0% found this document useful (0 votes)
211 views

20 MVA TF Test Report

The document provides a test report for a 3-phase transformer tested at JUUNL in Sikidiri, Jharkhand from October 10-11, 2019. It details the transformer specifications, references testing standards, equipment used, and results of various diagnostic tests performed on the transformer including tan delta and capacitance measurement of windings and bushings, insulation resistance, turns ratio, short circuit test, and SFRA test. The results are analyzed to evaluate the condition of the transformer according to technical standards.

Uploaded by

mayur dhande
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
211 views

20 MVA TF Test Report

The document provides a test report for a 3-phase transformer tested at JUUNL in Sikidiri, Jharkhand from October 10-11, 2019. It details the transformer specifications, references testing standards, equipment used, and results of various diagnostic tests performed on the transformer including tan delta and capacitance measurement of windings and bushings, insulation resistance, turns ratio, short circuit test, and SFRA test. The results are analyzed to evaluate the condition of the transformer according to technical standards.

Uploaded by

mayur dhande
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 45

1

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

Test Report of Transformer

KANOHAR ELECTRICALS MAKE, 20 MVA, 132/33/11 KV

At

Jharkhand Urja Utpadan Nigam Limited (JUUNL),


Sikidiri, Ranchi, Jharkhand.

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
2

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

Client : Jharkhand Urja Utpadan Nigam Limited

Location : Subernrekha Hydel Project, 132 KV S/s, Sikidiri

Work Order Details : Testing & Condition monitoring of outdoor


electrical equipments in 132 kV Switchyard,
Sikidiri (Work Order No: 31)

Report Submitted to : Electrical Maintenance Department

Report Revision : Rev. 0

Report Reviewed by

________________
Dr. Aradhana Ray
Engineering Consultant

PURPOSE OF DISTRIBUTION:

This document is distributed to JUUNL for their own commercial and maintenance
purposes. Rights to copy or distribute this document are only granted for the stated
purpose. The document may not otherwise be used or distributed without the prior written
permission of Laxmi Associates.

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
3

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

Contents:
1.0. Background …………………………………………………………………. 4
2.0. Scope of work………………………………………………………………. 4
3.0. Reference……………………………………………………………………… 4
4.0. Instrument used…………………………………………………………… 5
5.0. Transformer Details……………………………………………………… 5
6.0. Details of Test & Data Analysis……………………………………. 6
Tan Delta & Capacitance Measurement of Winding & Bushings
Insulation Resistance Test
Magnetizing Current Test
Turns Ratio Test
Magnetic Balance Test
Floating Neutral Test
Short Circuit Test
Vector Group Test
Winding Resistance Test
Dynamic Contact Resistance Measurement of OLTC
SFRA Test

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
4

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1. Background:

As a part of preventive maintenance activities Jharkhand Urja Utpadan Nigam


Limited (JUUNL) has decided to carry out testing on their Transformer.

For the stated purpose JUUNL, appointed Laxmi Associates as service provider & The
detailed test results and analysis are given in this document.

2. Scope of work:

Carry out diagnostic testing on Transformer and submit a detailed test report
according to work order for “Testing and Condition monitoring of outdoor
electrical equipment in 132kV Switchyard, Sikidiri. (Work Order No: 31)”

3. Reference:

Analysis of transformer in reference with the following standards and publications.

IEEE.62.1995. IEEE Guide for diagnostic field testing of electric power apparatus
Part-1: Oil filled Power transformers, Regulators and Reactors.

IEEE Std C57.12.90-1999.IEEE Standard test code for liquid immersed distribution
power and regulating transformer

IEEE Std C57-104-1991.IEEEGuide for the detection and determination of


generated gas in oil-immersed transformers and their relation to the serviceability of
the equipment.

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
5

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

4. Details of Instrument Used:

Equipment Make Sr. No Calibration Date


Tan Delta Megger 14880813 10-10-2019
IR Tester Kyoritsu E0073914 01-07-2019
Winding Resistance Vanguard 41084 07-12-2018
Multimeter Fluke 42750813WS 10-10-2019
Turns Ratio Vanguard 29029 24-10-2019
Leakage Meter Meco 16250264 22-12-2018
SFRA Megger 1100423 04-07-2019

5.0 Transformer Details

Company JUUNL Serial Number KT-20000/6

Location Sikidiri , Jharkhand Phase 3


Manufacturer Kanohar Electricals kV 132/33/11

Vector Group YNyn0d11 MVA 20

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
6

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

6.0 Details of Test Results and Analysis:

6.1 Tanδ And Capacitance Measurement of Winding:


OTI: 30°C
a. Combination: HV/LV

Test Capacitance Tanδ


Combination Mode
Voltage (nF) (%)
2 KV 6.66137 0.318
HV/LV UST 5 KV 6.66271 0.319
10 KV 6.60025 0.317
2 KV 3.77939 0.249
HV/ground with LV Guard GST-g 5 KV 3.77946 0.248
10 KV 3.74511 0.245
2 KV 10.4410 0.293
HV/LV+Ground GST 5 KV 10.3411 0.291
10 KV 10.3450 0.292
2 KV 6.66306 0.318
LV/HV UST 5 KV 6.66359 0.319
10 KV 6.60180 0.316
2 KV 5.96522 0.395
LV/ground with HV Guard GST-g 5 KV 5.96569 0.395
10 KV 5.91053 0.387
2 KV 12.6290 0.357
LV/HV+Ground GST 5 KV 12.5076 0.353
10 KV 12.5124 0.351

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
7

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

b. Combination: HV/TV

Test Capacitance Tanδ


Combination Mode
Voltage (nF) (%)
2 KV 4.18364 0.339
HV/TV UST 5 KV 4.18385 0.342
10 KV 4.14563 0.339
2 KV 4.04264 0.263
HV/ground with TV Guard GST-g 5 KV 4.04277 0.262
10 KV 4.00564 0.259
2 KV 8.22701 0.303
HV/TV+Ground GST 5 KV 8.14823 0.301
10 KV 8.15103 0.301
2 KV 4.18381 0.341
TV/HV UST 5 KV 4.18397 0.341
10 KV 4.14585 0.337
2 KV 9.27998 0.368
TV/ground with HV Guard GST-g 5 KV 9.19088 0.365
10 KV 9.19434 0.363
2 KV 13.4634 0.359
TV/HV+Ground GST 5 KV 13.3342 0.353
10 KV 13.3395 0.356

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
8

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

c. Combination: LV/TV

Test Capacitance Tanδ


Combination Mode
Voltage (nF) (%)
2 KV 12.0768 0.400
LV/TV UST 5 KV 11.9612 0.399
10 KV 11.9665 0.400
2 KV 3.30613 0.340
LV/ground with TV Guard GST-g 5 KV 3.30613 0.336
10 KV 3.30738 0.328
2 KV 15.3854 0.386
LV/TV+Ground GST 5 KV 15.2378 0.385
10 KV 15.2436 0.384
2 KV 12.0786 0.400
TV/HV UST 5 KV 11.9626 0.398
10 KV 11.9687 0.398
2 KV 8.74137 0.354
TV/ground with HV Guard GST-g 5 KV 8.65750 0.350
10 KV 8.66129 0.347
2 KV 20.61910 0.380
TV/HV+Ground GST 5 KV 20.61950 0.379
10 KV 20.62710 0.378

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
9

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

6.2 Tanδ And Capacitance Measurement of Bushing:


Bushing
Make : CGL Mode Test Voltage (kV) Capacitance(pF) Tanδ (%)
Rating : 145kV
2 252.932 0.235
U-Phase
UST 5 252.945 0.237
145100003
10 252.929 0.242
2 250.940 0.225
V-Phase
UST 5 251.235 0.226
145100004
10 251.236 0.228
2 247.869 0.221
W-Phase
UST 5 247.881 0.221
145100009
10 247.802 0.196

6.3 Insulation Resistance Measurement :

IR Value(in GΩ) at 5 kV PI
Connection
15 Sec 60 Sec 600 Sec (600/60 Sec)
HV/LV 2.55 5.03 24.6 4.89
HV/TV 4.34 7.95 33.3 4.19
LV/TV 2.08 4.18 21.1 5.05
HV/E 3.29 4.84 9.10 1.88
LV/E 2.48 4.30 18.9 4.40
TV/E 3.45 6.95 27.2 3.91

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
10

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

6.4 Magnetization Current Test :

With 1-phase power supply


HV SIDE
TAP VOLTAGE APPLIED (VOLTS) CURRENT MEASURED IN mAmps
NO. 1U – N 1V – N 1W – N 1U 1V 1W
1 230.0 230.0 230.0 1.917 1.454 1.706
5 230.0 230.0 230.0 2.097 1.523 1.863
17 230.0 230.0 230.0 2.741 1.986 2.396

With 1-phase power supply


LV SIDE
TAP VOLTAGE APPLIED (VOLTS) CURRENT MEASURED IN mAmps
NO. 2U – N 2V – N 2W – N 2U 2V 2W
5 230.0 230.0 230.0 17.79 15.29 17.19

With 1-phase power supply


TV SIDE
TAP VOLTAGE APPLIED (VOLTS) CURRENT MEASURED IN mAmps
NO. 3U-3W 3V-3U 3W-3V 3U 3V 3W
5 230.0 230.0 230.0 38.64 28.60 35.92

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
11

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

6.5 Turn Ratio Test (Voltage Ratio Test)

a. Combination: HV/LV
MEASURED RATIO
TAP POS. 1U-N/ 1V-N/ 1W-N/
2U-N 2V-N 2W-N
1 4.2128 4.2108 4.2110
2 4.1593 4.1589 4.1575
3 4.1079 4.1080 4.1067
4 4.0560 4.0560 4.0558
5 4.0049 4.0049 4.0041
6 3.9535 3.9528 3.9522
7 3.9022 3.9031 3.9027
8 3.8541 3.8547 3.8531
9 3.8026 3.8026 3.8023
10 3.7518 3.7512 3.7508
11 3.7037 3.7033 3.7033
12 3.6519 3.6517 3.6505
13 3.6010 3.6011 3.6030
14 3.5522 3.5532 3.5519
15 3.5004 3.5015 3.5015
16 3.4484 3.4496 3.4491
17 3.4018 3.4076 3.0080

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
12

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

b. Combination: HV/TV
MEASURED RATIO
TAP POS. 1U-N/ 1V-N/ 1W-N/
3U-3W 3V-3U 3W-3V
1 7.2864 7.2868 7.2878
2 7.2003 7.1966 7.1978
3 7.1098 7.1072 7.1097
4 7.0199 7.0188 7.0190
5 6.9314 6.9298 6.9299
6 6.8429 6.8394 6.8403
7 6.7518 6.7483 6.7492
8 6.6668 6.6669 6.6666
9 6.5771 6.5789 6.5776
10 6.4837 6.4863 6.4823
11 6.4010 6.4038 6.4018
12 6.3146 6.3148 6.3115
13 6.2238 6.2247 6.2229
14 6.1397 6.1403 6.1375
15 6.0496 6.0514 6.0514
16 5.9642 5.9612 5.9615
17 5.8809 5.8789 5.8799

c. Combination: LV/TV
MEASURED RATIO
TAP POS. 2U-N/ 2V-N/ 2W-N/
3U-3W 3V-3U 3W-3V
5 1.7278 1.7278 1.7280

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
13

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector
6.6 Magnetic Balance Test:

HV SIDE 1-PHASE

TAP Applied Voltage in Volts


1U-N 1V-N 1W-N
246.3 219.2 29.90
1 109.8 246.1 139.6
24.05 225.8 246.5
246.7 218.3 30.58
5 107.2 246.5 140.4
26.3 224.4 246.3
247.6 215.1 33.33
17 107.0 247.4 141.4
26.63 222.7 247.4

LV SIDE 1-PHASE

TAP Applied Voltage in Volts


2U-N 2V-N 2W-N
247.3 202.4 46.5
5 104.8 246.9 143.0
37.04 213.3 247.6

TV SIDE 3-PHASE

TAP Applied Voltage in Volts


3U-3V 3V-3W 3W-3U
430.1 332.9 100.1
5 179.9 430.3 251.0
80.6 355.3 431.1

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
14

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

6.7 Floating Neutral Test:

Applied voltage to HV Side & measured voltage across neutral to earth.

Voltage Applied
HV Winding Voltage Measured (V)
(V)
1U-N 246.3
1V-N 246.1 N-EARTH 0.381
1W-N 246.5

6.8 Short Circuit Test:

Applied 1 phase Voltage in HV Side and Measured Current in HV & LV Side. While LV
kept shorted.
HV/LV

HV Side
HV Side (Applied Volts) LV Side
TAP POS. (Current in Amp)
Isc (A)
1U-N 1V-N 1W-N 1U 1V 1W
1 246.2 244.4 249.0 2.40 2.36 2.40 10.30
5 246.9 244.4 249.2 2.74 2.69 2.76 11.06
17 244.5 244.7 248.4 4.11 4.06 4.10 14.01

Applied 1 phase Voltage in HV Side and Measured Current in HV & TV Side. While TV
kept shorted.
HV/TV

HV Side
HV Side (Applied Volts) TV Side
TAP POS. (Current in Amp)
Isc (A)
1U-N 1V-N 1W-N 1U 1V 1W

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
15

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector
1 243.2 242.9 245.0 1.5 1.5 1.5 20.5
5 242.9 243.1 245.6 1.7 1.7 1.7 20.0
17 242.0 242.1 245.1 2.6 2.6 2.6 26.0

6.9 Vector Group Test:

Vector Group: YNyn0, Results are in Volts.


Apply 3-ᴓ, 415 Volts in HV Terminals and Shorted: 1U-2U
Connections Measured Voltage Remarks/Condition
1U-1N 246.2
1V-1N 244.4
1W-1N 249.0 1) 1W-2W =1V-2V
1W-2W 321.6 2) 1W-2V < 1V-2W
1V-2V 316.6 3)1U-1N = 1U-2N+2N-1N
1W-2V 347.1
1V-2W 321.4 THUS VECTOR GROUP
1U-1N 245.1 YNyn0 CONFORMED.
1U-2N 61.2
2N-1N 182.6

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
16

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

6.10 Measurement of Winding Resistance :

a. HV Side WTI=39⁰C

WINDING RESISTANCE IN mOhms


TAP
1U-N 1V-N 1W-N
NO.
At 30 ◦C At 75 ◦C At 30 ◦C At 75 ◦C At 30 ◦C At 75 ◦C
1 1008.0 1179.169 1012.0 1183.849 1013.0 1185.018
2 995.8 1164.898 995.2 1164.196 998.8 1168.407
3 982.2 1148.988 981.6 1148.286 982.4 1149.222
4 966.8 1130.973 967.4 1131.675 970.3 1135.067
5 957.0 1119.509 953.8 1115.766 958.2 1120.913
6 940.3 1099.973 941.5 1101.377 946.6 1107.343
7 925.7 1082.894 925.9 1083.128 938.2 1097.517
8 914.0 1069.207 911.9 1066.750 920.7 1077.045
9 902.1 1055.286 897.6 1050.022 910.4 1064.996
10 889.0 1039.962 883.6 1033.645 898.8 1051.426
11 882.4 1032.241 871.5 1019.490 883.1 1033.060
12 861.3 1007.558 859.0 1004.867 875.8 1024.520
13 851.2 995.743 847.3 991.181 856.2 1001.592
14 839.8 982.407 834.1 975.739 844.0 987.320
15 826.4 966.732 818.7 957.724 830.7 971.762
16 810.0 947.547 806.3 943.218 820.9 960.298
17 797.2 932.573 791.9 926.373 803.0 939.358

b. LV Side WTI=32⁰C
WINDING RESISTANCE IN mOhms
TAP
2U-N 2V-N 2W-N
NO.
At 32 ◦C At 75 ◦C At 32 ◦C At 75 ◦C At 32 ◦C At 75 ◦C

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
17

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector
5 61.47 71.370 61.82 71.776 61.78 71.730

c. TV Side WTI=32⁰C
WINDING RESISTANCE IN mOhms
TAP
3U-3W 3V-3U 3W-3V
NO.
At 32 ◦C At 75 ◦C At 32 ◦C At 75 ◦C At 32 ◦C At 75 ◦C
- 58.50 67.921 58.77 68.235 58.34 67.735

6.11 Dynamic Contact Resistance Measurement of OLTC


U-PHASE FORWARD

U-PHASE REVERSE

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
18

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

V-PHASE FORWARD

V-PHASE REVERSE

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
19

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

W-PHASE FORWARD

W-PHASE REVERSE

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
20

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

6.12 SFRA Test


1U-N ALL OPEN TAP-1

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
21

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1V-N ALL OPEN TAP-1

1W-N ALL OPEN TAP-1

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
22

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1U-N ALL OPEN TAP-5

1V-N ALL OPEN TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
23

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1W-N ALL OPEN TAP-5

1U-N ALL OPEN TAP-17

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
24

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1V-N ALL OPEN TAP-17

1W-N ALL OPEN TAP-17

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
25

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1U-N LV SHORT TAP-1

1V-N LV SHORT TAP-1

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
26

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1W-N LV SHORT TAP-1

1U-N LV SHORT TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
27

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1V-N LV SHORT TAP-5

1W-N LV SHORT TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
28

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1U-N LV SHORT TAP-17

1V-N LV SHORT TAP-17

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
29

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1W-N LV SHORT TAP-17

1U-N TV SHORT TAP-1

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
30

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1V-N TV SHORT TAP-1

1W-N TV SHORT TAP-1

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
31

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1U-N TV SHORT TAP-5

1V-N TV SHORT TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
32

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1W-N TV SHORT TAP-5

1U-N TV SHORT TAP-17

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
33

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1V-N TV SHORT TAP-17

1W-N TV SHORT TAP-17

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
34

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

2U-N ALL OPEN TAP-5

2V-N ALL OPEN TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
35

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

2W-N ALL OPEN TAP-5

2U-N LV SHORT TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
36

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

2V-N LV SHORT TAP-5

2W-N LV SHORT TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
37

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

3U-3V AT TAP-5

3V-3W AT TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
38

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

3W-3U AT TAP-5

3-PHASE COMPARISION

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
39

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector
1U-N, 1V-N & 1W-N ALL OPEN TAP-1

1U-N, 1V-N & 1W-N ALL OPEN TAP-5

1U-N, 1V-N & 1W-N ALL OPEN TAP-17

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
40

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1U-N, 1V-N & 1W-N LV SHORT TAP-1

1U-N, 1V-N & 1W-N LV SHORT TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
41

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1U-N, 1V-N & 1W-N LV SHORT TAP-17

1U-N, 1V-N & 1W-N TV SHORT TAP-1

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
42

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

1U-N, 1V-N & 1W-N TV SHORT TAP-5

1U-N, 1V-N & 1W-N TV SHORT TAP-17

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
43

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

2U-N, 2V-N & 2W-N ALL OPEN TAP-5

2U-N, 2V-N & 2W-N TV SHORT TAP-5

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
44

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector

3U-3V, 3V-3W & 3W-3U AT TAP-5

*** END OF REPORT ***


Please contact us in case of any further query regarding this report.
Thanking you,

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02
45

Consultancy |Third party Inspection |RLA | Testing & Commissioning |Training in Power Sector
For & on behalf of Laxmi Associates

Dr. Aradhana Ray 


E-mail:[email protected], Mobile No.09374076950
Laxmi Associates (Engineering consultancy & Service Provider)
Sun Enclave ,Office No.13-14-15, Near Suncity Paradise, Manjalpur, Vadodara- 390020
http://www.laxmiassociates.in

Site JUUNL Client JUUNL


Location SIKIDIRI, JHARKHAND Test Date 10-11-2019 to 11-11-2019
Testing Engineer SURAJ PANDEY & SANJAY Report Prepared By HETAL JADHAV
Equipment Tested 3-PHASE TRANSFORMER Report Sr. No. LA/19-20/1898/02

You might also like