0% found this document useful (0 votes)
99 views

Item Description Unit QTY Retaining Wall For Block A 1.excavation & Earth Works Spec REF Unit Price Total Price

The document provides a bill of quantities for excavation, concrete, and masonry works for three retaining wall blocks (A, B, and C). For Block A, the estimated costs are $12,006 for excavation and earth works, $1,963 for concrete works, and $50,276 for masonry works, totaling $64,245. For Block B, the costs are $16,651 for excavation, $1,963 for concrete, and $62,351 for masonry, totaling $80,965. Excavation costs for Block C are provided for one item.

Uploaded by

temesgen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
99 views

Item Description Unit QTY Retaining Wall For Block A 1.excavation & Earth Works Spec REF Unit Price Total Price

The document provides a bill of quantities for excavation, concrete, and masonry works for three retaining wall blocks (A, B, and C). For Block A, the estimated costs are $12,006 for excavation and earth works, $1,963 for concrete works, and $50,276 for masonry works, totaling $64,245. For Block B, the costs are $16,651 for excavation, $1,963 for concrete, and $62,351 for masonry, totaling $80,965. Excavation costs for Block C are provided for one item.

Uploaded by

temesgen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

SPEC UNIT TOTAL

ITEM DESCRIPTION UNIT QTY


REF PRICE PRICE

RETAINING WALL FOR BLOCK A

1.EXCAVATION & EARTH WORKS


1.1
Excavate in ordinary soil for trench foundation to a depth not exceeding
300cm from reduced level. m3 67.83 -
1.2
Fill around stone masonry to maintain the desired level with selected
borrowed non expansive material and compact in layers not exceeding
20cm. m3 14.17 -
1.3
Cart away surplus excavated material to a distance not exceeding 5kms. m3 53.66 -

TOTAL CARRIED TO SUMMARY ...... 0.00

2.CONCRETE WORKS
Concrete :

The specified concrete strength must be confirmed by laboratory test.


2.1
5cm thick lean concrete in C-5 with minimum cement content of
150kg/m3 of concrete under:
a) stone masonry m2 35.70 -

3. MASONRY WORKS
3.1
50cm thick stone masonry foundation below ground level bedded in
cement mortar (1:3) in full joints. m3 39.72 -
3.2 Ditto but above ground level. m3 3.80 -
TOTAL CARRIED TO SUMMARY ...... 0.00

1
SPEC UNIT TOTAL
ITEM DESCRIPTION UNIT QTY
REF PRICE PRICE

RETAINING WALL FOR BLOCK A

1.EXCAVATION & EARTH WORKS


1.1
Excavate in ordinary soil for trench foundation to a depth not exceeding
300cm from reduced level. m3 67.83 75.00 5,087.25
1.2
Fill around stone masonry to maintain the desired level with selected
borrowed non expansive material and compact in layers not exceeding
20cm. m3 14.17 280.00 3,967.60
1.3
Cart away surplus excavated material to a distance not exceeding 5kms. m3 53.66 55.00 2,951.30

TOTAL CARRIED TO SUMMARY ...... 12,006.15

2.CONCRETE WORKS
Concrete :

The specified concrete strength must be confirmed by laboratory test.


2.1
5cm thick lean concrete in C-5 with minimum cement content of
150kg/m3 of concrete under:
a) stone masonry m2 35.70 55.00 1,963.50

3. MASONRY WORKS
3.1
50cm thick stone masonry foundation below ground level bedded in
cement mortar (1:3) in full joints. m3 39.72 1150.00 45,678.00
3.2 Ditto but above ground level. m3 3.80 1210.00 4,598.00
3.3 pointing m 2
50.35
TOTAL CARRIED TO SUMMARY ...... 50,276.00

1
SPEC UNIT TOTAL
ITEM DESCRIPTION UNIT QTY
REF PRICE PRICE

RETAINING WALL FOR BLOCK B

1.EXCAVATION & EARTH WORKS


1.1
Excavate in ordinary soil for trench foundation to a depth not exceeding
300cm from reduced level. m3 89.25 -
1.2
Fill around stone masonry to maintain the desired level with selected
borrowed non expansive material and compact in layers not exceeding
20cm. m3 22.44 -
1.3
Cart away surplus excavated material to a distance not exceeding 5kms. m3 66.81 -

TOTAL CARRIED TO SUMMARY ...... 0.00

2.CONCRETE WORKS
Concrete :

The specified concrete strength must be confirmed by laboratory test.


2.1
5cm thick lean concrete in C-5 with minimum cement content of
150kg/m3 of concrete under:
a) stone masonry m2 35.70 -

3. MASONRY WORKS
3.1
50cm thick stone masonry foundation below ground level bedded in
cement mortar (1:3) in full joints. m3 51.02 -
3.2 Ditto but above ground level. m3 3.04 -
TOTAL CARRIED TO SUMMARY ...... 0.00

2
SPEC UNIT TOTAL
ITEM DESCRIPTION UNIT QTY
REF PRICE PRICE

RETAINING WALL FOR BLOCK B

1.EXCAVATION & EARTH WORKS


1.1
Excavate in ordinary soil for trench foundation to a depth not exceeding
300cm from reduced level. m3 89.25 75.00 6,693.75
1.2
Fill around stone masonry to maintain the desired level with selected
borrowed non expansive material and compact in layers not exceeding
20cm. m3 22.44 280.00 6,283.20
1.3
Cart away surplus excavated material to a distance not exceeding 5kms. m3 66.81 55.00 3,674.55

TOTAL CARRIED TO SUMMARY ...... 16,651.50

2.CONCRETE WORKS
Concrete :

The specified concrete strength must be confirmed by laboratory test.


2.1
5cm thick lean concrete in C-5 with minimum cement content of
150kg/m3 of concrete under:
a) stone masonry m2 35.70 55.00 1,963.50

3. MASONRY WORKS
3.1
50cm thick stone masonry foundation below ground level bedded in
cement mortar (1:3) in full joints. m3 51.02 1150.00 58,673.00
3.2 Ditto but above ground level. m3 3.04 1210.00 3,678.40
3.3 pointing m 2
50.35
TOTAL CARRIED TO SUMMARY ...... 62,351.40

2
SPEC UNIT TOTAL
ITEM DESCRIPTION UNIT QTY
REF PRICE PRICE

RETAINING WALL FOR BLOCK C

1.EXCAVATION & EARTH WORKS


1.1
Excavate in ordinary soil for trench foundation to a depth not exceeding 300cm
from reduced level. m3 89.25 75.00 6,693.75
1.2

Fill around stone masonry to maintain the desired level with selected borrowed
non expansive material and compact in layers not exceeding 20cm. m3 22.44 280.00 6,283.20
1.3
Cart away surplus excavated material to a distance not exceeding 5kms. m3 66.81 55.00 3,674.55

TOTAL CARRIED TO SUMMARY ...... 16,651.50

2.CONCRETE WORKS
Concrete :

The specified concrete strength must be confirmed by laboratory test.


2.1
5cm thick lean concrete in C-5 with minimum cement content of 150kg/m3 of
concrete under:
a) stone masonry m2 35.70 55.00 1,963.50

3. MASONRY WORKS
3.1
50cm thick stone masonry foundation below ground level bedded in cement
mortar (1:3) in full joints. m3 51.02 1150.00 58,673.00
3.2 Ditto but above ground level. m3 3.04 1210.00 3,678.40
TOTAL CARRIED TO SUMMARY ...... 62,351.40