease renewable every 30 years. The land
ownership will be with KINFRA. The total land for lease will be 189 acres.
A onetime Rs. 1.5 Crore per acre will be levied as lease premium.
Every year a lease rental equivalent to 5% of the cost of the land will be payable annually. (Rs.
30 Lakh per acre on a developed land price of Rs. 5.50 Crore).
The investor will not feel the impact of high land prices from this structure.
9.1.2. Expenses
The expenses will be in terms of Operations & Maintenance of the utilities and estate, the depreciation
and income tax component.
i. Market Development
As discussed in the market study section of the report a sustained intensive and extensive campaign
will have to be launched for next 5 years. An amount of 80 lakhs annually will have to be the budget
for the campaign annually.
ii. O&M expenses
A 5% is levied on all utility infrastructure (Power, Water and effluent treatment) and 3% on roads,
structures (Gates & Boundary Wall/Fencing), Administration Building and Estate on the Capital Cost
annually.
iii. Depreciation
40% depreciation has been considered on written down value for all utilities, roads, building and
structures as applicable under the law.
iv. Income Tax
A flat tax of 25% is levied along with a cess component of 15% amounting to 28.75%.
v. Escalation
A 6% escalation is likely both on the revenue as well on the expense side. This does not effect while
assessing the Internal Rate of Return and Net present value.
P a g e |243
Revenue Streams
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Contingency (5%) 4 5 3 1 1 1 1
PMC (1.5%) 1 2 1 0 0 0 0
Table 9-4: Working Results (Rs. Crore- Rounded off to nearest Integer)
Years 0 1 2 3 4 5 6 7 8 9 10 11 12
REVENUES
BPCL Land
Transaction 400
Power
Distribution 2 8 15 19 24 26 27 28 28 28
Cost
Water
Distribution 0 3 5 6 8 9 9 9 9 9
O&M 3 6 7 8 9 9 9 9 9 9 9 9
Total Revenue 400 117 141 67 106 105 90 98 104 106 107 107 107
EXPENSES
Marketing 1 1 1 1 1 1 0.80 0.80 0.80 0.80 0.8
Utility
Maintenance 0 0 1 3 4 5 5 6 6 6 6 6
Estate
Maintenance 0 0 3 5 6 6 7 7 7 7 7 7
Contingency
(5%) 0 0 0 0 1 1 1 1 1 1 1 1
Total Expenses 1 1 5 9 11 13 13 13 14 14 14 14 14
Profit Before
Depreciation 399 116 137 58 95 92 77 85 90 92 93 94 94
LESS:
Depreciation 0 35 67 63 50 37 27 21 13 8 5 3 2
P a g e |244
Revenue Streams
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Profit before
Tax 0 81 69 -5 50 55 50 64 78 85 89 91 92
Tax 0 23 20 0 14 16 14 19 22 24 26 26 27
Profit After Tax 0 58 49 -5 36 39 36 46 55 60 63 65 66
Cash
Generation 399 93 117 58 86 76 63 67 68 68 68 68 67
Cumulative
Cash 399 492 608 666 752 828 891 957 1025 1093 1161 1229 1296
Generation
Table 9-5: Cash Flow (Rs. Crore- Rounded off to nearest Integer)
Years >>
0 1 2 3 4 5 6 7 8 9 10 11 12 13
Opening Cash
Balance 0 397 402 403 405 460 517 568 624 692 759 827 895 962
BPCL Land
Transaction 400
Internal accruals
from Operations 0 93 117 58 86 76 63 67 68 68 68 68 67 67
Less; Cost of
Development 1 88 115 56 31 18 12 12
Less: Preliminary
& Preoperative 2
Cost
Closing Cash
balance 397 402 403 405 460 517 568 624 692 759 827 895 962 1029
P a g e |245
Revenue Streams
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
b. Benefits
The benefits in Rupee equivalent is summarised:
P a g e |246
Cost Benefit Analysis & Investment Criteria
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
INTANGIBLE BENEFITS
12% 10% 8% 6%
P a g e |247
Cost Benefit Analysis & Investment Criteria
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Table 10-4: KINFRA Petrochemical Park: CBA Economic Benefit (Rs. Crore)
Costs & Benefits Discounting rate (%)
12% 10% 8% 6%
BENEFITS
COSTS
948 954 959 965
e. Project Risks
The project has very minimal risks. The development cost will be staggered depending on the response
from investors to set up the projects in the park. The BPCL with their plans will effectively bring to the
table the feedstock (Presently being met through imports) for consumption at the park. As the
Feedstock made available will be more than competitive with no real logistics cost which is otherwise
incurred in imports one does not foresee any issues in investors setting up their respective
manufacturing facility. The probabilistic possibilities creating some level of risk in the project along
with its mitigation is provided in table 10-5. As can be inferred the project risks can be effectively
mitigated.
Table 10-5: Risk Probabilities and its mitigation
Probable Risk Probability Mitigation
1. The BPCL Plant commissioning / 10% Can at best effect the land absorption.
production is delayed / not up to required
capacity
2. There is a further delay in development of 20% This can affect the marketing pitch for
the park land / investors.
3. The BPCL may not be in a position to 30% This could be a problem. However, the
provide the feedstock due their requirement in the park of feedstock is
commitment to units outside the park in only a 30-35% of the feedstock envisaged
India. to be produced by BPCL
4. The investors may take more time to 30% The development will be staggered in line
come in (Low level / delayed land with the response to land demand.
absorption)
P a g e |248
Cost Benefit Analysis & Investment Criteria
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
11.2. Scoping
The Ministry of Environment, Forest and Climate Change (MoEF&CC), Govt. of India through its
notification of 14th September 2006 and its subsequent amendments under the Environmental
Protection Act, 1986, classifies the projects under category – Cat.7 (c). The details of the categories
mentioned in the below given table are as follows:
Table 11-1: The Details of the Categories
Project or Activity Category with Threshold Limit Conditions if any
A B
7 (c) Industrial estates / If at least one industry Industrial estates Special condition shall
Parks / complexes in the proposed housing at least one apply
/ areas, export industrial estate falls Category B industry and
processing Zones under the Category A, area <500 ha. Note:
(EPZs), Special entire industrial area Industrial Estate of area
Economic Zones shall be treated as below 500 ha. and not
(SEZs), Biotech Category A, Industrial estates of housing any industry of
Parks, Leather irrespective of the area. area> 500 ha. and not category A or B does
Complexes. housing any industry not require clearance.
Industrial estates with belonging to Category A
area greater than 500 or B
ha. and housing at least
one Category B
industry.
assessment, environment management plan will be formulated. Whole study will be summarized and
concluded with some recommendations to attain sustainable development.
The public hearing as required under the Notification will be conducted as per the guidance of PCB in
line with EIA notification 2006 and as prescribed in TOR. The EIA report will be upgraded after public
hearing incorporating concerns of public raised at the time of Public Hearing.
Environmental Study has been carried out within 10 km radius of the project area over a period of
March - May 2018 (summer season).
Project Description This chapter elaborates the project salient features, location,
2. methods of estimation of reserves, manpower requirement, project
implementation schedule, proposed schedule for implementation,
P a g e |250
Environmental & Sustainability Aspects
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Description of the The chapter defines Physiography, topography, drainage, land use
Baseline geology and hydrology of study area, study period, concept and
Environmental methodology adopted for baseline data collection, establishment of
3. Components baseline for valued environmental components covering physio-
chemical, biological and Socio-economic components and base maps
of environmental components.
Anticipated Assessment of anticipated environmental impacts due to
Environmental development activities. Suggesting measures for mitigating those
4. Impacts & impacts are the main core of this chapter.
Mitigation Measures
Alternative General information of alternative technology, alternate site, details
5. Technology of building materials, energy conservation, and transportation.
15mn ton through FCC route together with setting up a large petrochemical complex. The products
and by products from proposed petrochemical complex and refinery will offer the feedstock for
setting up various downstream petrochemical units in the region that will spur the economic
development of the entire area.
P a g e |252
Environmental & Sustainability Aspects
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |253
Environmental & Sustainability Aspects
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
project has been formulated and the same will be implemented. The effective implementation and
close supervision of the environmental management to mitigate the environmental impacts, which
are likely to arise due to the construction and operation phases of the project could be achieved
through a suitable institutional mechanism. Following table presents the environmental monitoring
framework for the project where parameters, frequency and no. of samples for the environmental
monitoring are suggested.
Table 11-5: Environmental Monitoring Plan
S. No. Attribute Parameters Frequency No. of
Samples
1. Ambient Air SO2 μg/m3, Six Monthly 10
3
Quality NOx μg/ m ,
PM10 μg/ m3,
PM2.5 μg/ m3,
Lead μg/ m3,
CO mg/ m3,
Ammonia μg/m3,
O3, Benzene (C6H6), Benzo-Pyrene
(BaP), Arsenic (As), Nickel (Ni),
Hydrocarbons (HC), Volatile
Organic Carbons (VOCs)
2. Noise Quality Leq Noise Level in dB (A), 24 Hrs Six Monthly 10
(Day and Night)
3. Water Quality
Ground water As per IS: 10500:2012 & its Six Monthly 2-5
& Surface amendments / IS: 3025, 1632 /
Water quality APHA
P a g e |256
Environmental & Sustainability Aspects
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
An institutional framework with clear assignment of roles and responsibilities will be broadly prepared
with which location of Emergency Control Centre and Assembly Points will be identified.
Communication system and alarm systems for effective communication in the event of a disaster are
broadly identified. DMP for natural hazards such as cyclones was broadly prepared. Mutual aid
scheme, composition of District Level Emergency Committee and aspects relating to community
involvement for dealing with off-site disasters were broadly prepared.
P a g e |257
Environmental & Sustainability Aspects
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |258
Environmental & Sustainability Aspects
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The proposed Petrochemical Park is located within the existing Industrial Estate limit and all the land
used for the provision of facilities belongs to the KINFRA. Moreover, present road and railway
connectivity will be augmented to support new development, few new internal roads will be
developed.
The anticipated impact during construction of the project are soil contamination that may be caused
from roadside litter, oil spillage from machinery, sanitation and waste disposal, spillage of hazardous
chemicals etc. Any soil contamination will also impact river water as the site is located near the river
Chitrapuzha.
Mitigation Measures
Considering the activities and their impact on land and soil the following mitigation measures are
discussed below.
All the waste has to be collected and nothing to be dumped on land or water.
The contractor will be held responsible to clean all debris before leaving the construction site
and also, to make necessary arrangements with scrap dealers to sell off the waste scraps.
The waste from labor camps and administrative activities during construction will all be
disposed of through municipal facility.
Impacts on water resource are two-fold, one increased water demand and disposal of wastewater.
Additional water demand due to this project is anticipated towards construction activities and drinking
water needs for labors and employees. At present water is sourced from KINFRA Export Promotion
Industrial Park (KEPIP) and the same source is planned to be used to supply for the Petrochemical Park
also. KEPIP is 100% subsidiary of KINFRA. It is generally assumed that 80% of the domestic
P a g e |260
Risk Assessment & Mitigation Measures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
consumption is generated as sewage, which if discharged untreated will act as a source of water
pollution. Wastewater generated will be treated in STP.
Other sources of contamination are accidental disposal of construction debris and spillage of oil and
grease from the vehicles and construction machineries.
The construction activities have potential influence on the water resources within the activity area.
Natural drainage may be impacted due to the provision of the road network and hence it needs careful
planning.
Mitigation Measures
In order to mitigate negative impacts on water that are expected from the project, the following
measures will be implemented:
Chitrapuzha river is on the west side of the project boundary. Proper greenbelt will be
developed along the water body as per the guidelines. The development shall be carried out
in such a way to ensure proper drainage by providing surface drainage systems including
storm water network, etc.
The embankments of any surface water bodies will be raised to prevent contamination from
run-off.
Workers shall be provided proper sanitation facilities including mobile toilets vans.
All the wastewater will be collected and treated using soak pits and sludge from soak pits will
be cleaned.
The construction site and camp will be provided with temporary drainage to avoid water
stagnation/ ponding near work and camp sites to curb vector borne diseases;
Fuel/ oil storage will be sited away from any waterbodies; leakage of oil wastes from oil
storage and vehicles shall be avoided in order to prevent potential contamination of streams
or ground water;
Surface runoff from machine operations, oil handling areas/devices will be treated for oil
separation before being discharged into the river;
Waste Oil/ grease/ lubricants are categorized by MoEF&CC as Hazardous Wastes. All such
waste will be collected and stored at a protected place and sold to a vendor authorized by
Kerala PCB or MoEF&CC.
No construction activity will be undertaken during monsoon period.
Air emissions due to construction activities, fuel burning, vehicle movement, machinery and DG sets
are the most significant sources of air pollution during construction phase.
Air pollution can cause significant impacts on the environment, and subsequently on humans, animals,
vegetation and materials. It primarily affects the respiratory, circulatory and olfactory systems in
humans. In most cases, air pollution aggravates pre-existing diseases or degrades health status,
making people more susceptible to other infections or the development of chronic respiratory and
cardiovascular diseases.
P a g e |261
Risk Assessment & Mitigation Measures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Mitigation Measures
Power supply from State Electricity Board shall be sourced for electrically operated
construction machinery/equipment.
The use of DG set would be limited to backup during power failure;
Dust suppression systems (water spray) will be used near the earth handling sites, asphalt
mixing sites and other excavation areas to reduce the wind-blown fugitive dust emissions.
Earth moving equipment, such as bulldozer with a grader blade and ripper will be used for
excavation work.
Excess idling of construction equipment as well as vehicles to be prohibited.
The labors shall be provided with clean fuel so that they neither cut the trees for fuel wood
nor burn firewood.
Vehicles and construction equipment will be fitted with internal devices i.e. catalytic
converters to reduce CO and HC emissions.
All stationary machines/ DG sets / construction equipment emitting the pollutants will be
inspected weekly for maintenance and shall be fitted with exhaust pollution control devices;
Vehicles and machineries will be regularly maintained to conform to the emission standards
stipulated under Environment (Protection), Rules 1986.
“No Objection Certificate (NoC)” for setting up of crusher, hot-mix plant and DGs will be
obtained from Kerala Pollution Control Board;
Ensure that all vehicles must possess Pollution under Control (PUC) Certificate and shall be
renewed accordingly;
All the roads in the vicinity of Project site and the roads connecting quarry sites to construction
sites will be paved to minimize the fugitive emissions.
If any of the road stretches are not paved due to some reason, then adequate arrangements
will be made to spray water on such stretches of the road.
During construction phase, there could be high noise levels due to operation of various construction
equipment and increased number of vehicles supplying man and material to the site. It is known that
continuous exposure to high noise levels above 90 dBA affects the hearing acuity of the
workers/operators or residents and hence, require mitigation planning.
Mitigation Measures
The construction works will be carried out during the day time. The work hours should be
limited depending on convenience of the local people.
Noise levels of machineries used shall conform to relevant standards prescribed in
Environment (Protection) Rules, 1986. Workers shall not be exposed to noise level more than
permitted for industrial premises, i.e. 90 dBA (Leq) for 8 hours; Exposure of workers near the
high noise levels areas can be minimized. This can be achieved by job rotation/automation,
use of ear plugs, etc.
Labor camps shall be established away from high noise generating area. Workers exposed to
high noise level shall use ear plugs or ear muffs;
Regular maintenance of all vehicles and machinery shall be made mandatory to keep noise
under check;
P a g e |262
Risk Assessment & Mitigation Measures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Any ‘High Noise Area’ shall be posted with warning signs and will have restricted access.
Noise from air compressors could be reduced by fitting exhaust mufflers and intake mufflers.
Chassis and engine structural vibration noise can be dealt with by isolating the engine from
the chassis and by covering various sections of the engines.
Crushers, if any, will be fitted with rock lining to act as natural sound insulator during the
crushing process;
Noise levels from the construction equipment can be reduced by fitting of exhaust mufflers
and the provision of damping on the steel tool.
It is proposed to develop a greenbelt within the project premises including along the road
stretches.
Noise from the DG set should be controlled by providing an acoustic enclosure or by treating
the enclosure acoustically.
Regular monitoring and maintenance of all the equipment and DG sets shall be taken up to
keep a note on noise levels and to take corrective actions.
E) Impacts on Ecology
The land is an industrial area of approximates 500 acres original with FACT, further allocated to FRBL,
KEIL, M/s. BPCL Petroleum Complex and KINFRA Petrochemical Park 500 acres.
Area need to be cleared for construction purpose as due to heavy rain in this zone, growth of wild
plant is very high.
The major drainage features in the area are Chithra Puzha River which flows in close proximity to the
western boundary of the site and Ambalamedu Lake in the eastern side of the site. There natural
drainage of the site is from east to west towards the Chithra Puzha River. So, any run off containing
any hazardous material will flow to these water bodies affecting the aquatic life.
Mitigation Measures
All care shall be taken that trees shall be protected as far as possible while site clearing and
infrastructure development.
In consultation with Forest Department, more than twice number of the trees will be planted
in lieu of trees removed.
No construction activity will be allowed during the monsoon season so as to avoid breeding
period of fishes.
Care will be taken to avoid any disturbance to the nearby local habitants w.r.t to traffic, noise or air
pollution due to construction activities. Local laborer’s will be hired for construction activities
generating employment opportunity in the area.
The most likely impacts from the operation phase of the project will be on the Chithra Puzha River
water, primarily due to (a) effluent from stack yard; (b) oily wastes such as bilge water, washing water,
P a g e |263
Risk Assessment & Mitigation Measures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
lubricant oil and other residues from vessels and machineries (c) sewage; (d) cargo spillage. All these
may lead to odor and degradation of water quality.
Mitigation Measures
A sewage treatment plant will be provided to treat all the waste that is expected to be
generated due to project operations.
Effluent generated from stack yard will be treated in a settling tank. The sludge produced will
be mainly dust, which will be dried on sludge drying beds.
The effluent from workshops, oil storage, etc. will contain oil and grease particles which shall
be treated in an oil skimmer. The collected oily matter is stored in cans and disposed of
through authorized waster recycler.
Strom water drain shall be made to collect run off from rain but care shall be taken that it is
not contaminated.
Vehicle traffic to service cargo at the Petrochemical Park, emissions from process units, cargo handling
and fuel burning at labor camps are the major source of air pollution during operation phase.
Mitigation Measures
All the process unit need to adopt air pollution control devices as per the guidelines of
respective processes.
All vehicles shall have a valid PUC certificate and regular maintenance shall be mandated.
All the roads in the vicinity of the project site will be paved or black topped to minimize the
entrainment of fugitive emissions.
If any of the road stretches cannot be blacktopped or paved due to some reason or the other,
then adequate arrangements will be made to spray water on such stretches of the road.
For wind generated dust, a windshield with a wire mesh fencing with fast growing creepers
up to a height of 10 m around the stockyard shall be installed.
In addition to all the above measures, a 10m wide greenbelt will be developed for dust
arresting proposes.
No unauthorized labor settlement shall be allowed in the vicinity of the project.
Noise due to equipment and vehicles and human activities will be chief sources. Noise from vehicles
will be attributed to the engine, vibration, friction between tyres and the road, and horns. Increased
levels of noise depend upon volume of traffic, road condition, vehicle condition, vehicle speed, and
congestion of traffic and the distance of the receptor from the source.
Mitigation Measures
Noise levels of process equipment used shall conform to relevant standards prescribed in
Environment (Protection) Rules, 1986. Workers shall not be exposed to noise level more than
permitted for industrial premises, i.e. 90 dBA (Leq) for 8 hours;
Exposure of workers near the high noise levels areas can be minimized. This can be achieved
by job rotation/automation, use of ear plugs, etc.
P a g e |264
Risk Assessment & Mitigation Measures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Workers exposed to high noise level shall use ear plugs or ear muffs;
Regular maintenance of all vehicles and machinery shall be made mandatory to keep noise
under check;
Any ‘High Noise Area’ shall be posted with warning signs and will have restricted access.
It is proposed to develop a greenbelt within the premises including along the road stretches.
Noise from the DG set should be controlled by providing an acoustic enclosure or by treating
the enclosure acoustically.
Regular monitoring and maintenance of all the equipment and DG sets shall be taken up to
keep a note on noise levels and to take corrective actions.
D) Impact on Ecology
Once Petrochemical Park is in operation, major impacts are anticipated from industrial processes,
cargo handling and wastewater discharge.
Release of heavy metals and other chemicals and compounds from the spilled cargo in long run may
cause bioaccumulation of these substances in sediment as well as aquatic flora and fauna.
The constituents of oil are toxic to aquatic life and release of oil contents on to water will result in
formation of a shining film on the surface of water which prevents dissolution of oxygen across the
surface of water. Moreover, oil gets accumulated on the body of the small species of fish or
invertebrates and coat feathers and fur, reducing birds' and mammals' ability to maintain their body
temperatures.
Once the project is operation, a green belt will be developed around the project site and river
shoreline.
Mitigation Measures
The following actions shall be taken to avoid any major damage due to oil spill:
Booms, skimmers and dispersant inventory shall be maintained to contain spill at the project
location.
All recovered oily material shall be disposed-off properly. Either to waste oil dealers or
dumped in secured landfill sites.
Run off from the cargo handling area will be treated in ETP before discharging to water body.
It is envisaged that during operation stage impacts are mostly positive in nature. Once the project is
operational, the project has several benefits to the immediate affected community and society in
large.
The following positive impacts envisaged from the project:
Employment generation for locals
Development of road connectivity
Business opportunity due to ware-housing, cargo handling (stevedoring), transport
requirements. In addition, under Corporate Social Responsibility initiatives will be undertaken
P a g e |265
Risk Assessment & Mitigation Measures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
in consultation with the local administration and local population to benefit local population
and environment.
1. The BPCL Plant commissioning / 10% Can at best effect the land absorption.
production is delayed / not up to required
capacity
2. There is a further delay in development of 20% This can affect the marketing pitch for
the park land / investors.
3. The BPCL may not be in a position to 30% This could be a problem. However, the
provide the feedstock due their requirement in the park of feedstock is
commitment to units outside the park in only a 30-35% of the feedstock envisaged
India. to be produced by BPCL
4. The investors may take more time to 30% The development will be staggered in line
come in (Low level / delayed land with the response to land demand.
absorption)
12.3. Conclusion
The project site faces no significant environmental or social issues. The master plan for the project has
been conceptualized in such a manner so as to reduce the environmental impacts of the project on
the surrounding settlements. The project shall bring in major investments to the region covering a
wide range of sectors – connectivity, industry, social infrastructure.
The project when fully operational also brings in direct and indirect employment, thereby opening up
employment opportunities for the youth in the catchment region. Additionally, the induced
development due to the Petrochemical Park, definitely bound to bring in more benefits to the local
population and the overall region. The proposed project will therefore immensely add to the social
economic value of the region.
P a g e |266
Risk Assessment & Mitigation Measures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |267
Project Management Organization
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
S. Responsibility of member
Components Responsibility of developer
No industry
Developer will provide the conveyance system
for treated wastewater from industry holding
tank to common guard pond, in case of
industries which would like to have full-
fledged treatment facility in their premises.
4 Wastewater Developer shall provide the CETP for Industries which would like to
treatment treatment of effluents based on type of have full-fledged treatment
and disposal industry in case of industries which would like
facility in their premises should
to utilise the industrial park CETP facility.
treat the effluent up to marine
discharge standards.
The marine discharge facility of treated Industry specific critical
wastewater shall be provided. pollutants shall be treated
upto marine discharge
standards.
5 Treated i. Developer shall monitor the treated i. Industries which would like
wastewater wastewater at following locations on daily to utilise the industrial park
monitoring basis, in case of industries which would CETP facility, monitoring of
protocol like to utilise the industrial park CETP wastewater on daily basis
facility: by member industry shall
Member industry wastewater holding be carried out as per CETP
tank with online monitoring facility for inlet standards at
pH, TDS, COD and TOC, for other respective holding tanks
parameters like heavy metals shall be with online monitoring
monitored by manual collection of facility for pH, TDS, COD
wastewater samples by the developer. and TOC.
Respective CETP guard pond Industries which would like to
Common guard pond have full-fledged treatment
Developer shall monitor the treated facility in their premises,
wastewater at member industry holding tank wastewater monitoring on
on daily basis which shall comply marine daily basis by member industry
discharge standards in case of industries at holding tank shall be carried
which would like to have full-fledged out as per marine discharge
treatment facility in industry premises. standards.
6 Rainwater Rainwater harvesting pits in green areas shall Rainwater harvesting pits in
harvesting be provided. industry premises shall be
provided.
7 Waste Sludge generated from STP shall be Member industry shall have
management composted and will be used as manure for their independent Hazardous /
greenbelt / green areas development. Non-hazardous waste
collection and segregation
CETPs shall have a temporary storage facility system.
for 30 days, wastes shall be periodically Industries shall have a
disposed to nearby TSDF. temporary storage facility for
30 days detention which will
be designed as per the
requirement. Wastes shall be
P a g e |268
Project Management Organization
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
S. Responsibility of member
Components Responsibility of developer
No industry
periodically disposed to nearby
TSDF by the member industry.
Industries shall follow “The
Hazardous Wastes
(Management, Handling and
Transboundary Movement)
Third amendment rules,
2010”.
8 Post project Developer shall conduct post project Industry specific critical
environment environmental monitoring as per the post pollutants shall be monitored
al monitoring project monitoring programme. at industry level.
The air quality results of industrial park area
shall be displayed at main entrances.
9 Stack - Stack monitoring shall be
monitoring carried out by member
industry.
10 Greenbelt Greenbelt development along industrial park Greenbelt / green areas shall
development boundary and green areas in common areas be developed in the industry
shall be developed. level as per Kerala Pollution
Control Board norms.
11 Strom water Strom water collection along roads, common Strom water collection within
management areas and utilities shall be provided. the industry shall be provided
and discharge facility into the
common storm water drains
shall be provided.
12 Truck parking Truck Terminals means for truck parking are Member industry shall provide
provided at the main entrances of the on-site parking spaces for
industrial park. This parking space will serve trucks within the industry
the trucks until custom clearance to enter the premises.
industrial park.
P a g e |269
Project Management Organization
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The roles and responsibilities of different departments and integration of their horizontal and vertical
linkages with other departments and the overall structure of Industrial Park management shall be
clearly defined so as to ensure smooth functioning. There should be different committees and
platforms to address various issues related to the Industrial Park. Also, a public relations and grievance
redressal cell should be set up accessible to all the stakeholders of the project.
P a g e |270
Project Management Organization
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The PMC shall provide overall Project Management Services covering but not limited to the
following:
Establish Project Management System and Procedures
Planning & Scheduling Control and monitoring
Cost Control
Change order Control Management
Project Documentation Control
a) The PMC shall plan and monitor Project Activity Schedule using Primavera P6 or MS
Project. The PMC shall review the overall Project Schedules/network, identifying critical
path, discussing with the Contractor(s), conducting weekly monthly review meetings,
setting priority activities and target dates for completion of sub-activities, etc and the
timely completion of the Project.
b) The PMC shall also produce one Master Overall schedule and report overall progress
every fortnight. The PMC shall prepare detailed discipline wise schedules for setting out
targets; coordinate and on request by Kinfra, assist Kinfra in work progress presentations
/ discussions as may be required.
c) The PMC shall monitor the Project (both physical & financial) during entire Project
duration and shall submit Dailey fortnightly reports as well as during intermediate
periods, as required by Kinfra. Cost Control of Project considering resource mobilisation
and resource levelling, Analysis of Project records; Identification of present conditions;
Forecasting requirements for completion; Preparation of incremental and cumulative
costs records.
d) The PMC shall review and update the networks and Project schedules regularly and take
/ initiate pro-active actions to avoid delays and ensuring timely completion of the Project
P a g e |271
Contract Management Strategy
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
and also suggest remedial actions to catch up the delayed activities. The PMC shall
develop Project Information system for highlighting slippage and hold up the
Contractor(s) for management, action and control.
e) The PMC shall be a single point contact for all technical and contractual matters as well
as site office coordination. The PMC shall coordinate the activities of all parties including
KINFRA to effectively deliver their services.
f) The PMC shall carry out the function of accounting, financial record and controls of all
the Project related activities including payments schedules and deliverables of
Contractor(s).
g) The PMC has to review and finalize Quality Control Manual and construction safety
manual to be prepared by the Contractor(s).
h) The PMC shall coordinate the activities such as site take over, discussion with KINFRA and
the Contractor(s), review Contractor ‘s work schedule, work plan and implementation
schedule as per the contract, review of master list of equipment’s and materials, review
of master list of personnel, review of the Contractor‘s insurance policy, making
arrangements for items like site office, laboratories etc.
i) In case of deviations / variations in the Project specifications, the PMC shall compute the
saving / excess in the Project costs due to the same, the time attributable to the
deviations, review and recommendation of the rate analysis, estimated quantity, Finance
implications etc.
j) The PMC shall address issues relating to specific site conditions, review matters related
to supervision of safety and environment management measures by Contractor(s) for the
Project.
k) The PMC shall supervise Quality control, commissioning procedures and assist KINFRA in
issuing certificate of satisfactory completion of works / milestones, establishment of
quality control lab at site by the Contractor(s). All the necessary Quality Control tests shall
be carried out by the Contractor(s) under the supervision of the PMC and the test results
to be accepted by the PMC and recommended to KINFRA.
l) The PMC shall make necessary arrangements for supervision in case the agency prefers
to work in the night shift, to keep the time lines as the case may be. The PMC shall extend
all the necessary cooperation to attend the RFP in the minimum possible time to enable
the contractor to maintain the progress duly fulfilling the quality requirements.
m) The PMC has to issue quality certificate (to ensure compliance with the technical
specifications and contract requirements) for the works being carried by the
Contractor(s).
n) Safety Control of both the public and the workforce through co-ordination with APIIC /
Contractor(s) to resolve the problems due to environmental impacts within the laws,
regulations and policies of the State. PMC to deploy senior safety officer to monitor
construction safety measures, keeping the blasting operations in view that may require
to take place by the side of the live Highway on which traffic is flying 24 x 7.
o) PMC shall evaluate the safety plan of the contractor both with respect to the work force
working in site and the people and traffic moving on the road., and suggest proper
measures to ensure max possible safety for the commuters, both due to the work and
also due to the movement of the work force and the construction fleet.
P a g e |272
Contract Management Strategy
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
p) The PMC shall undertake performance control with respect to the quality of works
materials proposed by the Contractor(s) and delivered to the Project site by conducting
the required test specified in the specifications periodically as set and approved by APIIC,
these will include:
i. Quality tests on all construction material & completed works as per requirement
and make sure they comply with the Standards & Specifications and accepted
method of quality control.
ii. Inspection & certification of quality equipment procured by Contractor(s) by
inspecting the manufacturer ‘s certificates and test results and ensure compliance
with the specifications including the calibration of equipment as per the necessity.
q) The PMC shall document the EPC Contractor ‘s activities & issue letters/work
instructions/notice recommendations as and when required.
r) While execution of the Project, in case of technical issues where execution drawings are
found not to be suitable / erroneous, the PMC shall come out with an engineering
solution to the problem being faced, and issue the revised drawings, by interacting with
the Contractor(s), KINFRA and co-ordinate for issuance of appropriate changes / revisions
and monitor the execution of the same incorporating the changes into the original plan
with supporting drawings.
s) The PMC shall hold Project site review meetings on weekly basis where KINFRA and other
officials of the KINFRA/Government may also be present. The PMC shall conduct
meetings and prepare MOM and follow-up action plan / action taken plan that shall be
reviewed in the next meeting.
t) The PMC shall submit the progress reports to KINFRA and in the formats required for
various government authorities as necessary. In addition, the PMC is required to update
and present the actual progress report as and when required for review by APIIC. The
PMC shall carryout, in coordination with KINFRA all the activities required for the safe
and timely completion of the Project without cost over-runs / minimizing Cost Overruns;
assure quality of work as per applicable standards in all activities related to the Project.
u) The PMC shall liaise with KINFRA and Contractor(s) to resolve execution related problems
encountered during the Construction Stage. The PMC shall also undertake the following
activities and where appropriate make suitable suggestions.
i. Assist KINFRA to address legal issues associated with the Contract. Any assistance
with respect to court cases and contract agreement needs to be provided.
ii. Analyse and allocate / apportion delays attributable to KINFRA, Contractor(s), etc
and suggest remedial as well as penal action. Assist in interpreting and applying
the various legal provisions of the contract documents, and in amicably resolving
disputes.
iii. If required, assist KINFRA in establishing a system to monitor the Project‘s
environmental impact indicators, review the data collected, evaluate the
effectiveness with which the environmental mitigation and monitoring measures
are implemented and recommend action to be taken.
iv. Provide effective and regular supervision of the works and ensure their quality
and conformity with the standards and specifications prevention rather than post
corrective remedial measures.
P a g e |273
Contract Management Strategy
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
v. Compile and review all day-to-day quality control data obtained from the
construction sites, and verify the accuracy of such data by random checks of the
records and by carrying out independent testing as necessary;
vi. Provide certification on the quality of works accomplished and on their conformity
to specifications and drawings; The PMC shall ensure that the works are
completed in accordance with the approved design.
vii. Examine and make recommendations on all claims from the Contractor(s) for time
extension, extra compensation, variation, order, change in scope or expenses or
other similar matters;
viii. Propose and present for approval any changes in the plans that may be deemed
necessary indicating any effect the changes may have on the contract and prepare
all required change orders;
ix. If the PMCs consider any item of work substandard or unacceptable, they will
advise the KINFRA in writing about it, providing full justifications thereof with all
necessary supporting data including test results;
v) Quality Assurance System
i. The PMC shall prepare and implement Quality assurance system with the approval
of the KINFRA. The PMC shall designate a quality assurance manager who shall
formulate and monitor the quality system for this project. He shall monitor project
quality standards and shall conduct regular checks and the documents shall be
released only after his concurrence.
ii. The quality of the services shall be ensured by deployment of resources –
personnel and equipment and through regular interaction with KINFRA.
w) Post Construction Phase
i. The PMC should perform performance tests on all the works to the satisfaction of
KINFRA.
ii. The PMC shall collect and submit as-built drawings duly checked, to be submitted
in 3 sets of hard copy bound and 1 set of soft copy in pen drive (Editable version).
iii. The PMC shall review and finalise all as- built drawings/data developed by the
Contractor(s)
iv. The PMC shall develop a detailed Inventory of items and the Project as a whole
v. The PMC shall submit final report, which will contain all technical and financial
information of the project right from conceptualization to completion. The final
report should be a complete comprehensive document including as-built
drawings, variations, problems faced, actions taken, major events, contract
changes, claims or disputes or any other substantive matters having an effect on
the cost and progress of the work etc.
P a g e |274
Contract Management Strategy
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The first option bestows the responsibility of performance to the Industrial Park management and
requires involvement of a dedicated wing for each of the facilities. The second option requires
establishing relation with a private service provider through a well worked out contract based on
which the running of the facility is awarded with Industrial Park management monitoring. The services
that may be taken up include:
Wastewater collection and treatment (CETP and STP)
Desalination plant
Solid waste collection and disposal etc.
Assuming that the Development Contract will be awarded on a Single Package, a construction
sequence has been developed showing all the project related activities and is provided after this
section. The total time assumed for the activities is around 7 years till the date of commercial
operations and a detailed project implementation schedule has been provided below.
P a g e |275
Implementation Schedule & WBS
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |276
Statutory Clearances
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |277
Quality Management Plan
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
o Pre-defined Drawing Issuance Schedule (DIS) filtered from Project Master Programme
(PMP) and issued to relevant departments to warn them ahead of the drawing
requirement
o At last but not the least Design Audit for third party, if required
Project Programming
o Should exploited the power of Primavera to generate Multi Level Project Scheduling
(MLPS), Interfacing of Primavera and Excel will be developed to generate of Weekly,
Monthly, Quarterly and Yearly Cash Flow from Project Master Programme (PMP)
Developed in Primavera (P3)
o Multi-Level Project Scheduling (MLPS) is carried out in Primavera (P3) separately for
Project Master Programme (PMP)
Detailed Design Programme (DDP)
Detailed Construction Programme (DCP)
o Updating of PMP is done at site using SURE TRACK 2.0 and this information is fed in
P3 to generate different types of MIS reports
Cost Management through - Financial Control Manual (FCM) Called - Red Book
o Project Data Sheet
o Quantity Surveying of each phase
o Project Financial Summary
o Status of Cost element as per Code of Account (COA) followed for the project
o Monthly Cash Flows
o Earned Value Reporting
o Copy of relevant Change Orders
P a g e |278
Quality Management Plan
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |279
Quality Management Plan
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |280
Quality Management Plan
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The success of industrial parks depends on efficient and responsive management. A park’s managing
company must provide guidance and support so that business planning is conducted smoothly. Park
operation, maintenance, information, procedural support, and trouble-shooting; quick and effective
responses to customer demands are key parameters governing the success.
The Park operator will be responsible for the operation and maintenance of the following Basic
infrastructure inside industrial parks:
Roads
Drainage
Water supply
Sewerage
Domestic solid waste disposal
Electricity
Common Utilities if any- Steam, DM water, fuel supply etc.
Telecommunications / Broad banding
Fire fighting
Security and Surveillance
Others
A basic responsibility of the operator will be to secure maximum value for money from the O&M of
the Park’s infrastructure assets. Operator can adopt various strategies to optimize the returns
generated from those assets; the framework in below figure offers a structured overview of
P a g e |281
Operations & Maintenance Plan
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
management strategies (represented by the outer circle) and enablement strategies (represented by
the inner circle).
The key role of the agency or organization responsible for its management will be to;
Be accountable for park property management and coordination of service provision to tenant
companies, particularly for common infrastructures and services as well as other forms of
industrial symbiosis.
Increase the utility of the existing infrastructure asset, by maximizing its utilization and
enhancing its quality for each user.
Decrease the total costs of providing the infrastructure service – not just by reducing
internalized O&M costs but also by mitigating the environmental and social externality costs.
Increase the lifetime value, by extending the asset’s life to maintain the benefits over an
extended period,
Play a core leadership role in designing and monitoring key performance indicators (KPIs) for
the park, looking at economic, social and environmental criteria.
Provide an interface between tenant companies and the authorities. May act as a facilitator,
moderator and/or mediator.
An effective park management model will be set up to share and recover park level costs/benefits. It
will be necessary to think about the cost recovery model envisioned for the Park to ensure that: a) the
park management cost is factored into the cost-recovery strategy and b) tenant companies are willing
to pay for the services offered by the park operator. The design of the park would be optimized the
contributions from various revenue sources such industrial synergies within and outside the Park. It is
widely recognized that management is more effective when it provides incentives rather than inflating
subscriptions or service fees. This aspect will be examined in more detail.
P a g e |282
Operations & Maintenance Plan
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Depending on the existing context and policy frameworks, following park management models (or
combinations thereof) may be looked into:
Public administration units or state-run companies, which can cover both the management
and some aspects of leadership of the industrial park
Private associations, private companies or real estate agents, generally responsible for park
management aspects with participation in leadership remaining optional
Pragmatically, Park management models should be participative and decided at the earliest
development -al stage. Instead of reproducing forms of management from a pre-existing company or
government body (which can lead to bureaucracy), the selection will be based on a detailed
assessment, such as a Strength Weakness Opportunities and Threats Analysis (SWOT analysis). Each
management model presents advantages and disadvantages. It is possible to make general
observations;
b) Setting up of park operations and management functions
A management structure identifies units for particular functions. Those functions may be delivered by
the Park management staff itself or subcontracted to service providers. All functions need to be
rationalized following a lean management approach, which aims to maximize customer value while
minimizing inefficiencies in critical resources such as human effort, space, capital or time. Key
functions of park management which are particularly important to classify as an industrial park are:
c) Mobilize resources and ensure financial sustainability
Financial self-sustainability will be the basis of any Industry Park project operations. Therefore, from
the planning phase, it will be necessary to think about the model of cost recovery envisioned for the
conceived eco-industrial park and to ensure that:
The management cost of the Industrial Park is factored in the cost-recovery strategy
Tenant companies are aware of the added value of the Park management and are willing to
pay for the services offered by the Industrial Park operator/Manager
Tenant companies require a perceived (and prefer ably documented) value for money for the services
and lean management from the Park operator. The conditions under which investors and tenants are
invited may determine future willingness to pay.
d) Designing and rolling out Industrial Park plans
Park management will be responsible for translating the leadership vision for the -industrial park into
actionable plans that are aligned with applicable standards. It has to be a participatory process with
all the stakeholders and particularly the tenant companies to interpret those standards in specific
contexts and identify the interventions, objectives, resource and indicators using tools common to
any project management. The performance of the Industry Park management in upholding its duties
would form part of the plan.
P a g e |283
Operations & Maintenance Plan
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |284
Operations & Maintenance Plan
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |285
Operations & Maintenance Plan
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
19. Annexures
This section describes the list of following Annexures:
P a g e |286
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Ethyl
Benzene,
/styrene
2 Cumene,
0 Oil additives, flame
Cyclohexane Pharmaceuticals,
1 retardants, oil well
, adhesives, Latex
9 Benzene 40 NA drilling chemicals,
paints, thinners,
Aniline, cleaner solvents,
disinfectants etc.
Resins…
Chlorobenze
ne,
Miscellaneo
us
Polyacrylic acid
Acrylate copolymers used as
Glacial Acrylic
2 Acrylic esters (by Dispersants Paints and coatings,
Acid/
0 Acid-ester BPCL); 10 /antiscalants, cosmetics,
Polyacrylic
1 grade anionic detergents
Glacial acid
9 Acrylic Acid polyelectrolytes for
water treatment,
P a g e |288
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |289
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
VAM/EVA/V
AE,
EPDM.
Paints and coatings,
EthanolAmine Surfactants,
MEG, cosmetics, textiles,
s herbicides
additives
Ethanol
Amines, Non-ionic
2 Ethoxylates Detergents
Surfactants
0 Ethoxylates
EO 10 solvents for paints
2 Glycol Ethers
Glycol and inks
2
Ethers,
Slovents,
Ethylene – Ethylene electrolytes, Home/personal
Carbonates. carbonate surfactants products
/ethoxylates
2 Nylon 66,
0 Caprolactu Nylon 6 Resins
Nylon 6 (50) FACT Tyre Cords
1 m and Yarn
9
Surface active agent,
syndetergent,
dyeing and printing
Propylene auxiliary, emulsifier,
Glycol, Iso printing ink Pharmaceuticals,
propanolamin auxiliary, petroleum pesticide, Inks,
Iso-
e additive, Detergents etc
propanolami
pharmaceutical
ne,
Intermediate, ,
PO Propylene <10 electroplating
Glycol additive, etc.
2 ethers,
0 Paints and in the
As solvents and
2 Propylene Propylene production of
coupling agents in
2 Carbonate. Glycol ethers coatings, inks, resins
paints
and cleaners
Solvents for
Propylene Adhesives and
Adhesives, paint
Carbonate cosmetics
strippers, cosmetics
Fiber glass products
UPRs
Solvents for Fragrance,
Propylene (Unsaturate
100 UPRs Fragrance, cosmetics and
Glycol (PG) d polyester
cosmetics and personal care
resins)
personal care industries,
products; carriers,
P a g e |290
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
humectants and
preservatives.
PU Products-Auto
Polyol components, Rigid
PU Resins 250 PU Resins
Ethers and flexible foams,
elastomers etc.
PET Bottles,
MEG/DEG technical textiles
PET Resins 100 PET Resins
/TEG
PET Components
Source: Consultant’s own expert assessment and BPCL inputs.
P a g e |291
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
19.2. Annexure 2A: Market Demand for Target Petrochemical Intermediates &
Additional Land Requirement for Its Manufacturing in India (2017-27)
8000
Polyisobutylene (PIB) 0.7 16000 /12% (50%) 41694 10
10000
Methacrylic Acid (MAA) 0.7 10000 /14% (100%) 37072 9
41000 Average
Methyl Ethyl Ketone
2.6 47000 /10% (87%) 115806 4000 tons 29
(MEK)
(varies
Butyl Acetate, Iso 38000 between
1.4 38000 /6.5% (~100%) 71331 18
butane acetate 3000 to
Ethylene Vinyl Acetate 166000 5000)
(EVA) / Vinyl Acetate 5 166000/9% (~100%) 392982 98
Ethylene (VAE)
3,30,000
VCM 25 1100000/9% (30%) 1834100 459
Total 938
Sources: Chemical & Petrochemical statistics at a glance by Department of chemicals and petrochemicals Ministry of
chemicals and fertilizers GOI, Directorate General of Commercial Intelligence & Statistics, Ministry of Commerce & Industry;
P a g e |292
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Global consulting and publications like IHS, ICIS, imarc group; business wire ; Platts etc;.; Report of the Sub-group on
Petrochemicals for the 12th Five Year Plan& Consultant data base and assessment on land absorption norms drawn from
various past projects
19.3. Annexure 2B: Market Demand & Land Requirement for Target Downstream
Industries- (Specialty Chemicals & End Products) In India (2017-27)
P a g e |293
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
German chemical Park concept is widely regarded as one of the best examples of integrated
production strategies with the most efficient use of resources. As a chemical production and
associated process industries location, Germany is a global heavyweight, ranking first in Europe.
Germany’s greatest appeal for chemical companies lies in its market size within Europe. This is largely
due to the presence of strong client industries including the automotive sector. The country’s
historical export strength and research environment are also attractive factors. Specific strengths in
innovation, productivity and resource efficiency all help establish Germany as an attractive chemical
industry production location. These factors, together with sensible labor market reforms, have led the
German chemical industry being able to consolidate its market-leading position in Europe Years of
investment and production optimization have resulted in a network of highly integrated production
sites: Germany’s unique “Chemical Parks.” At present Germany have around 35 chemical sites each
with unique features. (The details of one of the Park are illustrated in Annexure 3). These are linked
by advanced infrastructure with first-class energy supply, offering service provision through site
management companies whose core business is the on-site supply of utilities. With their plug and play
concept, Germany’s chemical parks are able to offer state-of-the-art conditions for international
investors. They can choose the services from a site operator that suits their business model best. The
new production site, developed sites and site security services are all made available for the investor’s
core activities. Optional services such as warehousing, logistics, and analytics can also be requested
as needed. German chemical parks increase cost effectiveness by splitting cost and overhead – a
benefit to both the site operator/owner and investor.
Supporting Different Business Models Chemical parks offer a wide range of business models. Subject
to the investor’s individual requirements, land can be leased or purchased in order to establish a
production unit. At the other end of the scale, a site operator invests in and operates the new plant
for the investor on a custom or toll manufacturing basis. Cost-competitive production through flexible
site operators.
Planning Support Services, Investors are supported by a number of investment planning and
construction services. The most sought-after service is for permit applications. Licensing procedures
are completed quickly and efficiently with the competent public authorities assisting in the process
from a very early stage. + Fast implementation of the new business.
Provision of Utilities and Services such as wastewater treatment, thermal treatment of production
residue, emergency services, industrial safety, fire protection, environmental services, analysis and
testing services, rail dispatching, and product storage are all widely available at chemical parks. All
chemical services available on-site.
Powering Chemical Parks Secure power supply is imperative for profitable industrial plant operation.
Chemical parks are made secure through the provision of a number of redundant supply lines. Most
chemical parks operate their own on-site power plants in order to secure supply. An undisrupted
supply of steam and overall energy cost are also key success factors. By generating both heat and
P a g e |294
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
power from various primary energy sources, chemical parks are well placed to utilize the high
efficiencies found with combined cycle heat and power (CHP) generation. Plants within any one
chemical park are linked to duplicate transmission networks that ensure stable supply in the case of
disruption of one line. Supply by two independent systems ensures continuity even in the event of
random acts of nature. This power supply set-up makes chemical parks ideal sites for investors in the
process industries. Secure power supply.
2. Jurong Singapore
Singapore has no oil or gas resources and limited land space. But against all odds, it has achieved
tremendous success in the petrochemical industry. Today, Singapore is the third-largest oil refining
center in the world, the largest bunkering port and, one of the top 3 oil trading hubs in the world and
the price discovery center of Asia’s oil trading industry. Some countries have seen some difficulty in
attracting specialty chemical investments due to lax intellectual property laws. Singapore has
managed to gain investor confidence in this sector due to its intellectual property protection laws,
access to skilled labor and research and development capabilities.
Singapore has grown to become one of Asia’s, and one of the world’s leading and most cost-effective
locations for producing petrochemicals. At the heart of this success is Jurong Island, which started
out as a collection of small islands and is now home to three major oil companies. Today, Jurong
Island is an amalgamation of seven small islands, which after reclamation gives it a total land area of
approximately 3,000 hectares. In an ambitious land reclamation project that was officially completed
in 2009, Singapore has connected seven of its islands to form Jurong Island. The island has a land
mass of some 3,000ha and, according to Singapore’s Economic Development Board (EDB), hosts
more than 100 companies from the US, Europe and Asia. The list includes heavyweights such as
DuPont, Huntsman, BASF, Perstorp, Dainippon Ink & Chemicals, and Sumitomo Chemical.
With improvement in chemical manufacturing processes over the years, the industry has moved
towards having integrated manufacturing in a cluster, which has everything within itself. Refineries
provide the primary feedstock for conversion to petrochemicals, which in turn, undergoes
downstream processes using the latest infrastructure, utilities and energy provisions, available inside
the cluster. As common facilities and services such as utilities, energy, and transport are shared, less
land is required for manufacturing, leading to substantial cost-savings.
This dedicated plug-and-play infrastructure has made the Jurong Island one of the world’s top 10
petrochemical hubs, with a total investment by more than 100 companies exceeding S$47 billion
employing around 9000 people.
Upstream companies including Shell, ExxonMobil and Petrochemical Corporation of Singapore (PCS)
have built world scale integrated cracker complexes providing a wide range of feedstock. This
feedstock is then channeled to various downstream companies such as Sumitomo Chemicals, Lanxess,
and Asahi Kasei. The island also has more than 10 projects that are currently under development, with
almost 60 percent of the island’s land area been allocated to various companies.
Seamless integration via a network of pipelines makes it possible for companies to buy and sell
feedstocks and products literally over the fence, as the output of one plant is the input for other
neighbouring plants. This saves time and transportation costs as well as reduces the risk of spillage
and contamination.
P a g e |295
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
A comprehensive host of third-party providers is also at hand for outsourcing functions such as waste
water treatment, utilities, and storage requirements. For instance, Hitachi Engineering provides EPC
(Engineering, Procurement, and Construction) services; Sembcorp, Tuas Power Utilities provide
effluent treatment services; and Pipenet, Keppel Merlimau Cogen provide utility services.
This results in savings of up to 25-30 percent in capital outlay and 10-15 percent in logistics costs while
allowing the companies to focus on their core business activities.
Safety and Security: The entire Jurong Island was gazetted as a protected area in 2001, and a
security framework was put in place to protect investors’ assets. There is round-the-clock air, sea
and land surveillance, as well as security checks of all vehicles and personnel entering the island.
Singapore Civil Defence Force also operates two fire stations at the island.
R&D: Situated on the Island is the Institute of Chemical and Engineering Sciences (ICES), an
autonomous national research institute under A*STAR (Agency for Science, Technology and
Research), which undertakes research programmes in developing new processes and applications
for the chemical industry.
Training: Furthermore, the Singapore Economic Development Board (EDB) had set up a Chemical
Process Technology Centre (CPTC) on the island to support the training of new entrants to the
chemical industry and to enhance the capabilities of existing professionals. This is critical because
proprietary manufacturing processes are key to the competitiveness of petrochemicals
companies, while product differentiation is critical to the growth of specialty chemicals.
Development of a skilled workforce is central to Singapore’s continued development of Jurong
Island.
The CPTC is owned by the Singapore EDB and managed by Petrofac Training. Said to be the
first training centre in the world to house an industrial-scale petrochemical process plant,
CPTC allows trainees to experience ‘live’ plant conditions in a safe and controlled
environment.
Even with a skilled workforce and all the available training, companies concede that with
so many options it is difficult to attract even trained chemical engineers into the
petrochemical sector.
Floating structures: In addition to the just opened JRC, JTC is studying the feasibility of
floating structures for oil products and petrochemicals storage to be known as the Very Large
Floating Structure (VLFS). VLFS will be designed to be either moored to land or function as
stand-alone units. It will take up only 5 hectares of foreshore space as compared to 20
hectares of land space for the same storage capacity of 3,00,000 cubic metres
In a bid to enhance its competitiveness and drive the next phase of growth for the chemical industry
in Singapore, the government has unveiled a Jurong Island version 2.0 (Jlv2.0) initiatives, a 10-year
master-plan. It is aimed at new infrastructure developments; system-level optimization of valuable
resources like energy, carbon, water and land; and turning the island into a “living lab” for companies
to develop integrated innovative solutions. Moreover, Jlv2.0 will focus on better integration of refinery
and petrochemical facilities, introduction of new feedstocks such as LPG, and exploring bio-feedstock.
P a g e |296
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Another focus will be on generating a critical mass of olefin capacity. This will help foreign investors in
setting up new manufacturing activities in higher value chemical chains such as C4s and C5.
SCIP is located in the south of Shanghai, on the boundary between Jinshan District and Fengxian
District. With the A4 Expressway that connects Shanghai-Nanjing and Shanghai-Hangzhou Expressway
network, it is only a 45-minute drive, or 50 kilometers, away from downtown. There are railway sub-
lines for its exclusive use connecting to the 113-kilometer-long Pudong Railway (Fengxian-Pudong
Airport-Zhangmiao). The park is connected to Huangpu River and Yangtze River water system via
dredged inner river channel system. Apart from an exclusive port, SCIP is only 55 kilometers away from
the Yangshan Deep Water Port (10 million standard containers). The park is only 50 kilometers away
from Pudong International Airport and Hongqiao International Airport. In short, transportation here
is very convenient, be it by sea, by land or by air.
Shanghai Chemical Industry Park (SCIP) has total planning area of 29.4 square kilometers almost same
size as Jurong. SCIP is one of the industrial projects with the largest investment in China during the
10th Five-year Plan. Its Phase 1 investment totaled RMB150 billion (on 10 sq km). It is the first
industrial zone specialized in the development of petrochemical and fine chemistry businesses, and
the southern center of Shanghai’s six industrial bases. The industrial output of SCIP will achieve
RMB100 billion when all approved projects are put into operation. SCIP is known as the "Wing of
Industrial Take-off of Shanghai".
Built with the advanced “integration” conception adopted by the world’s largest scaled chemical
parks, SCIP provides investors with best investment environment by integrating production projects,
public utilities, logistics, eco protection and administration services. So far, many well-known public
engineering companies have set up plants here, including BP, BASF, Bayer, Degussa, Huntsman, SUEZ,
Vopak, AIR LIQUIDE, Praxair, etc. SCIP aims to be one of Asia’s largest and most advanced
petrochemical bases.
Shanghai Chemical Industry Park is the first industrial zone specialized in the development of
petrochemical and fine chemistry businesses, and also one of the four industrial production bases in
Shanghai. It is built with advanced development conception of World-Class and large-scaled Chemical
Park. It is to provide investors in the Park with best investment environment by combination of
production projects, public utilities, logistics, and environmental protection and administration
services. SCIP is set out to be one of the largest and the most integrated and advanced world
petrochemical bases in Asia.
Excellent infrastructure: A "utilities island" integrating the supply of water, electricity, steam and
industrial gases is highly efficient in providing at competitive costs. A wide scope of services including
potable water, industrial water, wastewater treatment, steam, jetty, tank farm and industrial gases
and incinerator is available on demand.
Assured supply of basic feedstock: The petrochemical projects aim to supply enormous basic chemical
materials amounting to totally 6,500,000t/a such as ethylene, propylene, benzene, toluene, SM, PE,
PP, PS, PVC, MDI, TDI, poly-isocyanates, polycarbonates, PTHF, phenol & acetone etc. These basic
chemical materials can provide abundant feedstock for the downstream processing industry.
P a g e |297
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Involvement of foreign companies for infrastructure projects: SCIPDC has established joint ventures
with large foreign companies to construct and operate utility and waste disposal services. The list of
projects includes a waterworks (340 million RMB) and a waste water treatment plant (398 million
RMB) with Sino-French Water Development Co., Ltd, a subsidiary of the Suez group which is based in
Hong Kong, and a waste incinerator (510 million HKD) with Swire SITA Waste Services Ltd. working for
the Suez Group and the New World Group of Hong Kong. A heating and power station with
cogeneration was constructed as a 70:30 JV with Singapore SembCorp Utilities for 2.81 billion RMB,
and the dock and tank storage facilities ($210 million) were built in collaboration with Vopak of
Holland. Sinopal, a JV between Air Liquide and Praxair, supplies industrial gases to producers at SCIP
($120 million investment). All of these facilities went into operation between 2004 and 2006. An
impressive infrastructure is being put in place at SCIP. Future goals include integration of
environmental protection programs and further implementation of the “circular economy” strategies.
The MSEZ proposition of infrastructure & services could potentially translate into lower capital
investments by as much as 15 – 20% and operating costs by 10% – 30%, typical of similar clusters
elsewhere in the world. In addition, SEZ benefits allow units several other advantages including duty
free imports of raw materials and tax exemptions on exports revenue.
MSEZ has attracted investments to the tune of USD 2.5 Bn thus far, with more in the pipeline. Nearly
70% of the land in Phase I has already been occupied. The projects that are under production/advance
implementation include OMPL (ONGC Mangalore Petrochemical Ltd) Aromatic Complex of 1.1 mn ton
capacity manufacturing Para xylene and Benzene; JBF plant for manufacture of 1.2 mn ton of PTA and
0.5 mn tons of PET resins; ISPRL for storage of 1 mn ton crude oil in underground caverns, Cardolite
industries for Epoxy resins; Syngen for producing APIs and Anthea Aromatics for producing specialty
chemicals. The zone is now a multiproduct SEZ and is targeting other sectors.
The average land price in Mangalore SEZ is around Rs 1.5 crore/acre and annual lease rentals of Rs 1
lakh/acre and annual O&M charges of Rs 110 per sq mtr. The zone has dual pricing structure with
higher land premiums for intermediate units and lesser for downstream industries.
The SEZ despite excellent infrastructure support has confronted problems in attracting investments
due mainly to SEZ policy constraints and policy dilution over the years in attracting investments in the
Petrochemical sector. In addition, it has not been able to secure assured supplies of basic feedstock
from the neighbouring refinery for the downstream industry. The major issues faced by MSEZ in
attracting investments has to do with a) dilution in SEZ policies like imposition of MAT and dividend
distribution taxes etc, b) Insistence on meeting NFE criteria in SEZ which precludes manufactures to
sell end products in domestic market which is the main market for petrochemicals and c) Lack of
assured supply of basic feedstock from refinery to the downstream industry. As a result, SEZ had to
convert itself into multiproduct SEZ in order to target industries from other sectors to increase its
occupancy.
5. DAHEJ PCPIR-India
Gujarat PCPIR (GPCPIR) is a specifically delineated Investment Region planned for the establishment
of production facilities for petroleum, chemicals and petrochemicals. PCPIR located at Dahej, is spread
over the blocks of Vagra and Bharuch, South Gujarat. It is spread over 453 sq km of brownfield area in
the Gulf of Khambhat in the west, Narmada river & Aliyabet island in the south, villages of Vagra and
Bharuch block in the east and Bharuch-Dahej railway line in the north. The area has a domestic tariff
area and an SEZ named Dahej SEZ. GIDC has got 12000 Ha land outside SEZ and 1732 Ha in SEZ. Most
of the units are in Specialty chemical and pharmaceuticals sector in the zone.
P a g e |299
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Strategically positioned to the east of Delhi-Mumbai Industrial Corridor (DMIC), the PCPIR at Dahej,
Gujarat has received infrastructure investment of USD 2.42 Billion from Gujarat Infrastructure
Development Corporation (GIDC). The anchor tenant ONGC has invested USD 4.07 Billion in the
project which is expected to create total employment of 90,000 once completed. The current total
investments accrued/committed in Dahej PCPIR by industries is estimated at $ 24 bn. The current
employment generated in 2016 is estimated at 28000 nos in the PCPIR.
The infrastructure provided at Dahej includes:
Water Infrastructure: GIDC supplies 33 MGD raw water drawn from Narmada River. GWSSB provides
drinking water through Narmada Canal. 100 MGD additional water supply network is proposed in the
PCPIR with a provision for separate water supply network of 20 MLD in SEZ. O&M of water
infrastructure will be managed through a SPV - Gujarat PCPIR Services Ltd. (JV of GIDC and Multi
Mantech).
Power Infrastructure: Power is available from Gujarat Urja Vikas Nigam Ltd. from 220 KV sub-station,
linked with the state grid by 220 KV circuit line. Construction work has already started in 2640 MW
coal-based power plant by proposed Adani Power. Torrent Energy Ltd. is co-developer for power
distribution in Dahej SEZ. Power distribution network is in place. Project of 1500 MW is under
implementation in SEZ. Underground network of distribution line has been laid. There is also a
provision of inter units feeding grid within Dahej SEZ in case of power failure in a unit.
There are 7 ITIs in PCPIR and within 30 km radius and skill up-gradation centers set up by GIDC and
private companies such as Essar, ABG Shipyard, L&T etc.
Logistics & Warehousing infrastructure:
Adani-Petro LNG has a capacity to handle 20 million tonnes of coal a year. Dahej Port handles varied
commodities such as coal, silica sand, rock phosphate, steel products and project cargo and
machinery items. The coal import terminal at Dahej is equipped with two jetties with a deep draft
of 14mmetres each, thus enabling berthing of large capsize vessels.
GIDC is proposing 80-hectare chemical logistic park planned in PPP mode through a JV Company of
GIDC and IL&FS IDC. Land has been earmarked and process is on to select a developer. It will be
the only chemical logistic park in India.
GIDC is to form SPV Company in JV with Kribhco Infrastructure Ltd. (KRIL) to develop a CFS in PCPIR.
Gas Supply
GSPL state-wide gas grid handles over 13 MMSCMD through its 2200 km network. This covers the
PCPIR.
Gujarat Gas network close to GPCPIR, at Ankleshwar (3 MMSCMD).
Being in the heart of chemical industry (Gujarat) Dahej has major advantages in terms of easy access
to large markets and also domestic feedstock supply. Large investments have accordingly come into
Dahej PCPIR but much more needs to be done by way of infrastructure supply for garnering more
investments. In SEZ areas the entire land has been leased and units have by and large become
operational. In DTA, large lands have been acquired by potential investors but not many operational
units have come up. Most of the land is understood to have been procured for speculation purposes.
P a g e |300
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
The land price at Dahej is quite competitive at INR 1520 per sqm in DTA area and INR 1730 per sqm in
SEZ, Including Rs 15 per sqm/yr charges for PCPIR Welfare Society.
Dahej PCPIR however has major constraints in terms of access to social and urban infrastructure. The
nearest big town Bharuch is almost 50 kms away from the zone. It is becoming difficult to attract senior
level technical manpower. The connectivity through Rail and Air is real challenge. The nearest rail head
is 50 kms away and the nearest Airport is 90 kms (Baroda). Bharuch to Ankleshwar connectivity is very
poor due to high traffic congestion. These increase the connectivity problems.
Dahej has a very limited capacity port and there is high Dependency on Pvt. Owned Jetties for trade
of chemicals; future Port expansion difficult at Dahej. Most of the companies have to use long distant
JNPT and Mudra sea port for trade of Chemicals which is real dampener.
Water which is life line for chemical industry has been radioed at Dahej due to insufficient water
supply in the zone. In times to come this will be a major constraint in attracting investments here.
Dahej does not have umbrella environmental clearances like other smaller Parks thereby each unit
has to go for individual environmental clearances increasing project gestation. The PCPIR has yet to
provide for CETP which again makes the effluent disposal a costly affair. Most of the success of zone
is due to advantages of Gujarat as chemicals hub rather than that of Dahej as a location. Also, many
units have re located from other parts of Gujarat due to strict environmental legislations in larger cities
like Vapi and Ankleshwar etc.
P a g e |301
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
6. Secured Landfill
7. Marine outfall On-Shore pipelines
8. Exclusive ready built space for individual R&D purpose
Physical Infrastructure:
1. 40 Km Effluent Collection & Conveyance systems
2. 34Km Water Pipeline Network
3. 62 Km Power Distribution Network
4. 2 Electrical Sub-Stations (33KV/11KV)
5. Dedicated power feeders with transmission network to the door-step of the Industry
6. Water Reservoirs & Tanks
Services in operation:
1. Central cafeteria
2. Fire Station with trained crew and Fire Tender to fight any chemical and hazardous calamities
3. Bank with ATM & Post-office
4. Telephone Exchange with high speed Broadband Internet facility
5. Fully functional Weigh Bridge
6. Exclusive Police Out Post
7. Fuel dispensing station
8. Well-furnished Guest Rooms & Club House
Social Infrastructure:
1. Exclusive Housing Colony in near proximity
2. Facilities to empower rehabilitees and provide community support through Ramky Foundation
3. Emergency Medical Centre with ambulance operating round-the-clock with doctors and
supporting staff
P a g e |302
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Andhra IP Thippayapall,
0.02 2.50 Kakinada 0.46 0.24 0.20
Pradesh Kadapa Dist
Davanagere Dist
Bidadi,
Karnataka 0.85 Somanahally, 0.53 0.10 0.04 0.03
Ramanagar Dist
Mandya Dist
Irungattukottai
Pudukottai IP,
Industrial Kancheepuram
Complex, Dist
0.05 Pudukkottai Dist Sriperumbudur
Tamil Nadu 0.90 0.42 0.27 0.90
Manamadurai IP, Kanchipuram
Industrial Dist
Complex, Oragadam
Sivagangai Dist Industrial
Growth Centre
Anjangaon Mini Ambernath
Maharashtra 0.02 Industrial Area, 2.50 Phase-III, 0.36 0.08 0.04
Amravati Dist Ambernath Dist
Dabhoi,
Gujarat 0.08 2.30 Rajkot 0.79 0.57 0.40
Vadodara Dist
KINFRA Small Kalamassery Hi-
Kerala 0.13 Industries Park, 2.59 tech Park, 1.04 1.15 1.50
Kasargod Dist Ernakulam Dist
Balangir-NID
Orissa 0.04 Phase II, 1.25 Khurda 0.24 0.15 0.10
Bolangir Dist
Source: APIIC, KIADB, SIPCOT, MIDC, GIDC, KINFRA, IDCO Odisha
P a g e |303
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Land Rates
State SEZ Name
(Rs Cr/Acre)
Zydus Infrastructure Pvt Ltd
Gujarat 3.80
Sanand, Ahmedabad
Karnataka KIADB, Hassan 0.22
Dr. Reddy’s Laboratories Ltd.
0.19
Devunipalavalas, Srikakulam
Hetero Infrastructure SEZ
0.7 - 0.8
Nakkapali, Visakhapatnam
PREVAILING LAND RATES IN FAVORED LOCATIONS FOR SETTING UP PHARMA UNITS IN INDIA
Land Rate
States Location
(Cr/Acre)
Baddi, Solan Dist
Himachal
*Original Allottment price, Current Resale price is INR 1.5 *
Pradesh
6.07 Cr as vacant land not available.
Bio Tech Park, Karakapatla, Jeedimetla, Hyderabad 0.40
Telangana
Genome valley 0.78
P a g e |304
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
PREVAILING LAND RATES IN FAVORED LOCATIONS FOR SETTING UP CHEMICAL UNITS IN INDIA
Land Rate
States Location
(Cr/Acre)
P a g e |305
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Lease
Vacant Land premium
Name of Industrial Park Sector
(Acres) (Rs Cr per
Acre)
KINFRA Apparel Park Thumba, Apparel/Garments
3.97 1.66
Trivandrum Industries
SEZ IT/ITES & Film and Video Park
14.02 0.69 IT/ITES
Kazhakoottam
Food Processing/ General
KINFRA Park, Adoor 14.22 1.28
Industries
KINFRA Small Industries Park,
12.67 1.15 General Industries
Kunnamthanam
Textile/ General/
KINFRA Textile Centre, Kannur 64.42 0.24
Garment Industries
KINFA Integrated Industrial & Textile General/ Textile
16.35 0.59
Park, Palakkad Industries
Source: KINFRA
P a g e |306
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
19.7. Annexure 5: State wise Comparison of Industrial Land Prices Near and Away
from Refinery Locations and Major Cities
STATEWISE COMPARISON OF INDUSTRIAL LAND PRICES NEAR AND AWAY FROM REFINERY
LOCATIONS AND MAJOR CITIES
Port
Rates Located in Proximity to
Location Name of the Estate Availability in
Cr/Acre Major City Refinery
vicinity
Jamnagar-1
1.63 No No Yes
Jamnagar (Shanker Tekri)
Jamnagar-III 0.90 No No Yes
Panipat Industrial Area 3.64 No No Yes
Panipat
Samalkha 3.12 No No Yes
Bakimpady 3.50 Yes Yes Yes
Mangalore
Thannirubhavi 4.07 Yes Yes Yes
Mathura Mathura A 1.32 No No Yes
Ambattur Industrial Area 25.08 Yes Yes Yes
Thirumazhisai Industrial
7.67 Yes Yes Yes
Area
Chennai
Althur Industrial Estate 6.01 Yes Yes Yes
Kakkalur Industrial
3.51 Yes Yes Yes
Estate
Cuddalore Vadalur Industrial Estate 2.16 No Yes Yes
Marol Industrial Area 18.37 Yes Yes Yes
Mumbai Wagle Industrial Estate 8.24 Yes Yes Yes
Dombivali Industrial Area 5.36 Yes Yes Yes
Faridabad Sector- 31 &
8.62 Yes No No
59
Haryana near
Delhi IMT Sohna 6.27 Yes No No
I.E. Gurugram 1.21 Yes No No
Jedimetla 5.73 Yes No No
Industrial Park Kucharam 1.27 Yes No No
Industrial Park
Hyderabad 1.15 Yes No No
Turkapally
Adibatla 0.84 Yes No No
Pashamylaram 0.63 Yes No No
P a g e |307
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |308
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |309
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
A portion of o Employment
employer cost subsidy
contributio o Entrepreneurs
n for o Assistance for technology hip
additional acquisition and up development
D Oth employees gradation subsidy
. ers above 31- o Reimbursement of o Capital grant
03-2016 training fee for Quality
o Transport subsidy for infrastructure
level to be
labour o Marketing
borne by
Syndication
governmen o Training
t for 3 years subsidy
3 Incentives for MSME
Purchase/lease of
100 % exemption on
Sta industrial land/shed/
100% stamp duty Stamp duty on
mp buildings, mortgages –
exemption in Industrial land sale &
Dut Reimbursement of
industrial parks lease deeds, loan
y 100% of stamp and
agreements
transfer duty
Micro Enterprises -
30% Value of Fixed
Cap Assets: max. ` 18
lakh capital subsidy
A ital Capital subsidy @ 20%
Small Enterprises - of 25%: Max Rs 1
. Sub of the fixed assets
25% Value of Fixed crore
sidy
Assets: max 45 lakh)
Medium Enterprises
- 55 lakh
5% annually for 6
Inte Interest subsidy for years on term loan 5% annually for 5
rest seven years including a for Micro years on term
Sub moratorium of two Enterprises. loan: Max Rs 40
5 % Interest Subsidy
sidy years Lakh/yr
on Technology
Upgradation Loan
B VAT Micro & small 100% exemption on 100%
. / enterprises: 100% Entry Tax on 'Plant &
reimbursement
CST reimbursement of net Machinery' for 3
P a g e |310
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
ISO Series
o Employment
A portion of Certification: 75% of
cost subsidy
cost (max. 75,000)
employer o Entrepreneurs
o Assistance for BIS Certification:
contribution for hip
technology 50% fees max.
additional development
acquisition and up 20,000 & 25% cost
oth employees subsidy
gradation max. 50,000
ers above 31-03- o o Capital grant
Reimbursement of Technology
2016 level to be for Quality
training fee Adoption: 25% of
infrastructure
borne by o Transport subsidy cost (max. 50,000)
o Marketing
government for for labour Technology
Syndication
3 years Business Incubation
o Training
Center: 25% cost
subsidy
max: 50 lakhs.
Source: Industrial Policy Documents of the state
P a g e |311
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
(1) Every room intended for human habitation shall abut on an exterior or interior open space or
verandah open to such exterior or interior open space and such open space shall be maintained
for the benefit of the building exclusively and shall be entirely within the owner's own premises
and shall be open to the sky and is barred from being subdivided, partitioned or legally bifurcated
or transacted, in any manner whatsoever, till such date when the structure itself is demolished
and shall be kept free from any erection thereon other than those specially allowed in these rules.
(2) In case a group of buildings are to be put up within any plot belonging to the same owner or
by different owners of adjoining lands jointly the area of the land remaining after accounting for
the mandatory front, rear and side yards from the boundary of the plot shall be considered as
buildable area of the plot where the buildings may be constructed subject to the conditions
regarding floor area ratio, coverage, access, light and ventilation. for the whole plot, distance
between the various blocks within this area shall be minimum 2 meters for building upto 10 meters
height and 3 meters exceeding that height.
(3) Every building upto 10 meters in height shall have a minimum front yard of 3 meters depth:
Provided that where 3 meters depth cannot be maintained laterally throughout due to the peculiar
shape of the plot , it shall suffice if the mean depth at all points not less than 1.80 meters.
(4) Every building upto 10 meters in height shall have a minimum rear yard of 2 meters depth:
Provided that where 2 meters depth cannot be maintained laterally throughout due to the peculiar
shape of the plot, it shall suffice if the mean depth is not less than 2 meters with minimum depth
at all point not less than 1.00 meter.
Provided further that in the case of buildings upto 7 meters height, it shall suffice if the mean
depth is not less than 1.50 meters with minimum depth to at all points not less than 1.00 meter.
Provided further that in the case of buildings upto 7 meters height, the depth of rear yard may be
reduced to not less than 75 cms without any opening such as door and window on that side,
however ventilator opening may be made at a height of 2.20 meters from the corresponding floor
level.
Provided also that in the case of buildings up to 7 meters height, the depth of rearyard may be
reduced or even abut the plot boundary without any manner of opening on that side if the owner
of the plot on that side voluntarily agrees for the same in writing.
(5) Every building up to 10 meters in height shall have a minimum side yard of 1.20 meters on one
side and a minimum of 1.00 meter on the other side.
Provided that in the case of buildings up to 7 meters height, the depth or yard on one side may be
reduced to not less than 75 cms without any opening such as door and window on that side, but
however, ventilator opening may be made at a height of 2.10 metres from the corresponding floor
level if the side yard on the other side have a minimum of 1.20 meters.
P a g e |312
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Provided further that in the case of building unto 7 meters height the depth of side yard on one
side other than that having 1.20 meters may be reduced below 75 cms or even abut the plot
boundary without any manner of opening on that side, if the owner of the plot on that side
voluntarily agrees for the same in writing.
(6) Any room intended for human habitation and not abutting on either front, rear or side open
air spaces shall abut on an interior open space whose width shall not be less than 2.4 meters:
Provided that in the case of buildings up to 7 meters height it shall be sufficient if such interior
open space has a minimum width of 1.5 meters.
(7) Sufficient land shall be kept unpaved or sufficient opening shall be provided in the land to allow
percolation of rain water in the plot itself and rain, water from a plot shall be connected with
public drainage system only in case of plots with impermeable soil.
(8) For buildings above 10 meters in height, in addition to the minimum front, rear and side open
spaces required for height up to 10 meters, there shall be provided proportionate increase in such
minimum open space at the rate of 0.5 meter per every 3 meters height exceeding 10 meters:
Provided that such additional set back corresponding to increase in may be provided, for the whole
building at ground level or for corresponding floors at their level.
(10) No construction or hanging of any sort shall be permitted to project outside the boundaries
of the site.
(11) Every open space provided, either interior or exterior shall be kept free from any erection
thereon and shall be open to the sky and only cornice, roof or whether shade not more than 0.60
meter width shall overhang or project over the said open space so as to reduce the width to less
than the minimum required:
Provided that where the open space is minimum 0.60 meter the cornice, roof or weather shade
shall be limited to 30 cms. and where the open space is less than 0.60 meter no projection
whatsoever shall be permitted:
Provided further that where the open space has minimum 1.50 meters. cornice roof or weather
shade up to 75cms shall be permitted and increase in the width of cornice roof of weather shade
shall be permitted corresponding to increase in the open space:
Provided further that no door or window shall he permitted if the open space on that portion is
less than 1 meter:
Provided further that open stair or flight of steps or ramps meant as access to upper or lower
floors shall be permitted in the open space if such stair, step or ramp has minimum 60cms distance
from the boundaries.
Provided also that the underneath of the ramp shall not be enclosed however pillars may be
permitted for its support. (12) The front, rear and side set-backs for constructions below ground
level (basement floor, etc.) shall be the same as that required for a 10 meters height building of
the same occupancy group constructed above ground level.
P a g e |313
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
(1) The minimum distance between the central line of a street and any building other than a
compound wall or fence or outdoor display structure shall be 4.5 meters and that between plot
boundary abutting the street and building shall be 3 meters.
Provided that in the case of cul-de-sac of whatever width but not exceeding 250metres length or
pedestrian lanes and streets up to average 3 width or internal roads and streets of whatever width
within or leading to and residential colony, it shall be sufficient if the distance between the plot
boundary abutting the street and building is 2 meters for buildings up to 7 meters height
irrespective of the distance from the central line of the road to the building.
Provided further that in the case of lanes not exceeding 75 meters length leading to one or more
individual plots it shall be sufficient if the distance (between the plot boundary abutting the lane
and the building is 1.50 irrespective of the distance from the central line of the lane.
(2) Any restriction under street alignment or building line or both, if any fixed for area and
restriction under any development plan or any (town planning scheme or approved road widening
proposal or any other or byelaws shall also apply simultaneously to all buildings in addition to the
provisions contained in sub rule (1).
(3) The provisions contained in sub rules (1) and (2) shall apply invariable all buildings where the
front, rear or side yard abuts a street or gain access through a street.
No person shall construct any building other than compound wall within 3 meters, from any plot
boundary abutting national highways, state highways or other roads-notified by Municipality:
Provided that open ramps or bridges or steps or similar structures with or without parapets or
railings shall be permitted as access from the street to the building within that 3 meters and
cornice roof or weather shade not exceeding 75 cms shall be permitted to project from the
building into such 3 meters.
27. Developments including land subdivision and plot development for residential use.
All new developments including land subdivisions and plot developments shall be subject to the
following, namely:
(i) the area of any newly subdivided plot, reconstituted plot or building plot shall be not less than
125 square meters with an average width of 6.00 meters:
Provided that for row housing where side open spaces are not required, it is sufficient if the plot
has an average width of 4.50 meters.
(ii) every plot shall have a frontage of not less than 4 meters on any abutting street;
(iii) every street shall have not less than 7.00 meters width and shall be motorable:
P a g e |314
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Provided that in the case of cul-de-sacs with length not exceeding 250 meters, it is sufficient if the
street (cul-de-sac) has not less than 5.00 meters width and in the case of cul-de-sacs not exceeding
75 meters, it is sufficient if the street (cul-de-sac) has not less than 3.00 meters width:
Provided further that in residential areas where motor able street cannot made due to difficult
terrain, the width of any new street shall be not less 5.00 meters and where the length of such
street does not exceed 250 meter it is sufficient if the street has not less than 3.00 meters width.
(iv) when the area of the land under development work, layout or subdivision is 50 acres or more,
ten percent of the total area shall be provided for recreational open spaces and shall be suitably
located to be accessible the residents of the layout.
Provided that while considering the area of the land, the area of any contiguous land belonging to
the same owner, though not proposed 1 immediate development shall be taken into account;
(v) the recreational open space to be provided under item (iv) shall have an access as if it were a
separate plot and as far as possible it shall be in 1 piece and in no case less than 2 areas in area
with a minimum width of 6 meters.
(vi) the layout or subdivision proposal shall be in conformity with the provisions of published or
sanctioned development plan for the area and if the land is affected by any reservation for a public
purpose, the Secretary may agree to adjust its exact location to suit the development but not so
as to affect its area;
(vii) the street junctions shall be splayed or rounded off to give sufficient turning radii and sight
distance for vehicles and the side if the splay shall be a minimum of 4 meters for roads up to 10
meters and shall be a minimum of 1 meter for roads exceeding 10 meters width.
(viii) in the case of lay out or sub division of land having an area of two hectares or more a suitable
plot for an electric transformer shall be provided;
(ix) in the case of development permits, approval of the District Town Planner shall be obtained
for land upto 0.5 hectares in area and approval of chief Town Planner shall be obtained for land
exceeding that area.
(x) if the site forms part of approved layout, copy of sub division layout shall be enclosed along
with the plans for approval; and
28. Development including land sub-division and plot development for mercantile (commercial)
development. - All new developments land including sub-divisions and plot developments shall be
subject to the following:
(i) the width of every new street, public or private, intended for use as cart or carriage way giving
access to or through a commercial precinct consisting of a continuous row of shops exceeding ten
in number shall not be less than to meters except in the case of cul-de-sac not exceeding 150
meters length, Where the minimum width shall be 7 meters;
P a g e |315
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
(ii) the frontage of every commercial plot abutting the street, shall have a minimum width of 6
meters;
(iii) no plot with a layout proposed for commercial development shall be an area less than 60 Sq.
meters;
(iv) for every plot within a layout for commercial development, building line from the street shall
not be less than 3 meters;
(v) no plot intended to house a service garage or auto workshop with in a layout for commercial
development shall be of an area less than 300 sq.mts and an average plot width less than 12
meters.
(vi) the approval of the Chief Town Planner or an officer authorized by him shall be obtained for
the layout of all new commercial street and land sub-division exceeding five plots.
29. Development including land sub-division and plot development for industrial
development.- All new developments including land sub- divisions and plot developments shall be
subject to the following:-
(i) the width of every new street, public or private, intended for use as a cart or carriage way giving
access to or through an organized industrial area with not less than six constituent units, shall be
minimum 10 meters:
Provided that in the case of small industrial units or cul-de-sac not exceeding 150 meters length,
the minimum road width shall be 7 meters.
(ii) the minimum size of industrial plot abutting street shall be 400 sq. meters in extent with a
width of not less than 15 meters:
Provided that the minimum plot requirement in item (ii) shall not apply to small industrial units;
(iii) in industrial layouts a place for installation of transformer shall be provided in consultation
with the Chief Electrical Inspector or an officer authorized by him;
(iv) the approval of the Chief Town Planner or an officer authorized by him shall be obtained for
the layout of industrial streets and land sub-division exceeding five plots;
Note: For the purpose of these rules small industrial unit means an industrial unit classified as such
by Government from time to time or an industrial unit not included in Schedule 1 of the Factories
Act, 1948.
(v) the usage of plots proposed for development or redevelopment shall be governed by the
provisions contained in the development plan or detailed town planning scheme prepared for the
locality:
Provided that where no such plan exists, the usage of plots shall be as approved by the Chief Town
Planner or an officer authorized by him.
P a g e |316
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
OCCUPANCY
30. Occupancy of buildings.
(1) The occupancy of any building or part thereof shall be governed by the usage of plots
proposed for development or redevelopment according to the provisions contained in the
development plan or detailed town planning scheme prepared for the area.
(2) All buildings, whether existing or hereafter proposed, shall be classified in one of the
following occupancies according to the use or character of occupancy, namely:
Group AI Residential
Group A2 Special Residential
Group B Educational
Group C Medical/Hospital
Group D Assembly
Group E Office/Business
Group F Mercantile/Commercial
Group GI Industrial
Group G2 Small industrial
Group H Storage
Group 1(1) and Group
Hazardous
1(2)
Notes: (i) Any building not specifically covered by any of the occupancies under sub rule (2)
shall be in the group which most nearly resembles its exiting or proposed use.
(ii) Any building which accommodates more than one use under sub-rule (2) shall be included
under the most restrictive group.,
(a) Group AI. - Residential Building shall include any building in which sleeping
accommodation is provided for normal residential purposes, with or without cooking and or
dining facilities. They shall include one or multifamily dwellings, apartment houses or
residential flats. Small professional offices or spaces for advocates, doctors, engineers,
architects, chartered accountants, beauticians, tailors, photographers, videographers,
telephone booth operator, computer professionals, typists, electrical or electronic
equipment service professionals, not exceeding 50 sq. metres floor area and used as part of
principal residential occupancy are also included in this group. Further, lodging or rooming
houses, tourist homes, dormitories, hostels and hotels not exceeding 150 sq. metres floor
area are included in this group.
(b) Group A2. - Special Residential building shall include all lodging or rooming houses,
dormitories, tourist homes, hostels hotels exceeding 150 sq. metres floor area with or
without conference halls, community halls, dining halls or assembly rooms Crèches, day care
centres, children's nursery, reading rooms libraries and educational buildings not exceeding
150 sq. metres floor area are also included in this group.
P a g e |317
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
(c) Group B.- Educational building shall include all educational buildings or part thereof
exceeding 150 sq. metres floor area, used for school, college, institution, education and or
research.
(d) Group C. - Medical or Hospital Building shall including any building or part thereof-
exceeding 150 Sq. metres of build-up area used for purposes such as medical or other
treatment or care of persons suffering from physical or mental illness, disease or infirmity,
care of infants, convalescents or aged persons. Hospitals, sanitoria, clinic, homes for the aged
and the infirm, convalescent homes, mental hospitals are included in this group.
(e) Group D.- Assembly building shall include any building or part of a building exceeding 300
sq. metres of total floor area where people, congregate or gather for amusement, recreation,
social, religious, patriotic, civil, travel and similar purposes such as theatres, motion picture
houses or cinemas, assembly halls for educational dramatic or theoretical presentation,
auditoriums wedding halls, community halls, exhibition halls, art galleries, museums libraries,
skating rings, gymnasiums, congregation, dance halls, club rooms, passenger stations or
transport terminals, recreation piers, amusement park structures, viewing stands, grand
stands, stadia and circus tents.
(f) Group E. Office or business building shall include any building or part of a building having
a total floor area of more than 300 sq. metres which is used for transaction of public or private
business or for accommodating offices of public or private agencies or for the keeping of
records, accounts and similar purposes. Local, State and Central Government office and
buildings for office purposes constructed by private sector and quasi government agencies
and buildings for the use of defence, court houses, public utility buildings, jails and prisons
are included in this group.
(g) Group F. Mercantile or commercial building shall include any building or part of a building
which is used for display and sale of merchandise such as shops, stores, markets, either
wholesale or retail. Banking and financial institutions, public and private business houses,
professional establishment of doctors, dentist, engineers, architects, lawyers, pathological
laboratories, tailor shops, video shops, barbershop, beauty parlours, newsstands, milk
booths, restaurants and non-nuisance type of small establishment like armature winding
shops using power motor or machine of capacity not exceeding 3 horse power are included
in this group. Further, buildings or part of buildings used exclusively for parking of vehicles
(parking buildings, parking plazas etc.) are also included in this group.
Notes. - (1) Any building with not more than 150 sq. metres built up area accommodating the
use under Group C and with not more than 300 sq. metres built up area accommodating the
use under Groups D, E and H shall be included in Group F.
(2) Minor merchandising operations in buildings primarily meant for other uses shall be
covered by the group under which the predominant occupancy is classified.
Group G1.- Industrial building shall include any building or part thereof where products or
materials of all kinds and properties are fabricated, assembled or processed. It includes
workshops, assembly plants, laboratories, dry cleaning plants, power plants, pumping
stations, smoke houses, laundries, gas plants, refineries, dairies, saw mills, and the like.
P a g e |318
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
(j) Group G2. Small industrial building shall include any building or part thereof where
products or materials of all kinds and properties are fabricated, assembled or processed by a
small-scale industrial unit.
Note: 'Small scale industrial unit' means an industrial unit carrying on small scale industry
classified as such by government from time to time for this purpose but does not include an
industry included in schedule 1 of the Factories Act, 1948.
Group H. Storage building shall include any building or part thereof used primarily for the
storage or sheltering (including servicing, processing or repairing incidental to storage) of
goods, wares or merchandise (except those involving highly combustible or explosive
products or materials), vehicles and the like. Ware-houses, freight depots, transit sheds, store
houses, garages, hangers, grain elevators, barns and silos are included in this group. Minor
storage incidental to other occupancies shall be treated as part of the predominant
occupancy.
(1) Group I (I). Hazardous building shall include any building or part of a building which is used
for purposes which create air and sound pollution of minor nature and or producing effluents
which does not cause very adverse environmental effects. Automobile wash stalls,
automobile service stations, service garages with repairing facilities, welding workshops, are
included in this group. Poultry farms with more than [x x x] 20 hens or ducks, dairy with more
than [ x x x ] 6 cattle, kennel with more than [x x xl 6 dogs are also included in this group.
(m) Group 1 (2)- Hazardous building shall include any building or part of a building which is
used for the storage, handling, manufacturing processing of highly combustible, explosive,
poisonous, irritant, corrosive, toxic or noxious materials or products or any products or
materials producing dust. They shall include buildings and yards used for,-
(i) [ x x x ] storage under pressure of more than 1 Kg/cm2 and in quantities exceeding 70 m3
of acetylene, hydrogen, illuminating and natural gases, ammonia, chlorine phosgene, sulphur
dioxide, methyl oxide and all gases subject to explosion, fumes or toxic hazard;
(iv) manufacture of plastic goods, synthetic leather, ammunition, explosives and fireworks;
(v) crematoria, burial grounds, garbage dumping yards, abuttoirs (slaughter houses),
sewerage treatment plants, petrol filling stations, coal, wood and timber yards with saw mills;
(1) The maximum percentage of coverage permissible for each occupancy shall limit
the maximum area at any floor of a building. The floor area ratio value shall limit the
maximum buildable total floor area. Floor area ratio ie, F.A.R. shall be calculated as shown
below:
P a g e |319
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
(2) The percentage of coverage and the F.A.R. value of building under different occupancies
shall not exceed the maximum specified in Table 2 below.
TABLE 2
Coverage and Floor Area Ratio (F.A.R)
Maximum Maximum
Permissible permissible Maximum
Building use / Coverage F.A.R permissible
Sl.No.
Occupancy (percentage without F.A.R with
of plot additional additional fee
area) fee
(1) (2) (3) (4) (5)
1 Residential A1 65 3.00 4
2 Special Residential A2 65 2.50 4
3 Educational B 35 2.50 3
4 Medical/Hospital C 40 2.00 3
5 Assembly D 40 1.50 2.50
6 Office/Business E 40 2.00 3
Mercantile/Commercial
7 65 2.50 4
F
8 Industrial G1 40 1.50 0
9 Small Industrial G2 60 2.50 3
10 Storage H 60 2.50 3
11 Hazardous I(1) 30 1.00 0
12 Hazardous I(2) 25 0.70 0
(3) For permitting for FAR shown in column (5) of Table 2, an additional fee at the rate of
Rs.1000 per square meter exceeding the area permissible under column (4) shall be paid.
32.Height of buildings.
2[(1) The Maximum height of any building or part thereof shall be limited according to the
width of the street as follows:
(a) The maximum height of the building or part thereof shall not exceed twice the width of
the street abutting the plot plus twice the width of the yard from the building to the abutting
street and this height may further be increased proportionately at the rate of 3 metres for
every 50 cms. by which the building or the corresponding portion or floor of the building is
set back from the building line;
(b) If a building plot abuts on two or more streets of different width, the building plot shall
be deemed to abut the street that has the greater width for the purposes of this rule and the
P a g e |320
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
height of the building shall be regulated by the width of that street and shall be continued at
this height along the narrower street:
Provided that the height restriction as per this rule shall be compulsory only for buildings or
part of building coming within 12 metres of building line:
Provided further that appurtenant roof structures like staircase tower over head tanks, air
conditioning rooms, cellular telecommunication equipment or tower structures, cabin rooms,
chimneys, parapet walls and similar roof structures other than pent houses shall not be
included in the height of the building for the purpose of this rule:
Provided also that architectural features serving no other function except that of decoration
shall not be included in the height of the building for the purpose of this rule.]
(2) For buildings, structures and installations in the vicinity of airports the stipulations with
regard to height shall be further limited as shown in Table 3. This shall be subject to any
notification issued by Government of India under the Aircrafts Act 1, 1934.
[Provided that buildings, structures and installations exceeding the height shown in Table 3
shall be allowed if no objection certificate from the concerned airport authority is obtained
and produced before the Secretary for issuing the permit.]
TABLE 3
Aerodrome Vicinity Height Restrictions
3[Notes:- (1) No tree shall be allowed to grow above the height shown in column (4) within
the distance shown in column (2) and (3) respectively.
(2) For calculation of permissible height as per this sub rule the highest point of the building
without any exemption shall be considered.]
(33) Access
(1) The minimum clear width of access to a building and plots as well as the width of the
street giving access to the plot from the main street shall be as shown in Table 4.
Table 4
Access
Residential Non-Residential
Up to 300Sq. Above 300Sq.
Type of
Sl. No. Single Units Multiple Units meter of carpet meter of carpet
Building
area in each floor area in each floor
1. Single storey No minimum 1.20 metres 1.20 metres 3.60 metres
2. Two storeys 90 cms 3.60 metres 2.00 metres 5.00 metres
3. Three storeys 1.20 metres 5.00 metres 3.60 metres 5.00 metres
Above three
4. 3.60 metres 5.00 metres 5.00 metres 7.00 metres
storeys
[Provided that wherever off-street parking is required for the building as per these rules,
motor able access width shall be provided to the plot.]
Provided further that the access width of any building shall be modified to be in accordance
with the provisions in any detailed development plan for the area.
(2) No person shall at any time construct or cause or permit to construct or reconstruct any
building which in any way encroaches upon or diminishes the area set apart as access to that
building.
(3) No person shall construct a building or undertake construction work on a building which
reduces the access to any building previously existing, below the minimum width required
under these rules.
(4) No building shall be constructed so as to deprive any other building of an existing access.
(5) The space set apart as access shall be separately distinguishable from any house gully or
open space required to be provided under any other rule.
(6) Every access shall be drained and lighted to the satisfaction of the Secretary and man-hole
covers or other drainage, water or any other fittings laid in such access shall be flush with
finished surface level so as not to obstruct safe travel over the same.
34. Parking, loading and unloading spaces. - (1) Each of street parking space provided for
parking motor cars shall be not less than 15 Sq. mts. area (5.5 mts. x 2.7mts.) and for scooters
P a g e |322
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
and cycles the area of each parking space provided shall be not less than 3 sq. mts. and 1.5
sq. mt. respectively.
(2) For buildings of different occupancies, off-street- parking spaces for motor cars shall be
provided within the plot as specified in Table 5.
Table 5
off-street Parking Space
Sl. No Occupancy One parking space for every or fraction of
(1) Group A1- Residential (a) 8 units (with each unit upto 100 sq. metres of
Apartment Houses/Flats carpet area)
(b) 4 units (with each unit above101 sq. metres and
upto 150 sq. meter of carpet area)
(c) 2 units (with each unit above151 sq. metres and
upto 200 sq. meter of carpet area)
(d) Single unit (exceeding 200 sq metres of carpet
area)
(2) Group A2- Special (i) Rooms with attached bath and w.c.
Residential, Lodging and (a) 8 rooms (with each room upto 12 sq, metres
Rooming Houses, Tourist carpet area)
homes and hostels, (b) 5 rooms (with each room above 12
Dormitories without any sq. metres and upto 20 sq. metres carpet area)
attached eating facility such (c) 3 rooms (with each room above 20 sq, metres
as restaurant. Canteen, carpet area)
Cafeteria, mess or dining (ii) Rooms without attached bath and w.c.
(a) 18 rooms (with each room upto 5 sq, metres
carpet area)
(b) 12 rooms (with each room above 5
sq. metres and upto12 sq. metres carpet area)
(c) 6 rooms (with each room above 12 sq, metres
carpet area)
Note:- At the rate of one parking space for every 30
sq. metres carpet area of dining space/20 seats of
dining accommodation shall be provided in addition
to the above, in case of Special Residential. Buildings
attached with eating facility.
(3) Group B-Educational (i) 300 sq metres of carpet area.
(i) High Schools, Higher
Secondary Schools, Junior
Technical Schools, Industrial
Training Institute etc. (ii) 200 sq metres of carpet area.
(ii) Higher educational
institutes.
(4) Group C- Medical/Hospital 100 sq metres of carpet area.
(5) Group D- Assembly 25 seats of accommodation
Note:-
(i) In case of wedding halls and community halls, for
calculating the carpet area or seating
accommodation, for the purpose of off street
parking, the carpet area of either the auditorium or
P a g e |323
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Provided that in Second Grade Municipalities and Third Grade Municipalities it shall suffice if
75 per cent and 50 per cent respectively of the above parking is provided in village panchayats
where the provisions of the Kerala Municipality Building Rules, 1999 stand extended, off
street parking shall be provided as in third grade municipalities.
(3) Wherever any parking space is required under these rules, 25% of that area shall be
provided additionally for parking scooters or cycles.
(4) Every off-street parking space shall be provided with adequate vehicular access to a street;
area of drives, aisles and such other provisions required and adequate area for manicuring of
vehicles shall be provided in addition to the parking space.
(5) In addition to the parking space as in Table 5, in the case of Group F Mercantile or
Commercial, Group G-Industrial and Group H storage occupancies, loading and unloading
spaces each 30 sq. mts. shall be provided within the plot, at the rate of one such space for
each 1000 sq. mts. of floor area or fraction thereof, exceeding the first 700 sq. mts. of floor
area.
(6) Not exceeding fifty per cent of the area of mandatory open yard (space) shall be taken
into account for calculating the required off street parking space if such open space has
adequate vehicular access and area for maneuvering.
(7) The Government may, if adequate off street parking facility is available to their satisfaction
near the site proposed for building, in any parking building or parking area provided by the
Municipality or quasi-Government agency or private agency, permit the secretary by general
or special order and subject to conditions specified there in to allow reduction in off street
parking space in any or all buildings in that area to the extent not exceeding 50 per cent of
the required number of off street parking space.
P a g e |324
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |325
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
A thorough reconnaissance is done primarily to identify suitable existing geodetic control points in the
vicinity. The selected control point is accessible, preferably by vehicle, and has an open horizon.
The base receiver is set in the centre of the project area such that all the rover control points fall within
2.5km radius to attain sub centimetre accuracy.
The rover receiver is enclosed in a backpack, which affords a convenient means of conducting the data
collection. The antenna is mounted on a range pole, and the data collector is held by the operator.
This configuration is well suited to the mobility required for the fieldwork.
The Base Reference points were established with an observation time of 4 Hours. All the control points
were established with an observation time of 1 hour.
d) Post-processing operations
Trimble Business Centre Software is used for all the post processing operations. All data collected and
stored in the receiver relate to the World Geodetic System of 1984 (WGS 84) reference ellipsoid. The
data is processed on WGS 84 and converted to the local UTM coordinates once processing has been
completed.
Levelling
Carrying out the benchmark by deploying double fly levelling from the nearest Irrigation Dept.
Benchmark. The BM location with value was Obtained from BPCL. The Following BM was Used to
establish BMs Throughout the Project area with a MSL of 35.883m
Fly levelling was carried out using two good qualities Electronic Digital Levels and Bar-Coded Levelling
Staffs with Reading levels simultaneously. The levelling instruments were always kept free of
collimation error, which was checked and adjusted, before start of work every day.
Closing error in levelling was limited to 10L mm where L is the length of route in km.
Levelling was carried to all the Traverse control point to establish vertical control.
P a g e |326
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |327
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
List of Benchmarks
BENCHMARK LIST - KINFRA
2 TBM 1104299.577 650985.833 26.640 Bottom level of lamp pole in FRBL office
K2 circle, FACT, Kochi Division, Kerala.
3 TBM 1104747.869 651723.060 22.460 Top level of chamber wall in Sewage pond
K3 circle, FACT, Kochi Division, Kerala.
6 TBM 1104569.493 651998.801 20.833 Top level of pipe line pillar at lake bridge,
K6 near A2 land portion, FACT, Kochi Division,
Kerala.
7 TBM 1104037.956 652957.994 34.995 Top level of retaining wall, in front fact gate
K7 type 5, also near building no 505, FACT,
Kochi Division, Kerala.
P a g e |328
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |329
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
angular measurement, whichever is less (where L is the least count of the instrument and N is the
number of stations).
Traverse was done using Total Station Starting from a pair of GPS Points and run along the road for
about 2km and the traverse was closed to another pair of GPS Points.
Contouring
Spot level surveying at an interval of 20 meters grid was carried out in the entire project area. The
contours were interpolated at 0.50 meters’ intervals based on levelling conducted.
Surveying of Roads and recoding centreline levels at every 20m intervals and picking up all the
features along the Roads.
Surveying for locating the natural and manmade details as described earlier.
P a g e |330
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Calibration Certificates
The calibration certificate of instruments is enclosed after this page.
P a g e |331
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Drawings
The drawings were prepared directly on computers using standard software like Autodesk AutoCAD
2017 and Autodesk Civil 3D.
P a g e |332
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |333
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |334
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |335
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Findings
Field Observations
BOREHOLE NO: 1 (13.50m) (X=653039.8350, Y=1104094.3524) (RL:28.97m)
In BH-1, the top 3.70m comprise of dense to very dense silty clayey sand with lateritic gravel (reddish
brown) having S.P.T value of 47 to 56. Below this medium dense clayey sand with lateritic gravel
(yellowish and reddish) having S.P.T value of 18 was noted extending up to a depth of 5.00m. This was
followed by very stiff sandy silty clay with gravel (reddish and yellow) having S.P.T value of 21
extending up to a depth of 6.60m. From 6.60m to 9.40m medium dense to dense clayey silty sand
(yellowish brown) having S.P.T value of 23 to 36 was noted. At 9.40m SPT rebound was noted. Below
this soft weathered rock was noted extending up to a depth of 10.50m. This was followed by jointed
hard rock (white) extending up to a depth of 12.00m. From 12.00m to 13.50m jointed granitic hard
rock (white) was noted and the borehole BH1 was terminated at 13.50m. In the 1st lift of rock cutting
a core recovery of 29% and RQD of 15% was noted from 10.50m to 12.00m in the jointed hard rock
strata. In the 2nd lift of rock cutting a core recovery of 54% and RQD of 30% was noted from 12.00m
to 13.50m in the jointed hard granitic rock strata. Water table was noted at a depth of 4.00m from
ground level in the borehole during the time of investigation.
In BH-2, the top 3.70m comprise of gravel (reddish brown) and white gypsum having S.P.T value of
greater than 100. Below this clayey gypsum (white) having S.P.T value of 88 was noted extending up
to a depth of 5.00m. This was followed by very stiff sandy silty clay (yellowish) with white gypsum
having S.P.T value of 20 to 30 extending up to a depth of 11.00m. From 11.00m to 12.60m hard sandy
silty clay (yellowish) having S.P.T value of 34 was noted. Below this hard sandy clay (yellowish) having
S.P.T value of 34 to 51 was noted extending up to a depth of 15.70m. This was followed by very dense
silty sand (yellowish) having S.P.T value of greater than 100 extending up to a depth of 17.00m. From
17.00m to 18.60m very stiff clayey sandy silt (yellowish) having S.P.T value of 28 was noted. Below
this hard clayey sandy silt (yellowish) having S.P.T value of 33 was noted extending up to a depth of
20.50m. At 20.50m SPT rebound was noted. This was followed by hard granitic rock (greyish)
extending up to depth of termination of borehole BH2 at 21.50m. In the 1st lift of rock cutting a core
recovery of 83% and RQD of 83% was noted from 20.50m to 21.50m in the granitic jointed rock strata.
P a g e |336
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Water table was noted at a depth of 4.00m from ground level in the borehole during the time of
investigation.
In BH-3, the top 2.00m comprise of very dense silty clayey sand with lateritic gravel (reddish brown)
having S.P.T value of greater than 100. Below this hard sandy silty clay with lateritic gravel and white
gypsum (reddish brown) having S.P.T value of 33 was noted extending up to a depth of 3.60m. This
was followed by very stiff sandy silty clay with lateritic gravel and white gypsum (reddish brown)
having S.P.T value of 22 extending up to a depth of 5.00m. From 5.00m to 6.80m very stiff sandy clayey
silt with white gypsum (reddish brown) having S.P.T value of 29 was noted. At 6.80m SPT rebound was
noted. Below this weathered soft rock was noted extending up to a depth of 7.80m. This was followed
by hard granitic rock (light greyish) extending up to depth of termination of borehole BH3 at 8.80m.
In the 1st lift of rock cutting a core recovery of 61% and RQD of 34% was noted from 7.80m to 8.80m
in the granitic jointed rock strata. Water table was noted at a depth of 6.00m from ground level in the
borehole during the time of investigation.
BOREHOLE NO: 4 (11.30m) (X=651309.19, Y=1105192.35) (RL:5.148m)
In BH-4, the top 2.00m comprise of very dense clayey silty sand with lateritic gravel and white gypsum
(reddish brown) having S.P.T value of 53. Below this hard-sandy silty clay with lateritic gravel and
gypsum (reddish brown) having S.P.T value of 60 was noted extending up to a depth of 3.60m. This
was followed by stiff sandy silty clay with lateritic gravel and gypsum (reddish brown) having S.P.T
value of 12 extending up to a depth of 5.00m. From 5.00m to 6.60m stiff sandy silty clay with gravel
(yellowish brown) having S.P.T value of 13 was noted. Below this medium dense silty clayey sand with
gravel and gypsum (reddish brown) having S.P.T value of 11 was noted extending up to a depth of
8.00m. This was followed by medium dense silty clayey sand with weathered rock and gypsum
(reddish brown) having S.P.T value of 10 extending up to a depth of 9.00m. From 9.00m to 10.30m
weathered rock (greyish brown) was noted. Below this granitic jointed hard rock (light grey) was noted
extending up to a depth of termination of borehole BH4 at 11.30m. In the 1st lift of rock cutting a core
recovery of 92% and RQD of 66% was noted from 10.30m to 11.30m in the granitic jointed hard rock
strata. Water table was noted at a depth of 7.50m from ground level in the borehole during the time
of investigation.
BOREHOLE NO: 5A (12.00m) (X=649145.07, Y=1103570.74) (RL:2.582m)
In BH-5A, the top 3.70m comprise of soft sandy silty clay with white gypsum (greyish) having S.P.T
value of 2 to 3. Below this medium stiff silty clay with organic matter (dark grey) having S.P.T value of
5 was noted extending up to a depth of 6.70m. This was followed by very loose to lose silty clayey
sand (light grey and brown) having S.P.T value of 3 to 6 extending up to a depth of 9.80m. At 9.80m
SPT rebound was noted. From 9.80m to 10.50m soft weathered rock (greyish brown) was noted.
Below this jointed granitic rock (light grey and white) was noted extending up to a depth of
termination of borehole BH 5A at 12.00m. In the 1st lift of rock cutting a core recovery of 35% and
RQD of 35% was noted from 10.50m to 12.00m in the granitic jointed rock strata. Water table was
noted at a depth of 4.00m from ground level in the borehole during the time of investigation.
to very dense sand. This was followed by medium dense sand extending up to a depth of 5.00m. In
area of BH5A the top 3.70m comprise of soft clay. Below this medium stiff clay was noted extending
up to a depth of 6.70m. Since the top strata comprise of soil mixed with gypsum, shallow foundation
if adopted as such in this stratum will undergo differential settlements.
BOREHOLE 1:
For light structures, shallow foundation may be provided in the dense to very dense sand strata at a
depth of about 1.00m from the ground level. The bearing capacity of the strata will be controlled by
the settlement characteristics of medium dense sand layer beneath. Depending upon the intensity of
loading either wall footing, Isolated foundation, strip footing or raft foundation may be adopted.
Width = 2.0 m
A typical calculation is given below for BH-1, Depth-1.00m and Width of footing-2.00m
As per IS 6403-1981 clause 5.1.2 the Ultimate net Bearing Capacity in general shear failure
Average S.P.T. value of 33 is noted in the zone of influence of pressure (considering a footing of width
2m), From IS-8009-1976 bearing capacity for settlement of 25mm works out to be 15 T/m2
Hence a safe bearing capacity of 15T/ m2 may be taken for a footing of width 2.00m at a depth of
1.00 m in area of BH1 from ground level.
For medium heavy to heavy structures, bored cast in situ DMC pile terminating in the hard rock strata
noted from a depth of 10.50m can be adopted. If any weathered rock is noted during the boring
P a g e |338
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
operations then the piles should fully penetrate the weathered rock and should be seated on hard
rock.
BOREHOLE 2, 3 and 4:
In areas of BH2, BH3 and BH4, for the G+2 Storied Building/ Treatment Plant, for heavy structures,
bored cast in situ DMC pile terminating in the hard rock strata can be adopted. If any weathered rock
is noted during the boring operations then the piles should fully penetrate the weathered rock and
should be seated on hard rock.
Based on the crushing strength of the rock samples done at laboratory, the least uniaxial
compressive strength of rock samples is obtained as 4388 T/m2 at a depth of 20.50m-21.50m.
P a g e |339
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
Nj = 0.25
=379.76+3.07
As per IRC-78 2014 guide lines, practical aspects and considering, the strength of end bearing limited
to 5MPa. Hence the load of 700mm diameter pile can be assessed as 190 tonnes
(B) Capacity from Structural Strength Criteria:
1. Considering grade of Concrete to be used = M30
Hence the safe carrying capacity of the pile end bearing on the rock strata will be governed by the
rock strength criteria and the safe capacity of 700mm dia pile can be taken as 190 Tonnes.
BOREHOLE 5:
For light structures, shallow foundations may be provided after densifying the very loose to loose
sand layer by using suitable methods of ground engineering techniques such as sand piling, dynamic
compaction, vibro flotation etc.
Sand piles of 100mm diameter may be provided at 45cm spacing using displacement method
extending up to 6m or refusal for improvement of the weak strata. The improved soil can take a safe
bearing capacity of 7t/m2 for a footing of width 1.00m commencing from the improved strata at a
depth of 1.50m from the ground level. Depending upon the intensity of loading either wall footing,
Isolated foundation, strip footing or raft foundation may be adopted.
For medium heavy structures, bored cast in situ under reamed piles may be adopted terminating in
the loose sand strata at a depth of 9.00m. Suitable precaution has to be adopted in order to prevent
the sides from caving while boring through the loose/medium dense sand layer.
P a g e |340
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
For heavy structures, bored cast in situ DMC pile terminating in the hard rock strata noted from a
depth of 10.50m can be adopted. If any weathered rock is noted during the boring operations then
the piles should fully penetrate the weathered rock and should be seated on hard rock.
Recommendations
From the study of the boreholes, it was noted that, in areas of BH2, BH3 & BH4 the top 2.00m and
3.70m comprise of very dense sand and gravel & gypsum. Below this hard clay and clayey gypsum was
noted extending up to a depth of 3.60m and 5.00m. In area of BH1 the top 3.70m comprise of dense
to very dense sand.This was followed by medium dense sand extending up to a depth of 5.00m. In
area of BH5A the top 3.70m comprise of soft clay. Below this medium stiff clay was noted extending
up to a depth of 6.70m. Since the top strata comprise of soil mixed with gypsum, shallow foundation
if adopted as such in this stratum will undergo differential settlements.
BOREHOLE 1:
For light structures, shallow foundation may be provided in the dense to very dense sand strata at a
depth of about 1.00m from the ground level. The bearing capacity of the strata will be controlled by
the settlement characteristics of medium dense sand layer beneath. A safe bearing capacity of 15t/m2
may be adopted for a footing of 2m width commencing from the dense to very dense sand strata at a
depth of 1.00m from ground level. Depending upon the intensity of loading either wall footing,
Isolated foundation, strip footing or raft foundation may be adopted.
For medium heavy to heavy structures, bored cast in situ DMC pile terminating in the hard rock strata
noted from a depth of 10.50m can be adopted. If any weathered rock is noted during the boring
operations then the piles should fully penetrate the weathered rock and should be seated on hard
rock.
Safe vertical load carrying capacity of D.M.C. piles end bearing with adequate anchorage into hard
rock strata may roughly be assessed as
50cm 80t
60cm 110t
70cm 150t
P a g e |341
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
BOREHOLE 2, 3 and 4:
In areas of BH2, BH3 and BH4, for the G+2 Storied Building/ Treatment Plant, bored cast in situ DMC
pile terminating in the hard rock strata noted from a depth of 20.50m can be adopted. If any
weathered rock is noted during the boring operations then the piles should fully penetrate the
weathered rock and should be seated on hard rock.
Safe vertical load carrying capacity of D.M.C. piles end bearing with adequate anchorage into hard
rock strata may roughly be assessed as
60cm 140t
70cm 190t
BOREHOLE 5:
For light structures, shallow foundations may be provided after densifying the very loose to loose
sand layer by using suitable methods of ground engineering techniques such as sand piling, dynamic
compaction, vibro flotation etc.
Sand piles of 100mm diameter may be provided at 45cm spacing using displacement method
extending up to 6m or refusal for improvement of the weak strata. The improved soil can take a safe
bearing capacity of 7t/m2 for a footing of width 1.00m commencing from the improved strata at a
depth of 1.50m from the ground level. Depending upon the intensity of loading either wall footing,
Isolated foundation, strip footing or raft foundation may be adopted.
For medium heavy structures, bored cast in situ under reamed piles may be adopted terminating in
the loose sand strata at a depth of 9.00m. Suitable precaution has to be adopted in order to prevent
the sides from caving while boring through the loose/medium dense sand layer.
Load test are essential for accurate determination of pile capacity.
Safe carrying capacity of under reamed piles extending up to 9.00m, terminating in the loose sand
strata and with single bulb may roughly be assessed as
40cm 18t
50 cm 24t
P a g e |342
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
For heavy structures, bored cast in situ DMC pile terminating in the hard rock strata noted from a
depth of 10.50m can be adopted. If any weathered rock is noted during the boring operations then
the piles should fully penetrate the weathered rock and should be seated on hard rock.
Safe vertical load carrying capacity of D.M.C. piles end bearing with adequate anchorage into hard
rock strata may roughly be assessed as
60cm 110t
70cm 150t
For design consideration the horizontal load carrying capacity can be taken as 5% of the axial capacity
and the uplift capacity can be taken as 15% of the axial load capacity.
Initial Pile load tests shall be conducted to verify the pile capacities recommended.
If during piling it is observed that the soil profiles from piling operations are not consistent with the
bore logs, it may be immediately reported and designs revised if necessary. The foundation execution
is recommended under strict technical supervision.
References
Foundation Analysis and Design, J. E. Bowels, Mcgraw Hill Publication
Soil Mechanics and Foundation Engineering, K.R Arora, Standard Publishers Distributors,
Fourth Edition,1997
Soil Mechanics in Engineering Practice, 2nd Edition, Terzaghi K and Peck R.B, John Willey and
Sons,1967.
IS:6403-1981, Code of Practice for Determination of Bearing Capacity of Shallow Foundation.
Foundation Manual, N.V Nayak,1996.
Foundation Design and Construction, M.J Tomlinson, Viewpoint Publishers.
IS12070-1987, Code of Practice for Design of Shallow Foundation on Rock.
IS 2911 (PART1/SECTION 2)-1979, Code of Practice for Design and Construction of Pile
Foundation.
Pile Design, Poulos & Davis.
P a g e |343
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |344
Annexures
PETROCHEMICAL PARK AT AMBALAMUGHAL, KOCHI REVISED FINAL DETAILED PROJECT REPORT
P a g e |345
Annexures
Voyants Solutions Private Limited.
Grandiose, 7th Floor, Survey No.136/2 & 4
Opp. Rolling Hills, Gachibowli, Hyderabad- 500032
Ph.no: 040 – 4110 4160, Web: www.voyants.in