Pre-Commissioning Format For Reactor: I. General Details
Pre-Commissioning Format For Reactor: I. General Details
Region: NR-1
EQUIPMENT
DETAILS
Sr. No.: 15052-012 Type: 1-Phase Shunt Reactor
Equipment identification No.: Make: ABB
Year of Manufacture: Rating: 80 MVAr
Voltage Class :765√3kV Cooling Type: ONAN
Type of Neutral Grounding: Oil Make:
Oil type: Oil quantity:
Quantity of Radiator Date of Receipt at site:
Date of Starting of Erection: Date of Completion of Erection and Oil filling:
Equipment SAP ID:
Pre-Commissioning Procedures and Formats for Substation Equipment & Protection System 113
DOC: D-2-01-03-01-05
Pre-Commissioning Procedures and Formats for Substation Equipment & Protection System
114
Comments of Commissioning Team on test Results:
Insulation Insulation
Terminals Terminals
Value Value
CC-G CC-CL
CL-G Semi-shield –G (if provided) at 1 kV
Note:
i. Permissible value > 500 MΩ
ii. In case core insulation values are less than the permissible limit matter to be referred to
OEM for corrective measures and same to be checked during internal inspection for any
abnormality
iii. Ensure shorting of CC-CL & G after the completion of the testing
D) Internal Inspection
SL. Status
Internal Inspection
No. Yes No
Details photographs of all visible parts /components are taken during internal
1
inspection.(refer procedure2.1.6)
2 Any abnormality observed during internal inspection
3 Matter referred to manufacturing, CC-QA & I , CC-ENGG and CC-OS
(iii) Before filling oil, each drum has been physically checked for free Yes No
moisture and appearance
Make Capacity
Capacity Quantity
Remarks /
Sl.No Inspection Actions Date Time
Reading
1 Fill dry N2/ dry air till pressure of 4- 5psi (.3 kg/cm2 )
achieved
2 To be kept for 24 Hrs
3 In case pressure remain same, check for dew point
4 If dew point is achieved, proceed for evacuation
5 In case of drop in pressure, attend the leakages and
repeat the pressure test
6 If dew point is not OK, dry air/ N2 cycle to be carried out
till desired dew point is achieved
Remarks /
Sl.No Inspection Actions Date Time
Reading
1 Starting of evacuation on complete unit
Stopping of evacuation below the pressure of 5 kPa (50
2
mbar)
3 Pressure P1 in kPa after 1 hour of stopping evacuation
Pressure P2 in kPa after half an hour of reading pressure
4
P1
Leakage = (P2-P1) x V , V= Oil quantity in Cu mtr
*If leakage<3.6, continue evacuating
5
If leakage > 3.6, attend leakage and repeat process as
per Sr. No. 1 to 4.
6 Start of Vacuum reaching below 0.13kPa(1 Torr)
Pre-Commissioning Procedures and Formats for Substation Equipment & Protection System
120
Break of vacuum
* Vacuum process to be continued for 24 hrs Up to 145
7
KV, 48 hrs for 145 to 220kV and 72 hrs for 420 kV and
Above
V. PRE-COMMISSIONING CHECKS:
Status Deficiencies
Sl. No. Description Of Activity
Yes No , If Any
1 Reactor and its Auxiliaries are free from visible defects on
physical Inspection
2 All fittings as per out line General Arrangement Drawing
3 Check Main Tank has been provided with double earthing
4 Check neutral is grounded through separate connections.
Ensure metallic requirements as per specification (e.g. Cu) in
earthing strips used
5 Check that Marshalling Box, , Radiator Bank & Fan(if any)
etc. has been earthed
6 All nuts and bolts are tightened correctly as per specified
torque (as per manufacturers recommendation)
7 Check tightness of Terminal Connectors
8 Check leveling of Reactor and its accessories
9 Erection Completion Certificate along with list of
outstanding activities reviewed
10 Any Paint removed / scratched in transit has been touched
Up
11 Bushings are clean and free from physical damages
12 Oil level is correct on all Bushings
13 Check brazing of all Bushings Leads
14 Check oil leakage through any Joints / Valves etc.
15 Check oil drain valves are properly closed and locked
16 Check oil level in Main Conservator tank
17 Check oil level at conservator matches with oil temperature
of Reactor
18 Check OTI and WTI pockets and replenish the oil, if required
19 Check all valves for their opening & closing sequence
20 Check the colour of the breather silica gel
21 Check availability of oil in the breather cup
22 Check tightness of bolt of main unit after placed on
Foundation
23 Check busing test tap is grounded
24 Check the operation of flow sensitive shut off valve between
main tank & conservator, if any
25 Check the functioning of SPR (Sudden pressure relay) ,if any
26 Check no debris, loose T & P and oil strains on and around
the Reactor
27 Check door seals of Marshalling Box is intact and all cable
gland plates unused holes are sealed
28 Check that pressure relief valve is correctly mounted
29 Ensure unused secondary cores of Bushing CT’s, if any, has
been shorted
30 Check CT star point has been formed properly and grounded
at one end only as per scheme
31 Check that permanent and adequate lighting arrangements
are ready
32 Check that labeling and identification is permanent and
Satisfactory
33 Check that Buchholz Relay is correctly mounted with arrow
pointing towards conservator
34 Check cables are properly fixed and ensure cable entry at
the bottom
35 Ensure all Power and Control cable Terminals are tightened
36 Check all cables and Ferrules are provided with Number as
per Cable Schedule (Cross Ferruling to be checked)
37 Check that all cables are correctly glanded
38 Check external cabling from Junction Box to Relay / Control
Panel completed
39 Check that air has been released from the Radiators and
their headers/ Buchholz relay/Main tank/tank/Bushing
turrets etc
40 Check Fire Protection System & Emulsifier systems is
adequate & ready
41 Check that CC-CL & G are shorted
42 Check that neutral connection has twin conductor in case of
single phase unit
43 Check that all radiator bank valves on top and bottom
headers are open
44 Change over operation of ac supply from source- I to
source-II checked
45 Check the flanges of bushing for any crack after fixing
46 Calibration of OTI & WTI performed as per procedure
47 Ensure Remote OTI and WTI data transfer to control room
is taking place
48 Ensure On-Line DGA is commissioned and kept “ON”
49 Ensure On-Line Dry out system is commissioned and kept
“ON”
50 Ensure that rain canopies have been provided on all PRDs,
Buchholz and OSRs.
51 Ensure tripping of the transformer from Buchholz Alarm.
52 Ensure that Ground Overcurrent or Broken Conductor
protection is enabled to prevent damage to NGR during
single phasing.
53 Check various interlocks provided with Fire Fighting Description Checked
as per the schematic Ref. Drg. of Interlocks
No.
N- HV ALL OPEN
Note:
a. Excitation current < 50 milli-Amperes, then difference between two higher currents should
be less than 10%.
b. Excitation current > 50 milli-Amperes, then difference between two higher currents should
be less than 15 %.
c. Value of centre leg should not be more than either outside for a three phase reactor.
d. Results between similar single phase units should not vary more than 10%.
Details HV NEUTRAL
Make ABB PASONIVILLA
Type
Sl. No. 1ZSCT10003622/01 HH03210845
Style No / Drawing
No
a) Tan Delta And Capacitance Measurement Of Bushing
a) HV & Neutral side
CAPACITANCE (MEASURED VALUE) pF
VOLTAGE REMARKS
HV NEUTRAL
SITE FACTORY SITE FACTORY SITE FACTORY
Measurement of C1
2 KV 571.869 479.487
5 KV 571.862 577.779 479.477 479.995
10 KV 571.890 575.875 479.497 479.306
Measurement of C2
1 KV
TAN δ (MEASURED VALUE) (%)
VOLTAGE REMARKS
HV NEUTRAL
SITE FACTORY SITE FACTORY SITE FACTORY
Measurement of C1
2 KV 0.287 0.264
5 KV 0.286 0.265
10 KV 0.287 0.264
Measurement of C2
1 KV
STATUS REMARKS, IF
SL. NO. DESCRIPTION YES NO ANY
A Control wiring
B Cooling System
a) Motor Fan
b) Motor Pump
c) Control wiring
* Permissible limit of IR value should be > 50 M Ω
b) Insulation Resistance Measurement in GΩ (Using 5000 V Megger)
OTI=25º C
i. Formula for calculating the resistance at 75°C: R75 = RT (235+75)/ (235+T), where RT =
Resistance Measured At Winding Temperature T.
ii. Permissible limit: ±5% variation between phases or from Factory test results
Insulation Insulation
Terminals Terminals
Value Value
CC-G CC-CL
CL-G Semi-shield –G (if provided) at 1 kV
Note:
i. Permissible value > 500 MΩ
ii. Ensure shorting of CC-CL & G after the completion of the testing
7. Oil Characteristics
(Sample to be taken prior to charging to Reactor and it should fulfill the recommendations as per
IS 1865 /IEC 60422)
DATE OF INTERFACIAL
MOISTURE TAN DELTA RESISTIVITY
OIL B.D.V. TENSION
SAMPLING
Permissible 70KV(min) 5 0.01 at 90º C 6x 10 ^12 Ω - 0.0 35 N/m at
Limit PPM(Max) (Max) CM at 90º C 27ºC (Min)
(Min)
Note:-
i. TCG should be below 1%
ii. One fresh oil sample per lot (from drum) shall be sent to Lab for carrying out Oxidation
Stability test
STATUS
SL.NO DESCRIPTION
OK NOT OK
1 Rotation direction of Fans
Pre-Commissioning Procedures and Formats for Substation Equipment & Protection System
130
9. Checks on Bushing CTs
MIN.KNE Imag.
Burde
Clas E @ Rct
LOCATION NOMENCLATURE Ratio n
s POINTVO Vk/4 (ohm)
(VA)
LT Vk (V) (mA)
PX/
HV CORE-1(1CT1) 300/1 A NA 300 40 1.0
PS
PX/
HV CORE-2(1CT2) 300/1 A NA 300 40 1.0
LINE SIDE PS
PX/
HV CORE-3(1CT3) 300/1 A NA 300 40 1.0
PS
HV CORE-4(1CT4) 300/1 A 1.0 10 NA NA NA
WTI 189.45/2 A 3.0 15 - NA NA
NEUTRAL CORE- 3000-2000- PX/ 12-8-
NA 3000 40
1(1NCT1) 500/1 A PS 2
NEUTRAL
SIDE NEUTRAL CORE- 3000-2000- PX/ 12-8-
NA 3000 40
2(1NCT2) 500/1 A PS 2
NEUTRAL CORE- PX/
300/1 A NA 300 40 1
3(1NCT3) PS
Insulation Resistance
Combination Unit
Neutral
Core 5-Earth GΩ >1
Core 6-Earth GΩ >1
Core 7-Earth GΩ >1
Core 8-Earth GΩ >1
Core 5-Core 6 GΩ >1
Core 5-Core 7 GΩ >1
Core 5-Core 8 GΩ >1
Core 6-Core 7 GΩ >1
Core 6-Core 8 GΩ >1
Core 7-Core 8 GΩ >1
BETWEEN Resistance
BUSHINGS UNIT
TERMINAL at 35 ºC at 75 ºC
5S1-5S2 Ω 0.4045 0.4753
6S1-6S2 Ω 1.378 1.613
6S1-6S3 Ω 5.556 6.501
6S1-6S4 Ω 8.568 10.03
NEUTRAL
7S1-7S2 Ω 1.397 1.638
7S1-7S3 Ω 5.704 6.680
7S1-7S4 Ω 8.806 10.30
8S1-8S2 Ω 0.7061 0.8262
IV. POLARITY TEST OF BUSHING CT’S
HV SIDE
CORE PRIMARY % OF
S1 - S2 % ERROR
20% 0.089
Core-1
50% 0.112
(1S1-1S2)
100% 0.131
300/1
120% 0.134
20% -0.202
Core-2
50% -0.178
(2S1-2S2)
100% -0.157
300/1
120% -0.152
20% -0.267
Core-3
50% -0.245
(3S1-3S2)
100% -0.224
300/1
120% -0.220
20% -1.115
Core-4
50% -0.557
(4S1-4S2)
100% -0.937
300/1
120% -1.382
NEUTRAL SIDE
CORE PRIMARY % OF
S1 - S2 % ERROR
20% -1.655
Core-5
50% -0.88
(5S1-5S2)
100% -0.234
189.45/2
120% -0.068
20% -0.073
Core-6
50% -0.055
(6S1-6S2)
100% -0.044
500/1
120% -0.041
20% 0.008
Core-6
50% 0.011
(6S1-6S3)
100% 0.013
2000/1
120% 0.013
20% 0.057
Core-6
50% 0.055
(6S1-6S4)
100% 0.060
3000/1
120% 0.060
20% -0.102
Core-7
50% -0.018
(7S1-7S2)
100% -0.064
500/1
120% -0.060
20% -0.019
Core-7
50% -0.015
(7S1-7S3)
100% -0.012
2000/1
120% -0.011
20% -0.002
Core-7
50% 0.001
(7S1-7S4)
100% 0.003
3000/1
120% 0.003
20% -0.095
Core-8
50% -0.082
(8S1-8S2)
100% -0.072
300/1
120% -0.071
Note: 1.0 CT should not saturate at 110% of Knee Point Voltage (KVp)
2.0 If Knee Point Voltage is not mentioned then Knee Point Current may be taken into consideration.
b) Stability test of differential and REF protection (at 10 kV) Ok Not Ok Remarks
Yes No Remarks
NOTE : Prove the tripping of associated breakers by actual operation of the various
devices and relays as per the schemes.
Yes No
a) Factory test results are available
b) All electrical test results compared with factory test results & found to be in order Yes No
Yes No
R-Ø A
Y-Ø A
B-Ø A
OTI ºC
WTI ºC
AMBIENT ºC
d) Maximum temperature after 24 hours ºC
e) Thermo vision scanning done at least after Yes No Remarks
24 hours of loading & repeated one week.
identification.
SL. DATE OF LOCATION VALUE REMARKS
NO MEASUREMENT
(Wherever 1.
Applicable) 2.
3.