Execution Monitoring Control
Execution Monitoring Control
Monitoring, and
Control
Goals of the Unit
• Plans have little value if not executed and, during
execution, monitored and updated to reflect the current
situation
• This unit introduces:
– The activities to put a plan into practice
– The techniques for monitoring and controlling your plans
(progress and costs against schedule and budget)
– Earned Value Analysis, a technique which allows the project
manager to monitor a project in an integrated way
Schedule
Define Kick Off
Schedule Activities
Define Costs
[Obtain
Approval]
Quality Management
Risk Management
• Goal:
– Systematic collection of data to assess the project status
• It can be performed on a regular basis (in which case the
frequency has to be chosen according tot he project size)
• It can be performed on a need basis (for exceptional
events, e.g., risks)
• Quantitative data can be collected based on the
monitoring means
• Qualitative data (e.g., team morale, “feeling” about the
status or difficulty of a given task) must also be collected
deviations &
Plan
P1 compare replan P2
assessment
(baseline) (new baseline)
A1
(actual plan)
describes captured by
Actual World
work
Approaches
• Focus:
– Here we focus on schedule, costs, and progress
• Non-integrated approach:
– Monitor schedule: understand whether we are late or early
– Monitor costs: understand whether we over or under budget
– Simple, but partial views
• Integrated approach:
– Earned Value Analysis: measure schedule, costs, and progress
together
– More complex, but a more comprehensive view
• Actual Values
– Actual status of the schedule
– Actual start, actual end, actual effort/actual progress
4. Re-plan:
1. Estimate effort and duration to end
2. Technique 1: efficiency with which actual effort has been expressed
w.r.t. planned effort
3. Technique 2: efficiency with which technical progress is expressed w.r.t.
planned progress
4. Share the new plan, and GOTO 2
• Disadvantages:
– Not sufficient to have an idea on the overall status of the
project (will we make it with the remaining money?)
• Definitions:
– Planned Value: the cumulative costs planned for the project.
Also called: Budgeted Costs of Work Scheduled
– Actual Costs: the cumulative costs actually incurred into.
Also called: Actual Costs of Work Performed
– Earned Value: the actual progress, expressed as the quantity
of planned value which has generated results
A 1000 A
B 2000 B
C 400 C
4000 3400
3100 3200 3300
3000
2000
2000
1000 500
0
M1 M2 M3 M4 M5 M6
• Rule 2.
– 50/50 Rule (50% of Planned Value at start and 50% at end)
– 20/80 Rule (20% at start and 80% at end)
– 0/100 Rule (0% at start and 100% at end)
PV
(Planned Value)
Cost
Variance
Schedule
Variance
EV
(Earned Value)
Time
ACt
• CPI (Cost Performance Index) compares work
performed to actual costs
• How much are we getting for each euro we
spend?
SPI
1
exactly like scheduled
and budgeted
late and late, but
late
CPI
over budget under budget
1
• Remarks:
– Lower part = baseline; upper part: actual & progress
• Questions:
– Are we late?
– Are we over budget?
Clean 400
Budgeted Cost of Work 800 1600 2400 4000 4800 5600 6800 7200 7600
Scheduled (BCWS)
€ 8,000
€ 6,000
BCWS € 4,000
€ 2,000
€0
w1 w3 w5 w7 Untitled 1
Refurnish 400
Clean
€ 8,000
€ 6,000
BCWS € 4,000
BCWP
€ 2,000
€0
w1 w3 w5 w7 Untitled 1
Refurnish 400
Clean
€ 8,000
€ 6,000
BCWS € 4,000
BCWP
ACWP € 2,000
€0
w1 w2 w3 w4 w5 w6 w7 w8
Refurnish
Clean
Budgeted Cost of Work Scheduled (BCWS) €800 €1,600 €2,400 €4,000 €4,800
Budgeted Cost of Work Performed (BCWP) €1,600 €1,600 €1,600 €3,200 €5,200
Actual Cost of Work Performed (ACWS) €900 €1,800 €2,700 €3,600 €6,000