Overall Project Progress: Details of Site Activities
Overall Project Progress: Details of Site Activities
Work Weightage in total PROGRESS TILL YESTERDAY(%) TODAY'S PROGRESS(%) TOTAL PROGRESS TILL DATE(%)
Sr. No
progress
1 325.75 13.81427475 9.2095165 7.3676132 9.57789716 3.6838066 6.44666155 4.60475825 5.34151957 17.49808135 13.81427475 11.97237145 13.998465
Piping Fabrication Progress (Offshore)
PROGRESS TILL YESTERDAY TODAY'S PROGRESS TOTAL PROGRESS TILL DATE
1 161.25
1 Hydrotest
2 Leak Test
DETAILED PIPING WORK PROGRESS (ONSHORE) : For Well No. D7
PROGRESS TILL YESTERDAY TODAY'S PROGRESS TOTAL COMPLETED TILL DATE
Total No. of NDT & other NDT &
Sr. No. Size of Joints MATERIAL Fit up Welding Fit up Welding NDT & other tests Fit up Welding
Joints tests other tests
(inch dia) (inch dia) (inch dia) (inch dia) (inch dia) (inch dia) (inch dia)
(inch dia) (inch dia)
10 DSS 0 0 0 0 0 0 0 0 0
1 0.5"
2 ALLOY 0 0 0 0 0 0 0 0 0
4 ALLOY 0 0 0 0 0 0 0 0 0
2 0.75"
10 DSS 0 0 0 0 0 0 0 0 0
31 ALLOY 0 0 0 0 0 0 0 0 0
3 1"
4 DSS 0 0 0 0 0 0 0 0 0
4 1.5" 2 ALLOY 0 0 0 0 0 0 0 0 0
16 CS-NACE & GALV. 0 0 0 0 0 0 0 0 0
5 2"
42 DSS 0 0 0 0 0 0 0 0 0
6 3" 1 DSS 3 0 0 0 3 0 3 3 0
7 3 ALLOY 0 0 0 0 0 0 0 0 0
4"
8 1 DSS 0 0 0 0 0 0 0 0 0
9 6" 24 DSS 42 30 24 12 18 15 54 42 39
TOTAL 45 30 24 12 21 15 57 45 39
Details of Site Activities
Completed of Welding for J-6 (Line No. 150-PF-150D1-0025) , Welding of Joints No. : J-9 & J-10
2 2
J-5 (Line No. 150-PF-150D1-0009) ( Line No. 150-PF-150D1-0025, Dwg No. : cowgd9123-74-3-DDW1-0025 SHT NO. 01 OF 07 REV.02 )
Details of Manpower
S.No DETAILS DETAILS
1 SUPERVISOR : 01 RIGGER FOREMAN : 01
2 FABRICATOR : 02 RIGGERS : 03 NOS
3 WELDER : 02 STOREKEEPER/ OFFICE ASSISTANT : 01
4 ELECTRICIAN : 01 QA/QC ENGINEER : 01