Overall Project Progress: Details of Site Activities

This document provides a progress report for the fabrication and installation of flowlines for well D7 at the DDW1 platform for ONGC's HPHT asset in Kakinada, India. It summarizes the overall project progress to date as 6.999% completed, with key work streams including onshore piping fabrication at 13.99% and offshore piping fabrication pending. Detailed progress updates are provided for various fabrication and testing activities both onshore and planned offshore. The report is intended for ONGC, the contractor Offshore MarineTech, and third party inspector International Certification Services.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
142 views1 page

Overall Project Progress: Details of Site Activities

This document provides a progress report for the fabrication and installation of flowlines for well D7 at the DDW1 platform for ONGC's HPHT asset in Kakinada, India. It summarizes the overall project progress to date as 6.999% completed, with key work streams including onshore piping fabrication at 13.99% and offshore piping fabrication pending. Detailed progress updates are provided for various fabrication and testing activities both onshore and planned offshore. The report is intended for ONGC, the contractor Offshore MarineTech, and third party inspector International Certification Services.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

FLOWARM FABRICATION AND INSTALLATION JOB FOR WELL D7 AT DDW1 PLATFORM,

ONGC HPHT ASSET, KAKINADA


LOCATION: OMTECH WORKSHOP, KAKINADA TENDER NO. : 9030010030 PROGRESS DATE 12-01-21
CLIENT: HPHT ASSET, OIL AND NATURAL GAS CORPORATION LIMITED, KAKINADA REPORTING DATE 13-01-21
THIRD PARTY INSPECTOR: INTERNATIONAL CERTIFICATION SERVICES PVT. LTD
CONTRACTOR: OFFSHORE MARINETECH PVT. LTD.

Overall Project Progress


PROGRESS TILL YESTERDAY(%) TODAY'S PROGRESS(%) TOTAL PROGRESS TILL DATE(%)

4.78894858 2.670759785 6.99923254

Work Weightage in total PROGRESS TILL YESTERDAY(%) TODAY'S PROGRESS(%) TOTAL PROGRESS TILL DATE(%)
Sr. No
progress

1 Piping Fabrication Progress (Onshore) 50% 10 5.34151957 13.99846508

2 Piping Fabrication Progress (Offshore) 30%

3 Pipe Supports Fabrication Progress (Offshore) 5%

4 Electrical and Instrumentation Work (Offshore) 10%

5 Pre-commissioning Work Progress (Offshore) 5%


Piping Fabrication Progress (Onshore)
PROGRESS TILL YESTERDAY(%) TODAY'S PROGRESS(%) TOTAL PROGRESS TILL DATE(%)

Sr. No. Total Inch Dia Welding


Fit up Welding NDT & Other Tests Fit up NDT & Other Tests Total Fit up Welding NDT & Other Tests Total
Total progress (Weightage -
(Weightage -20%) (Weightage -50%) (Weightage -30%) (Weightage -20%) (Weightage -30%) progress (Weightage -20%) (Weightage -50%) (Weightage -30%) progress
50%)

1 325.75 13.81427475 9.2095165 7.3676132 9.57789716 3.6838066 6.44666155 4.60475825 5.34151957 17.49808135 13.81427475 11.97237145 13.998465
Piping Fabrication Progress (Offshore)
PROGRESS TILL YESTERDAY TODAY'S PROGRESS TOTAL PROGRESS TILL DATE

Sr. No. Total Inch Dia Welding


Fit up Welding NDT & Other Tests Fit up NDT & Other Tests Total Fit up Welding NDT & Other Tests Total
Total progress (Weightage -
(Weightage -20%) (Weightage -50%) (Weightage -30%) (Weightage -20%) (Weightage -30%) progress (Weightage -20%) (Weightage -50%) (Weightage -30%) progress
50%)

1 161.25

Pipe Supports Fabrication Progress (Offshore)


PROGRESS TILL YESTERDAY TODAY'S PROGRESS TOTAL PROGRESS TILL DATE

Sr. No. Total No. of Supports Welding


Fit up Welding NDT & Other Tests Fit up NDT & Other Tests Total Fit up Welding NDT & Other Tests Total
Total progress (Weightage -
(Weightage -20%) (Weightage -50%) (Weightage -30%) (Weightage -20%) (Weightage -30%) progress (Weightage -20%) (Weightage -50%) (Weightage -30%) progress
50%)

Electrical and Instrumentation (E&I) Work (Offshore)


Sr. No. Work Description UOM Total Scope PROGRESS TILL YESTERDAY TODAY'S PROGRESS TOTAL PROGRESS TILL DATE

1 Tubing Laying Mtrs

2 Cable Tray Installation Mtrs

3 Cable Laying Mtrs

4 Instrument Installation Nos

5 Cable Glanding Nos

6 Cable Termination Nos

7 Cable testing Nos

Pre-commissioning Work Progress (Offshore)


Sr. No. Work Description PROGRESS TILL YESTERDAY TODAY'S PROGRESS TOTAL PROGRESS TILL DATE

1 Hydrotest

2 Leak Test
DETAILED PIPING WORK PROGRESS (ONSHORE) : For Well No. D7
PROGRESS TILL YESTERDAY TODAY'S PROGRESS TOTAL COMPLETED TILL DATE
Total No. of NDT & other NDT &
Sr. No. Size of Joints MATERIAL Fit up Welding Fit up Welding NDT & other tests Fit up Welding
Joints tests other tests
(inch dia) (inch dia) (inch dia) (inch dia) (inch dia) (inch dia) (inch dia)
(inch dia) (inch dia)
10 DSS 0 0 0 0 0 0 0 0 0
1 0.5"
2 ALLOY 0 0 0 0 0 0 0 0 0
4 ALLOY 0 0 0 0 0 0 0 0 0
2 0.75"
10 DSS 0 0 0 0 0 0 0 0 0
31 ALLOY 0 0 0 0 0 0 0 0 0
3 1"
4 DSS 0 0 0 0 0 0 0 0 0
4 1.5" 2 ALLOY 0 0 0 0 0 0 0 0 0
16 CS-NACE & GALV. 0 0 0 0 0 0 0 0 0
5 2"
42 DSS 0 0 0 0 0 0 0 0 0
6 3" 1 DSS 3 0 0 0 3 0 3 3 0
7 3 ALLOY 0 0 0 0 0 0 0 0 0
4"
8 1 DSS 0 0 0 0 0 0 0 0 0
9 6" 24 DSS 42 30 24 12 18 15 54 42 39
TOTAL 45 30 24 12 21 15 57 45 39
Details of Site Activities

SL NO. Activities performed today SL NO. Activities planned for tomorrow

A) DPT for Completed Welded Joints.


Fitment of J-13 & J-14 : B) WPQT for Small Bore DSS Piping
1 1 C) PMI Testing for inward Project Material free issued by ONGC
Line No. 150-PF-150D1-0025 , Ref. ISO DWG No. : COWGD9123-74-3-DDW1-0025 REV.02 Sht no. 02 of 07
C) PMI Testing for DSS Welded joints for weld fusion composition conformance.

Completed of Welding for J-6 (Line No. 150-PF-150D1-0025) , Welding of Joints No. : J-9 & J-10
2 2
J-5 (Line No. 150-PF-150D1-0009) ( Line No. 150-PF-150D1-0025, Dwg No. : cowgd9123-74-3-DDW1-0025 SHT NO. 01 OF 07 REV.02 )

Fitment of Joint No. : J-22 & J-23


3 RT for Completed Welded Joints. i.e. J-3 ( 6" ), J-6 ( 6" ) & J-5 ( 3" ) 3 ( Line No. 150-PF-150D1-0025, Dwg No. : cowgd9123-74-3-DDW1-0025 SHT NO. 02 OF 07 REV.02 )
& ( Line No. 150-PF-150D1-0025, Dwg No. : cowgd9123-74-3-DDW1-0025 SHT NO. 03 OF 07 REV.02 )

Other remarks and Constraints


Remarks : New Welder Arrived at location Dtd.12.01.2021 ( Mr. Vinod Gopi - TIG & ARC Welder )

Details of Manpower
S.No DETAILS DETAILS
1 SUPERVISOR : 01 RIGGER FOREMAN : 01
2 FABRICATOR : 02 RIGGERS : 03 NOS
3 WELDER : 02 STOREKEEPER/ OFFICE ASSISTANT : 01
4 ELECTRICIAN : 01 QA/QC ENGINEER : 01