Method Statement For Installation of Grills Diffusers Disc Valves and Louvers

This document provides a method statement for installing grilles, diffusers, louvers, and disc valves as part of a project. It outlines the purpose, scope, references, definitions, responsibilities, and equipment needed. The method statement covers supply and installation of these HVAC components in accordance with approved shop drawings, specifications, and manufacturer instructions. It assigns responsibilities to various project roles and describes safety and quality control procedures to be followed.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
528 views

Method Statement For Installation of Grills Diffusers Disc Valves and Louvers

This document provides a method statement for installing grilles, diffusers, louvers, and disc valves as part of a project. It outlines the purpose, scope, references, definitions, responsibilities, and equipment needed. The method statement covers supply and installation of these HVAC components in accordance with approved shop drawings, specifications, and manufacturer instructions. It assigns responsibilities to various project roles and describes safety and quality control procedures to be followed.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

PROJECT NAME

TITLE Ref. No. :


METHOD STATEMENT FOR REV. No. 0
INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES Date :
Page 1 of 11

PROJECT NAME

METHOD STATEMENT FOR

INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES


PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES Date :
Page 2 of 11

REVISION RECORD

This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.

Rev. No. Date By Chkd. Approvals Description and Page Numbers of Revisions

CONTENTS

1.0 PURPOSE

2.0 SCOPE

3.0 REFERENCES

4.0 DEFINITIONS

5.0 RESPONSIBILITIES

6.0 EQUIPMENTS

7.0 PROCEDURE
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES Date :
Page 3 of 11

8.0 ATTACHMENTS

1.0 PURPOSE

 This method statement is applicable for the Installation of Grilles, Diffusers, and Louvers & Disc
Valves for the project as mentioned in the Specifications & Approved Shop Drawings.

2.0 SCOPE

 This method Statement shall cover the Supply & Installation of Grilles, Diffusers Louvers &
Disc Valves in line with project requirements as indicated in the Approved Shop Drawings,
specifications & manufacturer’s instructions.

3.0 REFERENCE

3.1 Latest Approved shop drawings intended for HVAC.


3.2 Specifications
3.3 Project Quality Plan
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES Date :
Page 4 of 11

3.4 Project HSE Plan


3.5 Material Approval Request

4.0 DEFINITIONS

PQP : Project Quality Plan


PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Work Inspection Request
MIR : Material Inspection Request
ASHRAE : American Society of Heating, Refrigerating and Air-conditioning Engineers
SMACNA : Sheet Metal and Air-conditioning Contractor’s National Association

5.0 RESPONSIBILITIES:

 Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
 Project Manager
 Construction manager
 QA/QC Engineer
 Site Engineer
 HSE officer
 SK

5.1 Project Manager

 The work progress shall be carried out as per planned program and all the equipment’s required
to execute the works shall be available and in good condition as per project planned.
 Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.

5.2 Construction Manager

 Construction Manager is responsible to supervise and control the work on site.


 Coordinating with QA/QC Engineers, Site Team & Foremen for all activities on site.
 Control and sign all WIRs before issuing to Consultant approval.

5.3 Site Engineer

 The method of statement to the system shall be implemented according to the Consultant project
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES Date :
Page 5 of 11

specifications and approved shop drawings.


 Provision of all necessary information and distribution of responsibilities to his Construction
team.
 The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
 The constant coordination with the Safety Engineer to ensure that the works are carried out in
safe working atmosphere.
 The constant coordination with the QA/QC Engineer for any works to be carried out and initiate
for the Inspection for the finished works.
 He will ensure the implementation of any request that might be raised by the Consultant.
 Efficient daily progress shall be obtained for all the equipment and manpower.
 He will engage in the work and check the same against the daily report received from the
Foremen.
 The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.

5.4 QA/QC Engineer (MEP):


 The monitoring of executions of works at site and should be as per the approved shop drawings
and project specifications.
 Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
 He will follow and carries out all the relevant tests as per project specifications.
 Obtain the required clearance prior to Consultant’s inspections.
 Should acquire any necessary civil works clearances and coordination.
 QA/QC Engineer will assist the Consultant Engineer/ Inspector during Inspection.
 Check & ensure work is completed prior to offer consultant for inspection.
 Coordination with site construction team.
 He will assist the Consultant Engineer/ Inspector during the inspection.
 Ensure all works have been completed prior to raise inspection to the consultant.

5.5 Site Foreman


 The carrying-out of work and the proper distribution of all the available resources in
coordination with the Site Engineer on a daily basis.
 Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
 Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
 Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.

5.6 Safety Officer

 The implementation of all safety measures in accordance with the HSE plan and that the whole
work force is aware of its proper implementation.
 The implementation of safety measures is adequate to maintain a safe working environment on
the work activity.
 Inspection of all the site activities and training personnel in accident prevention and its proper
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES Date :
Page 6 of 11

reporting to the Construction Manager and the Project Manager.


 The site is maintained in a clean and tidy manner.
 Ensure only trained persons shall operate the power tools.
 Ensure all concerned personals shall use PPE and all other items as required.
 Ensure adequate lighting is provided in the working area at night time.
 Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
ladders.
 Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
 Ensure safe access to site work at all times.

5.7 Store Keeper (SK)

 Responsible for overall Store operations in making sure to store the material delivery to the site and
keep it in suitable area that will keep the material in safe from rusty and damage.
 One who will acknowledge the receiving of materials at site in coordination with QA/QC &
concerned Engineer.

6.0 EQUIPMENTS

Following tools shall be arranged before starting the job.


a. Tool Box.
b. Measuring Tape.
c. Hack Saw Blade
d. Spirit Level
e. Electric Drill Machine
f. Step Ladders
g. Threading Machine
h. Solvent Cement
i. Torque Wrench
j. Pipe Cutting Machine
k. Grinding Machine
l. Pressure Gauge
m. Hammer
n. Water Level Marker
o. Mobile Scaffolds
p. Staging Platforms
7.0 PROCEDURE

 Work Sequence/Procedure

7.1 General Requirements


 All the materials received at site shall be as per the approved technical material submittal
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES Date :
Page 7 of 11

for Grilles, Diffusers, Louvers & Disc Valves to be inspected upon receipt & approved by the
engineer prior in proceeding with the installation through MIR. Any discrepancies,
damages etc., should be reported to the supplier for rectification or replacement & to be
removed from site immediately.
 All construction/inspection/testing works shall be carried out in accordance with the
specifications & to be done by qualified Mechanical Engineers and shall be checked and
approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
 Contractor has to clarify the procedure for material delivery to the site through consultant
Engineer at site.

7.2 Material Transport/ Delivery

 Grilles, Diffusers, Louvers & Disc Valves are normally shipped & despatch for goods
condition and carefully loaded in containers with crating / boxing/ wrapped with plastics.
Hence, in case of transit damage, supplier must be informed immediately.
 Special care must be taken to ensure that units are offloaded from containers. Rough
handling can result in damage to the materials.
 Use appropriate type of vehicles in transporting the units and that they are protected
against mechanical & weather damage.
 All the received units shall be checked & inspected to ensure that it is complying with the
approved material submittals prior to site storage.

7.3 Storage on Site Store

 To ensure that deterioration of the Grilles, Diffusers, Louvers & Disc Valves does not occur
during storage, it is recommended to store the equipment in sheltered conditions that are
protected from weather elements and accidental damage.
 Grilles, Diffusers, Louvers & Disc Valves shall be protected with plastic/ tarpaulin or shall not
be removed from the shipping package unless otherwise instructed to do so.
 Avoid any mechanical shocks and strokes during handling operations.
 All packages for the equipment reaching the site shall be identified as per package list.

7.4 Sequence of Installation for the Grilles, Diffusers, Louvers & Disc Valves
7.4.1 Safety
 All site safety rules & regulations shall be complied with.
 Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in
the installation and shall be recorded.
 All operatives will be equipped with minimum personnel protective equipment; hard hat,
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES Date :
Page 8 of 11

coveralls, safety boots, safety glasses.


 The persons using cleaning fluid and solvent cement have to wear hand gloves.
 Ensure only qualified personnel shall install, test & commissioned the system.
 During Installation display warning sign boards to be provided and barricade the area whenever
necessary.
 Only competent, experienced & trained personnel shall perform all the required activities stated
in this method statement.
 Ensure that all operatives fully understand the method of these activities.
7.4.2 Pre- Installation Procedure
 Before commencement of installation activity, the supervisor must ensure that:
 Delivered Grilles, Diffusers, Louvers & Disc Valves have been inspected & approved via
MIR by the consultant prior to installation at site.
 All Grilles, Diffusers, Louvers & Disc Valves shall be checked against the relevant
schedules prior to installation & ensuring that they are of the correct size, type, model etc.
as indicated on the approved shop drawings & material submittal.
 All Installations & Pressure Testing of Pipe/ Duct works have been completed & approved
by the consultant.
 Ensure that the area shall be relatively clean, free of major airborne dust and contaminants
(moisture, oil, etc.)
 Relevant documents or certificates shall be presented at the time of inspection if required
by the Consultant. (Coordination Drawings, Reflected Ceiling Plan, etc.)
 Permission to start or Civil Clearances prior to installation has been given by the main
contractor.
 All relevant Shop drawings for the installation of the equipment shall be available &
approved by the consultant. No installation shall be done without Approved Shop
Drawings.
 Installation activities shall only commence when all associated works by the Civil has been
completed.
 Safe access shall be provided by the Main Contractor thru Work Permit in coordination
with the Safety in charge at site.
 Check the exact location of installation for the Grilles, Diffusers, and Louvers & Disc
Valves as per the approved shop drawings.
 Check for other services, making sure that there is no interference between each service &
adequate access to work and for future maintenance can be maintained.

7.4.3 General Installation Procedure for Grilles, Diffusers, Louvers & Disc Valves
 Ensure plenum or terminal boxes openings are compatible for Grilles, Diffusers, and
Louvers & Disc Valves to be installed.
 Ensure that plenums are correctly acoustically lined.
 Install sub-frame in the duct opening as manufacturer’s recommendation and ensure that
Grilles, Diffusers, Louvers & Disc Valves shall be installed correctly as per the direction of
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION OF GRILLES, DIFFUSERS, LOUVERS & DISC VALVES Date :
Page 9 of 11

flow.
 Prepare Grilles, Diffusers, Louvers & Disc Valves by installing sealing material to the
internal side of the mating flange, carefully locate Grilles, Diffusers, Louvers & Disc
Valves’ into sub-frame and locate locking screws and tighten until correct level and the
alignment is attached.
 Make sure that screws should be fixed into a metal/ wooden frame which sits in counter
sunked holes through border.
 If the aperture is in masonry, the hole locations should be marked, then drilled and plugged
to give more positive fixing.
 Concealed rear bracket fixing is for use when a hidden fixing is required but the installation
prohibits the use of clip fixing.
 For fixing of Grilles, Diffusers, Louvers & Disc Valves without dampers, the Grilles,
perforated, 4 way Diffusers, and Louvers & Disc Valves are positioned into opening with
metal/ wooden frame screws are fixed through the brackets fixed into the stack of Grilles,
Diffusers, Louvers & Disc Valves to the frame holes.
 For Grilles, Diffusers, Louvers & Disc Valves with dampers, the dampers can be fixed with
Grilles, Diffusers, Louvers & Disc Valves border by clip or rivets and damper is fixed by
screwing to the duct opening. Otherwise the damper alone can be directly screwed to the
duct chute.
 After final alignment, carefully tighten the Grilles, Diffusers, Louvers & Disc Valves’ until
airtightness is achieved.
 Ensure that all Grilles, Diffusers, Louvers & Disc Valves are left in closed position and
protection shall be provided until handing over.
 Ensure that each installation of Grilles, Diffusers, Louvers & Disc Valves is undamaged,
clean and screwed tight prior to inspection.
 After all installation has been done, raise immediate inspection for approval.

8.1. ATTACHMENTS

8.2. Inspection & Test Plan


8.3. Installation Check Sheet
8.4. Risk Assessment