Assignment 4 - Variances - 50140
Assignment 4 - Variances - 50140
Q1. Woodeezer Ltd makes quality wooden benches for both indoor and outdoor use. Results have been
disappointing in recent years and a new managing director, Peter Beech, was appointed to raise
production volumes. After an initial assessment Peter Beech considered that budgets had been set at
levels which made it easy for employees to achieve.
He argued that employees would be better motivated by setting budgets which challenged them more in
terms of higher expected output. Other than changing the overall budgeted output, Mr Beech has not yet
altered any part of the standard cost card.
Thus, the budgeted output and sales for November 2002 was 4,000 benches and the standard cost card
below was calculated on this basis:
£
Wood 25 kg at £3.20 per kg 80.00
Labour 4 hours at £8 per hour 32.00
Variable overheads 4 hours at £4 per hour 16.00
Fixed overheads 4 hours at £16 per hour 64.00
192.00
Selling price 220.00
Standard profit 28.00
Overheads are absorbed on the basis of labour hours and the company uses an absorption costing
system. There were no stocks at the beginning of November 2002. Stocks are valued at standard cost.
1
Q2. McDermott plc is a manufacturer of beds. It uses a standard absorption costing system to monitor
performance of managers and departments. A standard absorption cost card for one of its models, the
Dreamer, is given below.
£ £
Selling price 250·00
Production costs
Direct material: 12 metres at £1·50 per metre 18·00
Direct labour: 4 hours at £6·00 per hour 24·00
Variable overhead: 4 hours at £15·00 per hour 60·00
Fixed overhead: 4 hours at £10·00 per hour 40·00
142·00
Gross profit 108·00
Budgeted production and sales are 1,000 Dreamers per month.
Actual results for the manufacture and sale of Dreamers for the most recent month were as follows:
Sales: 1,200 beds at £240 each.
Production: 1,300 beds
Direct material (purchased and used): 16,000 metres at £1·40 per metre
Direct labour (worked and paid): 5,000 hours at £6·00 per hour
Variable overhead £75,500
Fixed overheads £54,600.
There were no opening stocks of finished goods.
Required:
(a) Calculate the following variances for the most recent month
(i) Direct materials price and usage variance;
(ii) Direct labour rate and efficiency variance;
(iii) Variable overhead rate and efficiency variance; and
(iv) Fixed overhead expenditure and volume variance.
(v) Sales volume contribution and sales price variance;
Explain the differences between standard absorption costing and standard marginal costing in the
following areas:
(i) the sales volume variance;
(ii) the fixed overhead variances;
(iii) stock valuation and its effect upon profit.
(no further calculations are required) (10 marks)
2
3
Q4. The summary production budget of a factory with a single product for a four week period is as
follows:
Production and sales quantity 240,000 units
Production costs:
Material: 336,000 kg at £4.10 per kg
Direct labour: 216,000 hours at £4.50 per hour
Variable overheads: £475,200
Fixed overheads: £1,521,600
Sales revenue £6,000,000
Variable and fixed overheads are absorbed at a predetermined direct labour hour rate.
During the four week period the actual production and sale was 220,000 units which incurred the
following costs:
Material: 313 060 kg costing £1 245 980
Direct labour: 194 920 hours costing £886 886
Variable overheads: £433 700
Fixed overheads: £1,501,240
Sales revenue £6,160,000
Required:
(a) Calculate standard cost card showing gross profit (6 marks)
(b) Calculate the cost variances for the period.
i. Material price variance (£37,566 fav)
ii. Material usage variance (£ 20,746 adv)
iii. Labour rate variance (£9,746adv)
iv. Labour efficiency variance (£13,860 fav)
v. Variable overhead efficiency variance (£6,776 fav)
vi. Variable overhead expenditure variance (£4,876 adv)
vii. Fixed overhead expenditure variance (£20,360 fav)
viii. Fixed overhead volume variance (£126,800 adv)
ix. Sales price variance (£660,000 fav)
x. Sales volume variance (Gross profit: £6.89 / unit, £137,800 adv) (12 marks)
(c) Give reasons in each case why the direct labour efficiency, variable overhead efficiency and fixed
overhead volume variances may have arisen. (8 marks)
4
Q5. Extract from the records of AMAX Limited are as under
Budget (£) Actual (£)
Sales revenue 27,000,000 27,295,000
Variable cost
Raw material 7,500,000 8,461,450
Labour 9,375,000 9,463,125
Variable overheads 3,000,000 2,976,125
Contribution 7,125,000 6,396,300
An analysis of the above figures has revealed the following:
Actual units manufactured and sold were 3% (1,500 units) more than the budgeted production and sales
quantity and actual sale price was lower by £10 per unit.
One unit of finished product requires 3 kgs of raw material and actual raw material price was 6% higher
than the budgeted price.
Budgeted labour cost per hour was equivalent to 150% of budgeted raw material cost per kg.
Production department records show that labour utilization per unit of finished product was 1/8 hour more
than the budget.
Variable overheads varied in line with labour hours.
Required:
Compute eight relevant variances and prepare a statement reconciling budgeted contribution with the
actual contribution. (20 marks)
Q6.
5
Theory of standard costing and variances
Standard costing system most suited to an organization whose activities consists of a series of common
or repetitive operations and the input required to produce each unit of output is specified
Types of standard
There are four types of standard cost, as follows.
Ideal standard
This is a standard that reflects perfect performance and is the minimum cost that is possible under ideal
operating conditions (for eg no losses, no idle time, 100% efficiency of labour, no machine breakdown etc).
Because ideal standards are unattainable, they are unlikely to be used in practice, since inability to achieve
them is likely to have a demotivating effect on managers and employees.
Basic standard
This is a standard that remains unchanged for long periods of time. Because it remains unchanged, it
allows efficiency trends over time to be identified. Because basic standards do not reflect current
conditions, they are of limited use if current conditions differ significantly from those existing when the
standard was set. They are therefore seldom used.
Attainable standard
This standard allows for normal levels of wastage and operation, and represents a cost level achievable
under reasonably efficient working. Attainable standards may be difficult to achieve, but they do not
represent impossible targets for employees.
An attainable standard is considered to represent the best target against which to compare current
activity and is the preferred standard to use in planning, budgeting and cost control.
Current standard
This standard is one established for use over a short period of time and relates to current conditions.
6
The preparation of standard costs
A standard cost has two elements, namely a physical measure of a resource and a price per unit of
resource. A standard cost for material, for example, consists of a specification of the kilograms of material
required per unit of product, and a specification of the price paid per kilogram. When setting standards,
both elements need to be determined.
Standard costing is best suited to operations which are repetitive, where the quantity of resource needed
to produce a given quantity of output can be specified. It is therefore suited to manufacturing processes
and the provision of repetitive services, such as the processing of loan applications in a financial
institution.
Standard costs can be developed through the application of quantitative analysis, such as the engineering
approach, which uses technical specifications or time and motion study, and the accounts analysis
approach, which analyses past accounting information. Quantitative analysis of past accounting
information through techniques such as the high-low method and regression analysis can provide a cost
function that can be used in the preparation of a standard cost.
7
iv) What has happened in the past
The historic pattern of variances should be considered and variances identified which are unusual
compared to variances recorded in previous periods. Statistical control charts may be used for this
purpose. Here, variations about the arithmetic mean are recorded and compared to control limits, set for
example at plus and minus two standard deviations from the mean.
Variances outside of the control limits are investigated. Statistical analysis of performance in previous
periods can be used to determine the expected mean value and the standard deviation.
Causes of variances
Reasons for material price variance
Purchasing department is responsible for price variance
Favourable (actual price less than standard price)
Company might have used cheap quality material
Company might have changed supplier
Availability of unforeseen discount
Overall decrease in price level
Overall decrease in demand or increase in supply
Standard might be inappropriate
Adverse (actual price higher than standard price)
Company might have used high quality material
Urgent purchasing due to poor inventory management
Overall increase in price level
Overall increase in demand or decrease in supply
Reasons for material usage variance
Production department is responsible for usage variance.
Favourable (actual consumption less than standard consumption)
Company might have used high quality material
This might be result of skilled labour
Proper machine maintenance
Standard might be inappropriate
Adverse (actual price higher than standard price)
Company might have used cheap quality material
Company might have employed unskilled labour
Lack of proper machine maintenance
Standard might be inappropriate
8
Reasons for labour efficiency variance
Production department is responsible for usage variance.
Favourable (actual hours less than standard hours required)
Use of experienced labour
Use of good quality material
Better machine or equipment available for the manufacturing
Improved working conditions
Adverse (actual hours higher than standard hours required)
Use of less skilled labour or lack of training
Use of low quality material
Lack of machine maintenance
Poor working conditions