Object Orientation is a term used to describe the object – oriented(OO) method of building
software. In an OO approach, the data is treated as the most important element and it
cannot flow freely around the system. Restrictions are placed on the number of units that
can manipulate the data. This approach binds the data and the methods that will
manipulate the data closely and prevents the data from being inadvertently modified. The
following figure shows the method1, method2, method3, and method4.
The ‘object’ forms the basis around which the following properties revolve:
1. Encapsulation
Encapsulation:
In Object Orientation, a class is used as a unit to group related attributes and operations
together. The outside world can interact with the data stored in the variables that represent
the attributes of the class only through the operations of that class. Thus, the operations act
as interfaces of the object of the class with the outside world.
For example, consider the class Employee with attributes empID, empName and
dateOfJoining with is given below
What is OOAD?
An object-oriented system is composed of objects. The behavior of the system results from
the collaboration of those objects. Collaboration between objects involves them sending
messages to each other. Sending a message differs from calling a function in that when a
target object receives a message, it itself decides what function to carry out to service that
message. The same message may be implemented by many different functions, the one
selected depending on the state of the target object.
Object-oriented analysis
Object-oriented analysis (OOA) looks at the problem domain, with the aim of producing a
conceptual model of the information that exists in the area being analyzed. Analysis models
do not consider any implementation constraints that might exist, such
as concurrency, distribution, persistence, or how the system is to be built. Implementation
constraints are dealt during object-oriented design (OOD). Analysis is done before the
Design[citation needed].
The sources for the analysis can be a written requirements statement, a formal vision
document, interviews with stakeholders or other interested parties. A system may be
divided into multiple domains, representing different business, technological, or other areas
of interest, each of which are analyzed separately.
Object-oriented design
The concepts in the analysis model are mapped onto implementation classes and interfaces.
The result is a model of the solution domain, a detailed description ofhow the system is to
be built.
What is UML?
Unified Modelling Language (UML) is the set of notations,models and diagrams used when
developing object-oriented (OO) systems.
UML is the industry standard OO visual modelling language. The latest version is UML 1.4
and was formed from the coming together of three leading software methodologists; Booch,
Jacobson and Rumbaugh.
UML allows the analyst ways of describing structure, behaviour of significant parts of
system and their relationships.
The Unified Modeling Language is commonly used to visualize and construct systems
which are software intensive. Because software has become much more complex in recent
years, developers are finding it more challenging to build complex applications within short
time periods. Even when they do, these software applications are often filled with bugs, and
it can take programmers weeks to find and fix them. This is time that has been wasted,
since an approach could have been used which would have reduced the number of bugs
before the application was completed.
However, it should be emphasized that UML is not limited simply modeling software. It can
also be used to build models for system engineering, business processes, and organization
structures. A special language called Systems Modeling Language was designed to handle
systems which were defined within UML 2.0. The Unified Modeling Language is important
for a number of reasons. First, it has been used as a catalyst for the advancement of
technologies which are model driven, and some of these include Model Driven Development
and Model Driven Architecture.
Because an emphasis has been placed on the importance of graphics notation, UML is
proficient in meeting this demand, and it can be used to represent behaviors, classes, and
aggregation. While software developers were forced to deal with more rudimentary issues
in the past, languages like UML have now allowed them to focus on the structure and
design of their software programs. It should also be noted that UML models can be
transformed into various other representations, often without a great deal of effort. One
example of this is the ability to transform UML models into Java representations.
Unified Process
The Unified Software Development Process or Unified Process is a popular iterative and incremental software
development process framework. The best-known and extensively documented refinement of the Unified
Process is the Rational Unified Process (RUP).
Profile of a typical project showing the relative sizes of the four phases of the Unified
Process.
OVERVIEW
The Unified Process is not simply a process, but rather an extensible framework which should be customized
for specific organizations or projects. The Rational Unified Processis, similarly, a customizable framework. As
a result it is often impossible to say whether a refinement of the process was derived from UP or from RUP,
and so the names tend to be used interchangeably.
The name Unified Process as opposed to Rational Unified Process is generally used to describe the generic
process, including those elements which are common to most refinements. The Unified Process name is also
used to avoid potential issues of trademark infringement since Rational Unified Process and RUP are
trademarks of IBM. The first book to describe the process was titled The Unified Software Development
Process and published in 1999 by Ivar Jacobson, Grady Booch and James Rumbaugh. Since then various
authors unaffiliated with Rational Software have published books and articles using the name Unified
Process, whereas authors affiliated with Rational Software have favored the name Rational Unified Process.
The Unified Process is an iterative and incremental development process. The Elaboration, Construction and
Transition phases are divided into a series of timeboxed iterations. (The Inception phase may also be divided
into iterations for a large project.) Each iteration results in an increment, which is a release of the system that
contains added or improved functionality compared with the previous release.
Although most iterations will include work in most of the process disciplines (e.g.Requirements, Design,
Implementation, Testing) the relative effort and emphasis will change over the course of the project.
In the Unified Process, use cases are used to capture the functional requirements and to define the contents of
the iterations. Each iteration takes a set of use cases or scenariosfrom requirements all the way through
implementation, test and deployment.
Architecture Centric
The Unified Process insists that architecture sit at the heart of the project team's efforts to shape the system.
Since no single model is sufficient to cover all aspects of a system, the Unified Process supports multiple
architectural models and views.
One of the most important deliverables of the process is the executable architecture baseline which is created
during the Elaboration phase. This partial implementation of the system serves and validate the architecture
and act as a foundation for remaining development.
Risk Focused
The Unified Process requires the project team to focus on addressing the most critical risks early in the
project life cycle. The deliverables of each iteration, especially in the Elaboration phase, must be selected in
order to ensure that the greatest risks are addressed first.
PROJECT LIFECYCLE
Inception
Elaboration
Construction
Transition
Inception Phase
Inception is the smallest phase in the project, and ideally it should be quite short. If the Inception Phase is
long then it may be an indication of excessive up-front specification, which is contrary to the spirit of the
Unified Process.
Outline the use cases and key requirements that will drive the design tradeoffs
Identify risks
The Lifecycle Objective Milestone marks the end of the Inception phase.
Elaboration Phase
During the Elaboration phase the project team is expected to capture a healthy majority of the system
requirements. However, the primary goals of Elaboration are to address known risk factors and to establish
and validate the system architecture. Common processes undertaken in this phase include the creation of use
case diagrams, conceptual diagrams (class diagrams with only basic notation) and package
diagrams (architectural diagrams).
The architecture is validated primarily through the implementation of an Executable Architecture Baseline.
This is a partial implementation of the system which includes the core, most architecturally significant,
components. It is built in a series of small, timeboxed iterations. By the end of the Elaboration phase the
system architecture must have stabilized and the executable architecture baseline must demonstrate that the
architecture will support the key system functionality and exhibit the right behavior in terms of performance,
scalability and cost.
The final Elaboration phase deliverable is a plan (including cost and schedule estimates) for the Construction
phase. At this point the plan should be accurate and credible, since it should be based on the Elaboration
phase experience and since significant risk factors should have been addressed during the Elaboration phase.
The Lifecycle Architecture Milestone marks the end of the Elaboration phase.
Construction Phase
Construction is the largest phase in the project. In this phase the remainder of the system is built on the
foundation laid in Elaboration. System features are implemented in a series of short, timeboxed iterations.
Each iteration results in an executable release of the software. It is customary to write full text use cases
during the construction phase and each one becomes the start of a new iteration. Common UML (Unified
Modelling Language) diagrams used during this phase include Activity, Sequence, Collaboration, State
(Transition) and Interaction Overview diagrams. The Initial Operational Capability Milestone marks the end
of the Construction phase.
Transition Phase
The final project phase is Transition. In this phase the system is deployed to the target users. Feedback
received from an initial release (or initial releases) may result in further refinements to be incorporated over
the course of several Transition phase iterations. The Transition phase also includes system conversions and
user training. The Product Release Milestone marks the end of the Transition phase.
remote services are temporarily unavailable (such as the inventory system), they must still
be capable of capturing sales and handling at least cash payments (so that the business is
not crippled).
A POS system increasingly must support multiple and varied client-side terminals and
interfaces. These include a thin-client Web browser terminal, a regular personal computer
with something like a Java Swing graphical user interface, touch screen input, wireless
PDAs, and so forth.
Furthermore, we are creating a commercial POS system that we will sell to different clients
with disparate needs in terms of business rule processing. Each client will desire a unique
set of logic to execute at certain predictable points in scenarios of using the system, such as
when a new sale is initiated or when a new line item is added. Therefore, we will need a
mechanism to provide this flexibility and customization.
OOA/D is generally most relevant for modeling the application logic and technical service
layers.
The NextGen case study primarily emphasizes the problem domain objects,
allocating responsibilities to them to fulfill the requirements of the application.
Object-oriented design is also applied to create a technical service subsystem for
interfacing with a database.
In this design approach, the UI layer has very little responsibility; it is said to
bethin. Windows do not contain code that performs application logic or processing. Rather,
task requests are forwarded on to other layers.
Inception Phase
This is the part of the project where the original idea is developed. The amount of work done here is
dependent on how formal project planning is done in your organization and the size of the project. During
this part of the project some technical risk may be partially evaluated and/or eliminated. This may be done by
using a few throw away prototypes to test for technical feasability of specific system functions. Normally this
phase would take between two to six weeks for large projects and may be only a few days for smaller projects.
The following should be done during this phase:
Assess the capablilities of any current system that provides similar functionality to the new
project even if the current system is a manual system. This will help determine cost savings
that the new system can provide.
Utilize as many users and potential users as possible along with technical staff, customers,
and management to determine desired system features, functional capabilities, and
performance requirements. Analyze the scope of the proposed system.
Identify feature and functional priorities along with preliminary risk assessment of each
system feature or function.
For large systems, break the system down into subsystems if possible.
Identify all major use cases and describe significant use cases. No need to make expanded
use cases at this time. This is just to help identify and present system functionality.
Develop a throw away prototype of the system with breadth and not depth. This prototype
will address some of the greatest technical risks. The time to develop this prototype should
be specifically limited. For a project that will take about one year, the prototype should
take one month.
Present a business case for the project (white paper) identifying rough cost and value of the
project. The white paper is optional for smaller projects. Define goals, estimate risks, and
resources required to complete the project.
Set up some major project milestones (mainly for the elaboration phase). A rough estimate
of the overall project size is made.
Preliminary determination of iterations and requirements for each iteration. This outlines
system functions and features to be included in each iteration. Keep in mind that this plan
will likely be changes as risks are further assessed and more requirements are determined.
This phase is done once the business case is presented with major milestones determined (not cast in stone
yet) and management approves the plan. At this point the following should be complete:
The inception phase has only one iteration. All other phases may have multiple iterations.
The overriding goal of the inception phase is to achieve concurrence among all stakeholders on the lifecycle
objectives for the project. The inception phase is of significance primarily for new development efforts, in
which there are significant business and requirements risks which must be addressed before the project can
proceed. For projects focused on enhancements to an existing system, the inception phase is more brief, but is
still focused on ensuring that the project is both worth doing and possible to do.
Objectives
operational vision, acceptance criteria and what is intended to be in the product and what
is not.
Discriminating the critical use cases of the system, the primary scenarios of operation
Estimating the overall cost and schedule for the entire project (and more detailed
Essential Activities
Formulating the scope of the project. This involves capturing the context and the
most important requirements and constraints to such an extent that you can derive
acceptance criteria for the end product.
make/buy/reuse, so that cost, schedule and resources can be estimated. The aim here is to
demonstrate feasibility through some kind of proof of concept. This may take the form of a
model which simulates what is required, or an initial prototype which explores what are
considered to be the areas of high risk. The prototyping effort during inception should be
limited to gaining confidence that a solution is possible - the solution is realized during
elaboration and construction.
Preparing the environment for the project, assessing the project and the organization,
Milestone
The Lifecycle Objectives Milestone evaluates the basic viability of the project.
Tailoring Decisions
The example iteration workflow shown at the top of this page represents a typical Inception iteration in
medium sized projects. The Sample Iteration Plan for Inception represents a different perspective of the
breakdown of activities to undertake in an Inception iteration. This iteration plan is more complete in terms
of workflow details and activities, and as such, more suitable for large projects. Small projects might decide
to do only a subset of these workflow details, deviations should be challenged and documented as part of the
project-specific process.
Project planning
Risk identification and analysis
Estimating the Budget
The Use Case Model
The Use Case
Model describes the proposed functionality of the new system.A Use Case represents
a discrete unit of interaction between a user (human ormachine) and the system.
A Use Case is a single unit of meaningful work; forexample login to system, register with sy
stem and create order are all UseCases. Each Use Case has
a description which describes the functionality thatwill be built in the proposed system.
A Use Case may 'include' another UseCase's functionality or 'extend' another
Use Case with its own behaviour.
Use Cases are typically related to 'actors'. An actor is a human or machineentity that inter
acts with the system to perform meaningful work.
A Use Case description will generally include:
1. General comments and notes describing the use case;
2. Requirements - Things that the use case must allow the user to do, such as <ability to updat
e order>,<a< span="">bility to modify order> & etc.</a<>
3. Constraints- Rules about what can and can't be done. Includes i) pre-conditions that must
be true beforethe use case is run -e.g. <create order> must precede <m<
span="">odify order>; ii) post-conditions that must be trueonce the use case is run e.g.
<order is modified and consistent>; iii) invariants: these are always true -e.g. an order</m<>
must always have a customer number
4. Scenarios
- Sequential descriptions of the steps taken to carry out the use case. May include multiplesce
narios, to cater for exceptional circumstances and alternate processing paths;
5. Scenario diagrams -Sequence diagrams to depict the workflow - similar to (4) but
graphically portrayed.
6. Additional attributes such as implementation phase, version number, complexity rating, ste
reotype andstatus
Actors
An Actor is a user
of the system. This includes both human users and othercomputer systems. An Actor uses
a Use Case to perform some piece of workwhich is
of value to the business. The set of Use Cases an actor has access todefines their overall rol
e in the system and the scope of their action.
Constraints, Requirements and Scenarios
The formal specification of a Use Case includes:
1. Requirements. These are the formal functional requirements that a
UseCase must provide to the end user. They correspond to the functionalspecifications fou
nd in structured methodologies. A requirement is
acontract that the Use Case will perform some action or provide some valueto the system.
2. Constraints. These are the formal rules and limitations that a
Use Caseoperates under, and includes pre- post- and invariant conditions. Apre-
condition specifies what must have already occurred or be in place before the
Use Case may start. A post-condition documents what will betrue once the
Use Case is complete. An invariant specifies what will betrue throughout the time the Use
Case operates.
3. Scenarios. Scenarios are formal descriptions of the flow of events thatoccurs during a
Use Case instance. These are usually described in text andcorrespond to a textual represen
tation of the Sequence Diagram.
Includes and Extends relationships between Use Cases
One Use Case may include the functionality of another as
part of its normalprocessing. Generally, it is assumed that the included Use Case will be cal
ledevery time the basic path is run. An example may be to list a set of customer
orders to choose from before modifying a selected order - in this case the <listorders>
Use Case may be included every time the <m<
span="">odify order> Use Case isrun.</m<>
A Use Case may be included by one or more Use Cases, so it helps to reduceduplication of f
unctionality by factoring out common behaviour into Use Casesthat are re-
used many times.
Sequence Diagrams
UML provides
a graphical means of depicting object interactions over timein Sequence Diagrams. These t
ypically show a user or actor, and the objectsand components they interact with in the exec
ution of
a use case. Onesequence diagram typically represents a single Use Case 'scenario' or flowof
events.
Sequence diagrams are an excellent way to document usage scenarios and toboth capture r
equired objects early in analysis and to verify object usage laterin design. Sequence diagra
ms show the flow of messages from
one object toanother, and as such correspond to the methods and events supported by acla
ss/object.
The diagram illustrated below shows an example of a sequence
diagram, withthe user or actor on the left initiating
a flow of events and messages thatcorrespond to the Use Case scenario. The messages that
pass betweenobjects will become class operations in the final model.
Implementation Diagram
A Use Case is a formal description of functionality the system will have whenconstructed.
An implementation diagram is typically associated with a UseCase to document what desig
n elements
(eg. components and classes) willimplement the Use Case functionality in the new system.
This
provides a highlevel of traceability for the system designer, the customer and the team that
will actually build the system. The list of
Use Cases that a component orclass is linked to documents the minimum functionality that
must beimplemented by the component.
The example above shows that the UseCase "Login" impleme
nts the formal requirement "1.01 Log on to the website".It also states that the Business Lo
gic component and ASP Pages componentimplement some or all of the Login functionality.
A further refinement is toshow the Login screen (a web page) as implementing the Login in
terface.These implementation or realisation links define the traceability from the formalre
quirements, through Use Cases on to Components and Screens.
Generalization
Association
Extend
Include
Generalization between use cases is similar to generalization between classes – child use case inherits
properties and behavior of the parent use case and may override the behavior of the parent.
Use cases can only be involved in binary Associations. Two use cases specifying the same subject cannot be
associated since each of them individually describes a complete usage of the system.
Extend Relationship
Extend is a directed relationship from an extending use case to an extended use case that specifies how and
when the behavior defined in usually supplementary (optional) extending use case can be inserted into the
behavior defined in the use case to be extended.
Note: Extended use case is meaningful on its own, independently of the extending use case, while
the extending use case typically defines behavior that is not necessarily meaningful by itself.
The extension takes place at one or more extension points defined in the extended use case.
The extend relationship is owned by the extending use case. The same extending use case can extend more
than one use case, and extending use case may itself be extended.
Extend relationship between use cases is shown by a dashed arrow with an open arrowhead from
the extending use case to the extended (base) use case. The arrow is labeled with the keyword «extend».
Registration use case is meaningful on its own, and it could be extended with optional Get Help On
Registration use case
The condition of the extend relationship as well as the references to the extension points are optionally shown
in a Note attached to the corresponding extend relationship.
Registration use case is conditionally extended by Get Help On Registration use case in extension point
Registration Help
Extension Point
An extension point is a feature of a use case which identifies (references) a point in the behavior of the use
case where that behavior can be extended by some other (extending) use case, as specified by
an extend relationship.
Extension points may be shown in a compartment of the use case oval symbol under the heading extension
points. Each extension point must have a name, unique within a use case. Extension points are shown as text
string according to the syntax:
::= [: ]
The optional description is given usually as informal text, but can also be given in other forms, such as the
name of a state in a state machine, an activity in an activity diagram, a precondition, or a postcondition.
The Unified Process consists of cycles that may repeat over the long-term life of a system. A
cycle consists of four phases: Inception, Elaboration, Construction and Transition. Each
cycle is concluded with a release, there are also releases within a cycle. Let's briefly review
the four
phases in a cycle:
* Inception Phase - During the inception phase the core idea is developed into a product
vision. In this phase, we review and confirm our understanding of the core business
drivers. We want to understand the business case for why the project should be attempted.
The inception phase establishes the product feasibility and delimits the project scope.
* Elaboration Phase - During the elaboration phase the majority of the Use Cases are
specified in detail and the system architecture is designed. This phase focuses on the "Do-
Ability" of the project. We identify significant risks and prepare a schedule, staff and cost
profile for the
entire project.
* Construction Phase - During the construction phase the product is moved from the
architectural baseline to a system complete enough to transition to the user community.
The
architectural baseline grows to become the completed system as the design is refined into
code.
* Transition Phase - In the transition phase the goal is to ensure that the requirements have
been met to the satisfaction of the stakeholders. This phase is often initiated with a beta
release of the application. Other activities include site preparation, manual completion, and
defect identification and correction. The transition phase ends with a postmortem devoted
to learning and recording lessons for future cycles.