Open navigation menu
Close suggestions
Search
Search
en
Change Language
Upload
Sign in
Sign in
Download free for days
100%
(1)
100% found this document useful (1 vote)
4K views
Chipping Methodology
chipping methodology
Uploaded by
WeeBooh Wit-a
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Download now
Download
Save Chipping Methodology For Later
Download
Save
Save Chipping Methodology For Later
100%
100% found this document useful, undefined
0%
, undefined
Embed
Share
Print
Report
100%
(1)
100% found this document useful (1 vote)
4K views
Chipping Methodology
chipping methodology
Uploaded by
WeeBooh Wit-a
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Download now
Download
Save Chipping Methodology For Later
Carousel Previous
Carousel Next
Save
Save Chipping Methodology For Later
100%
100% found this document useful, undefined
0%
, undefined
Embed
Share
Print
Report
Download now
Download
You are on page 1
/ 6
Search
Fullscreen
ABDEL 740 Suite, 7" Floor Trinity Plaza Tower Aone Sure CORPORATION Email Address:
[email protected]
ph METHODOLOGY FOR “CHIPPING OF CONCRETE SLAB FLOOR OPENINGS FOR KEAD RISER” 4. PURPOSE The purpose of this Method Statement is to outline the sequences and the methods of worked intended to be used for the chipping of the concrete slab floor openings for the riser ducts. 2. SCOPE OF WORKS The scope of works comprises: - Chipping of the concrete slab floor openings for the riser duets. - Installation and dismantling of debris collecting scaffolds under the bays. 3. REFERENCES a. Key Plan Drawings b. Project Specification . Quality Assurance Manual. d. Health, Safety and Environmental Manual. 4, DEFINITIONS a. PIC Project in Charge b. Engineers Project Engineer, Site Engineer and QA/QC Engineer. AFC Approved Drawings issued from the client for Construction. d. RED MARKED Red-marked Drawings/Rediined drawings are the official contract drawings that have changes / mark up during construction to show as-built e. SEQ Site Engineering Query£81 Site Instruction 9. Contractor A contractor is responsible for the day-to-day oversight of the construction site and management of vendors and trade. h, Sub-Contractor A subcontractor is an individual or in many cases a business that signs a contract, to perform part or all the obligations of another contract. i PTW Permit to work. 5. RESPONSIBILITIES a. Project Manager ‘* Overall in-charge of the project and reports to the General Manager. b. Site Manager ‘+ Leads all construction activities and enforces strict adherence to all project requirements. Report to the Project Manager. c. Engineers ‘+ Ensure that alll related works are carried out in accordance with the approved drawings, specifications, schedule, quality and safely. Report to Site Manager. d. QC Engineer © Ensure that alll related works are carried out in accordance with approved drawings, specifications, schedule, quality and safety. © Conduct inspection on all site work installation / testing including Factory requirements / concern on site. Function administratively under Site Manager but report directly to QA / QC Department Head e. Technicians ‘+ Ensure that all testing required as specified in project specifications and contractual obligations are properly executed in compliance with quality, safety and standard requirements. Report to Engineers6. PROCEDURE 6.1 Preparations. 1. Check false floor openings, GIS building and existing GIS control panel to ensure safety, workability and environmental requirement. 2. Review GIS drawings and project specifications. 3. Installation of wooden catwalks over the cable located between the access door and the work area. 4. Deliver of scaffolding to site and off-loading. 5. Installation of scaffolding in GIS building basement. 6. Protect existing panels from dust by installing a make shift nylon cover enclosure to cover the false opening during the chipping process. 6.4 Installation Activities * Obtain work permit ‘= Identify the work to be done * Brief the personnel engaged in the acti * Secure the area with Caution tape «Ensure that the safety engineer's approval of the cordoned ’s prior to start 1. Installation of scaffoldings. a. Obtain Permit to Work b, Before the work commences, worked area will by the authority to ensure that safe conditions and environment exist for the work. Have a tool box meeting to review all method statements and safely measures with the working team. ©. All scaffolding installation shalll check per standards d. The area will be cordoned off to exclude unauthorized entry. @. Only teams suited to work in this environment will be allowed to undertake this task. f. All access will be via ladder which must be securely tied. At no time personnel climb the outside of the scaffold structure. 4g. All materials will be stored at the work place in an orderly and safe manner. h. Only tools especially designed for the purposed of installing and dismantling of scaffolds will be used, regular check will be made. i. Only quality materials will be used, any materials found to be damage or in poor condition must be placed aside for collection and removal. j. Where the scaffold cannot be completes in one operation, immediately after commencement of the installation, a priority inspection tag will be place at each point access displaying the words "DO NOT USE SCAFFOLD" k. On completion any surplus materials must be stacked in an orderly and safe manner to be collected immediately. |. Install nylon containments on the scaffold to collect debris and dust emission arising from the cutting operation above. (Dust must be contained).2. Chipping of Concrete Slab Floor Openings. Obtain work permit. Ensure the instruction in the PTW are correct. Have a tool box meeting to review all method statements and safely measures with the working team. Prepare all materials needed for the works. Only competent personnel are allowed to perform the works. Before the work commences, worked area will by the authority to ensure that safe conditions and environment exist for the works. {. Mark the position of the designated work area. 4g. Ensure that the marked designated area is approved by the authority h, Start the work to manually chip the false floor opening by using electric portable drill machine. i. Collect the debris and dust in appropriate nylon containments in the basement on the scaffolding. j. Ensure complete opening is restored and debris removed. vo pao 3. Tools And Equipment 1, Pick-ups 2. Hand Tools / Electric Tools 3, Ladder, Scaffolis 4, Safety Risk Assessment The contractor will be responsible for all necessary safety measure at all Times. All works related will be executed in accordance with the Client and ABDEL CONSTRUCTION CORPORATION Health Safety and Safety Plan, The work will only proceed when Permit To Work (PTW) has been issued, The PTW will be kept on display on site during the works. Special Attention will be given to: + Cordoning off specified working area and provision of applicable Safety waming sign boards. (Warning of Hole Hazard") 6 « All important task activities and potential hazards including existing controls have been properly mentioned on the Risk Assessment prepared (attached) 5. Attachment ‘Key plan to show location of work to take place.2 9 away ott met)
You might also like
Waterproofing Inspection Report
PDF
100% (2)
Waterproofing Inspection Report
1 page
TECHNICAL DATA SHEET of RUST CONVERTER
PDF
0% (1)
TECHNICAL DATA SHEET of RUST CONVERTER
1 page
TDS - PPro Concrete Epoxy LV - 051520 PDF
PDF
75% (8)
TDS - PPro Concrete Epoxy LV - 051520 PDF
3 pages
Method Statement For Demolition of Concrete and Asphalt Paving
PDF
80% (5)
Method Statement For Demolition of Concrete and Asphalt Paving
3 pages
Method Statement For I Beam Installation
PDF
100% (1)
Method Statement For I Beam Installation
5 pages
PPR Pipe Installation Method
PDF
81% (16)
PPR Pipe Installation Method
2 pages
Method Statement Fire Protection Installation
PDF
No ratings yet
Method Statement Fire Protection Installation
45 pages
97 Glass Removal and Replacement-JOB PROCEDURE
PDF
100% (1)
97 Glass Removal and Replacement-JOB PROCEDURE
2 pages
Title: Soil Poisoning: Work Method Statement
PDF
No ratings yet
Title: Soil Poisoning: Work Method Statement
10 pages
Afronatay - CHB Laying & Plastering
PDF
100% (2)
Afronatay - CHB Laying & Plastering
34 pages
Jha For Chipping and Drilling Concrete Step Step Discription Hazards Hazard Control
PDF
No ratings yet
Jha For Chipping and Drilling Concrete Step Step Discription Hazards Hazard Control
7 pages
Concrete Epoxy HV PDF
PDF
50% (2)
Concrete Epoxy HV PDF
2 pages
Method Statement For Detailed Suspended Ceiling Cebu
PDF
100% (1)
Method Statement For Detailed Suspended Ceiling Cebu
8 pages
Scaffold Methodology
PDF
50% (2)
Scaffold Methodology
3 pages
JHA - Installation of Pipe & Support For Fire Protection 1
PDF
100% (2)
JHA - Installation of Pipe & Support For Fire Protection 1
7 pages
Glass Works Methodology
PDF
83% (6)
Glass Works Methodology
3 pages
Risk Assessment Carbon Steel Pipes Installation (Grooved & Threaded)
PDF
No ratings yet
Risk Assessment Carbon Steel Pipes Installation (Grooved & Threaded)
6 pages
Method Statement FOR Testing and Commissioning: Plumbing, Sanitary and Drainage System
PDF
No ratings yet
Method Statement FOR Testing and Commissioning: Plumbing, Sanitary and Drainage System
10 pages
Methodology of CHB
PDF
100% (1)
Methodology of CHB
15 pages
Jsa For Gypsum Fixing & Dismentling
PDF
No ratings yet
Jsa For Gypsum Fixing & Dismentling
5 pages
JSA - Changing Light Bulbs
PDF
100% (4)
JSA - Changing Light Bulbs
1 page
Description Technical Data: BOYSEN® Quick Drying Enamel
PDF
100% (2)
Description Technical Data: BOYSEN® Quick Drying Enamel
2 pages
Construction Method Statement For Installation of Chilled Water Piping System
PDF
100% (2)
Construction Method Statement For Installation of Chilled Water Piping System
5 pages
JHA For Tiling Work
PDF
86% (7)
JHA For Tiling Work
1 page
Control System Integration Project: CONTRACT NO.: EDC 13-228/GC113-036
PDF
100% (3)
Control System Integration Project: CONTRACT NO.: EDC 13-228/GC113-036
7 pages
Job Safety Analysis (Jsa) - Water Proofing Work
PDF
No ratings yet
Job Safety Analysis (Jsa) - Water Proofing Work
6 pages
METHOD STATEMENT For Kitchen
PDF
No ratings yet
METHOD STATEMENT For Kitchen
35 pages
Work Methodology FOR Chipping and Restoration Works For Electrical
PDF
100% (1)
Work Methodology FOR Chipping and Restoration Works For Electrical
5 pages
PMCM Form-024 Inspection Request Waterproofing Works
PDF
No ratings yet
PMCM Form-024 Inspection Request Waterproofing Works
1 page
Method Statement For Demolition of Brick Concrete Walls at c01 For Door Window Opening PDF
PDF
No ratings yet
Method Statement For Demolition of Brick Concrete Walls at c01 For Door Window Opening PDF
2 pages
METHODOLOGY EE-Panelboard and ECB Installation
PDF
No ratings yet
METHODOLOGY EE-Panelboard and ECB Installation
4 pages
Method of Statement For Waterproofing
PDF
50% (2)
Method of Statement For Waterproofing
2 pages
Sample JHA
PDF
100% (3)
Sample JHA
1 page
Jha Cistern Tank
PDF
No ratings yet
Jha Cistern Tank
6 pages
Working Procedures For Roughing Ins
PDF
No ratings yet
Working Procedures For Roughing Ins
1 page
Doron EP Bond
PDF
100% (1)
Doron EP Bond
2 pages
METHOD STATEMENT For Roll-Up Doors Installation
PDF
100% (2)
METHOD STATEMENT For Roll-Up Doors Installation
16 pages
Methodology Tapping Methodology of Waterline
PDF
100% (1)
Methodology Tapping Methodology of Waterline
20 pages
1116-01 Method Statement For Gas Works
PDF
100% (3)
1116-01 Method Statement For Gas Works
3 pages
Steel Asia Rebar Shape Codes
PDF
100% (3)
Steel Asia Rebar Shape Codes
2 pages
Checklist For Dismantling & Preservation of Existing MEP Works-Final
PDF
100% (2)
Checklist For Dismantling & Preservation of Existing MEP Works-Final
2 pages
JSA - Trench Works - Road Cutting
PDF
100% (3)
JSA - Trench Works - Road Cutting
1 page
Technical Data Sheet: Davies Powerfloor Epoxy Floor Coating
PDF
100% (1)
Technical Data Sheet: Davies Powerfloor Epoxy Floor Coating
1 page
Method Statement of Using Tie Rod For Formwork Rev.01
PDF
86% (7)
Method Statement of Using Tie Rod For Formwork Rev.01
2 pages
Chipping Works Methdology
PDF
No ratings yet
Chipping Works Methdology
6 pages
JHA For Painting Work
PDF
100% (2)
JHA For Painting Work
2 pages
Painting Work MOS FCHS
PDF
No ratings yet
Painting Work MOS FCHS
4 pages
Method Statement For CHB Laying
PDF
No ratings yet
Method Statement For CHB Laying
2 pages
PTW JHA Partition Work
PDF
No ratings yet
PTW JHA Partition Work
3 pages
2020 06 17 JSA For Installation of The AC Unit in The Server Room
PDF
No ratings yet
2020 06 17 JSA For Installation of The AC Unit in The Server Room
11 pages
Method Statement For Raceway
PDF
50% (2)
Method Statement For Raceway
2 pages
Method Statement For Conventional Formwork Blog
PDF
100% (1)
Method Statement For Conventional Formwork Blog
9 pages
Job Safety Analysis:: RTR DRAIN LINE REPLACEMENT (Excavation and Backfilling)
PDF
No ratings yet
Job Safety Analysis:: RTR DRAIN LINE REPLACEMENT (Excavation and Backfilling)
5 pages
Method Statement For Installation of Hangers and Supports
PDF
No ratings yet
Method Statement For Installation of Hangers and Supports
5 pages
JOB HAZARD ANALYSIS Deep Excavation-2
PDF
No ratings yet
JOB HAZARD ANALYSIS Deep Excavation-2
9 pages
Product List Complete
PDF
No ratings yet
Product List Complete
6 pages
Method Statement For Chipping of False Floor Opening
PDF
0% (1)
Method Statement For Chipping of False Floor Opening
7 pages
PMT-MS-018 Rev.00 - Method of Statement For Chpping and Coring Wworks
PDF
No ratings yet
PMT-MS-018 Rev.00 - Method of Statement For Chpping and Coring Wworks
4 pages
New Updated Wms Residential
PDF
No ratings yet
New Updated Wms Residential
17 pages
4. Metal Ceiling Exterior Installation
PDF
No ratings yet
4. Metal Ceiling Exterior Installation
17 pages
3rd Floor VMAB Mechanical Plan ACU
PDF
No ratings yet
3rd Floor VMAB Mechanical Plan ACU
1 page
VRV Catalogue
PDF
No ratings yet
VRV Catalogue
168 pages
Supreme PVC & PPR Brochures
PDF
100% (1)
Supreme PVC & PPR Brochures
28 pages
Mine Environmental Management
PDF
No ratings yet
Mine Environmental Management
8 pages