PROBLEM SET # 2
engine, lash adjuster is used. Equation below shows the link between the lash adjuster price (p)
3000 − 𝑝
𝐷=
0.15
To maximize total revenue, what demand should be considered? What important dat
Given:
𝐷=
.
Solution:
Get number of demands to maximize revenue
𝐷=
.
𝑝 = 3000 − 0.15𝐷
Take note that 𝑇𝑜𝑡𝑎𝑙 𝑅𝑒𝑣𝑒𝑛𝑢𝑒 (𝑇𝑅) = 𝑝𝐷
𝑇𝑅 = 𝑝 ∗ 𝐷 = 3000𝐷 − 0.15𝐷
Answer:
𝑫 = 𝟏𝟎, 𝟎𝟎𝟎 𝒖𝒏𝒊𝒕𝒔 𝒑𝒆𝒓 𝒎𝒐𝒏𝒕𝒉
Answer:
𝑫𝒊𝒄𝒆 = 𝟐, 𝟗𝟏𝟐 𝒊𝒄𝒆 𝒃𝒍𝒐𝒄𝒌𝒔
A part is being considered for manufacture on two currently owned machines. The capital
investment in the machines is roughly the same and can be overlooked. The production capabilities
and reject rates of the machines are the most significant distinctions between them. Consider the
table below.
Machine A Machine B
The material cost is Php 300.00 per part, and all defect-free parts can be sold for Php 600.00 each.
For either machine, the operator cost is Php 750.00 per hour and the variable overhead costs is Php
a. Assume that the daily demand for this part is large enough that all defect-free parts can be
b. What would the percent of parts rejected have to be for the other machine to be as profitable
Given:
Operating Cost (𝐶 ) = 𝑃ℎ𝑝 250 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟
Material Cost (𝑐 ) = 𝑃ℎ𝑝 300.00 𝑝𝑒𝑟 𝑝𝑎𝑟𝑡
Parts price (𝑝) = 𝑃ℎ𝑝 600.00 𝑝𝑒𝑟 𝑝𝑎𝑟𝑡
Machine A
Production hours (𝑡) = 7 ℎ𝑜𝑢𝑟𝑠/𝑑𝑎𝑦
Rejected parts rate (𝑥) = 5%
Rate of production (𝐷) = 100 parts/hour
Machine B
Production hours (𝑡) = 6 ℎ𝑜𝑢𝑟𝑠/𝑑𝑎𝑦
Rejected parts rate (𝑥) = 12%
Rate of production (𝐷) = 130 parts/hour
Solution:
A. Assume that the daily demand for this part is large enough that all defect-free parts
Answer:
𝑴𝒂𝒄𝒉𝒊𝒏𝒆 𝑨 𝒔𝒉𝒐𝒖𝒍𝒅 𝒃𝒆 𝒔𝒆𝒍𝒆𝒄𝒕𝒆𝒅 𝒘𝒊𝒕𝒉 𝒂 𝑇𝑜𝑡𝑎𝑙 𝑃𝑟𝑜𝑓𝑖𝑡 𝑜𝑓𝑃ℎ𝑝 187,250.00/𝑑𝑎𝑦
B. What would the percent of parts rejected have to be for the other machine to be as
(𝑃ℎ𝑝 187,250.00/𝑑𝑎𝑦)
(𝑥) = 0.09668
Answer:
𝒙 = 9.67%