Ico Qap Final
Ico Qap Final
Table of Contents
1 Introduction
1.1 Background.
1.2 Objectives of the Quality Assurance Plan.
1.3 Importance of Quality Assurance plan.
1.4 Project Quality Policy.
1.5 Some Terminology.
1.5.1 Quality.
1.5.2 Quality Control.
1.5.3 Quality Assurance.
1.5.4 Acceptance.
1.5.5 Confirmatory Test.
1.5.6 Process Control Test.
1.6 Effective Quality Control.
1.6.1 Pre-Requisites of Effective Quality Control.
1.6.2 Quality of Work.
1.7 Need for Quality Control/Assurance.
2 Quality Management
2.1 The Management Frame Works.
2.2 Quality Cycle.
2.3 Contractors Responsibilities.
5 Method of Statement
5.1 Method Statement- Clearing and Grubbing
5.1.1 Scope.
5.1.2 Reference Documents.
5.1.3 Inspection and Test Plan.
5.1.4 Bench Marks.
5.1.5 Equipment Details.
2
5.1.6 Safety and Protection of Environment.
5.1.7 Personal Employed for Supervision.
5.1.8 Tolerances.
5.2 Method of Statement sub formation(Embankment) and Capping Layer
5.2.1 Scope.
5.2.2 Reference Document.
5.2.3 Materials.
5.2.4 Preparation of Bed.
5.3 Unbound Material Earth work
5.3.1 Scope
5.3.2 Reference Document.
5.3.3 Materials.
5.3.4 Frequency of Test and Sampling.
5.4 Sub Base –Unbound Material
5.4.1 Scope.
5.4.2 Reference Documents.
5.4.3 Materials.
5.4.4 Frequency of Testing and Sampling.
5.5 Prime Coat/ Tack Coat
5.5.1 Scope.
5.5.2 Frequency of Testing and Sampling.
5.6 Sub Base-Base Course Asphalt Concrete
5.6.1 Scope.
5.6.2 Reference Documents.
5.6.3 Materials.
5.6.4 Frequency of Testing and Sampling.
5.7 Wearing course
5.7.1 Scope.
5.7.2 Reference Documents.
5.7.3 Materials
5.7.4 Frequency of Testing and Sampling.
5.8 Method of Statement of all Structures
5.8.1 Scope.
5.9 Ancillary Works
5.9.1 Scope of Work.
5.10 Management and Maintenance Performance Measures
5.10.1 Road Usability.
5.10.2 Road User Service Levels.
5.10.3 Road User Service Levels on the Existing Road before Completion of
Improvements.
5.10.4 Road User Service Levels after Completion of Improvements.
3
5.10.5 Road Durability.
5.10.6 Road Roughens.
5.10.7 Non- Compliance.
5.10.8 Management Services.
5.11 Inspection of Service Levels by the Team Leader
5.11.1 Formal Inspections of Service Levels.
5.11.2 Informal Inspections of Service Levels.
5.12 Design Proof Checking Engineer
5.12.1 Contract Review.
5.12.2 Pavement Design Works.
5.13 Project Control and Administration
5.13.1 Contract Review.
5.13.2 Pavement Design Works.
6 Acceptance Criteria
6.1 Request for Review.
6.1.1 Material and Construction Works.
6.1.2 Testing.
6.1.3 Surveyor.
6.1.4 Inspection.
6.1.5 Measurement.
6.2 Non-Conforming Reports (NCR).
7 Tests on completion.
7.1 Tests on Completion: Annexure -D
8
8.1 Performance for Site Instruction, NCR, QC Tests and Checklist.
8.1.1 Quality Control Checklist.
8.1.2 Site Instruction.
8.1.3 Non-Compliance.
8.1.4 Survey Strip Layer chart.
8.1.5 Management and Maintenance Service Level.
8.1.6 Documentation.
9 Conclusion
9.1 LIST of Tables
9.2 Sub formation(Embankment)and Capping Layer
9.2.1 Materiel Specifications.
9.2.2 Test Frequency.
4
9.4 Sub Base Unbound Material
9.4.1 Materiel Specifications.
9.4.2 Test Frequency.
5
ABBREVATIONS
6
1 INSTRUCTION
1.1 Background.
Project: EPC Contract for Permanent Anticipated Works between KP24 and KP105 of Transgabonaise
National Road from Libreville to Francevelli located in the Republic of Gabon.
The Société Autoroutière du Gabon (SAG) awarded Contract of the Project Road to Afcons
Infrastructure Limited for Design, Improvement Works and Management and Maintenance Services
(EPC) from PK 24+000 to PK 105+000.
As per the Contract Agreement the Contractor is required to appoint an Independent entity as
Contractor’s Independent Control Officer (ICO) whose roles and responsibilities are:
Review Engineering studies and Execution studies (including VISA Mission).
Implementing the contract Program and take into account the modifications occur during its
implementation.
Certifying the completion of Milestones. ( Annexure - A) attached for detailed procedure
Translating in terms of specifications the requirements up to a level of detail sufficient to
ensure the control of the execution of the works.
Drafting and submitting to the contractor, which will further
Communicate with the Employer the contents of as Built Documents and validating the
compliance of the elements collected by EPC. Attached ( Annexure- B)
Carrying out, on a regular basis, as may be further described, in particular, in the
Employers Requirements, and in accordance with the progress of the works, external
controls of the construction in accordance with the quality assurance plan submitted by
EPC.
Confirming satisfactory progress on the critical path items and/or hard points in support of
the ad hoc justifications and to report on a monthly basis to the Contractor for
Communication to the Employer and its advisers.
Attending the tests during execution and on completion.
Approach Methodology
M/s CEG’s approach and methodology has been based on experience in executing similar projects
around the globe and project requirement. M/s CEG has assisted various clients in the
implementation and providing Engineering and Management solutions to engineering planning,
designing, contract administration, design review, quality control & quality audit, cost control and
value engineering, variation orders, environmental management plan & HSE audit etc. and thus
7
brings on board a rich experience in engineering excellence. M/s CEG has a pool of international
experts to cater to the services in different geographies of the globe.
The basic concept of the process is that the Contractor performs adequate sampling, testing and
inspections to ensure a quality output and ICO team performs to ensure that the Contractors Quality
Control test results are accurate and conform within the acceptable limits. However, the system
requires that both the Contractor and the ICO representative have to work together, who are
competent in sampling, testing and inspection of all the specified works.
The contractors are fully responsible to mobilize the competent personnel, to establish comfortable
laboratory and to supply accurate apparatus/equipment’s to perform quality control as per
commitment and undersigned in the Contract.
To achieve this said objectives of assessing and ensuring quality, it is essential to have a Quality
Assurance Plan (QAP) for the job in the initial stage itself and followed by until the completion of the
Contract.
During the operation of Contract if any deficiency and improvements, amendments is felt necessary,
this Document will be amended as per provision of Contract.
The system requires that both the Contractor and the ICO's Representative have Material Engineer
who are competent in testing and inspection of all road works. The general idea is that the
Contractor has to perform the necessary tests and inspection to ensure that all his works in road
construction meet the specification instead of "after the fact" testing to see if all works meet the
specifications. This approach enables the Contractor much more control over his operations. The
Contractor is responsible for the product from the beginning to the end, from the design changes to
the construction of works till the final acceptance of all the works. The Construction ICO monitors
the Contractors process of testing to make sure that what he is doing is adequate and accurate.
Ensuring quality and durability of the product and uniform performance of Construction Contractor
8
is the most important aspect of the Construction Supervision assignment of the ICO's
Representative engaged by the Contractor.
The Contractor's part of this QMS process is referred as Quality Control (QC), while the Construction
Supervision ICO's part of the process is referred as Quality Assurance (QA). The Contractor is
responsible to mobilize competent personnel and laboratory equipment's to perform his quality
control as per his Construction Quality Assurance Management Plan, and the ICO is responsible to
provide competent personnel to perform and implement the Quality Assurance Plan. To achieve this
said objectives of assessing and ensuring quality, it is essential to have a Quality Assurance Plan
(QAP) for the job in the initial stage itself.
In respect of the project Quality Policy, the ICO Team carryout role on the project to produce
products as per Agreement and Specification. This can be achieved by dedicated, committed and
qualified team members and by following QAP systems established for the Project as documented in
this QA Manual.
This QAP Manual established for the Project Team conforms to the requirement of Quality policy
disseminated by the company at corporate level, which is restated here under.
Consulting Engineers Group Ltd is committed to persistently meet the expectations and requirement
of its Employer by providing innovative, optimal, efficient, and effective and time bound better
engineering practices. This shall be achieved through proficient human resources and developing
harmonious environment at site.
9
Quality Assurance of a job is defined as a process that to ensure build the quality of work right from
the beginning and inspect regularly during the production periods, adopted control procedure that
has been properly design and acceptance.
1.5.4 Acceptance
Acceptance is the operations, inspections, sampling and testing that are conducted to determine
whether the product or service will be qualified for use and payment Acceptance is determined
using a statistically based acceptance plan in construction with assurance that the Contractor has
fulfilled the quality control obligations. Acceptance is the responsibility of the ICO representative/
Team Leader.
Process controlled specifications in combination with end product requirement are best suited to
Gabon conditions. In addition, control exercised by the Employer's Representative at each stage of
road construction or its elements for dimensional correctness and/or accuracy, meeting the laid
down acceptance criteria is ideal for a production of a quality work in practice.
ICO's Representative (Contractor Independent Control Officer) is not to accept a substandard input
or a substandard work at any stage. A substandard input or a work must be rejected and should not
be accepted. Acceptance of a substandard input or work at a reduced rate is no solution. A
substandard work must be either redone or rectified by the Contractor to the full satisfaction of the
Employer's Representative to conform to prescribed drawings and specifications. Availability of a
Quality Assurance Plan in the initial stages of work and its implementation at all relevant stages
including maintenance alone ensure a durable and functional product over its design life as
envisaged in the design document.
10
(i) Setting up of field laboratory
(ii) Equipping the laboratory with adequate equipment and personnel
(iii) Specifications and estimates must be provided for quality control
(iv) Documentation and Periodic appraisal of data for improvement
As per the provision in the Contract, the Contractor is to construct a laboratory building and set-up
the laboratory for the sole use of the Project Team. The contractor has to conduct necessary
inspections and testing jointly with ICO.
The Contractor is to submit his design and drawings for the approval of ICO prior proceed with the
construction activities.
(i) Specifications
Specifications applicable to project works are in accordance with "Employers Requirements Part III-2
Performance Specifications. The EPC Contractor responsible for establishing fully equipped
laboratory in accordance with the EPC contract.
Quality Inputs
Process Control as per specificationPeriodic Check Quality Outcome
The main inputs are Men, Materials, Machines, Money and Time. The contract document specifies
Qualification and experiences of key personnel for the job. The documents specify the materials,
their qualities and acceptable dimension limits for their use. Process control as per specification are
incorporated in the contract documents. Further they specify the functional requirements of the
machinery and or equipment to be used in the Production process. The other inputs i.e. money and
time, are normally established by the Contractor.
The inspections during production process are carried out as laid down in the Contract documents
and the codes mentioned therein jointly by the EPC Contractor and the ICO. The application of
these activities would nearly assure a quality product at the end.
11
better utilization of materials, also affords a significant reduction in user assets in terms of lower
costs of vehicle operation, transportation and maintenance.
2. Quality Management
2.1 The Management Frame Works
The ICO’s Representative’s will ensure that high quality of construction is achieved and that all works
are undertaken as per approved Engineering Designs and Specification as specified in the Contract
Document.
This will be achieved by ensuring effective real time supervision and monitoring by the ICO Team.
The Team will carry out all routine construction supervision duties. The Quality Management
Framework is given in the following Figure.
Obviously, it is noted that effective coordination between team members will be ensured through
periodic review meetings, so that common problems and remedies are known to each member of
the team. The ICO team structure is shown in the following figure.
12
Pre- Commencement Activities of Contractor Construction Activities by Contractor
Mobilization and management: Men, Machines, Applicable
Money, Materials: remedial and corrective measures
Setup quality control systemPre- Commencement Implementation by self-control
Activities of Contractor
Mobilization and management: Men, Machines,
Money, Materials:
Setup quality control system Analysis of Problem by the ICO
Study and plan the works Finding the defects
Obtain various approval Suggest remedial measures
Design and drawing approval
Start the works
Study and plan the works
Quality Assurance by Monitoring
Obtain various approval
and System Development,
Design and drawing approval
Carrying out periodical checks
Start the works
The contractor is responsible for developing, presenting, implementing and supplementing a quality
control procedure to ensure that all aspects of his work meet the standards set forth in the
specifications and is of acceptable quality. The Contractor is totally responsible for quality
throughout, and he is to take all necessary measures to ensure quality by adopting correct
construction practices to produce the end products of acceptance quality.
It is mandatory for the contractor to provide all facilities as stipulated in the Contract document such
as fully furnished Office, Power, Staff Quarters, Vehicles, and all Equipment’s and its running and
maintenances etc. QA/QC procedures to be adopted and he should be satisfying the ICO about
adequacy and safety of his program as per Contract.
13
The details of construction methodology including the details of construction machineries proposed
and to be used by the Contractor. The sequence and series of the various activities and schedule got
to be approved by the ICO before commencement of work. The Contractor has to provide a trial run
of each major items as per the contract document in order to maintain the given specifications and
tolerances.
The Contractor has to establish the field laboratory to conduct all quality control/quality assurance
tests. He will ensure that the laboratory is managed by the adequately by qualified and trained
staffs. The Contractor has also responsible for calibration of laboratory equipment at periodical
interval during the tenure of the project.
The Contractor is to collect the samples of construction materials jointly with the ICO or Employer
for testing and receive approval from the ICO office prior to use in the field.
The Contractor is to take precautionary safety measures for environment and social issues. He shall
be keeping all the equipment in good working condition and get them periodically checked to
control the hazards and pollution, further Contractor shall address and settle the social issues as per
social and rehabilitation plan.
The Contractor shall prepare the traffic management plan to maintain the smooth traffic flow during
the construction stage. He must make all necessary arrangement for the safe traffic diversion and
shall install traffic signals in appropriate location.
The Contractor shall satisfy that the site data furnished by the ICO is in order, and in case of any
discrepancy, he should get it correct through the ICO.
The Contractor shall establish the survey control points in the construction field as required with
close accuracy. He must establish bench marks near by the major structures like as Bridge structure,
buildings, any permanent structure shall re-establish any disturbed Bench mark/ reference point and
apply periodical checks on it.
The Contractor shall stack out the centre line pegs as well as offset pegs in every 20 m interval in the
straight portion and every beginning midpoint and end of the curve in every stages of construction
with accuracy.
The Contractor shall write and rewrite the chainages in close interval, specially shall write the
chainages in permanent structures. The font of the letters shall be legible.
The Contractor shall firmly install traffic sign post, guard post and any informatorily post in every
hazardous and critical section of the road.
14
3 Contractor’s Construction Activities
The Contractor is required to carry out the following major construction works. However, safety
measure is always considering at first.
Survey Works: Establishing all ground control points, permanent bench marks and well
as temporary bench marks as required then stake centre pegs and offset pegs.
Cleaning, grubbing top debris up to 10 cm depth and dismantle any structures within the
road corridor.
Earth Works- Embankment filling /Cutting, and Capping layers.
Sub-base Unbound materials
Prime coat, Tack coat
Base course Asphalt concrete
Wearing course
Construction of Structures (Side drains, Pipe culvers, RCC box culvert, Bridges)
River training works
Protective works line, side slope in cutting, backfill, selected back fill.
Road furniture’s (Road marking, Sign post, Kerb stone, guard post, crash barriers)
Any other work for smooth working such as coordinating with respective service
provider/ authorities, cutting trees, shifting of public utilities and removal of
encroachments.
Environment and Social mitigation measure.
Pre-construction Stage: Details preparations are necessary before undertaking any construction
activity. Their nature will vary from work to work, location to location, and project to project.
However, it can be broadly classified in to the following categories.
Procurement of Materials, Storing and testing: This shall be done well in time to ensure that
quarries are identified and approved. Factory made procurement shall be done and get approval
from the Employer.
15
3.1.1 Setting out
This setting out of road centreline excavation plan for structures are to be carried out in advance and
as per the guidelines given in the Standard Specification and approved drawing. The setting out will
include establishment of Bench Mark, Ground Control points, centre line, reference line by using the
highly precise survey equipment.
The Contractor’s Independent Control Officer will review the Safety Report and
furnish its comments thereon to CE/Afcons.
16
The Contractor’s Independent Control Officer will review the construction methodology and
the procurement, engineering and construction time schedule sent to it by the EPC and
furnish its comments.
Quality Assurance Manual and Plan forms the basis of quality of the work. It is therefore
essential that the Quality Assurance Manual and Plan prepared by the EPC will be checked
and approved. Thus, the Contractor’s Independent Control Officer will check contents of
Quality Assurance Plan and Manual of EPC as per requirements of Quality Management
System (as per ISO 9001), standards &specifications. The Contractor’s Independent Control
Officer will also offer their comments for modifying/ improving the document. After
receiving the modified document, the Contractor’s Independent Control Officer will approve
the QAM and Quality Plan, send one copy to the SAG.
Construction Period
The Contractor’s Independent Control Officer will review the monthly progress report
furnished by the EPC and send its comments thereon to the EPC and Employer SAG).
On a daily basis, the concerned key personnel of Contractor’s Independent Control Officer
will inspect the Construction Works based on the Request for Inspection Note raised by the
EPC, ensure compliances to the following activities.
Review of construction including progress, quality and safety of construction.
Witnessing quality inspection tests at labs established by EPC. Review of
quality of work shall be done in reference to Quality Assurance Plan (QAP)/Manual
and ISO 9001:2008, Standards & specifications as set forth.
On a monthly basis, the Contractor’s Independent Control Officer will prepare a
Monthly Inspection Report. The Contractor’s Independent Control Officer will submit
a copy of its Inspection Report to the Employer (SAG) and the EPC.
In the event that the EPC fails to achieve planned / scheduled progress, the
Contractor’s Independent Control Officer will undertake a review of the progress of
construction and identify potential delays, if any. Upon receipt of a report from the
EPC, the Contractor’s Independent Control Officer will review the same and send its
comments to the Employer (SAG) and the EPC Contractor (Afcons) forthwith.
The Contractor’s Independent Control Officer shall carry out all the Tests and
recommend for issuing a Completion Certificate or Provisional Certificate, as the
case may be.
17
Review the Environmental Management Plan.
Review the Quality Assurance and monitoring provisions during the design and
construction phases.
Review matters relating to Traffic Management Plan, Temporary diversions and
public safety measures proposed by EPC Contractor.
Regular monitoring of Progress of works and identify potential delays, if any, and
issue of instructions to take remedial measures to expedite the progress.
Review of Monthly Progress report submitted by the EPC Contractor and gives his
comments / observations to Employer (SAG).
Verify and Certify EPC contractors Interim Payment certificates.
Supervise the compliance and verification of As-Built Drawings.
Recommend for issuing of Provisional / Completion certificate.
Ensure all communications, instructions, drawings etc. are kept in safe custody and
hand over to Employer (SAG).
The Annexure –C is attached for detailed reference of review procedures as per Cl 1.4
of EMPLOYERS REQUIREMENTS PART-III.2: PERFORMANCE SECIFICATIONS.
18
Will inspect the site as per ‘Request for Inspection” (RFI) raised by the EPC for each layer.
Will check the Surface lines and levels of the layers constructed by EPC are as per approved
cross sections.
Upon his Approval next layer shall be processed.
19
limits for end products. The method of statements for the following main items of work is detailed
in these Chapters and the format/check lists are attached as Annexures to this report.
Clearing and Grubbing
Method of Statement sub formation(Embankment) and Capping Layer
Sub Base –Unbound Material (GNT2 Granularity 0/31.5)
Prime coat / Tack coat
Base Course-Asphalt Concrete (0/20 Class 2 High modulus asphalt concrete)
Wearing course (0/14 Class 3 High modulus asphalt concrete)
Method of Statement for All structures
Method of Statement for Ancillary works
5.1 Method statement Clearing Curbing
5.1.1 Scope.
The scope of work covers all the operations required to be executed as per Employers Requirements
Part III-2 Performance Specifications clause 4.0.
20
2. Stripping and loading: Dozer, Excavator, Mortar Grader, and Trucks.
Every benchmark is to be checked levelled by a forward run and a subsequent backward run forming
a closed "loop."
21
This item covers all the operations required to form earth work, embankment and sub-grade (also
called as capping layer) to the required lines and levels as per the requirements of widening of
existing road as well as construction of new road.
5.2.3 Materials
The material shall be conforming to Employer’s Requirements Part III-2 Performance Specifications
clause 5.1. It shall be free from logs, stumps, roots, rubbish or any other ingredient likely to
deteriorate or affect the stability of the embankment /Capping layers.
The maximum size of coarse material shall not exceed 300 mm and 80mm for rock fill and 2/3rd of
the layer thickness for other fill material after compaction.
The maximum compacted thickness of the layer shall not be exceeding 300 mm.
The following tests on material shall be done for acceptability criteria: -
The materials obtained from roadway excavation will be tested for its suitability for use as
fill material. Only when it is not suitable, fill material shall be obtained from approved
borrow pits.
Approved material from roadway excavation/borrow pits are excavated by
excavators and transported in dump trucks to the embankment site.
Acceptance Criteria for Embankment Fill Materials
Tolerance: T
Characteristics Specifications Test Rate
Recommendation : R
Materials
< 300 mm
Dmax
% of Fine < 35 % 1/1500 m3
22
compaction in Technical guide
Compaction q4
95 % pd OPN 50%
1/Profile
92% pd OPN 100%
i. Stripping and storing topsoil: The top soil shall be stripped to a depth of 150 mm and
stored in stockpiles of height not exceeding 3m, if so directed by the ICO. The original
ground supporting the embankment shall be levelled to facilitate placement of first layer of
embankment, scarified, mixed with water and then compacted by rolling as per SETRA
Technical Guide LCPC July-2009.
ii. Shaping and Compaction of the Road bed on Suitable Material: In case where the existing
ground beneath embankment has a density below 95% of MDD, the layer shall be scarified
to a minimum depth of 150 mm, watered and re-compacted in accordance with the
requirements of SETRA Technical Guide LCPC July-2009.
iii. Capping Layer: However, these materials will be often required to produce sufficient cover
on weak Capping Layers. It is used in the lower pavement layers as a substitute for thick sub
base to reduce costs. The physical requirement of capping layer as per in the Table given
below Employer’s Requirements Part III-2 Performance Specifications.
Physical Requirement of Capping Layer: -
23
Capping layer materials of lateritic gravel and any crushed stone, must meet the following
specifications. This material can be used for lateritic gravel sidewalk base.
Tolerance: T
Characteristics Specifications Test Rate
Recommendation : R
Materials
Lateritic gravel or unbound MDE≤45
1/1500 m3
material
1/1000 m3
Dmax < 80 mm
Tolerance: T
Characteristics Specifications Test Rate
Recommendation : R
Plasticity index(PI) < 25 1/1000 m3
% of fine (80µm) <35% 1/1000 m3
Normal Proctor ≥2050kg/m3 1/2000 m3
Swelling <0.5% 1/5000 m3
CBR 90% 4days immersion >30% 1/2000 m3
Implementation Test Section
Compaction
water content OMC +2,-2 % 1/500 m3
20
Compaction q3-Inspection test lot 98.5 % pd OPN 50% Measurements
1000m 96% pd OPN 100%
3
Additional acceptance Criteria: Measurements
100 %
Thickness ±2 ar 20ml
3
Topographic Measurements
Measurements
-Inspection lot 1000m 100 %
±2 ar 20ml
2
Irregularity Measurements – Longitudinal and Measurements
Straightedge test –(NP-98-218) Transverse < 2ar 100ml
24
50m
Process:
The approved soils from roadway excavation/borrow areas shall be excavated and
transported to the site of embankment.
The material shall be spread in layers of uniform thickness not exceeding 300 mm
compacted thickness over the entire width of embankment by mechanical means and
finished by motor grader.
The moisture content shall be checked and if found to be out of limits, the same shall be
made good.
If the moisture is high, it shall be dried, by aeration and exposure to the sun, till the
moisture content is brought down to the required level. Compaction shall be suspended in
inclement weather.
If the moisture content is less, water shall be sprinkled by water tanker having sprinkler
attachment and mixed thoroughly in soil by mechanical means till uniform moisture
content is obtained.
The moisture content of each layer shall be checked. It shall be in between 2%above OMC.
Compaction shall be done as per SETRA Technical Guide LCPC July-2009. Vibratory or other
rollers shall be used for achieving the required results.
The surface of the embankment shall be maintained at such a cross slope as will shed water
and prevent pounding.
Compaction tests shall be conducted to confirm the field dry density by nuclear density
gauge or by sand replacement method and rapid moisture meter shall be used to measure
field moisture content.
The next layer shall be placed only after achieving the required test result and due
approvals.
Before commencement of the actual construction of Capping Layer, a trial section shall be
demonstrated so that the adequacy of equipment and processes are established.
Equipment Details:
Excavation and Loading: Hydraulic Excavators
Transport: Dump Truck.
Spreading and grading: Dozers, graders and tractors.
Watering: Water tankers fitted with sprinklers.
Compaction: Vibratory rollers.
Testing equipment's: As per required standards.
25
Contractor technical staff shall be deployed to proceed the works, supervision and defects
rectification.
Activities:
Obtain and check latest construction drawing.
The centreline and batter lines shall be marked and got checked by the Engineer's
representative.
The benchmarks shall be established after connecting with the GPS benchmarks in the
region.
The grid levels shall be recorded and got verified by ICO.
The cross sections are plotted and the required profile of the proposed road section is
superimposed and the batter lines shall be identified and submitted for approval of ICO.
The layout is set-out and beacons are established and protected.
Approvals of borrow material obtained.
Establish OMC & MDD and CBR value for all soils.
Check for clearing and grubbing.
Check for stripping.
Check for bed compaction.
Check for approved borrow areas.
Excavate, transport and dump in approved areas for dumping.
Spread in uniform layer and grade to the required lines and levels.
Check moisture content and rectify if needed.
Compaction using adequate mechanism/ rollers verify field Density for layers.
If the density up to requirement not achieved repeat rolling until the required density is
achieved.
Record the test results and process the filing system.
Proceed to next layer until the level for next course is reached
Obtaining required compaction.
The reach is ready for next process.
26
6. NF P 97-117-2.
7. SETRA Technical Guide LCPC July-2000.
5.3.3 Materials
The material shall be conforming to Employer’s Requirements Part III-2 Performance Specifications
clause 5.1. It shall be free from logs, stumps, roots, rubbish or any other ingredient likely to
deteriorate or affect the stability of the embankment layers.
The maximum size of coarse material shall not exceed 300 mm for rock fill and 2/3rd of the layer
thickness for other fill material after compaction.
The maximum compacted thickness of the layer shall not be exceeding 300 mm.
The following tests on material shall be done for acceptability criteria: -
The materials obtained from roadway excavation will be tested for its suitability for use as
fill material. Only when it is not suitable, fill material shall be obtained from approved
borrow pits.
Approved material from roadway excavation/borrow pits are excavated by
excavators and transported in dump trucks to the embankment site.
Materials
unbound material MDE≤45, LA ≤45 1/1500 m3
Dmax < 80 mm
1/1000 m3
Plasticity index(PI) Not Measurable
27
5.4 Sub Base (Unbound Material)
5.4.1 Scope
Sub base course (unbound) is placing just over the prepared Capping as per the approved drawing
and the technical specification of the Contract. The granular sub base either natural quarry material
or graded river bed material or crusher run. It covers all the operations required to form granular
sub base course to the required lines and levels as per the drawings and the technical specification
of the Contract.
5.4.2 Reference Documents
1. Employer’s Requirements Part III-2 Performance Specifications.
2. EN 13285 the unbound mixture will be a GNT2 granularity 0/31.5.
3. NF P 18-545 and NF EN 13242.
4. NF P 98-115.
5. NF P 98-218
5.4.3 Materials
The quarry for GSB material shall be identified.
The material shall be the consisting of natural gravel, crushed gravel, crushed rock, river bed or
combination of crushed rock & natural gravel, or any other material complying with the
requirements of the clause 5.2(5.2.1) as per the Employer’s Requirements Part III-2 Performance
Specifications and approved by the ICO.
The complete sub base shall contain no material having a maximum dimension exceeding two thirds
of the compacted layer thickness. The following tests on material shall be done.
Grading Requirement:
According EN 13285 the unbound sub base mixture will be a GNT2 granularity 0/31.5.
Physical Requirement of Sub base:
Tolerance: T
Characteristics Specifications Test Rate
Recommendation : R
Aggregates:
28
Granularity T: GTc 25/15 or 20/15 or
Manufacturing characteristics of the GC 80/20 20/17.5 1/1000 T
gravel type III F2
FL 35
Granularity
Cleanliness
Flattening
Sand Manufacturing characteristics: GA 85
Type b
Granularity MB2.5 and SE45
MB-Methylene blue T : GTA10
Cleanliness of the elements < 2mm SE –Sand Equivalent 1/1000 T
Approved material at a selected location and care shall be taken to prevent contamination of
unbound sub base material.
Construction Process:
The selected sub-grade layer shall be checked for density and bed preparation before
placing the sub base material for any damage or deficiency which shall be made good as
directed by the ICO.
The approved granular material from stockpile shall be transported to the site.
The material shall be spread in layers of uniform thickness not exceeding 300mm
compacted thickness over the entire width of capping layer by mechanical means and
finished by motor grader.
The moisture content shall be checked and if found to be out of limits, the same shall be
made good.
If the moisture is high, it shall be dried, by aeration and exposure to the sun, till the
moisture content is brought down to the required level. Compaction shall be suspended in
inclement weather.
If the moisture content is less, water shall be sprinkled by water tanker having sprinkler
attachment and mixed thoroughly by mechanical means until uniform moisture content is
obtained.
The moisture content of each layer shall be checked. It shall not be in more than +2% -1%
above OMC.
The compaction shall be completed as soon as possible after the material has been spread.
Vibratory rollers shall be used for achieving the required results.
The compaction shall be done to achieve minimum field density 95% of Modified Proctor
NF P98-115 for a single test. Around structures, compaction shall be done by using small
vibratory roller/plate vibrators.
The surface of the sub base shall be maintained to the required cross fall.
The tests shall be conducted to confirm the field dry density by Sand
Replacement Method.
Before commencement of the actual construction of sub base course, a trial section shall
be demonstrated so that the adequacy of equipment and processes are established.
Only when such a trial section has been satisfactorily laid and finished and complies with
the specified requirements, the actual sub base layer work shall commence.
29
Equipment Details:
Excavation and Loading: Hydraulic Excavators
Transport: Dump Truck
Spreading and grading: Dozers, graders and tractors
Watering: Water tankers fitted with sprinklers
Compaction: Vibratory rollers
Testing equipment's: As per required standards.
Activities:
Obtain and check latest construction drawing.
The centreline and batter lines shall be marked and got checked by the Engineer's
representative.
The benchmarks shall be established after connecting with the GPS benchmarks in the
region.
The grid levels shall be recorded and got verified by ICO.
The cross sections are plotted and the required profile of the proposed road section is
superimposed and the batter lines shall be identified and submitted for approval of ICO.
The layout is set-out and beacons are established and protected.
Approvals of borrow material obtained.
Establish OMC & MOD and CBR value for all soils.
Check for stripping.
Check for bed compaction.
Check for approved borrow areas.
Spread in uniform layer and grade to the required lines and levels.
Check moisture content and rectify if needed.
Compaction using adequate mechanism/ rollers verify field Density for layers.
If the density up to requirement not achieved repeat rolling until the required density is
achieved.
Record the test results and process the filing system.
Proceed to next layer until the level for next course is reached
Obtaining required compaction.
The reach is ready for next process.
Construction Tolerances:
Surface Level ± 2cm,
30
Layer Total Width,0 to + 5 cm and Theoretical edge layer + 3cm shown in the drawing.
Thickness, the mean layer thickness of the lot is not less than the specified thickness minus ± 2cm.
5.4.4 Frequency of Testing and sampling
In the leadership of material engineer the lab team shall be deployed for the required test of the
layer, frequency of sampling and test will be conducted as per the prescribed specification in the
established laboratory. However, if third party test required will be sent accordingly.
The following Table given the testing frequency for process control.
Tolerance: T
Characteristics Specifications Test Rate
Recommendation : R
Implementation (NF P98-115)
1/5000 T
Proctor Compaction
water content OMC +2,-1 % 1/500 m3
20
Measureme
Compaction q2-Inspection test lot 97 % pd OPN 50%
nts
1000m 95% pd OPN 100%
3
Thickness % Measurements at the Measureme
100 %
prescribed thickness. nts 20ml
3
Topographic Measurements
Measureme
-Inspection lot 1000m 100 %
±2 ar nts 20ml
2
Irregularity Measurements – Longitudinal ≤ 1.0cm Measureme
100 %
Straightedge test –(NP-98-218) Transverse < 1.5cm nts 100ml
Prime Coat:
A prime coat is a thin layer of cutback bitumen such as C55B(F)5 sprayed on to the existing
31
subbase surface. It assists in promoting and maintaining adhesion between Sub base layers
of the pavement. Application rate of prime is likely to lie within the range of 1.1kg/m2 of
residual bitumen and spraying temperature is in between 45 0c to 700c and surface
temperature shall be above 150c. The prime shall be penetrating completely under the
surface.
Process
No longer than 24 hours before spraying, the layer to be primed shall be broom and
cleaned of all loose or deleterious material by means of a rotary broom and hand brooms.
A light spray of water, sufficient to dampen the surface, shall be uniformly applied to the
layer immediately before the application of the primer. If the water is over applied the
layer shall be allowed to dry until a uniform damp surface is obtained.
Before any prime material is sprayed the layer to be primed shall be checked for
compliance with the surface and other requirements specified. Any sections not complying
with the specified requirements shall be corrected as specified.
Twine-reinforced paper or other suitable approved material shall be used at all joints at the
beginning and end of all sprays in order to obtain a neat start and cut-off. Curing period is
likely to minimum 24hrs-48hrs or as per ambient temperature.
All prime materials stored in a heated condition shall be stored in a container with a
properly functioning circulation system and having a securely fitting lid. No heat shall be
added to materials delivered above storage temperature until the temperatures are below
those specified above unless the materials are intended for immediate use.
The primer shall be applied in one or more lanes evenly over the full width of the road and
allowed to penetrate and cure until traffic can pass over the surface without the wheels
picking up the prime. All traffic shall be kept off the surface until this condition is obtained.
The total width of primed surface shall be 15cm outwards both sides of the edge of
granular base course. If primer is applied in more than one lane, allowance shall be made
for overlapping the lanes by 100 mm.
Where it is not feasible for traffic to use bypasses, the primer shall be applied and allowed
to penetrate for as long as is practicable before a blinding layer of mineral aggregate is
applied.
As soon as the primed surface has dried sufficiently to allow the traffic to pass over the
road without picking up or otherwise damaging the primed surface, the road shall, where
practicable, be opened to public traffic for a period of 3 days.
Before commencing with the actual construction of any Prime Coat, laying a trial section
shall be demonstrated so that the equipment and processes that are proposed to be used
will enable to construct the Prime Coat in accordance with the specified requirements.
The trail section(s) shall be laid where indicated by the ICO. Only when such a trial section
has been satisfactorily laid and finished, and complies with the specified requirements, the
actual permanent work shall commence.
Tack Coat
Tack coat is a straight run bitumen. The primary function of a tack coat is to act as a glue to
assist bonding of a new surface layer to a previously bituminous surface. The application
rate of tack coat range in between 400gms/m 2 and temperature ranges 1450c to 1700c.
Before application of tack coat the surface shall be broom and cleaned of all loose or
deleterious material by means of a rotary broom and hand brooms.
32
5.5.2 Frequency of Testing and sampling
In the leadership of material engineer the lab team shall be deployed for the required test of the
layer, frequency of sampling and test will be conducted as per the prescribed specification in the
established laboratory. However, if third party test required will be sent accordingly. The following
the testing frequency for process control test as per Employer’s Requirements Part III-2 Performance
Specifications Clause 5.2.4.
Prime Coat
Rate of Fluidized bitumen per 1.1kg/m 2
Rate of Spread of Binder Tolerance < ±10%
Tack coat
Rate of Spread bitumen per 400gm/m2
Rate of Spread of Binder Tolerance < ±10%
Accuracy of Spread binder, Tolerance <15%
Rate Test Implementation 1/1000m2
33
5. EN 933-9.
6. EN 12591 of EN 14023.
7. EN 1426.
8. EN 1427.
9. EN 12595 or12596.
10. EN 13108-1.
11. EN 13108-20.
12. EN 13108-21.
13. EN 13036-7.
14. NF P 98-150-1.
5.6.3 Materials
All materials shall be handled and stockpiled in a manner will prevent contamination of deleterious
substance, segregation or damage.
The Contractor shall as often as necessary test and control the materials produced directly, or the
materials received from suppliers, to ensure that the materials comply with the specified
requirements.
Mix Design
The contractor shall be designed the mix design of Asphalt Concrete for Base course based on the
recommendations given in the EN 13108-1 and 13108-20 carried out Test Procedure and get
approval from the ICO. Base course Asphalt material made of 0/20(EME2) class 2 high modulus
asphalt concrete, must meet the following requirements.
Material Requirement
Characteristics Specifications Test Rate
Aggregates:
NF P18-545 and NF EN 13043 1/5000T
Intrinsic Characteristics: DNC code
Coefficient Los Angles(LA) LA ≤30 1/5000T
Micro-Deval Coefficient (MDE) MDE≤25
Granularity
Manufacturing characteristics of the gravel type III
Granularity GC 85/20
Cleanliness F1 or F2 if MBF 10
1/1000 T
Flattening FL 25
Sand Manufacturing characteristics: Type a
Granularity GF 85
1/1000 T
Cleanliness of the elements < 2mm MB2
34
Filler AggregateEN13043
Equipment Requirements
Hot Mix Asphalt Mixing Plant:
Water tanker fitted with sprinklers
Air Compressor: Tractor mounted I Truck mounted or self-wheeled
Bitumen Distributor
Drag Broom: Power operated capable to distribute chips evenly.
Compaction: 2 nos. PTR capable of creating a tire pressure of 275 Kpa or as directed
by the ICO.
Front End Loader: To load aggregate on tippers at stockpile
Tippers: Adequate nos. to transport aggregate from stockpile to site.
Paver with automatic electronic screed controls.
Testing equipment's: As per required standards.
Construction Process
35
Before commencing with the actual construction of any asphaltic course and surfacing
layers, lying of a trial section shall be demonstrated, so that the equipment and processes
that are proposed to be used will enable to construct the asphaltic layers in accordance with
the specified requirements. The trial section(s) shall be laid where indicated by the Team
Leader.
Obtain and check the approved construction drawing.
The centreline and batter line shall be marked and get checked by the supervision
consultant.
Surface shall be clean and if needed rectification, rectify.
The cut edge of the existing layer shall be painted with a thin coat of bitumen that is tack
coat.
The mixture shall be delivered to the paver in such a manner that the paver will never be
forced to stop for lack of asphalt. Only minimal hand-working of asphalt shall be permitted
after discharge from the paver and before rolling and shall only be carried out with wooden
spreaders. Operatives shall not be permitted to walk on un-compacted asphalt. Paving shall
cease when rain starts falling or when, in opinion of the Team Leader, the surfaces to be
paved are visible wet.
The mix shall be rolled as soon as possible after it has been laid by combination of vibratory
and non-vibratory steel-tired flat rollers and pneumatic-tired rollers in sequence. Rolling
shall commence with a self-propelled pneumatic-tired roller working parallel to the centre
line of the road from the shoulders towards the crown of the road until the whole surface
has been covered at least three times with the wheels of the roller initially.
All joints between adjacent sections of the work shall be made by cutting back the layer
against which material is to be placed and cutting wheel shall be used for cutting joints.
Before a new layer is placed next to an existing layer the cut edge shall be painted with coat
bituminous of the same type used for tack coat. The outside edges of completed asphalt
layer shall be trimmed along the shoulders and parallel to the centre line to give the finished
width shown on the drawings, with tolerances specified.
Only when such a trial section has been satisfactorily laid and finished, and complies with
the specified requirements, the actual permanent work shall commence.
Falling Weight Deflector Meter and International Roughness Index (IRI)/ Roughness Profile-
meter Tests shall be carried out on completion of the road section or before its handover.
36
supervision and defects rectification. The ICO team shall have approved working drawing in
hand.
5.6.4 Frequency of Testing and sampling
In the leadership of Material Engineer, the lab team shall be deployed for the required test of the
layer, frequency of sampling and test will be conducted as per the prescribed specification in the
established laboratory. The minimum testing frequency that will be required from the Contractor in
terms of Clause 5.2(5.2.1) as per Employer’s requirements Part III-2 Performance Specifications for
the purpose of process control shall be given in the Table. However, if third party test required will
be sent accordingly.
Characteristics Specifications Test Rate
Composition in relation to the reference
formulation (absolute value) for the average
of 4 samples (EN 13108-21)
Bitumen content %
Formula±0.3 2 extractions
Aggregates (passing 0.063mm) Formula ± 2 minimum per
Formula ± 3 day
Aggregates (2mm passageways) (EN 12697-1)
Formula ± 4
Aggregates (6-10-and 14mm passageways)
Formula ± 5
Aggregates (20mm passageways)
2
Irregularity Measurements –Straightedge test Longitudinal ≤ 1.0cm Measurements
–(EN13036-7) Transverse < 1.5cm 100ml
37
1
Layer total width: 0 to +5cm. Measurements
Width carriageway
Theoretical edge layer ±3cm 50ml
38
1/5000T
Micro-Deval Coefficient (MDE) MDE≤15
1/20 000T
Polished stone Value(PSV) <50
Granularity
Manufacturing characteristics of the gravel type III GC 85/20
Granularity F1 or F2 if MBF 10
Cleanliness FL 25
1/1000 T
Flattening
Voids – Rigden(EN1097-4)
V28/45
Delta ring and ball(EN13179-1)
ΔR&B 8/25
Harmful fines(EN933-9) 1/500 T
MBF 10
Grading: Grading requirement for Asphalt Concrete Base course shall comply EN 13108-1
Table 1&2
Bituminous Binder: The bituminous binder shall be 20/30 penetration grade shall be
complied with the requirement of EN 12591 and as per Employer’s Requirements Part-III-2
Performance specification clause 4.3.2.2 and bitumen sampling shall comply with the
relevant procedure as described in EN 12591.
Elasticity Modulus Requirements: The Elasticity requirements for mixes designed for more
than 5 million Mesa traffic are as per specification table NF P 98-150-1.
Core Cutting: The Contractor shall be provided suitable coring machines capable of cutting
100mm diameter cores from the completed Asphaltic layer as directed by the Engineer.
Equipment Requirements
39
Hot Mix Asphalt Mixing Plant:
Water tanker fitted with sprinklers
Air Compressor: Tractor mounted I Truck mounted or self-wheeled
Bitumen Distributor
Drag Broom: Power operated capable to distribute chips evenly.
Compaction: 2 nos. PTR capable of creating a tire pressure of 275 Kpa or as directed
by the ICO.
Front End Loader: To load aggregate on tippers at stockpile
Tippers: Adequate nos. to transport aggregate from stockpile to site.
Paver with automatic electronic screed controls.
Testing equipment's: As per required standards.
Construction Process
Before commencing with the actual construction of any asphaltic course and surfacing
layers, lying of a trial section shall be demonstrated, so that the equipment and processes
that are proposed to be used will enable to construct the asphaltic layers in accordance with
the specified requirements. The trial section(s) shall be laid where indicated by the Team
Leader.
Obtain and check the approved construction drawing.
The centreline and batter line shall be marked and get checked by the supervision
consultant.
Surface shall be clean and if needed rectification, rectify.
The cut edge of the existing layer shall be painted with a thin coat of bitumen that is tack
coat.
The mixture shall be delivered to the paver in such a manner that the paver will never be
forced to stop for lack of asphalt. Only minimal hand-working of asphalt shall be permitted
after discharge from the paver and before rolling and shall only be carried out with wooden
spreaders. Operatives shall not be permitted to walk on un-compacted asphalt. Paving shall
cease when rain starts falling or when, in opinion of the Team Leader, the surfaces to be
paved are visible wet.
The mix shall be rolled as soon as possible after it has been laid by combination of vibratory
and non-vibratory steel-tired flat rollers and pneumatic-tired rollers in sequence. Rolling
shall commence with a self-propelled pneumatic-tired roller working parallel to the centre
line of the road from the shoulders towards the crown of the road until the whole surface
has been covered at least three times with the wheels of the roller initially.
All joints between adjacent sections of the work shall be made by cutting back the layer
against which material is to be placed and cutting wheel shall be used for cutting joints.
Before a new layer is placed next to an existing layer the cut edge shall be painted with coat
bituminous of the same type used for tack coat. The outside edges of completed asphalt
layer shall be trimmed along the shoulders and parallel to the centre line to give the finished
width shown on the drawings, with tolerances specified.
Only when such a trial section has been satisfactorily laid and finished, and complies with
the specified requirements, the actual permanent work shall commence.
Falling Weight Deflector Meter and International Roughness Index (IRI)/ Roughness Profile-
meter Tests shall be carried out on completion of the road section or before its handover.
40
Social and Environment Safety Measures:
All effective and requisite safety measures shall be implemented to ensure full safety to all
the concerned work force, machinery, traffic and general public.
Effective and sufficient care shall be taken to minimize damage to the environment and
cleanliness in all works is given the utmost importance.
PPE compulsion for the navvies.
Traffic diversion, sings, delineation, barricades are placing as per required.
Bitumen content %
Formula±0.3
Aggregates (passing 0.063mm)
Formula ± 2
Aggregates (2mm passageways)
Formula ± 3
Aggregates (6-10 mm passageways)
Formula ± 4
Aggregates (14mm passageways)
41
Formula ± 4
Implementation (NF P98-150-1)
Compaction Test Board
Absolute compactness % -inspection lot 20 Measurements
1000ml (interval method according XP P98- 92 ≤ c ≤ 100 +1 test core/500ml
151) Vi ≤ c ≤ Vs to check thickness
and compactness
Thickness % Measurements at the by hydrostatic
prescribed thickness. weighing
2 Measurements
Topographic Measurements -Inspection lot ±1ar 100ml
1000ml
Irregularity Measurements –Straightedge Longitudinal ≤ 0.3cm 2 Measurements
test –(EN13036-7) Transverse < 0.5cm 100ml
Evenness test according to the test method Short wave bond Psw≥6
LPC n046-2 July 2009 or EN 13036-5 Medium wave bond
inspection lot 1000ml Pnw≥6,Long wave bond
Plw≥5
Materials
42
All general requirements of materials (Cement, Coarse aggregate, Fine aggregate and Steel, Gabion
wire) shall conform to the applicable Specifications.
Both coarse and fine aggregates shall be free from the deleterious contamination. Steel shall be used
free from the rust and tested.
Equipment Details
Back hoe excavator for excavation of trench, foundation.
Tripper trucks for transportation of fabricated and fabricated materials.
Concrete mixture with weight batcher having water measuring system shall be used.
Ordinary motorized concrete mixture may be used if the permission given by the Engineer.
Vibrator both needles and plat shall be used for effective compaction of concrete.
Water pump if required in the drain out the ground water.
Crane for lifting and placing of Hume pipe.
Nails, hooks and props as per required for erection of form works.
Personnel Employed for Execution and Supervision
In leadership of Team Leader, Bridge Engineer, Material Engineer shall be deployed from ICO
side for the supervision, identification of defects and issues the necessary site instruction,
similarly the Contractor technical staff shall be deployed to proceed the works, supervision
and defects rectification. The ICO team shall have approved working drawing in hand.
Sampling and Testing
The sampling of all materials as per the ERPS Specification shall be collected and tested in
the laboratory established in the site for this project work and filling system of tested
reports shall be updated accordingly.
Referring documents
Employer’s Requirements Part III-2 Performance Specifications
French and European Standards to be respected.
Equipment Details
Back hoe excavator for excavation of trench, foundation.
43
Tripper trucks for transportation of fabricated and fabricated materials.
Concrete mixture with weight batcher having water measuring system shall be used.
Ordinary motorized concrete mixture may be used if the permission given by the Engineer.
Vibrator both needles and plat shall be used for effective compaction of concrete.
Water pump if required in the drain out the ground water.
Crane for lifting and placing of Hume pipe.
Nails, hooks and props as per required for erection of form works.
44
5.10.2 Road User Service Levels
The Contractor is required to maintain the Contract road in compliance with the Service Levels
defined in the Specifications. The road is divided into the following principle elements:
Carriageway
Shoulders
Drainage
Bridges
Slopes and Right-of-Way
Traffic Safety
For each road element, one or more Performance Indicators are identified. For each
Performance Indicator, one or more Service Levels are specified w h i c h must be complied
w i t h . If a road element develops a defect which brings its condition below t h e Service
L e v e l , then the Contractor h a s to take action t o correct the defect and restore the
Service Level within the time period permitted which forms part of the Service Level.
The tables provided in Annexure 3 define the Services Levels, time permitted for
correction in days and method of measurement. Failure to maintain any specified Service
Level within the time. Permitted is defined as a Non-Compliance f o r which a deduction
will be made from payments t o the Contractor f o r Management a n d Maintenance
S e r v i c e s until the defect is corrected.
5.10.3 Road User Service Levels on the Existing Road before Completion of Improvements
The Cont ract or i s required t o maintain t h e existi ng g r a v e l r o a d i n c l u d i n g t h e r o a d
sections under construction and diversion routes at a reasonable Service Level for road users
until the construction of improvements is completed. The Performance Indicators and Service
Levels follow the same rationale as those specified for the improved road, including deductions
from payments for non-compliance but the number of Performance Indicators is smaller and the
Service Levels are lower as shown in Annexure 5
45
a) Measurement
The Team Leader will measure the road roughness in terms of the International Roughness Index
(IRI). The Contractor will be informed in advance and invited to attend all measurements. The
Contractor shall provide a Class 1 precision Roughness Profilometer according to the specifications
as defined by EN 13036-5, and calibrate/validate and maintain it as per the manufacturer's
requirements. The Evenness shall be calculated, in 50 m intervals in each direction and on average
calculated for each 1 km section of the road.
b) Service Levels
The average roughness over 1 km section of road in both directions based on the roughness of100 m
sections must be less than or equal to the IRI values shown in the table in Annexureure3. The
maximum roughness in any 100 m section must be less than or equal to the IRI values shown in table
in Annexure 5 otherwise the 1 km section is Non-Compliant and subject to a deduction for the
monthly lump payment until it is corrected. Measurements are made following completion of
construction and at the annual anniversary of completion of construction. The Service Level permits
a reasonable increase in roughness over the period of the contract as shown in the table in
Characteristics Specifications Test Rate
Evenness test according to the test method LPC Short wave bond Psw≥6
n046-2 July 2009 or EN 13036-5 inspection lot Medium wave bond Pnw≥6,Long
1000ml wave bond Plw≥5
46
k) Program of performance Non-compliance 20% and withhold 50% from
and initial annual report payments for Improvement Work against non-
l) Agreed additional works submission and non-finalization of “as built drawings”
program h) 365 days before fro start date- reduction for non-
m) Project management compliance 5%
facilities i) 30 days before scheduled completion date –
n) Design quantity reduction for Non-compliance 20%
management plan and j) 90 days after completion date – reduction for Non-
construction quality compliance 20%
management plan k) Initial programme 28 days from start date, annual
o) Contract Quality update three year rolling programme in monthly
Assurance management report corresponding to year end–reduction to Non-
plan including: compliance 10%
Traffic management l) 7 days from Employers notice to proceed – reduction
plan for Non-compliance 5%
Environment and m) Temporary facilities 28 days from start date.
social management Permanent facilities to be handed over in 120 days for
plan start of work (refer item 8 of addendum 1)
Health and safety Establishment of laboratory 120 days from start date
management plan – reduction for Non-compliance 205
Emergency n) With inception and partial design report –reduction
procedures plan for Non-compliance 5%
p) Traffic management o) With inception report – reduction for Non-compliance
plan, health and safety 5%
management plan, and p) Full implementation of the plan – reduction for Non-
emergency procedure compliance 5%
plan q) Full implementation of the plan including restorations
q) Environment and social of barrow areas and quarries – reduction for Non-
management plan compliance 20%
The formal inspections would allow the comparison of the information on compliance provided by
the Contractor in the standard tables which are part of his Monthly Statement, with actual
measurements taken in locations to be determined by the Team Leader.
47
5.11.2 Informal Inspections of Service Levels
The Team Leader may carry out informal inspections of Service Levels as part of his general
mandate given to him by the Employer. He may do so on his own initiative, at anytime and
anywhere o n the roads included in the contract. He must use his own means for those
inspections. If he detects any road sections where the Service Level criteria are not met, he is
obliged to inform the Contractor within 24 hours in writing, in order to enable the Contractor to
take remedial action as soon as possible. The results of informal inspections may not be used by
the Team Leader for purposes of correcting the Contractor's monthly statements or applying
penalties or liquidated damages, except for cases in which the road has been completely
interrupted and the criteria of Road Usability has not been met.
48
5.13.2 Design Work
Contractor will provide the minimum specified pavement Thickness and depending on the sub
grade soil strength contractor will recommend and apply the necessary pavement layers to
adequately address the stated requirements. Contractor will design maintenance works which
provides the required outcome yet provides an advantage to the Employer, the Road User and
the Contractor in terms of enhanced performance (increased lifecycle), construction
timeframes, and/ or Environmental considerations. The Contractors Design will also provide
widening of the Road to Comply with Road types R60 in G a b o n Geometric Design Manual
and the Minimum design criteria's. In case of discrepancy between the various Design Criteria,
each particular case will be discussed and justified and presented to the Team Leader for approval.
The Contractor is solely responsible for completing the detailed Design for the Improvement
Works and Maintenance Works in accordance with the intent of the Contract and the scope of the
Conceptual Designs. This includes, Route selection, Topography Survey, geometrical Investigation,
geometrical Design, Geometric and Pavement Design Resettlement Action Plan, Bridge Design,
Assessments of existing Structures and Design of strengthening Works, Bridge Construction and
Rehabilitation, Culvert Design, retaining wall Design, Permanent Signing, Pavement Marking, Routine
maintenance, as require, period maintenance to comply with the required service life for the
pavement. Design Document and record drawings of as built plans.
6 Acceptance Criteria
6.1 Request for R eview
As mentioned in method statement the contractor, in the approved format, shall submit the
Inspection summary, 24 hours prior to execution of each and every activity or related activity
according to the Contract Document. The ICO will assign the Inspection summary to the
respective activity in charge/section head to attend the same. The section head will get the work
inspected and will forward to TL to close it. The Inspection summary will be pertaining to either.
6.1.1 Material and Construction Works
All material brought to site/ construction works executed at site shall conform to relevant codes/ as
per specifications (This has been brought in various method statements). Material and related
items of works shall be tested at regular frequencies as specified. Materials do not conform to
applicable specifications shall deemed to be rejected and shall be removed from the work site or
as instructed by TL.
6.1.2 Testing
The Tests on executed item of work I workmanship shall be conducted as per quality testing
plan. The testing result shall be duly combined and submitted to TL as per requirement. Only
those test results that are not accepted by TL, contractor shall be resubmitted after carryout
rectification as directed or remove unsuitable item of work from site to spoils and replace with
fresh material for further approval.
6.1.3 Surveyor
Survey works for checking layout, levels and benchmarks will be carried out and the works will
be accepted as per the specifications.
49
6.1.4 Inspection
Inspection of completed works will be carried out to check if the produced is in conformity to the
specification. Inspection may also be required for the intermediate works before
commencement of the succeeding activity.
6.1.5 Measurement
Inspection summary will also be raised by the Contractor for measurement of works of the
completed works or before dismantling of existing structure/property for payments.
The consultant shall verify the corrective action for its effectiveness before closing out. The
Contractor's Team Leader shall ensure that the NCR is closed out within the agreed time frame
for disposal.
50
Defiance in addressing NCR (Preparation of proposed disposition I corrective action) or defiance in
implementation of approved disposition/corrective action within agreed time frame shall lead to
the rejection of non-conformity product.
7 Tests on Completion
7.1 The tests upon completion of the project works are carried out as per the Annexure – D
attached as per Employers requirements Part III.2: Performance Specifications.
(Attached - Annexure – D)
Contractor:
1. Road Manager
2. Deputy Manager
3. Safety Expert
4. Quality Assurance Specialist
51
8.1.3 Non-Compliance
However, the Monitoring Consultant site personnel shall be issued the Non-Compliances whenever
they found the works are in substandard, the Contractor shall be rectified the substandard works
within the stipulated response time with satisfaction of Monitoring Consultant representatives. The
Non-compliance form enclosed in Annexure-3.
The form of Survey Strip Chart as attached in Annexure-4. These are extremely important when layer
number with respect to drawing issued is to be checked and vis-a- vis survey work needs to be done.
8.1.6 Documentation
Any documentation preparing by Consultant and Contractor shall have the specific standard format,
it shall be included Table of Contents, Abstract/ Executive Summary/ Introduction, the font of the
documents shall be either Arial or Times New Roman and normal font size shall be 12, except some
exceptional condition.
Conclusion
This Quality Assurance Manual has been prepared in order to implement the activities as stated in the
Contract provision and delivering the quality of works. It has prepared based on the Contract Clauses,
and Employer’s Requirements Part III-2 Performance Specifications. It has precisely described the
procedure of major works. Simultaneously, some important checklist formats have been developed to
ensure the quality of works, role and responsibility of Consultant key personnel’s and Contractors also
described in brief.
The Project Road construction, on the basis of (EPC), whereas, the Contractor has the entire
responsibility to perform the quality. The Construction Supervision CICO the Contractor’s process of
executing to make sure that what they are doing adequate and accurate as per SAG Standard
Specification.
However, if any ambiguity or unclear for understanding the Contact Clauses and Specification that will
be made interpretation by the Employer, which will be unanimous.
52
Annexure-01
Inspection Test Plan
53
Annexure - 02
Checklists
54
Annexure - 03
Site Instructions
55
Annexure - 04
Non Conformance Report
56
Annexure - 05
Quality Test Formats
57
Annexure - A
Certification of Milestones
58
Annexure - B
As Built Drawings
59
Annexure – C
Basis of Engineering & Execution studies
(VISA Mission)
60
Annexure - D
Tests on Completion
61