Bridge Chapter 03
Bridge Chapter 03
Reinforcement
Forms
Basic Form Requirements
Form Plans
Form Materials
Form Construction
Installation of Form Ties and Spreader
Chamfer Strips
Keyways
Preparation for Concrete Placement
Removal of Forms
Falsework
Reinforcement
Deformed Steel Bars
Identifying Reinforcing Steel
Reinforcement Details
Delivery, Storage, and Sampling
Installation of Reinforcement
Method of Measurement
Basis for Payment
CHAPTER THREE:
FORMS, FALSEWORK, AND
REINFORCEMENT
FORMS
Forms for concrete are like molds in that they shape and support concrete
until the concrete hardens sufficiently to stand without the forms. No
other factor has as much impact on the appearance of the substructure as
the quality of the formwork.
3-1
3) They are required to produce a uniform concrete surface
texture, including aesthetic or rustication details when such
a treatment is specified.
3-2
FORM PLANS
There are no plans for forms as such. The Contractor uses the detail sheets
of the plans to obtain the lines and dimensions of substructure units then
builds forms that produce those dimensions and lines.
In addition to producing the correct lines and dimensions, the forms are
required to also be capable of withstanding the pressure of plastic
concrete. The faster the concrete is poured, the greater the pressure and if
the concrete is poured too quickly, the walls of the form may fail. In
general, the pressure is greater in taller vertical forms than in horizontal
forms. Figure 3-2 gives the pressures of concrete poured into wall and
column forms at various pour rates in the number of feet poured per hour.
Forms (Figure 3-3) for substructure concrete may be made from wood,
metal, fiberglass, and even cardboard and fiber. No matter what materials
are used, however, the important property of the forms is that they are
strong enough to confine plastic concrete at the dimensions indicated on
the plans without bulging, sagging, or failing under the load.
3-3
Figure 3-3. Concrete Forms
Form materials are required to be inspected for quality and condition. All
form material that is in contact with exposed concrete surfaces, except for
the undersides of girders, slabs, and arch rings, is required to be lined
with approved plywood, metal, or other material that produces the desired
surface texture. The lining is required to be clean and free of surface
defects, grease, rust, or anything else that could mar or discolor the
concrete. In addition, the interior faces of form panels are required to be
coated with a formulated form oil to make the forms easier to remove and
to prevent concrete from sticking to the forms.
3-4
Wood and metal are by far the most common form materials. A typical
wood form consists of assemblies of 4 ft by 8 ft plywood sheets that have
been braced vertically by studs and horizontally by wales (Figure 3-4). To
provide maximum rigidity, the plywood sheets are required to be installed
with their grain perpendicular to the studs. Studs are required to also be
placed over all joints between the sheets.
The Technician is required to observe that the lumber used is neither too
green or too dry. Green lumber tends to shrink after installation and create
gaps between form panels that allow mortar to leak out. Lumber that is
too old and dried out is subject to warping.
3-5
Many Contractors build and use reusable wood forms. Reusable wood
forms are acceptable until they become too flexible to hold the concrete at
the right lines. Surfaces of reusable forms are required to be checked
closely for old concrete and other surface defects.
Metal forms (Figure 3-5) may be used in the construction of footings and
the walls of piers and abutments. These forms consist of ribbed metal
panels that do not require additional studs and wales. When maintained in
good condition and kept clean, metal forms may be used over and over
again.
3-6
Round forms (Figure 3-6) made of metal, fiberglass, or heavy fiber are
used in the construction of round columns.
The sides of the vertical forms are held together by form ties (Figure 3-7).
There are a variety of designs, but most ties include three parts: a spreader
rod, bolts, and washers. Many Contractors use snap ties. The ends of
snap ties are designed to break off just below the surface of the concrete.
3-7
FORM CONSTRUCTION
3-8
INSTALLATION OF FORM TIES AND SPREADER
The Technician is required to observe that the tie rods, which are left in
the concrete, are installed so that there is sufficient concrete cover over the
rod ends. One to two inches of concrete is typical. Insufficient cover over
the rod ends may cause staining and spalling of the concrete surface.
In addition to the form ties, the Contractor may also use temporary
wooden spreaders and struts to maintain the interior dimension of the
form. Spreaders are used most often in tall, narrow wall forms. Wooden
spreaders are not to be used, however, for inside walls that are less than 2
ft thick. All wooden spreaders are required to be removed prior to the
pour.
CHAMFER STRIPS
KEYWAYS
3-9
Figure 3-9. Keyways
Prior to the concrete pour, forms are required to be checked with survey
instruments for proper alignment and elevation. All trash and construction
debris is required to be removed from the interior of the forms. When a
form is too tall or narrow to permit easy worker access to the interior, the
Contractor is required to build access panels near the bottom of the form
to permit the removal of trash.
REMOVAL OF FORMS
Forms may not be removed until the concrete is strong enough to stand
without damage. On some contracts, the specific time required may be
determined by the results of concrete beam or cylinder tests. On other
contracts, the following periods, except for days when the temperature is
below 40° F, may be used as a guide:
3-10
FALSEWORK
3-11
Figure 3-11. False Piers
The Technician should never take for granted that the falsework is
adequate. The falsework is required to be monitored throughout the
concrete pour and the curing period. Simple devices called tell tales
(Figure 3-12) may be attached to the falsework to measure any settlement
that may occur. If movement on the tell tales occurs during the pour, the
Contractor is required to stop the operation and provide additional bracing.
In some cases, a bulkhead or a construction joint is necessary and the
falsework is required to be modified before continuing the pour.
3-12
Section 702.14(b) describes the conditions necessary to permit falsework
removal. The procedure includes primarily the time and temperature
requirements regarding specific parts of a structure. Removal of
falsework may also be controlled by concrete beam test results.
REINFORCEMENT
While formwork gives concrete the shape and texture, reinforcement gives
the concrete strength. Specifically, reinforcement provides concrete with
tensile strength, the ability to withstand bending stresses without cracking.
Earth movement, wind stresses, and the movement of the superstructure
because of expansion and contraction with temperature changes are
examples of forces that may twist and bend substructure units. Without
reinforcement, most concrete structures would crumble to the ground.
To protect reinforcing steel from rust, many contracts now require the use
of epoxy-coated bars in locations throughout the structure. In the past,
epoxy-coated bars were reserved for areas that were more subject to
moisture penetration, such as bridge decks. Researchers have discovered,
however, that reinforcing steel rusting is more pervasive than previously
believed. As a result, more and more contracts require the use of epoxy-
coated reinforcing steel in other areas of the structure.
3-13
Figure 3-13. Reinforcing Bars
The ASTM identification system has designations for bar sizes that are
approximately equal to the number of 1/8 inches in the diameter of the bar.
For example, a #3 bar has a diameter of 3/8 of an inch, a #4 bar has a
diameter of 4/8 or half an inch, a #6 bar has a diameter of 3/4 of an inch, a
#8 bar has a diameter of one inch, and so on.
Also note the column listing the weight of each size bar in pounds per
foot. This weight is used in determining the Contractor's payment for
reinforcing steel delivered and used on the job-site.
The continuous line and number systems (Figure 3-14) are the two ASTM
systems used for bar identification. Both systems include standard
markings on the bars which are used to identify the bar producer, the bar
size, the type of steel used, and the bar grade. The first mark is typically
the initial of the mill that produced the bar. The second mark is the bar
size (#3-#18). The third mark indicates the type of steel (new billet, axle,
or rail). The difference between the two systems of bar identification is
the way the bar grades are identified.
3-14
In the continuous line system, the grade of steel is indicated by one or two
lines located between the main ribs of the bar. One line between the main
ribs indicates the steel is Grade 60 (60,000 lb/in2 strength) and two lines
indicate the steel is Grade 75 (75,000 lb/in2 strength). Lower grades of
steel have no grade marks.
3rd mark -- Type (N for New Billet; A for Axle; l for rail)
High-strength bars are required to indicate grade marks: 60 or one line for
60,000 psi strength, 75 or two lines for 75,000 psi strength. Grade mark
lines are smaller and between the two main ribs, which are on opposite
sides of all American bars.
In the number system, grades are stamped on the bars numerically. Again,
anything below Grade 60 does not have a grade mark.
REINFORCEMENT DETAILS
3-15
Reinforcement information is located in the Bill of Materials section on
the detail sheets (Figure 3-16). This section lists the sizes, lengths, and
quantities of all bars required for a particular unit of the substructure.
Straight bars are identified by their size (for example, #10). Bent bars are
identified by a three- or four-digit bar mark.
The first digit or first two digits of a bar mark indicate the bar size, from
#3 to #18. The last two digits indicate the mark. The mark number, 01-
99, is used to differentiate between bent bars of the same size and shape
but of different lengths. The detail sheets also include drawings that
illustrate the shapes of all bent bars to be used.
3-16
The letter "E" following a bar size or mark in the Bill of Materials section
indicates that the bar is to be epoxy-coated. Alternately, since many
contracts are requiring the use of epoxy-coated bars throughout the
structure, there may be a note on the plans indicating that all reinforcing
steel is required to be epoxy-coated instead of the "E" in the Bill of
Materials.
Other useful information located in the Bill of Material section includes the
quantity of each bar size and mark number required, the lengths required,
the total weight of each size bar, and the total weight of all bars. Sheet
703-BRST-01 of the Standard Drawings for bridges contains additional
notes on reinforcing steel.
Epoxy-coated bars require careful handling and storage. Nicks and cuts
that go through the coating may allow moisture to penetrate and
eventually rust the bars. Any damaged area larger than 1/4 in. by 1/4 in. is
required to be repaired before visible rusting occurs. Extensive damage to
the coating may be cause for rejecting the bar. Section 703.04 defines
extensive damage.
3-17
INSTALLATION OF REINFORCEMENT
The Contractor may install the reinforcing steel piece by piece or assemble
the steel into a cage or mat that may be lifted and placed inside the forms.
When the steel is assembled outside the forms, the Technician is required
to ensure that the bars are tied securely to prevent displacement during the
installation.
Once the reinforcing steel is in place, the steel is not disturbed. Personnel
are discouraged from walking on the mats unnecessarily. Any loose,
broken, or missing ties are required to be replaced.
Clearances
The clearance between the reinforcing steel and the sides of the forms
determines the amount of concrete cover over the steel (Figure 3-17). Too
little cover may lead to rusting of the steel. Rust weakens the steel and
may also cause the concrete to crack and spall. As rust forms, the rust
takes up space and creates pressure inside the concrete.
3-18
Figure 3-17. Form Clearance
The plans indicate the amount of concrete cover required over the steel.
Typical coverage is 1 in. to 2 1/2 in. The required clearances may be
maintained by the use of approved metal supports or chairs (Figure 3-18)
that are placed between the steel and the forms. The chairs are embedded
by the concrete pour. Approved chairs have non-corrosive tips to prevent
the tips from rusting and staining the exterior surface.
3-19
The clearance between the bottom layer or mat of steel in a footing and the
bottom of the footing is required to be maintained. Appropriately sized
chairs may also be used there; however, some Contractors use mortar
blocks instead. The blocks are required to be made of the same mortar
mixture that is used in the footing pour. Other materials such as wood,
stones, or broken concrete are not permitted to support the bottom mat of
steel.
The plans may call for bars to be tied together vertically in pairs. This
procedure is called bundling. In effect, bundling doubles bar strength.
Bundled bars are generally found in the lower parts of tall forms where
bending stresses are the greatest. Bundled bars may be tied together every
3 ft as a minimum.
The plans are required to indicate the length of the bar splice. If the plans
do not indicate this length, and there is no other splice length given, the
general rule is that spliced bars are required to overlap one another by at
least 32 times the bar diameter. For example, # 6 bars have a diameter of
0.75 in. Therefore, the minimum overlap for two # 6 bars is 32 times
0.75 in. or 24 in.
3-20
Splices are not permitted at points with less than 2 in. of clearance
between the spliced bars and the nearest adjacent bar. In general, bars that
are size 14 and over may not be lapped spliced, but may be welded or
mechanically spliced in some special cases. Section 703.06 states that
construction joints may not be used within the limits of a spliced bar.
Dowels
Lap requirements are especially critical for bars that function as dowels
(Figure 3-20). These vertical bars are used to connect one section of the
substructure to another, forming an integral unit. They are commonly
used to tie a footing into a wall or column. If the dowels do not project
into the upper section by the planned amount, the connection between the
sections is weakened. The length of the bars and the distance they project
into the upper section is shown on the plans.
The spacing of the reinforcing steel in the bridge seat area is critical. Bars
that are out of position could interfere with the placement of the anchor
bolts for the bearing devices.
METHOD OF MEASUREMENT
Reinforcing steel, except for welded wire fabric, is measured by the pound
based on the theoretical number of pounds in place as indicated on the
plans or placed as ordered. The quantitiy of materials furnished and
placed is based upon the calculated weights of the reinforcing steel
actually placed in accordance with the Specifications. The weights may
be calculated using the figures from the table in Section 703.07 (Figure 3-
21).
3-21
Figure 3-21. Reinforcing Steel Weights
Both plain and epoxy coated reinforcing steel are paid for by the pound at
the contract unit price. Only bars that have been accepted for quality of
material and installation are paid for, and no additional payment is made
for wire, clips or other material used for fastening the steel in place. The
cost of those items has been included in the contract unit price.
If the Contractor elects to use larger bars than the ones required in the
plans, #10 bar instead of #8 bar for example, payment is based on the use
of the planned size.
If the Contractor elects to use shorter bars simply to make transporting the
bars easier and then uses unplanned but approved splices to obtain the
necessary lengths, the weight that is paid is still based on the lengths
shown on the plans. No additional payment is made for the extra length
needed to obtain the required lap.
3-22