Installation of Thermowell & Temperature Elements Check List

This document is a checklist for installing thermowells and temperature elements. It lists 15 check points to ensure the components are properly installed, including verifying approved drawings and specifications, checking for damage, ensuring proper placement and connections, and calibrating temperature elements. Upon completion, the subcontractor, quality engineer, and customer sign off to confirm the installation meets requirements.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
463 views1 page

Installation of Thermowell & Temperature Elements Check List

This document is a checklist for installing thermowells and temperature elements. It lists 15 check points to ensure the components are properly installed, including verifying approved drawings and specifications, checking for damage, ensuring proper placement and connections, and calibrating temperature elements. Upon completion, the subcontractor, quality engineer, and customer sign off to confirm the installation meets requirements.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSTALLATION OF THERMOWELL & Report No:

TEMPERATURE ELEMENTS
CHECK LIST Date:

Customer : Project: Project Code:


Sub- Contractor : WO No & Amndt, If any.:
Manufacturer : PO No & Amndt, If any.:
Item Description: Identification No.
Location : Sub Location:
Package: Drg No & Rev No :
FQP No. & Rev No. RFIC No.

Total Inspected & Total Inspected &


Total offered Quantity:
Accepted Quantity: Rejected Quantity:

Checked
Sl No Description of Check Points Remarks
Yes No NA

1 Approved Location drawing is available Drg No :

2 Approved P & ID is available Drg No :

3 Approved Data Sheet is available Doc No :

Make & type of Thermowell (TW) & Temperature Elements are approved by
4
client

5 Sub Contractor is pre qualified and approved

6 Method Statement is approved by client

7 Ensure valid calibartion of Temperarture Element

8 Ensure the Location and tapping point is verified as per approved P&ID

Ensure the Thermowell / Temperature Element is free from damages /


9
defect

Ensure Supplied Thermowell / Temperature Element specifications match


10
with approved Data Sheet

11 Ensure Tag plate is correct as per approved Drawings

Ensure the opening of the pipe is free from burrs and thermowell is inserted
12
freely.

13 Ensure the tightness of Thermowell flange with process line flange

14 Ensure the tightness of Temperature Element with Thermowell

Ensure the display orientation of Temperature Element is visible to operator


15
(applicable for TG only)

Note : This format can also be used for TEMPERATURE GAUGE (TG) / THERMOCOUPLE (TC) / RESISTANCE TEMPERATURE DETECTORS (RTD)

Remarks:

Signature of Sub - Contractor & Date Signature of TPL-FQE & Date Signature of Customer / Inspection Authority & Date
Format No. 08-03-05-FMT-I-FMI-CL-002-R00

Sh:1of1