Purpose of this document and attachments is to define the scope of work for surface condenser
system package, its engineering & deliverables for Engineering Contractor.
B. Definition:
HPCL Rajastan Refinery is hereinafter referred as owner, Engineers India Limited (EIL) is hereinafter
referred as PMC, L&T Hydrocarbon engineering (LTHE) is hereinafter referred as EPC contractor, Elliot
Group, Ebara Corporation India is hereinafter referred as Buyer. L&T Heavy Engineering IC is Supplier
of Surface Condenser System Package for this Project
TEI Engineering Consultants; Babcock Power APAC Pvt Ltd is hereinafter referred as Engineering
Contractor and L&T Heavy Engineering IC is hereinafter referred as Client for the purpose of this scope
of work agreement .
C. Scope
Engineering Contractor’s scope is to carry out the complete design and engineering of surface
condenser system package, which includes -
a. The thermo-hydraulic and mechanical design of surface condenser,
b. Detailing of complete condenser package,
c. Bill of Material and datasheets as well as drawings preparation,
d. The entire system design and engineering, basic engineering & RFQ preparation (for brought
out items), technical bid tabulation and provide vendor recommendation. Liaisoning with
finalized vendor.
e. Preparation of all documents as per the format required by Owner/PMC/EPC
Contractor/Buyer/Customer during bid stage as well as detailed engineering stage,
f. Resolution of the Owner/PMC/EPC Contractor/Buyer/Customer comments,
g. Technical Support for fabrication,
h. Please refer below annexures for further details:
Delay in deliverables beyond agreed schedule shall attract LDs. Extent of LD shall be as per commercial
terms and condition.
Thermo-Hydraulic and Mechanical guarantee of surface condensers and entire system shall be of
Engineering Contractor. Extent of liabilities shall be as per commercial terms and condition.
F. Preferences:
Sr.
Engineering Contractor Scope Responsibility Remark
No.
FIRM ENQ & POST-ORDER STAGE
Release of Engineering contractor thermal design e.g.
1 a. Mechanical Datasheets
b. GA sketch
Additional thermal design details e.g. (order stage)-
a. Tube Layout including finger lanes arrangement
b. Baffle Spacing sketch
c. Holdup time calculations- for Hotwell
d. Interconnecting duct pressure drop calculations
e. Thermal Hydraulic Design Report
2
f. FIV Report for all operating conditions
g. Flash Tank Design
h. Simulation for various operating conditions
i. Performance Test Procedure
j. Performance Curves considering various load
conditions, temperatures.
3 Deleted
4 Deleted
5 Deleted
6 GA-Drawing
As per Owner/PMC/EPC
7 Material selection
Contractor/Buyer
8 Mechanical design including foundation load data.
FEA for followings-
a. Channel box,
9 b. Tubesheet,
c. Nozzles load analysis &
d. Exhaust Neck along with bellow
Compliance to applicable codes, standards & all applicable
10
specifications
11 Detail drawings AutoCAD native files
Fabrication drawings in the L&T template Including weld # Weld details, seam nos.
12A
details, seam nos. etc. will be informed by L&T
12B Erection drawing/documents
13 Surface condenser 3D-CAD model
Owner/PMC/EPC Contractor/Buyer/Customer submission
14
drawings
Procurement specs & datasheets for Bought outs (Refer
15
Annexure -2)
System Engineering (includes but not limited to design and
16 engineering of CEP, Ejector system, Control Valves, and
instrumentation etc)
Description of Instrument/equipment
I. Auxiliary for condenser
Interconnecting Steam Duct with Expansion Joint
II. Rapid Evacuation Unit
Hogging Ejector(with silencer)
First Stage Ejector(Main)
First Stage Ejector(Standby)
Second Stage Ejector(Main)
Second Stage Ejector(Standby)
Piping along with Ejectors
Pressure Relief Valve for Ejector
Thermal Relief Valve for Inter/After Condenser Tube-side
Control Valves, Strainers, Steam Traps, Piping-parts and Supports
Isolation valves
Common Base Frame
Inter Condenser
After Condenser
Drain Trap with By-pass Piping for Inter Condenser
Drain Trap with By-pass Piping for After Condenser
Pressure Gauges for Ejectors (Hogging, first stage and second stage)
Pressure Gauges for Inter-After Condensers
Temperature Gauges for Inter-After Condensers
Air Leakage Meter for inter and after condenser
Temperature Indicators
III. Valves & Instruments for Condenser
Atmospheric Relief Valve
Vacuum breaker valve along with bypass skid
Temperature Gauges- CW side
Pressure Gauges- CW side
Thermal Relief Valve- CW side
Isolation valves
Level Transmitter for Hotwell
Level Gauge for Hotwell
Temperature Gauge for Hotwell
Pressure Gause - Condenser Shell
Temperature Gauge -Condenser shell
Pressure Transmitter - Condenser Shell
Condensate Level Control Valve for Hotwell- main and recycle line
Bypass and isolation skid for control valves
Junction Box
For Detailed List of engineering deliverables, please refer enclosed Major document
list